CONSTRUCTION COST ESTIMATE
KARLUK BULK FUEL SYSTEM
95% SUBMITTAL
KARLUK, ALASKA
COST CONSULTANT ENGINEER
HMS Inc. Raj Bhargava Associates
301 East Fireweed Lane
Anchorage, Alaska 99503
4103 Minnesota Drive
Anchorage, Alaska 99503
(907) 561-1653 February 25, 1991 (907) 562-0420 FAX
KARLUK BULK FUEL SYSTEM 2 KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
NOTES REGARDING THE PREPARATION OF THIS COST ESTIMATE
This estimate has been prepared from 95% drawings and spec/cut sheet received on
2/20/91 and provided by the following:
M 2 drawings Raj Bhargava Associates, Anchorage
Cc 2 drawings Tryck, Nyman and Hayes, Anchorage
s 1 drawing Tryck, Nyman and Hayes, Anchorage
This estimate is priced to reflect local force account labor with some skilled
contractor’s labor for Spring 1991 construction. All force account labor is priced at
$22.00 per hour. Skilled labor for subcontractor has been priced at $42.50 per hour.
An option is priced as all work by general contractor using A.S. Title 36 wage rates,
per diems, etc.
This is a statement of probable construction cost only and excludes:
1. A/E fees
2. Administrative costs
3. Cost of any other work not shown on the drawings
Unit prices and costs indicated in this estimate are based on current knowledge.
The possible effects of current hostilities in the Middle East have not been
considered in the preparation of this estimate.
KARLUK BULK FUEL SYSTEM aa 2 KARLUK, ALASKA 95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
SUMMARY
FORCE ACCOUNT AND SKILLED LABOR
BASIC Relocate 50,000 Gallon Tank 201,597
ADD 1. 2,000 Gallon Above Ground Tank 16,480
2. Aircraft Fill Line 94,868
TOTAL BASIC AND ADDITIVES 312,945
OR
OPTION All Work by General Contractor
BASIC Relocate 50,000 Gallon Tank 247,248
ADD 1. 2,000 Gallon Above Ground Tank 18,320
2. Aircraft Fill Line 105,459
TOTAL BASIC AND ADDITIVES 371,027
PAG KARLUK BULK FUEL SYSTEM = KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE
ESTIMATED CONSTRUCTION COST
SUMMARY
FORCE ACCOUNT AND SKILLED LABOR
Relocate 50,000 Gallon Tank
N ke and Fill es
Demolition 1,000 100 3,759 4,759
New Dike 10,024 522 11,484 21,508
Concrete Supports 4,702 90 1,980 6,682
Tank Relocation 2,114 252 9,439 11,553
Tank Piping 415 45 1,915 2,330
Truck Fill 876 ay 468 1,344
Remote Fill at Tank 3,434 88 3,639 7,073
Remote Fill at Barge 811 13 553 1,364
Ricwill Piping 31,790 1402 57,383 89,173
Sump Drain 915 34 1,118 2,033
SUBTOTAL 56,081 2557 91,738 147,819
General Conditions, Overhead
and Profit 48,861
SUBTOTAL 196,680
Contingency 2.50 4,917
201,597
PAGE 4 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES coral UNIT MATERIAL TOTAL LABOR MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
Demolitions
Remove 3'0"x6‘0"x1‘0" thick concrete
ballasts and straps from tank 4 EA NA 8 22.00 176 176
Puge 50,000 gallon tank of dangerous
vapors prior to relocation Be LOT NA 10 42.50 425 425
Drain tank of fuel or water contents
(assume 1,000 gallons) x Lot NA 4 42.50 170 170
Cut and remove 2" diameter x 48"
vent line i EA NA il 42.50 43 43
Ditto 1 1/2" stand pipe Y EA NA 1 42.50 43 43
Excavate and remove 4" diameter
buried drain pipe 40 LF NA 16 22.00 352 352
Ditto 4" gate valve 1 EA NA Included
Remove tank from dike and set on
(6) structural supports for
relocation 2 EA 1000.00 1,000 60 42.50 2,550 3,550
SUBTOTAL DEMOLITION 1,000 100 3,759 4,759
PAGE 5
KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES TOTAL
MATERIAL TOTAL LABOR MATERIAL
QUANTITY UNIT TOTAL HOURS RATE TOTAL AND LABOR
New Dike
Excavate gravel berm and save :
material for reuse 213 cy NA 54 22.00 1,188 1,188
Remove liner and dispose 896 SF NA 6 22.00 132 132
Excavate for new dike and stockpile 809 cy NA 200 22.00 4,400 4,400
Ditto at bottom of tank and sump
pit 128 cy NA 34 22.00 748 748
12" NFS under tank from stockpile 42 cy NA 20 22.00 440 440
Overall 12" liner bedding 6" under
and 6" over liner 221 cy 25.00 5,525 78 22.00 1,716 7,241
Form outside berm with stockpile 200 cy NA 50 22.00 1,100 1,100
Dispose surplus on site 400 cy NA 40 22.00 880 880
30 mil Cooley 1023S urethane liner 4,090 SF 1.10 4,499 40 22.00 880 5,379
SUBTOTAL NEW DIKE 10,024 522 11,484 21,508
PAGE 6 KARLUK BULK FUEL SYSTEM KARLUK, ALASKA 95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES TOTAL UNIT MATERIAL TOTAL MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE AND LABOR
Concrete Tank Support and Sump Pit
3,000 psi concrete slab and support
saddle (5) 14 cy 225.00 3,150 18 22.00 396 3,546
23 1/2"x23 1/2"x25" deep x 6" thick
concrete sump pit (1) a cy 225.00 225 2 22.00 44 269
Formwork to side of 8" slab and
support saddle 107 SF 1.50 161 12 22.00 264 425
Ditto curved to tank bottom profile 240 SF 2.85 684 36 22.00 792 1,476
Formwork to sump pit walls 32 SF 2.00 64 4 22.00 88 152
Bar reinforcement to saddles 850 LBS 0.35 298 12 22.00 264 562
Ditto sump pit 50 LBS 0.35 18 2 22.00 44 62
Geofabric to both sides of liner
at sump pit 48 SF 0.25 12 1 22.00 22 34
(2) 2"x6" AWW fixed to pit walls
with (2) 3/8" stainless steel bolts 6 LF 2.50 15 1 22.00 22 37
Drill 1 1/2" diameter drain hole in
wood 20 EA NA 1 22.00 22 22
‘ PAGE 7 KARLUK BULK FUEL SYSTEM KARLUK, ALASKA 95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
TOTAL
UNIT MATERIAL TOTAL MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES
onc. Tank Support and Sum) it Conti:
16"x16"x1 1/4" Neenah grate set on
wood frame 1 EA 75.00 75 L 22.00 22 97
SUBTOTAL CONCRETE TANK SUPPORT AND SUMP PIT 4,702 90 1,980 6,682
PAGE 8 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES TOTAL
UNIT MATERIAL TOTAL LABOR MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
Tank Relocation
Wire brush exterior of tank 2,487 SF NA 62 22.00 1,364 1,364
Remove tank from temporary supports
and set on new concrete slab/support
saddles 1 EA NA 80 42.50 3,400 3,400
Paint tank with Tnemec Series 135
Chembuild paint 2,487 SF 0.85 2,114 110 42.50 4,675 6,789
SUBTOTAL TANK RELOCATION 2,114 252 9,439 11,553
PAGE 9 KARLUK BULK FUEL SYSTEM KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES ROTAL
MATERIAL TOTAL LABOR MATERIAL
QUANTITY UNIT TOTAL HOURS RATE TOTAL AND LABOR
Tank Piping
Remove threaded fittings and cap
openings with doped plugs 4 EA NA 4 42.50 170 170
Cut hole for 8" emergency vent x EA NA 2 42.50 85 85
Ditto 3" vent 2 EA NA 2 42.50 85 85
Ditto 3" gauge hatch L EA NA 1 42.50 43 43
Ditto 4" truck fill a EA. NA 1 42.50 43 43
Plug above openings for air test 5 EA 15.00 75 5 42.50 213 . 288
Air test tank a LoT NA 16 42.50 680 680
Remove plugs for new fittings 5 EA NA 2 42.50 85 85
Weld 3"x60" vent pipe to tank 2 EA 40.00 80 3 42.50 128 208
Install 3" CB300-3 screened vent
to above 2 EA 25.00 50 3 42.50 128 178
Weld 3" CB232-3 gauge hatch with
locking cover to tank 1 EA 45.00 45 2 42.50 85 130
Weld 8" CB368 emergency vent to tank L EA 165.00 165 4 42.50 170 335
SUBTOTAL TANK PIPING 415 45 1,915 2,330
KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES UNIT MATERIAL TOTAL LABOR
PAGE 10
2/25/91
TOTAL
MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE
uc 11
4" welded steel pipe to bottom of
tank (1) 12 LF 15.00 180 2 42.50
4" elbow welded to pipe 1 EA 61.00 61 2 42.50
4" flanged Series F ball valve
welded to elbow z EA 225.00 225 2 42.50
4" Camlock OPW-644D quick disconnect
with dust cap welded to BV zh EA 185.00 185 2 42.50
Weld foot valve to bottom of fill
line inside tank + EA 225.00 225 3 42.50
SUBTOTAL TRUCK FILL 876 11
TOTAL
85
85
85
85
128
468
AND LABOR
265
146
310
270
353
1,344
PAGE 11 KARLUK BULK FUEL SYSTEM KARLUK, ALASKA 95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES TOTAL
UNIT MATERIAL TOTAL MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
Remote Fill Line at Tank
Weld 4" fitting to tank 2 EA 50.00 100 3 42.50 128 228
4" elbow welded to pipe 9 EA 61.00 549 18 42.50 765 1,314
4" welded ball valve 2 EA 225.00 450 4 42.50 170 620
4"x12" ditto flex connection 2 EA 115.00 230 3 42.50 128 358
4" Schedule 40 fill pipe up to berms 136 LF 15.00 2,040 54 42.50 2,295 4,335
4"x4"x24" AWW cribbing to above
at 10'0" o/c at EA 4.50 50 5 22.00 110 160
Cap fill line for airport additive 1 EA 15.00 15 a 42.50 43 58
SUBTOTAL REMOTE FILL LINES AT TANK 3,434 88 3,639 7,073
PAGE 12
KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES TOTAL
UNIT MATERIAL TOTAL LABOR MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
e Fil e r
Weld 4" elbow to prefabricated
pipe 1 EA 61.00 61 2 42.50 85 146
4" steel pipe welded to fittings
(3 sections) 2 LF 20.00 40 2 42.50 85 125
4" flanged check valve welded to
pipe a EA 215.00 215 3 42.50 128 343
4" ditto ball valve Class 150 1 EA 225.00 225 : 2 42.50 85 310
4" Camlock OPW-644D quick disconnect
with dust cap welded to BV 1 EA 185.00 185 2 42.50 85 270
3/4" locking globe valve with hose
end connection and 3/4"x12" pipe
leg welded to 4" pipe a EA 85.00 85 2 42.50 85 170
SUBTOTAL REMOTE FILL LINE AT BARGE 811 13 553 1,364
KARLUK BULK FUEL SYSTEM KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES
LABOR
TOTAL
PAGE 13
2/25/91
TOTAL
MATERIAL
MATERIAL TOTAL
QUANTITY UNIT TOTAL HOURS RATE
Ricwill Piping
Excavate 3'0"x3‘0" deep trench
and dispose 267 cy NA 66 22.00
Backfill with stockpile 307 cy NA 78 22.00
4" Schedule 40 pipe inside 8 5/8"x
10 gauge prefabricated asphalt
coated fiber reinforced pipe conduit
laid in trench 800 LF 33.25 26,600 1,080 42.50
End seals 2 EA 150.00 300 8 42.50
4"x8 5/8" elbows 10 EA 325.00 3,250 40 42.50
Cathodic protection 800 LF 2.05 1,640 30 42.50
SUBTOTAL 31,790 1,302
Sub‘s Instructor 10 MD NA 100 50.00
SUBTOTAL RICWILL PIPING 31,790 1,402
1,452
1,716
45,900
340
1,700
1,275
52,383
5,000
57,383
AND LABOR
1,452
1,716
72,500
640
4,950
2,915
84,173
5,000
89,173
KARLUK BULK FUEL SYSTEM oes KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES sores MATERIAL TOTAL MATERIAL
QUANTITY UNIT TOTAL HOURS RATE TOTAL AND LABOR
s n Pi
Excavate and backfill trench 27 cy NA 16 22.00 352 352
4" Schedule 40 drain pipe 46 LF 15.00 690 14 42.50 595 1,285
4" gate valve at outlet al EA 200.00 200 2 42.50 85 285
4"x6" long steel pipe welded at
inlet a EA 15.00 15 aL 42.50 43 58
4" plug to above 2 EA 10.00 10 al 42.50 43 53
SUBTOTAL SUMP DRAIN PIPE 915 34 1,118 2,033
PAGE 15 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
TOTAL
UNIT MATERIAL TOTAL MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE AND LABOR
RELOCATE 50,000 GALLON TANK, NEW DIKE AND FILL LINES
General Requirements
FORCE ACCOUNT
Mobilization/demobilization (local
contractor) . 7 LOT 750.00 750 1000.00 1,000 1,750
Freight 22 TONS NA 280.00 6,160 6,160
Equipment (backhoe, crane, etc.) 45 DAYS NA 250.00 11,250 11,250
Supervision 6 WKS NA 1800.00 10,800 10,800
Per diem (skilled labor only) 174 MD 40.00 6,960 NA NA 6,960
Clean up 6 WKS 50.00 300 70.00 420 720
SUBTOTAL 37,640
General liability insurance only
(no bonds) (37,640 + 147,819) 1 % 1,855
Contractor’s fee (on direct works
only) 5 % 9,366
SUBTOTAL GENERAL REQUIREMENTS 48,861
PAGE 1 KARLUK BULK FUEL SYSTEM °
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
ADDITIVES 1 AND 2 (FORCE ACCOUNT)
PAGE 17 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
ADDITIVE #1 TOTAL 2,000 GALLON ABOVE GROUND FUEL TANK TO POWER PLANT UNIT MATERIAL TOTAL LABOR MATERIAL QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
Demolitions
Excavate above and around buried
fuel tank and dispose (assume no
contaminated soils) 48 cy NA 12 22.00 264 264
Empty fuel from tank (assume 500
gallons) 2. LOT NA 2 42.50 85 85
Disconnect 1/2" FOS&R lines at day
tank inside building 2 EA NA a2 42.50 85 85
Ditto at tank 2 EA NA a) 42.50 43 43
Excavate to expose pipe 20 LF NA 4 22.00 88 88
Remove 1/2" FOS&R buried lines (2) 20 LF NA 2 42.50 85 85
Ditto vertically and inside
building (2) 12 LF NA 2 42.50 85 85
Remove 1/2" fusible valve and save
for reuse aL EA NA 0.50 42.50 21 21
Cut and remove 2"x60" vent and
fill pipes 2 EA NA 1 42.50 43 43
PAGE 18 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
ADDITIVE #1 a 2,000 GALLON ABOVE GROUND FUEL TANK TO POWER PLANT UNIT MATERIAL TOTAL BATERIAL, QUANTITY UNIT RATE TOTAL HOURS RATE ‘TOTAL AND LABOR
Demolitions (Continued)
Remove tank and dispose 1 EA NA 6 42.50 255 255
Fill tank hole and pipe trench with
gravel 119 cy 25.00 2,975 30 22.00 660 3,635
Grade and level disturbed ground 465 SF NA 2 22.00 44 44
SUBTOTAL DEMOLITION 2,975 64.50 1,758 4,733
New Tank and Piping
2,000 gallon closed top dike (Ace
and Tank Equipment Co.) tank complete
with I beam, skids, vents, connections,
and accessories set on gravel pad
overall size 6‘2"x8‘2"x16" long c EA 4250.00 4,250 40 42.50 1,700 5,950
1/2" copper Type K FOS&R lines (2) 60 LF 1.50 90 6 42.50 255 345
1/2" dielectric unions 2 EA 2.50 5 1 42.50 43 48
1/2" double swing joint 6 EA 3.50 21 3 42.50 128 149
Strike plate below 1/2" FOS at bottom
of tanks 1 EA 5.00 5 al 42.50 43 48
PAGE 19 KARLUK BULK FUEL SYSTEM KARLUK, ALASKA 95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
ADDITIVE #1 TOTAL 2,000 GALLON ABOVE GROUND FUEL TANK TO POWER PLANT eee aoe eeree Ee QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
lew T. and Pipin Co: nue
Reconnect FOS&R to day tank inside
building 2 EA 5.00 10 2 42.50 85 95
Reinstall 1/2" fusible valve i EA NA 0.50 42.50 21 21
1/2" Webster OSVA5O safety valve 4 EA 25.00 25 2 42.50 43 68
Attack fill spill containment box ;
CN200 to tank 1 EA 45.00 45 2 42.50 85 130
2"x24" galvanized vent pipe with
T and elbow assembly and 1/4" mesh
screen cover connected to tank 2 EA 22.50 45 3 42.50 128 173)
6"x6" AWW box made from 2"x6" lumber
for FOS&R at grade 10 LF 2.90 29 3 22.00 66 95
Seal 1/2" penetration into wall
with silicone and escutcheon plate 2 EA 5.00 10 a 22.00 22 32
Paint tank and dike with owner
selected paint 668 SF 0.15 100 10 22.00 220 320
SUBTOTAL NEW TANK AND PIPING 4,635 73.50 2,839 7,474
PAGE 20 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
ADDITIVE #1 pao 2,000 GALLON ABOVE GROUND FUEL TANK TO POWER PLANT UNIT MATERTAL SS TOTAL MATERIAL) QUANTITY UNIT RATE TOTAL HOURS RATE AND LABOR
SUBTOTAL ADDITIVE #1 7,610 138.00 4,597 12,207
General Requirements 31.71 % 2,413 1,458 3,871
Contingency 2.50 % 251 151 402
TOTAL ADDITIVE #1 10,274 138 6,206 16,480
PAGE 21 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
ADDITIVE #2 TOTAL
AIRCRAFT FILL LINE UNIT MATERIAL TOTAL MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE TOTAL AND LABOR
Remote Fill Line at Airport
Weld 4" elbow to prefabricated
jacketed pipe zt EA 61.00 61 2 42.50 85 146
4" steel pipe welded to fitting
(3 sections) 2 LF 20.00 40 2 42.50 85 125
4" flanged check valve welded to
pipe 1 EA 215.00 215 3 42.50 128 343
4" ditto ball valve Class 150 . EA 225.00 225 2 42.50 85 310
4" Camlock OPW-644D quick disconnect
with dust cap welded to ball valve 1 EA 185.00 185 2 42.50 85 270
SUBTOTAL REMOTE FILL 726 La 468 1,194
Ricwill Prefabricated Piping
Excavate 3'0"x3‘0" deep trench
and dispose 212 cy NA 52 22.00 1,144 1,144
Backfill with stockpile 245 cy NA 62 22.00 1,364 1,364
4" Schedule 40 steel pipe inside
8 5/8"x10 gauge prefabricated asphalt
coated fiber reinforced pipe conduit
laid in trench 635 LF 33.25 21,114 857 42.50 36,423 57,537
PAGE 22 KARLUK BULK FUEL SYSTEM KARLUK, ALASKA 95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
ADDITIVE #2 cores
AIRCRAFT FILL LINE UNIT MATERIAL TOTAL MATERIAL
QUANTITY UNIT RATE TOTAL HOURS RATE AND LABOR
emote F e irport Continued
Remove cap at tank fill line and
connect 4" fill line a EA 20.00 20 2 42.50 85 105
End seals 2 EA 150.00 300 8 42.50 340 640
4"x8 5/8" elbows 7 EA 325.00 2,275 28 42.50 1,190 3,465
Cathodic protection 635 LF 2.05 1,302 24 42.50 1,020 2,322
SUBTOTAL RICWILL 25,011 1,033 41,566 66,577
Sub‘s Instructor 5 MD NA 50 50.00 2,500 2,500
SUBTOTAL RICWILL 25,011 1,083 44,066 69,077
SUBTOTAL ADDITIVE #2 ; 25,737 1,094 44,534 70,271
General Requirements 31572 % 8,161 14,122 22,283
Contingency 2.50 % 847 1,466 2,314
TOTAL ADDITIVE #2 34,745 1,094 60,122 94,868
PAGE 23 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
OPTION - ALL WORK BY GENERAL CONTRACTOR
PAGE 24 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
OPTION - ALL WORK BY GENERAL CONTRACTOR oe UNIT MATERIAL TOTAL MATERIAL
QUANTITY UNIT RATE TOTAL HOURS AND LABOR
asic Bid (all je as force account bor rate an meral re
Direct Works . 56,081 2,557 42.50 108,673 164,754
General Requirements
Mobilization/demobilization 1 LOT 1500.00 1,500 5,000 6,500
Freight 22 TONS NA 300 6,600 6,600
Equipment (backhoe, cranes, etc.) 45 DAYS NA 350 15,750 15,750
Supervision 6 WKS NA 2,000 12,000 12,000
Per diem 174 MD 65.00 11,310 NA 11,310
Clean up 6 WKS 50.00 300 100 600 900
SUBTOTAL 217,814
Bonds and insurances 2.50 % 5,445
SUBTOTAL 223,259
Contractor's fee 7.00 % 15,628
Contingency 3.50 % 8, 361
TOTAL BASIC BID
(NOTE: General Requirements 45%)
247,248
PAGE 25 KARLUK BULK FUEL SYSTEM
KARLUK, ALASKA -
95% SUBMITTAL CONSTRUCTION COST ESTIMATE 2/25/91
TOTAL
UNIT MATERIAL TOTAL MATERIAL
QUANTITY RATE TOTAL HOURS RATE AND LABOR
OPTION - ALL WORK BY GENERAL CONTRACTOR
Additive #1
2,000 gallon above ground tank 7,610 138 4,597 12,207
General Requirements 45.00 % 5,493
Contingency 3.50 % : 620
TOTAL ADDITIVE #1 18,320
Additive #2
Aircraft fill line 25, 737 1,094 44,534 70,271
General Requirements 45.00 % 31,622
Contingency 3.50 % 3,566 _—_—_—
TOTAL ADDITIVE #2 105,459