Loading...
HomeMy WebLinkAboutConceptual Design & Cost of a 30 Megawatt Coal Fired Power Plant for Kodiak AK 1981 sal na 2 rae Mates ER EBASCO SERVICES INCORPORATED i a tet lg htt re adh See fie a 4 1.0 2. Ss 0 0 2.1 2.2 2.3 2.4 Zoo COST 3.1 Bd 3:3 3.4 PROCESS AND AUXILLIARY SYSTEM DESCRIPTION... . FUEL SUPPLY... SITE SERVICE CONSTRUCTION TABLE OF CONTENTS 1-1 . 1-2 . 2-1 . 2-1 2-15 . 2-16 2-17 . 2-18 « 3-1 3-1 3-4 . 3-5 The plant site required is some 30 acres including fuel handling and storage, the power plant itself, the ash handling systems and pond, and buffer zones for aesthetic protection. Figure 1-1 is a general pictoral view of the facility. 1.2 GENERAL PERFORMANCE CHARACTERISTICS The plant is designed to burn coal from the Usibelli mine. This coal is low in sulfur and has a higher heating value of 8,000 Btu/1b. The heat balance of the steam generator is shown, in simplified form (without blowdown and associated steam and heat recovery systems) in Figure 1-2. The heat balance of the power generation cycle is shown in Figure 1-3. The steam generator has a calculated thermal efficiency of 80.4 percent and the power generation cycle has a heat rate of 9,437 Btu/kWh. Therefore, the overall plant heat rate is calculated at 11,738 Btu/kWh (the power plant efficiency is 29.1 percent). On that basis the plant consumes 22 ton/h of coal and discharges 2.5 ton/h ash. The technical description and cost estimate of this plant are presented in subsequent sections. 1-2 COAL STORAGE PIEE STEAM | GEN. BUILDING COAL BARGE OFFLOADING J COAL TRANSFER BUILDING PICTORIAL VIEW, 30 MW PLANT DRY STACK GAS H,0 IN STACK GAS 2 H=63.4 H=1176 RADIATION & OTHER M=315.3x193 M=26. 8x102 Q=7.04x106 Q=20.0x10 Q=31.5x106 % T=350 T=350 HIGH PRESSURE STEAM > H=1453.1 M=270,600 ¢ Q=393.2x10 T=900 AIR (%xcs=20) H=0 M=303.1x103 FEEDWATER a Q= are HE T=80 H=406.9 H=270, 600 Q=110.1x10 T=430 H=8000 M=44.03x103 Q=352. 3x10 T=80 ASH AND UNCOMBUSTED FUEL H=2..8 M=4.99x103 Q=10.6x106 LEGEND: H=Enthalpy (Btu/1b) M=Mass (lbs) Q=Heat Flow (Btu) T=Temp (°F) FIGURE 1-2 SIMPLIFIED HEAT BALANCE OF STEAM GENERATOR HEAT BALANCE OF POWER GEN STEAM GENERATOR FIGURE 1-3 270 ,600# 865P-906°F-1453. RATION CYCLE ! | \ | | | - 183634 & L 1.5"HgA 1377.4n id id ae | 147048 \ | & 1303.24 ft 1 I | | \ \ | 10316# al r P 1228.51 SIs ! | |= | | | - = | 1 9454 a te 1439. 4H 8 wo 7 = 3 Bis § a “ale . = 8 elk 7 g =o scuba oe “Ta #5 Heater #4 Heater 45 eee cE #2 Heater #i Heate ; 169.5? Deaorator | SINS |g. 41P 8.35P 2706004 A 2706008 AP 70. 6P 4, 224,3554 a 224,3554 224,355# 430° 383.2 303.5° 179.8" Vv 94.0" 4o7h | ssertn 337.0h S°FTTO 273.2h 5° FTTO | 148.0h_p | 5° FITO| 62.4h oF FTO Tor Fv } jo? FTTO _ [tor FTO] TO” FTO 183634 330674 144204 gee 315.9° 189.8° 346.4h 286. 2h 157.8h 2706004 = 317634 305.9° : 277.6h eo LEGEND: - Enthalpy, Btu. 1b - Temperature, °F - Flow, Lb/Hr - Pressure, Psia Generator Output 30,000 _kW 1921034 994.3H 72.0h 2.0 TECHNICAL DESCRIPTION 2.1 PROCESS AND AUXILIARY SYSTEM DESCRIPTION 2.1.1 Overview Coal-fired steam-generating stations of today's design are a well known technology. Mechanically pulverized coal is mixed with air and blown into a —— furnace for combustion. The furnace contains walls of tubing filled with high pressure water which is generated into steam by the thermal energy of the combustion process. The steam is then exposed to a hot gas stream and becomes superheated by absorbing more energy. The energy contained in the steam is then piped to the steam turbine where the energy is transformed into mechanical energy. High pressure steam is converted into mass velocity by pressure reduction and blown into the turbine blades. This process con- verts the mass velocity to mechanical rotating energy (controlled wind-mil] principle) which in turn drives an alternator (generator) producing the electricity. The steam after releasing all of its usable energy is condensed by cold water and pumped back into the steam-generator for reuse. The station's design parameters have been selected to include throttle steam at 865 psig/900°F. The process shows the steam-generator being fed with 20 to 25 tons of coal per hour to generate 270,600 pounds per hour (1bs/hr) steam. The coal is fed into the furnace by a spreader stoker, Particulate and NO. emissions are reduced by staged combustion or by recirculation of combustion gases. The other antipollution controls are in the exhaust of the steam-generator, including a lime slurry FGD system for sulfur dioxide (S05) suppression, and a baghouse for particulate collection. The furnace will also have steam sootblowers on the tubing wall which will permit cleaning of the heat exchange surfaces during operation. The steam from the steam-generator is expanded in the turbine. The turbine exhausts to the condenser which operates at a vacuum Corresponding to the vapor pressure of the exhausting steam. Noncondensable gases are removed by vacuum pumps. The condenser is cooled by ocean water adjacent to the plant site. 2-1 The condensate from the steam cycle is pumped from the condenser through two heaters fed by extraction steam from the turbine to the deaerator where any gases including oxygen are removed from the water. From the deaerator the feedwater is pumped again through two heaters, fed by extraction from the turbine, back to the steam-generator. The feedwater temperature at the steam-generator is about 430°F where it is further heated by an economizer. The plant arrangement is shown on the plot plan (Figure 1-1). The basis is the arrangement of the turbine building and the steam-generator (boiler) with its accessories which lead to the stack. The basic arrangement of the turbine building and boiler building has been chosen for compact design minimizing the length of major piping. This arrangement can be turned as a block in any direction to suit the transmission line direction and/or the fuel delivery system and water supply system. For estimating purposes it is assumed that the plant is at least 1/10 mile from the waterfront unloading facilities. The site is assumed to be basically flat and rocky. It is adjacent to the Coast Guard Station to avoid problems of access to a remote site. 2.1.2 Fuel Handling System Coal Unloading Station The type of coal unloading station required for the plant is dependent on the coal transportation system. Coal will be delivered to the Kodiak site by barge. The type of coal unloading station required is a function of the mode of transport of the coal and the size of the power plant, hence the fuel requirements. In this case the coal will be transported to Kodiak by barge. The size and heat rate of the power plant have been stated previously. 2-2 The coal unloading station, therefore, consists of a 700 TPH clamshell barge unloader and a vibrating feeder discharging to a belt conveyor. The coal is transported to a distribution shed and then to outside storage (see Figure 2-1). Stacking and Reclaiming Initial coal deliveries at both sites will be used to establish a 32,000 ton (60 day) compacted dead or long term storage pile. The cap over the dead storage pile will be used for a 6000 ton live storage pile. The live storage capacity will be an 1l day supply at full load plant operation. Once the dead storage pile has been established and compacted, subsequent coal deliveries will be transported by an inclined/overhead conveyor tripper from the unloading hoppers to form the live storage pile. The belt tripper will be enclosed and weather protected the entire length of the live storage pile. The entire coal storage pile (dead and live) will be approximately 600,000 ft. It will occupy a space of about 1/2 - 2/3 acre. The coal will be reclaimed by a front end loader feeding to yard reclaim hoppers. The reclaim hoppers discharge to inclined conveyors that will take the coal to the coal gallery. There, the coal will be transferred to conve yors feeding the plant silos. Plant Storage In-plant silo storage capacity will be 40 hours. The silos are situated above the mills for gravity feed and will be provided with a fire protection system. 2.1.3 Steam-Generator The energy in the coal must be converted to high temperature and pressure steam in order to produce useful work. This process takes place in the steam-generator or boiler via coal combustion. The steam-generator for this 30 MW station will be an indoor spreader-stoker type designed to burn 2-3 MALIN ESIC FEPAKATIR 7 TELESCOPIC CAYTLE Tare O20 fons SODAYS BUCK INACSIVE FILE ST Re bret WBRATING ——b Ie FEE OER 0-125 J2H ~— WIDRATING FKLDER Q-725fPN LY?) METAL DES. —~ > WARATING FLEDER~ AMO CHUTES To } 125 [PH a= UT NO 2 r. FupeRe cages 1 , tn ING GRANMATOR mz (25 77H Ge. c4 2 INY WO SA CSS 725 7ev° FE S/LO soo L2NS 300 fons EBASCO SERVICES INCORPCRATED |ALASHA POWER AUSHOR/TY 5786 Oly. Aicw CR Ae APPROVED KOO/AK (5LAND PLANT ‘ane COAL AUNDLING FLOW DMG UNIT NO f° - loareasien run-of-the mine coal. The design parameters for the steam-generator are presented in Table 2-1. The boiler, turbine operator, and air quality. control systems will be housed in a single enclosed weatherproof building. The building will be of steel construction insulated with aluminum sandwiched insulation suitable for the environment. 2.1.4 Turbine-Generator The steam produced in the steam-generator is conveyed to the turbine where the steam's energy is converted to mechanical energy. The turbine rotor is connected to the generator which, when rotated, produces electricity. The turbine is to be of the 30 MW rating with five extraction stages and bottom exhaust. The five extractions are to be used for feedwater heating for the boiler. Turbine design conditions are as follows: Throttle pressure 865 psig Superheat Temperature 900°F Turbine Backpressure 1.5 in. Hg Final Feedwater Temperature 430°F The generator is to be designed for maximum capability of the turbine with a power factor of 0.85 and all cooling and sealing equipment is to be included. All equipment is to be designed for indoor installation. The turbine-gener- ator is to be equipped with all local and control room supervisory instru- mentation, including valve testing station and protective devices. Oil reservoir, oil cooler, and A-C and D-C oi] pumps as well as the gland seal system including piping as normally supplied with the turbine-generator, are to be included. In addition to the turbine-generator, condenser, condensate pumps, some of the feedwater heaters, feedwater pumps and other miscellaneous equipment, the building will also contain the control room, water transfer pumps, service water pumps, instrument air compressors, service air compressors, demineralizers, and motor control centers. 2-5 TABLE 2-1 STEAM-GENERATOR DESIGN PARAMETERS Steam Flow At Superheater Outlet Steam Pressure At Superheater Qutlet Steam Temperature At Superheater Outlet Feedwater Temperature At Economizer Inlet Coal Heating Value Ash Content of Coal Moisture Content of Coal Sulfur Content of Coal Nitiogen Content of Coal Ash Softening Temperature Hardgrove Grindability Factor Ash Sodium 270,600 1b/h 865 psig 900°F 430°F 8000 Btu/1b 8-10 percent 28 percent 0.2 percent 0.6 percent 2350°F 25 0.1 percent 2-15. Etectrical oP brant Ratings of the major pieces of electrical equipment are as follows: Ue - Generators, 35,294KVA; 0.85PF, 30MW, 20KF ve - Main Transformers, 12.5 delta to 69KV - Auxiliary Transformers, 3 winding 20MVA, delta to 4.16/4.16KV delta - Startup Transformer, 3 winding 20MVA, 69KV delta to 4.16/4.16KV wye - Switchgear 4.16KV medium voltage - Power Centers, motor control centers distribution panels etc. as required 2.1.6 Heat Rejection System The steam exiting the turbine is cooled to increase pressure differential across the turbine which subsequently causes the turbine to spin. In the cooling process, the steam is condensed and returned to the boiler for reuse. The cooling is effected in a heat exchanger (i.e., condenser) where an “outside" coolant (i.e., circulating cooling water) is used to cool the steam. The condenser is to be a single shell two pass with divided water box and hotwell. The hotwell is to have enough storage to allow proper level con- trol for surging and shall be properly baffled to keep the condensate at saturation temperature. The condenser shall include Muntz Metal tube sheets and inhibited Admiralty tubes with 70-30 copper nickel tubes in the air removal sections and the impingement areas. The condenser is to be shop fabricated including tubing and should be suitable for sea and barge ship- ment. The condenser will be used in a once through cooling application. For purposes of estimating an inexpensive intake channel along the bottom of Women's Bay was assumed. Lined 36 in. carbon stcel pipe was assumed for incoming and discharge water. It should include a condenser neck with dogbone type rubber expansion joint for connection to the turbine exhaust. Condenser design data are as follows: 2-7 Heat load 191 x 10° Btu/hr Tubes 1" 18 BWG x 36 ft Maxixmum Water Velocity 6.5 ft/sec Backpressure E.5. th. HG Circulating water pumps of the vertical pit type will be used. Traveling screens will be installed to protect the equipment from fish. 2.1.7 Water Quality Control The station water uses for a 30 MW coal-fired steam electric plant have been estimated for a Kodiak Island, Alaska location. Uses were determined for once-through marine cooling with wet ash sluicig system. A detailed water balance is presented in Figure 2-2. This system employs a flue gas desulfurization system (FGD), and a baghouse as required. Ash generation is assumed to average approximately 2.5 ton/hr (bottom ash plus collected fly ash) at full capacity. Ash Hendling System The system employed uses wet ash handling. This system is depicted in Figure 2-3. Due to regulatory changes and uncertainties, this would have to be reevaluated if more detailed design were contemplated. Significant to note is the fact that transport water from the ash ponds will be recycled. Ash ponds will be developed on 5-year increments and revegetated. Floor Drainage Treatment Facility This facility will provide treatment for the removal of suspended solids and oi 1/grease and will require both a primary and secondary treatment stage. The primary stage will consist of a gravity oil/water separator which will accomplish both suspended solids and floatable oi] removal. The secondary p———._ 70 RECEIVING t aep LLDTREAM EVAPORATION | t | | geet cl | . ‘S ~ | r A *| 2.0) | [ | aa ye re | Wl eelee L | coal | Fiz, Floor | | warer | DEMINER | rr { | | srozMae} 2] | prune & | iMrerseatrentL/* 4) uizer fy! i \ Ht ! Bo | WoPPERS | | Sysrem | j AREA | BIC | Summ | | system SYSTEM | Weal 1 ! } | } tl A IIA ! | : : if | | | oO. | aK lis i a8 T 4 aTTRPRLHI 1 | | c eur | | tere & | | { NECTION | BoT7omM K——-——-— | | rice ery ASH \ 14h | | TROUSH | OVERFLOW fy eats ai BRE | COOLING Kale ae WATER { coutection [* ‘i | 7 ee +— DISCHARGE LINE 32,4 ASK DISPOSAL AREA ( Asts Ovpesol Pend) Jo.° | RUNOFF | | | | \ | HOLOING | | | POD | | | | bal [ | | | | | OLDING 4 | | | ) BASIU a | | | ay | | CONVEYOR, | PEEP | | i i 7 i ¥. — uw 2 | 2] | Jou /usten | | SANITARY | Eaucuirarion| 2 T | By | | jvast EMATER | MID | byt SEPARATOR, xh | | TREATMENT /NEuTULATSA | o2s } ae | ¥ T 30.0 d.0) v0 val 1 vy \ ! j NOTES: I-ALL FLOWS ARE EXPRESSEDIN GALLOUSTER MINUTE (GPM). 2- FLOWS ARE OMILY AVERAGES AT 100%}. CAPACITY FACTOR. ~.| PATER Teer ree 22:2 Minin a DLvu0Ees 4, WaATreR Cows i 3. Zz FIGURE 2-2 AUXILIARY Cooling ln cae x WATER BALANCE DIAGRAK ‘| EBASCO SERVICES INCORPORATE 2 oy BOTTOM ASH HOPPER | ae ie cae | OACR FLU Sy WATER XI » oo lee { 7] ) PRESSVYKE PunPsE VA CUAL ~ ian HYORIVEVOR ~ a FIA [LK i \ | LESTER | GRAVITY FELD +) Shee ASH. PONG =. ep Lope 2/007 2 SLURKY [RANSLER PUMPS 22/0048 ALSURN WATER PUN PS | SASCO SERVICES INCOAPORATED | ALASKA PIV AWHORILY STG AES TASK APPROVED “ KOO/AK 151ANO PLAN, ae Se £1 SK-2 stage will consist of treatment for the removal of emulsified oils utiliz- ing either cartridge type separators or chemical coagulation. This prefab- ricated facility will be designed to handle an average daily flow of 5 gpm. The treated effluent will be discharged to the wastewater collection pump for reuse. Yard and Area Drainage System The yard and drainage system will effectively convey all runoff from the plant site to minimize potential site flooding. This discharge is not con- sidered to be a pollutant source or wastewater requiring treatment because no contamination of this discharge will occur on-site due to either process or materials storage activities. Coal Pile Runoff Holding Pond Facility Runoff and filtrate from the coal storage pile will be directed to collect- jon ditches located on the periphery of the pile and then conveyed to the coal pile runoff ponds for treatment prior to disposal to the yard and area grainage system. The holding pond will provide gravity settling for coal fines (suspended matter) washed out of the pile and pond effluent in excess of the design storm event will undergo pH adjustment, as necessary, to a range of 6.0 to 9.0 by the addition of caustic reagents. 2.1.8 Air Quality Control Due to the low sulfur content in the coal (0.2 percent by weight) and the stringent emission requirements of the New Source Performance Standards, the air quality control configuration for the plant will be a semi-dry flue gas desulfurization (FGD) system followed by a fabric filter baghouse. The FGD system will consist of two spray dryer vessels using a lime slurry. The FGD system will be designed to remove 70 percent of the sulfur dioxide from the gas stream at the unit's rated load. Control of the spray dryer will be governed by both the temperature and $0, concentration of the exit 2-11 flue gas. The flow of lime to the system will average 150-200 pounds of lime per hour. Lime pebbles will be hydrated on-site by a single slaker and Pneumatically transported to two storage silos each located near a spray dryer. These silos will have a 6-month holding capacity. From the silos, the hydrated lime will be pneumatically transported to mixing tanks provided below each spray dryer vessel. The two mixing tanks will be sized at for 10-day capacity. The fabric filter baghouse for particulate removal will consist of four parallel rows of compartments. Fabric filters will be designed to achieve a particulate removal efficiency corresponding to a maximum emission rate of 0.03 1b per 10° Btu heat input to the boiler. Filter Cleaning will be by both reverse air and shaker methods and will be automatically programned to be activated every 1/2 hour to 1 hour. Filter bags will be synthetic fabric coated with acid-resistant polymer resin for a service life of approximately 3 years. Continuous baghouse hopper ash removal will be required. 2.1.9 Ash Handling System A steam-generator which burns coal containing uncombustible mineral matter produces solid refuse classified, in general, as aSh. The ash is of two types: bottom ash/slag and fly ash. Bottom ash is the material dropped out of the combustion products in either a dry or molten state to the furnace bottom and collected in water impounded bottom ash hoppers. Fly ash consists of fine particles which leave the furnace with the flue gas and are collected in the baghouse system. The total quantities of ash to be generated are a function of the ash con- tent of the coal and the steam-generator coal firing rate. Based upon the plant's design specifications discussed in previous sections of this report, and assuming a fly ash/bottom ash ratio of 40/60, the anticipated quantities of ash are as follows: 2-12 Average Maximum Total Ash Production Rate 2.5 tons/hour 3.0 tons/hour Bottom Ash Production Rate 1.5 tons/hour 1.8 tons/hour Fly Ash Production Rate 1.0 tons/hour 1.2 tons/hour Bottom Ash The bottom ash will be continuously removed from the boiler. A water-filled trough is to be located below the boiler hopper openings and will contain a conveyor arrangement. This equipment will be sized for a maximum capacity of 3.0 tons per hour based on a maximum coal ash content of 10 percent. Flyash The flyash collected in the baghouse hopper and in the duct hoppers and the baghouse, will be transported to a flyash storage silo. 2.1.10 Solid Waste Disposal System From the storage silos located at the plant site, all plant solid waste will be trucked to a permanent solid waste disposal site, assumed to be situated in close proximity to the plant island. 2.1.11 Other Major Plant Equipment Condensate Pumps Two (2) vertical motor driven canned pumps designed for indoor installation are required. Each will have a capacity of 50 percent with the thrust bearings in the motors. The capabilities of each pump and motor are as follows: Condensate Temperature 92°F Condensate Flow 224 x 103 lbs/hr 2-13 The condensate pump length should be such that the NSPS required will not exceed the elevation of the suction flange when running at 130 percent of design capacity. The pumps shall be designed for parallel operation over the full range. Feedwater Heaters The feedwater heating system will have 4 closed type feedwater heaters and one open type feedwater heater (deaerator). The closed type feedwater heaters consist of 2 high pressure heaters and 2 low pressure heaters. The heaters will be of bolted head design. The high pressure heaters are of the integral desuperheating and draincooling design. The low pressure heaters are to have integral drain coolers. The high pressure heaters will cascade drain to the deaerator and the low pressure heaters will cascade drain to the condenser. All heaters shall be of the U-tube removable shel] design complete with roller type supports. The deaereator mounted on top of a five-minute capacity storage tank is to be integrally connected and equipped with stainless steel troughs and baffle plates. All nozzle connections for steam and feedwater are to be provided as nonnally required in a modern power plant for indoor installation. Design conditions for the deaerator are as follows: Water Storage 20 x 103 Ib Water Flow (In) 224 x 108 Ib/hr Water Flow (Out) 271 x 109 1b/hr Design Pressure 110 psig Operating Presure 70 psia Feedpumps Two (2) motor driven 50 percent capacity feedpumps and one hot standby turbine driven feed pump for indoor installation will be required. The feedpumps are to be of the multistage barrel type with an interstage takeoff for reheat desuperheating. Each feedpump is to be complete with motors, 2-14 shaft driven and electric driven oil pump, oi] cooler and oil tank, all mounted on a common base plate. The glands are to be sealed by mechnical seals. Each pump is to be designed for the following capability: Feedwater Temperature 310°F Feedwater Flow 271 x 10° 1b/hr Suction Pressure 100 psig The pumps should be able to operate out to 130 percent flow and the charac- teristic should be steadily rising toward shut-off without exceeding 120 percent of the design head. 2.2 FUEL SUPPLY The fuel supply is assumed to consist of Usibelli Mine coal, similar to that burned at the Healy 25 MW power plant. This coal has a higher heating value of 8,000 Btu/1b, a maximum moisture content of 28 percent, a typical ash content of 8 to 10 percent, and a sulfur content of 0.2 percent. All of the coal will be barged to the Kodiak site. Assuming a power plant Capacity factor of 80 percent and a heat rate of 11,740 Btu/kWh, some 154,000 tons/yr will be required. 2.3 SITE SERVICES The construction and operation of a 30 MW coal-fired power plant will require a number of related services to support all work activities at the site. These site services could include the following depending upon the actual location of the power plant: o Access Roads o Landing Facility o Labor Camp 2-15 2.3.1 Access Roads Gravel roads with a 9-inch gravel base will be required to connect the Plant site with the equipment landing facility. This road will be of minimal length. 2.3.2 Landing Facility The site will require construction of a marine landing facility to receive all construction materials, equipment, and supplies. This would be built in concert with the coal unloading facility. 2.3.3 Labor Camp Due to the need for over 100 workers on site a labor camp was assumed. Its costs include site preparation, development of a potable water supply, housing, sewerage and garbage disposal, recreation facilities, power supply, and managerial and supervisory office buildings. It is considered as an individual cost. Facilities built for the labor camp will be retained as part of the permanent installation as appropriate (e.g., wastewater treatment). 2.4 CONSTRUCT ION The number of workers necessary for construction of a 30 MW station will vary over the approximate three year construction period. Construction of this facility will require about 750,000 man-hours or 375 man-years of labor. Construction of this 30 MW station will follow nonnal acceptable consiruc- tion methods. While the steam flow exceeds the limits of packaged boilers, a modular design may be employed. A program of this magnitude begins with orderly development of the following requirements: 2-16 1) Utility services, such as electric light and power, water for industrial and potable use and fire protection, sanitary facilities, telephone communications, etc. 2) Temporary construction office facilities (with heating and ventilation furnished by contractors as required). 3) Temporary and permanent access roads, and railroad spur if required. 4) Temporary enclosed and open laydown storage facilities. 5) Oelivery of various types of construction equipment and vehi- cles, such as earth-moving equipment, concrete and materials hauling equipment, cranes, rigging equipment, welding equipment, trucks and other vehicles, tools, and other related types of construction equipment by truck, rail, or landing craft or a combination of these depending on the site. 6) Temporary office and shop spaces for various subcontractors. 7) Settling basins to collect construction area storm runoff. 8) Perinanent perimeter fencing and security facilities. 9) Safety and first aid facilities in strict compliance with OSHA regulations. Following completion of these initial construction site related activities, power plant systems construction will be initiated. 2.5 OPERATION AND MAINTENANCE When the coal-fired steam-electric power plant begins commercial operation, the facility will provide employment for approximately 35 employees, including a superintendent and assistant superintendent. The estimate of the plant's staffing requirements is based upon conversations with the superintendent of the Healy Plant of Golden Valley Electric Association. Employment of these personnel will continue throughout the 35-year life of the plant. Plant systems will be operated from the control room located in the main plant building. Some of the systems and equipment will also be controlled from local stations. In general, controls are automatic, although operators 2-17 can override the automatic controls and operate the plant Manually. To supplement the operational controls, the station will be equipped with an alarm system, fire protection system, Proper lighting, and a radio-telephone communication system. To prevent mechanical failure, periodic maintenance will be performed on all pressure systems, rotating machinery, heat sensitive equipment, and other operating equipment for malfunctions, leaks, corrosion and other such abnor- malities. In addition, the maintenance programs will monitor the revegeta- tion and erosion prevention programs initiated during the cleanup phase of construction. Trained maintenance crews will perform operational mainte- nance and will correct emergency malfunctions. In general all major maintenance functions will be performed during the plant's annual scheduled outages. The length of time required for these scheduled outages is estimated to be approximately 675 hours per year. This value corresponds to a scheduled outage rate* of 8 percent. * Scheduled Outage Rate = Scheduled Outage Hours x 100 Service Hours + Scheduled Outage Hours 2-18 3.0 COST ESTIMATES 3.1 CAPITAL COSTS A conceptual cost estimate for this 30 MW power plant has been developed, and is presented in Table 3-1. This cost estimate assumes "overnight construction." There are no allowances for interest during construction, price escalations over time, or other similar factors. The cost estimate is conservative, and has an accuracy level of #25 percent. 3.1.1 Basis of Capital Cost Estimate This conceptual cost estimate is based upon the Ebasco Code of Accounts rather than the Federal Energy Regulatory Commission (FERC) code of accounts. It is based upon a wealth of specific project experience. The estimate includes all facilities and systems required for an effective, self sustaining unit, except for the following items: chemistry laboratory; barges for coal and limestone delivery; front end loader or bulldozer for coal handling; dredging, if required, for barge unloadig facility; and o oOo Co switchyard and transmission facilities. The estimate of construction costs assumes that the entire job will be performed on a subcontract basis. It has a high labor cost due to the need to employ a work week of six ten-hour days. Additional costs are estimated based upon climate and the resulting construction schedule. Because this is a conceptual cost estimate, the following costs were also exc luded: Oo sales and use taxes; o land and/or land rights; o allowance for spare parts; and O owner-associated monitoring costs. 3-1 TABLE 3-1 CONCEPTUAL COST OF 30 MW COAL-FIRED POWER PLANT FOR KODIAK (1981 x 103) Cost Category Material Installation Total Improvements to Site 400 1,200 1,600 Earthwork and Piling 900 3,400 4,300 Circulating Water System 500 1,000 1,500 Concrete 900 2,900 3,800 Structural Steel, Lifting Equipment, Stacks 1,200 1,000 2,200 Buildings 1,200 2,100 3, 300 Turbine Generator and Accessories 5,000 300 5,300 Steam Generator and Accessories 4,000 2,300 6,300 Other Mechanical Equipment 2,000 600 2,600 Coal and Ash Handling Equipment 3,200 1,400 4,600 Piping 2,400 2,800 5,200 Insulation and Lagging 400 900 1,300 Instrumentation 500 100 600 Electrical Equipment 3,500 3,600 7,100 Painting 100 500 600 Air Quality Control Systems 5,200 4,100 9,300 Waterfront Construction 1,300 1,700 3, 000 Substation 300 100 400 SUBTOTAL 33,000 30, 000 63,000 3-2 TABLE 3-1 (CONTINUED) CONCEPTUAL COST OF 30 MW COAL-FIRED POWER PLANT FOR KODIAK (1981 $ x 103) Cost Category Material Installation Total Allowances for Construction Timing and Scheduling Due to Climatic Reasons 8, 000 TOTAL DIRECT COST 33,000 38,000 71,000 Indirect Construction 9,000 Contingencies ‘ 10,000 A and E Services 7, 000 TOTAL INSTALLED COSTS 97,000 ($3,233/kW) 3-3 3.1.2 Implications of Capital Cost Estimate With respect to the cost estimate, it is of particular importance to note that, while the steam generator (boiler) is too large to be supplied as a package unit, it could be supplied in modular fashion with much of the fabrication occurring at the site of manufacture. It is also of importance to note that the operating pressure of the boiler is sufficiently modest (865 psig) to obviate the need for extensive feedwater treatment. It is also significant to note that these capital costs represent a very early point on the economies of scale curve. This plant is sufficiently large that field erected systems are necessary and all stack gas control systems are required (e.g., S05 scrubber, baghouse). The level of sophistication in plant design is similar to a 100 MW power plant with the exception of a reheat cycle. Thus, the resulting capital costs are $3,233/kW installed. 3.2 OPERATION AND MAINTENANCE COSTS 3.2.1 Operation and Maintenance Costs The operation and maintenance costs for the 30 MW size plant, expressed in 1981 "Alaskan dollars", are as follows: Fixed Costs Staff (35 Persons) $1,070, 000 or $16.71 /kw-yr Variable Costs Operating Supplies and Expenses $ 42, 000/yra/ or 0.2 mils/kwh Maintenance Supplies and Expenses $ 84,100/yra/ or 0.4 mils/kwh a/ Assumes an 80 percent capacity factor. 3-4 3.2.2 Escalation Estimated real escalation of fixed and variable Operation and maintenance costs are as follows: Escalation Year (Percent) 1981 V5 1982 25 1983 1.6 1984 1.6 1985 hg 1986 1.8 1987 1.8 1988 220 1989 2-0 1990 2.0 1991 - on 2.0 3.3 FUEL COSTS Coal could be obtained from a variety of sources for the 30 MW Kodiak power plant. All such coal would have to be barged to the user facility. Recent estimates presented in the Request for Proposal for Cordova, Alaska were $45/ton for Usibelli Mine coal delivered by barge to Cordova. This price would probably not change appreciably if coal were barged to Kodiak. It was further stated that this coal price could be reduced in 5 to 8 years by development of the Beluga coal fields near the Cook Inlet. These coal costs are equivalent to $2.81/Btu x 106. at a heat rate for the power plant of 11,740 Btu/kWh, fuel costs are estimated at 33.0 mils/klh. 3.4 COST SUMMARY Resulting from this effort is a conceptual plant with an installed capital cost of $3,233/kW (#25 percent). 3-5 A summary of 1981 non-capital charges, assuming a capacity factor of De8 Ts as follows: Cost Cost Category (mi 1s/kWh) Labor Sl Supplies and Expenses 0.6 Fuel 33,0 Total 38.7 3-6