HomeMy WebLinkAboutClarifications Questions for RFP 12-11-14Clarifications/Questions for KEA RFP (2014) for Energy Storage Environmental • KEA will provide campus heat will be extended to any battery solution that needs maintenance heat during winter conditions. • KEA has a district heating system for all of its buildings. • There are not any cooling sources currently available. Electrical Interface • A 500 kVa transformer connecting at 480 V is available. If a larger transformer is needed KEA will specify and provide the transformer. • There is an existing breaker and protective relaying for a battery installation. The metering that will be used for the project is an existing EPM 6000 meter Accommodations • KEA has a 3 bedroom apartment with full kitchen and laundry that will be available for installers and be available at no charge. • Food is to be supplied by installers. Shipping Shippers: Barge: Northland Services Alaska Logistics Air: Alaska Airlines Everts Northern Air Cargo Lyndon Air Local Logistics - Added 12-14-2014 In order to simplify the RFP process KEA will assume responsibility for local transportation of the equipment once it reaches the Kotzebue dock. It will be less complicated to have us organize and supervise the local transportation. This will be done in conjunction with the equipment supplier. KEA will assume responsibility for equipment placement once on site. This will be done in conjunction with the equipment supplier. Multiple Responses Multiple bids will be accepted for different sized units