HomeMy WebLinkAboutAtqasuk Coal Project Phase II 1989NORTH SLOPE BOROUGH
Atqasuk Coal Project
Planning Department
Grier) Rabel
P.O), Box: 69
Barrow, Alaska 99723
PROJECT ATQASUK COAL PROJECT
Phase Il
PROJECT REPORT
c= DECEMBER, 1989
PREPARED BY
ARCTIC SLOPE CONSULTING GROUP
Engineers e Architects « Scientists « Surveyors
P.O. 650 Barrow, Alaska 99723
Telephone: (907) 852-4556 Fax: (907) 852-5733
NORTH SLOPE BOROUGH
ATQASUK COAL MINE PROJECT - PHASE II
RELI PROJECT # 13-127
PROJECT REPORT
NSB Contract No 87-103
December 1989
Prepared For:
NORTH SLOPE BOROUGH
P.O. BOX 69
BARROW, ALASKA 99723
Prepared By:
ARCTIC SLOPE CONSULTING GROUP
P.O. BOX 650
BARROW, ALASKA 99723
38 —” ARCTIC SLOPE CONSULTING GROUP
| . 7 ; Engineers * Scientists * Surveyors
Rick Sampson, Acting Deputy Director
Planning Dept
North Slope Borough
P.O. Box 69
Barrow, Alaska 99723
Subject: NSB Atqasuk Coal Mine Project Phase II
RELI # 13-127, Project Report
Dear Mr. Sampson:
Arctic Slope Consulting Group is pleased to submit herein our
Project Report on the Atqasuk Coal Mine Project, Phase III and
supplemental documents entitled, North Slope Borough, Atqasuk Coal
Mine Project Phase II - Project Installation Photographs and
Checklists and Atqasuk Coal Conversion Preliminary Feasibility
Study (Submitted July 89).
The NSB Coal Project has built upon the results of the previous
Phase I. Although there are many steps to be taken concerning the
development of the local coal resource in the areas of coal quality
and coal handling, this demonstration has made significant advances
towards that end and continues to create interest and support from
other public and private entities.
We look forward completing Phase III and discussing future
developments on this project with the North Slope Borough, City of
Atqasuk, and the Atqasuk corporation.
Kent M. Grinage
North Slope Regional Manager
KNG/jc
P.O. Box 650, Barrow, AK 99723 ° PH (907) 852-4556 ° FAX (907) 852-5733
BA Re Ra O7 W ° ANC HO R#A GE . FAIRBANKS
TABLE OF
SECTION
List of Tables.
List of Figures
1 -@ NTRODUCTION
Background. 7 :
Project Objectives.
Scope of Work
I
1
1.
1 tite
1 Project Organization. PWN INING PROGRAM
General
Mobilization.
Production Schedule
Stripping
M
2
2.
2
2
2 Mining. OPWNHE INSTALLATION REPORT.
3. General
3
3
3
s
1 | ll |e
-2 Production Schedule
3
4
General .
Observations. Pr Pad OAL UTILIZATION
1
2
PROJECT COST
5.1 General. . .
5.2 Cost Breakdown.
PROJECT WORK FORCE
6.1 General... :
6.2 Work Force Profile.
6.3 Labor Cost.
RECOMMENDATIONS.
7.1 Mining.
CONTENTS
Selection of Participants +i).
Equipment Purchase and Transport. bp HR PRR RR WNrRRR NNNNNN toed NNNRP RR WWWwWww 1 WNNRFR Pe ' PRR aun 1 PRR AnaAD ' 1 NP RB nw to RR
LIST OF TABLES
No. Page
5-1 Project Cost Breakdown. ............ 2... 5-2
6-1 Project Personnel Employment List. .......... 6-2
6-2 Project Labor Cost .......... . 6-3
LIST OF FIGURES
No. Page
2-1 Plan View of Mine Site ............2.2.2. 2. 2-3
2-2 Excavation Plan and Section. ............. 2-4
ii
1.@ INTRODUCTION
1.1 Background
The high cost of fuel oil on the North Slope has created hardships
amongst its residents and has suppressed economic development
throughout the region. This problem has further been compounded
by substantial decreases in state and local expenditures in capital
projects which have provided cash income opportunities to many
residents. Both the high cost of fuel oil and lack of cash income
are the key factors that make up the energy problems prevalent
throughout rural Alaska.
Aware of this problem and in response to the villages’ request, the
North Slope Borough (NSB) Assembly approved funds in June of 1987
for the NSB RELI Project 13-127, Atqasuk Coal Mine project. Upon
successful completion of the project the NSB Assembly voted to
continue with the project and on June 21, 1988 approved funding for
a Phase II Project.
The Phase II Project built on the work conducted under the Phase
I effort. Mining was conducted in the same area of the old Meade
River Coal Mine. As part of the project Arctic Slope Consulting
Group (ASCG) worked with the City of Atqasuk and the Atqasuk
Corporation to prepare a development plan entitled, Atqasuk Coal
Conversion Preliminary Feasibility Study.
1.2 Project Objectives
The overall objectives for the 1989 Program were similar to those
of the 1988 Program. The purpose of the Phase II Project is to
maximize on the use of the Atqasuk labor force and to mine and
deliver to the village a minimum of 200 tons of coal for use ina
pilot program to test the use of coal for residential heating.
The project yielded information on costs and operating requirements
which will assist in the analysis of mining methods best suited to
recovery of the Meade River coal and the benefits which can be
derived from its use. Other tasks of the project included
installation of ten additional coal stoves and monitoring of coal
use, and preparation of a development plan.
1.3 Scope of Work
The major project tasks undertaken by ASCG are presented below:
1) Project Management
The purpose of this task involves project
administration, control and scheduling, preparation
of monthly reports, and final project report
including a coal development plan for the community
of Atqasuk.
2) Mobilization
Planning of the mining operation and procurement of
the supplies and equipment required for performance
of the mining. Obtain all appropriate permits.
3) Mining
Using local labor and NSB heavy equipment excavate
200 tons of coal and stockpile at the gravel
stockpile area adjacent to the village.
4) Installation
Using local labor install ten (10) new coal-fired
residential heating units in selected participating
homes under the supervision of a qualified
technician.
5) Coal Utilization
Devise a method for delivery of the coal to the
residents which provides for a continuous supply and
a method for measurement of coal used at each
installation.
1.4 Project Organization
Funding for this project was provided by the NSB. ASCG were the
recipients of the NSB grant and were therefore responsible for the
Management of the overall project, installation equipment
procurement, installation supervision, mine planning and
supervision and final report preparation.
Local hiring, project coordination within the village, and
selection of demonstration participants were performed in the
village by a Project Coordinator residing in the community.
2.1
2.@ MINING PROGRAM
General
The 1988 - 1989 Atqasuk Mining Program was the continuation
of a North Slope Borough (NSB) funded program to utilize the
local coal resource to supplement and/or offset the heavy
reliance on diesel fuel for residential heating by local
residents. The goal of the 1988-89 program was to mine and
stockpile 200 tons of coal for use during the 1989-90 heating
season.
The program was begun in November, 1988, but not completed due
to engine failure in the Caterpillar D-7 being used for
ripping and dozing the overburden. No replacement machine was
available, so the project was shut down until repairs were
made.
Mobilization
Steve Denton of Denton Civil and Mineral (Steve supervised
the 1987 mining program) met with Kent Grinage, Project
Manager and Gene Grisel, Mining Supervisor, on November 3 to
discuss the mining programs for the NSB Western Arctic Coal
Demonstration Project and the Atqasuk Coal Project. On
November 5, Mr. Denton and Mr. Grisel flew to Atqasuk and met
with Mr. Leroy Gunderson, Village Project Coordinator, and
Jimmy Aikens, NSB Equipment Supervisor. Maintenance and
operation of the equipment, supplies required and personnel
were discussed. The mine site was visited to familiarize Mr.
Grisel with the area. Work was begun on November 6.
2.4
Production Schedule
Nov 6/88 Open road to mine site; locate materials.
Nov 7/88 Construct temporary bridge, begin stripping
operations.
Nov 8/88 No work - blizzard.
Nov 9/88 Engine failed in Caterpillar D-7 dozer.
Nov 10/88 Moved D-7 to NSB shop, boxed supplies and
closed down operation.
Mar 16/89 Began work again. Opened road to mine and
dozed snow from pit.
Mar 17-22/89 Ripping and dozing overburden on pit.
Mar 23/89 Began hauling coal - 9 loads.
Mar 24/89 Hauling Coal - completed 18 loads. 1 load to
Mrs. Burnell’s.
Mar 25/89 Backfilled pit, demobilized.
Stripping
A total sum of 2700 yd*> of overburden was removed in
approximately 73 hours by the D-7 and 50 hours by the 966 (See
Figure 2-1). Overall, these numbers represent about 37.2 yd’
excavated per hour of dozer operation time.
Mining
Old workings were encountered in the Southeast corner of the
pit, resulting in about a 50% loss of minable coal in the pit
due to the restrictions in equipment mobility caused by the
cramped work area (See Figure 2-2). Also, lower seams of
higher quality coal could not be effectively mined.
RECOMMENDED / FUTURE MINING AREA
OLD WORKINGS
1988 - 1989 PIT
PIT FROM 1987 SEASON
(BACKFILLED)
UNDERGROUND WORKINGS
(INTERSECTED 1987 SEASON)
HAUL ROAD “7
PREPAREO BY
ARCTIC SLOPE CONSULTING GROUP
Plan View
of Mine Site 1988-1989 SEASON ATQASUK COAL MINE D B NO. DATE ” 3663 SEPT. 1989
~ WASTE
(OLD WORKINGS)
PIT OUTLINE AT TOP OF COAL
PLAN
SCALE:1"= 20'
SECTION A-A
N.T.S.
iyure 2 - 2
Excavation Play PREPARED BY and Section
1988-1989 SEASON
ARCTIC SLOPE CONSULTING GROUP ATQASUK COAL MINE
ella SEPT. 1989
3.@ INSTALLATION REPORT
General
All installations were done in accordance with NFPA 211.
Selection of stoves for Phase II of this project was based on
results from Phase I. Most of the new participants have had
the benefit of seeing the previous project stoves in use, and
already had a good idea which stove would fit their needs the
best. Only two different stoves were installed, the Ashley
CW85 and the Harman Mark III.
The Ashley and the Harman stoves have an effective efficiency
rating of 55% to 65%. This figure is relative and comparable
to other units on the market.
The Ashley CW85 was chosen most frequently because of its
double wall construction and relatively cool exterior surface.
This made the CW85 particularly attractive to participants
with small children.
On the preliminary visit to Atqasuk, I conferred with the
participants and with them determined the best installation
location, keeping in mind optimum heat distribution and space
usage. The layout of most homes limited the choice of
installation locations, to one, and in some cases two areas.
Once the stove and it’s location were decided on, a materials
list was compiled.
3.3
Production Schedule
Jul 5/88 Travel to Barrow (meet with Project Manager).
Jul 6/88 Travel to Atgqasuk (meet with Mayor Kignak).
Jul 7-9/88 Survey housing and select participants.
Jul 20-25/88 Prepare materials list.
Aug 10/88 Bids due.
Aug 14/88 Awards bid.
Sept 10 -
Oct 3/88 Received installation materials and prepared
them for shipment to Atgasuk
Oct 5/88 Travel Atqasuk
Oct 6/88 Hold employee safety meeting and organize
installation materials.
Oct 7-13/88 Stove installations and build storage bins.
Oct 14/88 Travel to Barrow.
Selection of Participants
Residents of Atqasuk were notified of the project by the
village coordinator by means of written notices posted in
Prominent locations throughout the village. Persons
interested in participating in the coal project were requested
to contact the village coordinator.
The coordinator compiled a list of 21 interested persons.
Unfortunately the budget only allowed for 1@ installations.
The applicants were screened and 10 final participants were
selected.
The screening was done with the input of the village
coordinator, the Mayor and the installation supervisor. When
screening applicants the selection was based on; 1)
anticipated participation; 2) economic need: and 3) desire.
The final participants and the stove of their choice are
listed below:
1. Janey Itta Ashley CW85
2. Robert Itta, Sr. Ashley CW85
3. Sam Hopson, Sr. Ashley CW85
4. Mary Gunderson Harman Mark III
5. Thomas Itta, Jr. Ashley CW85
6. Thomas Kanayurak, Sr. Harman Mark III
7. Jimmy Nayukok Ashley CW85
8. Elizebeth Hollingsworth Ashley CW85
9. Jacob Shugluk Ashley CW85
10. Mike Shugluk Ashley CW85
Equipment Purchase and Transport
Because of the wide variety of materials needed the bid list
was divided into seven sections. With prospective bidders
encouraged to bid on all or any of the individual sections,
each of the seven sections received a minimum of two
competitive bids and were awarded to the low bidder with the
exception of Section 7 (Misc. Installation Materials). In
which case there were four bids, none of which were complete.
Thus, materials for this section were made at the discretion
of the installation supervisor using portions of the
respective bids where applicable.
Due to the similarities of the NSB Western Arctic Coal
Demonstration Project and the NSB Atqasuk Coal Project the
Materials Bid Lists were combined and materials consolidated
in Fairbanks for volume shipment to the respective villages.
To standardize bids and simplify logistics all bids were
F.0O.B. Fairbanks.
It was determined that the most economical way to deliver the
installation materials to Atqasuk would be via Northern Air
Cargo direct.
In some cases stoves were installed in locations that wood
heaters were previously installed, thus having chimneys and
in some cases full installations to contend with. This proved
to be a detriment rather than advantage. Prior to April of
1987 NFPA regulations allowed coal heating appliances to be
installed on Class A chimneys. Coal heating appliances
installed after this date are required to have a higher rating
of U.L. Standards - 108-HT, thus making it necessary to remove
existing chimneys to install chimneys with U.L. 103-HT rating.
All Chimneys installed were Security brand model ASHT having
U.L. 103-HT approval and were installed with the required
minimum 2’ air space. This 2’ air space is an area of
definite heat loss. But necessary! To minimize heat loss all
ceiling trim collars were therefore eliminating filtration
heat loss. Chimney were installed so that they terminated a
minimum of two feet above the peak of the roof to minimize the
possibility of down drafts. Chimney that penetrated the roof
line more than six feet were secured with a chimney brace.
To connect the stoves to the chimneys - Security double wall
connector pipe was used. Securities double wall pipe far
Surpasses NFPA’s required standard 24 gage single wall stove
pipe minimums and has many features that make it outstanding
for the application:
1) Inner liner is stainless steel all but eliminating
the need for replacement;
2) Outer wall is aesthetically pleasing black finish
and vented to allow cooling and heat distribution
through convection;
3) Available in a section of lengths and slip sections
eliminating the need for cutting;
4) Reduced clearances to combustible 6" rather than
18" for single wall;
5) Unique twist lock for tight joints. (Although not
required for twist lock pipe - three screws were
placed on each joint); and
6) Cool exteriors minimize the possibilities of burns
to small children.
Wall protection. NFPA standards state that the stoves
clearances to combustibles may be reduced by 2/3 (from 36’
without protection, to 12" with protection) by installing a
noncombustible material with one inch of air space behind it,
provided that noncombustible spacers are used. All
installation utilized this practice in order to minimize the
loss of living space. In many cases installation would not
have been possible without this practice. 24 gage galvanized
sheet metal with edges hemmed was used as the noncombustibles
materials with hatchannel spacers secured with screws.
Floor protection was fabricated from 5/8" Homasoto (a
commercial grade noncombustible material that meets FNPA
requirement for floor protection)d covered with 24 gage
galvanized sheet metal. This protection extended a minimum
of 16 inches in front of the stove door opening. Each
participant was supplied with appropriate safety equipment for
operation of his stove and instructed on the proper and safe
use and maintenance of their stove.
4.@ COAL UTILIZATION
4.1 General
This portion of the project involved the usage of coal by the
selected demonstration participants. As part of the monitoring
effort during this phase of the project, a fuel use monitoring
report prepared by ASCG for the Western Arctic Coal Demonstration
Project was utilized. These reports were used by the Village
Project Coordinator to track performance of the stoves, amount of
coal/oil consumed and comments of the participants. In addition to
the monitoring reports two LoFlo Fuel oil meters were installed.
Two houses of similar construction were selected to receive the
meters. One house was a participant in the coal demonstration,the
other was not. Meter readings were to be taken every two weeks.
The consistency wasn’t there throughout the demonstration period,
however, there were periods of consistency that makes the data
valid.
4.2 Observations
The following observations have been recorded:
1) All coal burning units selected for the demonstration
performed well.
2) As in Phase I, the primary use of coal has been as a
supplemental heating source to fuel oil, especially in
the newer type NSB housing.
3) Due to the inconsistent use of the monitoring reports by
the Coordinator, the data gathered is spotty.
4) Coal quality was not as good as Phase I. This was a
constraint to its use. Apparently the mining operation
hit the old underground tailings thus reducing the
selection of the higher quality coal.
As in the past coal was used as a supplemental fuel to oil. This
was due to the area heating limitations of the stand alone
conventional coal stoves used on this project and the style of
housing which utilizes forced air or hydronic heating systems in
order to reach all of the walled-in rooms in the house.
From the fuel use monitoring reports the following examples give a
representative picture of coal and oil use during’ the
demonstration period from 9/20/88 to 12/12/88. Overall coal use
provided from @% to 62% for the heating demand of 23 participants.
The mean being 16%. During this period, for the 23 participants,
coal displaced approximately 185@ gallons of fuel.
Analyzing the two metered homes, the period of 11/1/88 to 12/12/88
was selected due to the quantity and quality of the data taken.
During that 42 day period the coal participating home consumed 251
gallons of fuel and about 2290 pounds of coal. The non-coal
Participant consumed 337.8 gallons. The non-coal user consumed
86.8 gallons of fuel oil more than the coal user. This represents
about a 25% reduction in fuel oil usage for the coal-user.
5.@ PROJECT COST
5.1 General
The Atqasuk Coal mine Project Phase II, as part of the overall
energy resource development project, has provided much technical
and social data required to, develop appropriate mining methods,
demonstrate the applicability of modern coal stove technology and
assess the social acceptance, desires, and capabilities of coal
mining and end use by NSB residents.
5.2 Cost Breakdown
The NSB demonstration project represents the second mining effort
at the old Meade Rive Coal Mine. The project costs presented
include the cost of stove installation, mining, coal distribution
and project management.
Total project costs were $210,000. The test mining cost category
represented 25% of the total project budget. Table 5-1 presents
the project cost breakdown.
It should be noted the cost associated with all phases of the
project except for the installation of stoves are not
representative of cost conditions that would prevail under normal
operating conditions. The project scale is to small to provide
valid economic data to determine mining feasibility. Further, the
field effort was a test mining one that contained non-productive
costs that were necessary to get the field program up and running.
Overall mining costs are lower compared to last year due to the
elimination or reduction in non-recurring costs such as permitting
and initial mine planning and reconnaissance performed during
Phase I.
TABLE 5-1
Project Cost Breakdown
Project Management. .............48 2.84 8884 - $108,074.62
Administration $ 40,947.97
Project Coordinator 28,425.50 Development Plan 38,701.15
Mining Operation ...........0. 0.8 208 28 08 -$ 52,536.88
Field Supervisor 21,579.67 Supervisor Subsistence/Travel 5,940.12 Material 11,808.09 Rental 125.00 Labor 13,084.13
Coal Distribution ............0..0.2.222.288. -$ 5,687.99
Materials/Freight 4,859.99 Labor 828.00
Installation. ............ 2.0.28 084 2.2 eee -$ 43,700.57
Installation Supervisor 10,930.50 Supervisor Subsistence/Travel 7,114.59
Materials/Freight 18,324.17 Labor 7,331.25
Total $210,000.00
There were substantial increases in Project Management due to the
Village Project Coordinator (VPC) performing the coal distribution
tasks of the project. The VPC cost increased by 264% over last
years Program while the coal distribution cost category decreased
by 25% even though 100 more tons was extracted during Phase II.
In addition the Project Management category included the new sub-
category Development Plan.
6.@ PROJECT WORK FORCE
6.1 General
All labor requirements, except for field and installation
supervision were obtained through hiring North Slope residents from
the village of Atqasuk. The Project Village Coordinator (PVC)
maintained an employment list for the community. The PVC was
responsible for selection of the workers when notified by the field
supervisors that an employee was needed or a job became vacant.
6.2 Work Force Profile
The NSB Atqasuk Coal Mine RELI Project Phase II employed 9 Atqasuk
residents and four Barrow residents from September 12, 1988 to June
30, 1989. This project provided 1366 hours of work for the Atqasuk
work force. The total hours are below the original proposed crew
hour estimate of 1800 hours. This is due to the relative ease of
mining the coal.
The largest employment sector was in mining, with 6 workers, (46%
of total). In addition to mining, there were employed 2 stove
installers, (15 % of total), 1 project coordinator (8% of total),
and 4 expediters in Barrow (31%).
Personnel and job classifications are presented in Table 6-1.
TABLE 6-1
Project Personnel Employment List
Village Project Coordinator
Leroy Gunderson
Coal Mining Employees
Alfred Shugluk
Mike Shugluk
Tommy Shugluk
Robert Simmonds
Paul Bodfish
Mary Gunderson
Village Installers
Jack Ahkivgak
Ronald Brower
Expediters
Joe Akpik
Martin Oktolik, Jr.
James Tegoseak
Oliver Angashuk
6.3 Labor Cost
Labor costs for the entire project amounted to 27% of the overall
project cost. This is about 8% greater than Phase I. Labor cost
are presented in Table 6-2. Labor cost associated with mining make
up 23% of the total labor cost, a reduction of 15% over last year,
and 25% of the mining costs. The lower labor cost percentage for
mining reflects the additional labor required to distribute twice
as much coal as in the previous year. Further the village project
coordinator (VPC) distributed all the coal unlike the previous
year, therefore the majority of the local labor costs for
management and administration category is mostly the VPC’s efforts
in distributing coal.
Major Cost Categories
Management Fees and
Administration Cost and Mine
Planning
Mining and Stockpiling
20@ tons of coal
Coal Distribution
Stove Purchase and
Development Plan
TOTAL
TABLE 6-2
Project Labor Cost
52,540
5,690
43,700
38,700
$210,000
Project Cost
2s
25
@3
21
Local Labor Cost
$ 28,400
13,100
830
14,600
-Q-
$ 56,930
7.@ RECOMMENDATIONS
7.1 Mining
Future mining towards the South and West will have a high
probability of intersecting the old underground workings. Opening
a new pit away from the underground workings will be quite
expensive, as some 12,000 yd’ of overburden excavation will be
required, and the site would have to be drilled to establish
stratigraphy and coal reserves. Due to the high cost of developing
anew pit, it would be impractical to backfill it each season and,
therefore, dewatering would be required.
It is the writer’s opinion that in light of the present limited
mining program, future mining be directed to the immediate
Northwest of the old workings intersected during the 1987 season.
The final pit size should be at least 60 foot by 6@ foot at the top
the mining horizon. Any underground workings intersected should be
checked for methane immediately upon their being located.
A mechanic should be made available at the start of each shift’s
work to help get the equipment running and, also, at the end of the
shift to correct any problems that have developed.
During the spring of 1989 operations, no transportation was made
available for the mining supervisor. He subsequently used one of
the DJB trucks. Arctic Sloped Consulting Group has two Sno Tracks
available. One of these would work very well for transportation to
the mine from Atqasuk.