Loading...
HomeMy WebLinkAboutKnutson Creek Hydro Feasibility Study, Final Report v1.1     KNUTSON CREEK   HYDROELECTRIC FEASIBILITY STUDY        FINAL REPORT  NOVEMBER 2013                                Prepared for  PEDRO BAY VILLAGE COUNCIL  P.O. BOX 47020  PEDRO BAY , ALASKA 99647  Prepared by  polarconsult alaska, inc. 1503 WEST 33RD AVENUE, SUITE 310  ANCHORAGE, ALASKA 99503                 This page intentionally blank.       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  i  EXECUTIVE SUMMARY  In 2010, the State of Alaska funded the Pedro Bay Village Council (PBVC) to complete a  feasibility study of a hydroelectric project on Knutson Creek near Pedro Bay Village.  In July  2010, the PBVC retained Polarconsult Alaska, Inc. (Polarconsult) to complete the feasibility  study.  This report presents the results of the feasibility study.  Polarconsult has determined that a hydroelectric project on Knutson Creek is feasible from  technical, regulatory, and economic standpoints.  The recommended project is estimated to  supply 95.6% of PBVC’s current annual electric demand, and approximately 2/3 rds   of the village’s  total building heating needs through interruptible electric heating services.1  The recommended  project provides for significant future utility load growth and is estimated to lower the cost of  electricity for the community by up to 92%, depending on permit terms, financing, final  installed cost, and utilization of excess energy through interruptible electric heating services.   This study evaluated run‐of‐river hydroelectric project configurations at Knutson Creek with  installed capacity ranging from 100 to 1,000 kilowatts (kW), and finds that a 100 to 250 kW  project is best‐suited to the village’s long‐term needs.  The economic analysis identified a 200‐ kW hydroelectric project as the most cost‐effective configuration.    The 200‐kW project has a design flow of 18.25 cubic feet per second (cfs), which is conveyed  from a diversion and intake structure at river mile (RM) 2.59 down to a hydro powerhouse near  RM 1.25 via a 26‐inch‐diameter, 7,080‐foot‐long penstock.  Total gross head is 223.8 feet, and  net operating head at full flow is 206.5 feet.  The hydro powerhouse is connected to the  village’s existing electric distribution system via a 9,900 foot‐long buried power cable.  The  project includes 16,400 linear feet of new roads and trails.    Table ES‐1 Summary of Features for 200‐kW Project  PROJECT FEATURES VALUE  Project Design Flow 18.25 cfs  Normal Headwater Elevation 398.5 feet  Normal Tailwater Elevation 174.7 feet  Gross Project Head 223.8 feet  Penstock 7,080 feet of 26‐inch HDPE  Net Project Head at Full Flow 206.5 feet  Turbine Type Single Crossflow Turbine  Installed Generating Capacity 200 kW  Plant Capacity Factor 85.8%  Primary Power Lines 9,900 feet  Communications Lines 18,000 feet  Access Trails 16,400 feet                                                          1 Terms are defined in the Acronyms and Terminology section of this report.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  ii  To capture the full benefits of a hydro project on Knutson Creek, the village will have to refit its  community buildings and homes with interruptible electric heating systems.  Interruptible  electric heating systems powered by the hydro project will supply approximately 85% of the  annual space heating needs of seven community buildings and approximately 53% of the space  heating needs of all 33 homes in the village.  Existing electric utility load will use 12% of the  total energy output of the hydro project, and interruptible electric heating services will use  another 73%.  The remaining 15% of project output occurs during the summer months and is  unused, but is available for future growth or new beneficial applications.   The recommended project was evaluated under several hypothetical load growth scenarios and  maintains a BCR of greater than 1 over a range from ‐45% to at least +570% of existing utility  load.  Economic analysis of the project indicates it has a benefit‐cost ratio of between 1.18 and  2.00 compared to continued reliance on the diesel power plant.    Project economics include the benefits realized from interruptible heating applications.  If  interruptible heating applications are not developed in conjunction with the hydro plant, the  project benefits are limited to the value of fuel displaced at the diesel power plant, and the  benefit cost ratio is approximately 0.6 to 0.8.    Table ES‐2 Summary of Project Performance and Economics  PROJECT FEATURES VALUE  ENERGY PERFORMANCE OF RECOMMENDED PROJECT   Total Annual PBVC Prime Load Supplied by Diesel Plant   8,100 kWh (4.4%)  Total Annual PBVC Prime Load Supplied by Hydro Plant   174,100 kWh (95.6%)  Total Annual PBVC Prime Load (at generation) 182,200 kWh  Total Hydro Energy Dispatched to Supply PBVC Prime Load  174,100 kWh (11.6%)  Total Gross Excess Energy Dispatched to Interruptible Electric Heating Services 1,090,300 kWh (72.5%)  Remaining Excess Hydro Energy 239,300 kWh (15.9%)  Total Annual Hydro Generation 1,503,700 kWh  ECONOMIC EVALUATION OF RECOMMENDED PROJECT  Estimated Total Installed Cost (permitting, design, and construction) $4,502,000  Annual Reduction in Utility Fuel Purchases due to Hydro Project  16,600 gallons  Annual Reduction in Heating Fuel Purchases due to Interruptible Electric Heating Services 24,200 gallons  BENEFIT‐COST ANALYSIS Debt‐Financed  Project  Grant‐Financed  Project  Present Value of Project Benefits $7,334,000 $8,280,000  Present Value of Project Costs $6,234,000 $4,132,000  BENEFIT‐COST RATIO OF RECOMMENDED PROJECT 1.18 2.00  Estimated Electric Rate with Hydro Project (Standard Service) $1.255 per kWh $0.065 per kWh                                                                         (Interruptible Heating Service) $0.198 per kWh $0.065 per kWh  kWh kilowatt‐hours     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  iii  The bypass reach of the recommended project includes the upper one mile of anadromous fish  habitat in Knutson Creek, and the project will significantly decrease flow in this reach during the  winter months.  Fish surveys in 2012 indicate the affected reach receives approximately 100  adult Sockeye salmon.  The entire 1.59 mile project bypass reach is also resident fish habitat.    Based on consultations with the Alaska Department of Fish and Game, the feasibility analysis  includes an in‐stream flow reservation of 6.6 cfs at the diversion site, which is ½ of the median  annual minimum flow in Knutson Creek.  A flow reservation would also be supplemented by  significant inflow from tributaries that discharge into Knutson Creek along the project bypass  reach.    In‐stream flow reservations will have a significant impact on the project’s generating capacity  during the winter months, and should be minimized to the extent appropriate through the use  of off‐site mitigation.  This report quantifies the cost of in‐stream flow reservations to the  village, and identifies promising off‐site mitigation projects in the immediate project area.        Based on the findings in this study, continued development of this project is warranted.  Under  reasonable permitting and financing schedules, the project can be built and commissioned in  2016.  The following actions are recommended to advance this project.  (1) Initiate the permitting process for the project.  Key permitting activities include  determining whether the project is under the jurisdiction of the Federal Energy  Regulatory Commission, and continuing dialog with the Alaska Department of Fish  and Game regarding fish habitat permit conditions.   (2) Continue collecting hydrology data at the diversion, gauging station, and tailrace sites  along Knutson Creek, as well as at tributaries R1 and L1, to support efforts to secure a  fish habitat permit with reasonable conditions for the project.  (3)  Advance designs for the project.  Once permit conditions are known, the project  economics and installed capacity should be reviewed to finalize the installed capacity  for the project.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  iv            This page intentionally blank.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  v  REPORT PURPOSE, LIMITATIONS, AND COPYRIGHT NOTICE  Purpose of this Report  A feasibility study is the second stage of screening for a potential hydroelectric project, and  represents a comprehensive review of relevant factors that pertain to the technical, economic,  environmental, and political viability of developing a hydroelectric project at a given site or for  a given power need.  Depending on the available budget and the quality of existing information,  the feasibility study may include field data collection for key information necessary to complete  a technical, economic, and environmental review of the proposed project.   This feasibility study provides the Pedro Bay Village Council (PBVC) an in‐depth assessment of  the overall feasibility of a hydroelectric project at Knutson Creek, and provides information on  the advantages and disadvantages associated with various project sites and configurations.   This information is intended for use by the PBVC to decide whether to proceed with project  development.      Limitations  In conducting our analysis and forming the opinions and recommendations summarized in this  report, Polarconsult has relied on information provided by others, and has assumed this  information is complete and correct.  Also, Polarconsult has made certain assumptions with  regard to future events, conditions, and circumstances.  Polarconsult does not guarantee the  accuracy of the information, data, or opinions contained herein.  The methodologies employed  to perform the analysis and arrive at the conclusions in this report follow generally accepted  industry practice for this level of study.  We believe that the assumptions and methodologies  used are reasonable and appropriate for meeting the objectives of this study.  Future events  and information may result in outcomes materially different from those projected in this study.   Such events and information include, but are not limited to, future energy demand, supply, and  cost in Pedro Bay; actual site conditions such as ownership, topography, hydrology, and  geology; future trends in local construction, material, and labor costs; and national, state, or  local policies that may affect aspects of the project.   The contents and findings of this report are limited to potential development of a hydroelectric  project at Knutson Creek by the PBVC, and are suitable only for this intended purpose.  Any use  of this report and the information contained therein constitutes agreement that (1)  Polarconsult makes no warranty, express or implied, relating to this report and its contents, (2)  the user accepts sole risk of any such use, and (3) the user waives any claim for damages of any  kind against Polarconsult.  The benefit of such waivers, releases, and limitations of liability  extend to Polarconsult, its subcontractors, owners, employees, and agents.     Copyright  This report is copyright‐protected by Polarconsult and may not be reproduced in whole or part  without the prior written consent of Polarconsult.  The PBVC has the right to reproduce and use  this report for purposes related to hydroelectric development of Knutson Creek including,  without limitation, the right to deliver this report to regulatory and funding entities in support  of, or in response to, their inquires and proceedings.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  vi             This page intentionally blank.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  vii  TABLE OF CONTENTS  EXECUTIVE SUMMARY..............................................................................................................I ACRONYMS AND TERMINOLOGY............................................................................................VI 1.0 INTRODUCTION............................................................................................................1 1.1 PROJECT AUTHORIZATION AND PURPOSE ....................................................................................1 1.2 SUMMARY OF FINDINGS ...........................................................................................................1 1.3 PROJECT EVALUATION PROCESS .................................................................................................2 1.4 CURRENT AND PREVIOUS STUDIES ..............................................................................................4 2.0 COMMUNITY PROFILE..................................................................................................7 2.1 COMMUNITY OVERVIEW...........................................................................................................7 2.2 EXISTING ENERGY SYSTEM ........................................................................................................7 3.0 RECOMMENDED PROJECT.......................................................................................... 17 3.1 RESOURCE DESCRIPTION .........................................................................................................17 3.2 OVERVIEW OF RECOMMENDED PROJECT ...................................................................................18 3.3 DESCRIPTION OF PROJECT FEATURES ........................................................................................22 4.0 ECONOMIC ANALYSIS................................................................................................. 27 4.1 COST ESTIMATE FOR RECOMMENDED PROJECT ..........................................................................27 4.2 ECONOMIC EVALUATION OF RECOMMENDED PROJECT ................................................................28 4.3 PROJECTED ELECTRICITY RATES WITH RECOMMENDED PROJECT ....................................................30 4.4 SENSITIVITY ANALYSIS ............................................................................................................32 5.0 CONCLUSIONS AND RECOMMENDATIONS................................................................. 35 6.0 REFERENCES ............................................................................................................ 37    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  viii  APPENDICES  APPENDIX A –  PROJECT MAPS  APPENDIX B –  SITE PHOTOGRAPHS  APPENDIX C –  HYDROLOGY DATA   C.1 Available Hydrology Data    C.2 Stream Gauge Station Information    C.3 Flow Measurements and Station Calibration   C.4 Knutson Creek Hydrology Data   C.5 Knutson Creek Hydrology Model  APPENDIX D –  RESOURCE DATA AND ANALYSIS    D.1 Maximum Probable Flood   D.2 Review of Climate Effects on Hydropower Projects   D.3 Geotechnical Considerations  APPENDIX E –  ENVIRONMENTAL CONSIDERATIONS  E.1 Threatened and Endangered Species  E.2 Fisheries and Wildlife   E.3 Water and Air Quality  E.4 Wetland and Protected Areas  E.5 Archaeological and Historical Resources  E.6 Land Development Considerations  E.7 Telecommunications and Aviation Considerations  E.8 Visual and Aesthetic Resources  E.9 Mitigation Measures  APPENDIX F –   PERMITTING INFORMATION   F.1 Federal Permits   F.2 State of Alaska Permits   F.3 Local Permits   F.4 Other Permits and Authorizations  APPENDIX G –  COST ESTIMATES AND ECONOMIC ANALYSIS   G.1 Project Cost Estimate   G.2 Economic Analysis and Assumptions   G.3 Estimated Utility Electric Rates with Recommended Project  APPENDIX H –  TECHNICAL ANALYSIS   H.1 Hydro Project Modeling   H.2 Project Sizing Analysis   H.3 Evaluation of In‐Stream Flow Reservations    H.4 Different Utility Load Scenarios   APPENDIX I –   DRAFT REPORT REVIEW COMMENTS AND RESPONSES  APPENDIX J –   TABULAR HYDROLOGY DATA  APPENDIX K –   CONCEPTUAL DESIGN DRAWINGS      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  ix  LIST OF FIGURES  Figure 1‐1 Feasibility Evaluation Process Flowchart................................................................ 3 Figure 2‐1 Recent Monthly Peak and Average Power Generation........................................10 Figure 2‐2 Recent Electric Utility and Electricity Costs..........................................................15 Figure 3‐1 Typical Hydro Energy Output and Utilization, Recommended Project................21 Figure 5‐1 Project Development Schedule ............................................................................36 Figure A‐1 Project Overview and Location Map ...................................................................... 2 Figure A‐2 Map of Recommended Knutson Creek Project ......................................................3 Figure A‐3 Knutson Creek and Iliamna River Drainage Basins and Subbasins......................... 4 Figure C‐1 Stage‐Discharge Curve for Knutson Creek Upper Gauging Station........................ 6 Figure C‐2 Stage‐Discharge Curve for Knutson Creek Lower Gauging Station ........................ 7 Figure C‐3 2010‐2012 Knutson Creek Stage and Temperature Data.....................................10 Figure C‐4 2010‐2012 Knutson Creek Flow Data ...................................................................10 Figure C‐5 Daily Flow Statistics for Knutson Creek Based on Extended Record....................12 Figure C‐6 Flow Duration Curves for Knutson Creek at Proposed Intake Site.......................13 Figure D‐1 Bedrock Geology of the Project Area ..................................................................... 6 Figure D‐2 Surficial Geology of the Project Area...................................................................... 7 Figure E‐1 Estimated Knutson Creek Flow at RM 2.1 (Top of Anadromous Habitat).............. 5 Figure H‐1 Typical Daily Performance of Recommended Hydro Project................................. 5 Figure H‐2 Annual Performance Of Recommended Hydro Project (1996 through  2011)....................................................................................................................... 6      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  x  LIST OF PHOTOGRAPHS  Photograph B‐1 Exterior View of Existing Pedro Bay Diesel Power House........................B‐2 Photograph B‐2 Interior View of Existing Pedro Bay Diesel Power House........................B‐2 Photograph B‐3 Upper Gauging Station Looking Upstream..............................................B‐3 Photograph B‐4 Natural Outlet Control Structure at Upper Gauging Station...................B‐3 Photograph B‐5 View of Knutson Creek Reach at Lower Gauging Station........................B‐4 Photograph B‐6 View of Knutson Creek Lower Gauging Station.......................................B‐4 Photograph B‐7 View of Knutson Creek at River Mile 2.2, Looking Upstream..................B‐5 Photograph B‐8 View of Knutson Creek at River Mile 1.5, Looking Downstream.............B‐5 Photograph B‐9 View of Knutson Creek Downstream of Upper Gauging Station.............B‐6 Photograph B‐10 Oblique Aerial View of Lower Knutson Creek ..........................................B‐8 Photograph B‐11 Oblique Aerial View of Upper Knutson Creek..........................................B‐8 Photograph B‐12 Proposed Knutson Creek Diversion Site Looking Downstream...............B‐9 Photograph B‐13 Proposed Knutson Creek Diversion Site Looking Upstream..................B‐10 Photograph B‐14 Oblique View of Proposed Penstock Bridge Site Over Knutson  Creek ................................................................................................................B ‐10 Photograph B‐15 Elevation View of Proposed Penstock Bridge Site over Knutson  Creek ................................................................................................................B ‐11      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  xi  LIST OF TABLES  Table ES‐1 Summary of Features for 200‐kW Project............................................................... i Table ES‐2 Summary of Project Performance and Economics..................................................ii Table 2‐1 Estimated Community Energy Usage by Fuel Type and Purpose........................... 8 Table 2‐2 Existing Utility Generation Equipment ................................................................... 9 Table 2‐3 Recent Electric System Statistics ..........................................................................11 Table 2‐4 Historic Population Data.......................................................................................13 Table 2‐5 Local Demographics ..............................................................................................13 Table 2‐6 Comparative Median Household Incomes ...........................................................14 Table 2‐7 Pedro Bay Building Inventory ...............................................................................14 Table 3‐1 Technical Summary of Recommended Project.....................................................20 Table 4‐1 Estimate of Total Installed Cost for Recommended Project (200 kW).................27 Table 4‐2 Base Case Assumptions Used for Economic Analysis...........................................28 Table 4‐3 Summary of Economic Data for Recommended Project......................................29 Table 4‐4 Estimated PBVC Electric Rates with Recommended Project................................30 Table 4‐5 Sensitivity Analysis Results (Debt‐Financed Project)............................................32 Table C‐1 Summary of Hydrology Data for Knutson Creek..................................................... 2 Table C‐2 Flow Measurements at Knutson Creek and Tributaries......................................... 3 Table D‐1 Maximum Probable Flood at Knutson Creek .......................................................... 2 Table E‐1 Areas of Knutson Creek Subbasins ......................................................................... 4 Table G‐1 Cost Estimate for Recommended Project............................................................... 2 Table G‐2 Economic Analysis of Recommended Project ........................................................ 3 Table G‐3 Estimated Electric Rates with the Recommended Project..................................... 8 Table H‐1 Generation Dispatch Model Variables, Inputs, and Outputs.................................. 3 Table H‐2 Actual and Modeled Electric Demand.................................................................... 4 Table H‐3 Expected Range of Annual Performance for Recommended Project .................... 7 Table H‐4 Range of Project Design Parameters Considered and Recommended  Values...................................................................................................................... 8 Table H‐5 Economic Evaluation of Hydro Project Configurations.........................................10 Table H‐6 Heating Loads for Community Buildings and Homes...........................................11 Table H‐7 Impacts of In‐Stream Flow Reservations on Hydro Performance........................12 Table H‐8 Annual Performance of Recommended Project under Load Growth Cases........13    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc.    November 2013 – Final Report  xii            This page intentionally blank.         Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  vi  ACRONYMS AND TERMINOLOGY  F  degrees Fahrenheit  ABC Alaska Biological Consulting   ADCCED Alaska Department of Commerce, Community, and Economic Development  ADEC Alaska Department of Environmental Conservation  ADF&G Alaska Department of Fish and Game  ADNR Alaska Department of Natural Resources  AEA Alaska Energy Authority    AEE Alaska Energy and Engineering, Inc.   ATV all‐terrain vehicle  AS Alaska Statute  BBNC Bristol Bay Native Corporation, Inc.  BCR benefit‐cost ratio  btu British thermal unit  C.E. Civil Engineer  cfs cubic feet per second  coanda effect   The tendency of a moving fluid to stay attached to a smoothly convex solid  obstruction. A common example is the way a stream of water, as from a faucet,  will wrap around a cylindrical object held under the faucet (such as the barrel of  a drinking glass).   DCRA Division of Community and Regional Affairs (organized under ADCCED).  CPCN  Certificate of Public Convenience and Necessity   discharge A synonym for stream flow. Flow and discharge are used interchangeably in this  report.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  vii  EA environmental attributes. The term “environmental attributes” is used by the  utility industry to describe the desirable aspects of electricity that are generated  from environmentally benign and/or renewable sources. Environmental  attributes are tracked, marketed, bought, and sold separately from the physical  energy. Separating the environmental attributes from the physical energy allows  customers or ratepayers to elect to buy sustainable or “green” energy even if it is  physically unavailable from their electric utility.   excess power, energy, electricity  Electricity generated by the hydro project in excess of the utility’s current load.  Excess energy can be directed to one or more interruptible loads (such as electric  heat) and may or may not have economic value depending on when it is  available and how it is used. At times when there is no beneficial use for excess  energy, water flow into the turbine can be reduced so that no excess energy is  generated.    FERC Federal Energy Regulatory Commission   ft  foot, feet  GDM generation dispatch model. A model used to evaluate the performance and  output of proposed electric generation configurations (diesel and hydro).   HDPE high‐density polyethylene  in. inch, inches  interruptible power, energy, electricity, load, demand  Electricity that is generated by the hydro generator(s) in excess of system  demand (see excess power) and delivered to customers on a special interruptible  basis.  Utility generation and delivery of interruptible electricity starts and stops  without notice based on water availability and other criteria. Interruptible  energy is also called “dispatchable energy” in some documents.  interruptible electric heating service  A special metered electric service that provides energy for space heating, water  heating, or similar purposes.  Electricity is made available to the service only  when there is excess hydro (or other low‐cost) electricity generation capacity  available.  The service is automatically turned off by the utility at times when  utility demand is high enough to require operation of more expensive  generators.  Because the service is interruptible without notice, it is only suitable  for certain uses, and any important uses require a backup system.  Space heating  and water heating are common uses because a building’s existing systems can  serve as backup at modest or no cost.  The interruptible system can take many     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  viii  forms, and can be integrated with a building’s existing mechanical systems (an  electric boiler installed before an oil‐fired boiler, for example), or as an  independent supplemental system (an electric baseboard heater installed in a  building with an existing Toyo stove, for example).     ISER Institute of Social and Economic Research (University of Alaska Anchorage)  ISFR in‐stream flow reservation.  A minimum amount of flow that must be left in a  river or stream during all or certain times of the year.  kV  kilovolt, or 1,000 volts  kVA kilovolt‐ampere  kW kilowatt, or 1,000 watts. One kW is the power consumed by ten 100‐watt  incandescent light bulbs.  kWh kilowatt‐hour. The quantity of energy equal to one kilowatt (kW) expended for  one hour.   LFC liquidtite flexible conduit  LFMC liquidtite flexible metal conduit   mi mile, miles  NAD North American Datum   NREL National Renewable Energy Laboratory   O&M operations and maintenance  OMR&R operating, maintenance, repair, and replacement  PBC Pedro Bay Corporation, Inc.  PBVC Pedro Bay Village Council  PCE Power Cost Equalization (program)  P.E. Professional Engineer  Pedro Bay May refer to the village or the water body on Lake Iliamna, but generally refers  to the village in this report.  Polarconsult Polarconsult Alaska, Inc.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  ix  prime power, energy, electricity, load, demand   A use of electricity that utility customers expect to be supplied at their  convenience, as in turning on a light or television.  The utility is responsible for  taking all reasonable measures to supply sufficient energy into the utility grid to  meet all instantaneous prime demand of its customers.  Prime electricity can be  contrasted with excess or interruptible electricity, which is generated by the  utility only when conditions are favorable, and can be interrupted by the utility  without notice.     PTT pressure and temperature transducer   PVC  polyvinyl chloride  RM river mile  rpm revolutions per minute  SDR standard dimension ratio  space heating Heating of buildings.  May also include water heating for domestic use,  depending on the specific context and application.  USACE U.S. Army Corps of Engineers  USGS U.S. Geological Survey  V volt  VPSO Village Public Safety Office / Officer       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  1    1.0 INTRODUCTION  1.1 PROJECT AUTHORIZATION AND PURPOSE  In July 2010, the Pedro Bay Village Council (PBVC) hired Polarconsult Alaska, Inc. (Polarconsult)  to perform a feasibility study for a hydroelectric project on Knutson Creek.  This report presents  the findings of the feasibility study and makes recommendations for further action based upon  the feasibility study findings.    A draft of this report was issued in November 2012 for review and comment.  This final version  of the report incorporates comments received from the community and from the Alaska Energy  Authority through October 2013.  Comments and major revisions made to the draft report are  summarized in Appendix I.  1.2 SUMMARY OF FINDINGS  The feasibility analysis described in this report finds that a run‐of‐river hydroelectric project on  Knutson Creek is feasible from technical, regulatory, and economic standpoints.  An installed  capacity of approximately 100 to 250 kilowatts (kW) is best‐suited to the village’s long‐term  energy needs.  The recommended project can lower energy costs for Pedro Bay Village by up to  92% from current electric utility rates, depending on permit conditions, project financing, final  installed cost, and utilization of excess energy through interruptible electric heating services.  The economic analysis identified a 200‐kW hydroelectric project as the most cost‐effective  configuration.  A 200‐kilowatt (kW) project will have a design flow of 18.25 cubic feet per  second (cfs), which is conveyed from a diversion and intake structure at river mile (RM) 2.59  down to a hydro powerhouse near RM 1.25 via a 26‐inch‐diameter, 7,080‐foot‐long high‐ density polyethylene (HDPE) penstock.  Total gross head is 223.8 feet, and net operating head  at full flow is 206.5 feet.  The hydro powerhouse is connected to the village’s existing electric  distribution system via a 9,900‐foot‐long buried power cable.  The project includes 16,400  linear feet of new roads and trails.  The project location is shown on Figure A‐1, and the project  layout is shown on Figure A‐2.    The recommended project is estimated to supply 95.6% of Pedro Bay’s current annual electric  demand, displacing 16,600 gallons of fuel annually.  At a fuel cost of $5.83 per gallon, the  project is estimated to reduce utility fuel expenses by $96,778 annually.  The recommended  project can also supply approximately 86% of the annual space heating needs of seven  community buildings, and approximately 56% of the annual space heating needs of the  community’s 33 homes, through interruptible electric heating systems.  This application of  excess hydro output will displace an additional approximately 24,200 gallons of heating fuel  annually, saving the community an additional $156,500 per year.  Interruptible heating  applications use 73% of the total energy output of the recommended project, with normal  utility demand using another 12%.  At existing utility demand levels, 15% of the project’s total     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  2  energy output is calculated to remain unused and available for future growth.  In order to  realize the full benefits of a hydro project on Knutson Creek, it is necessary for the village to  refit its community buildings and homes with interruptible electric heating systems.    An economic analysis of the project indicates it has a benefit‐cost ratio (BCR) of between 1.18  and 2.00 compared to continued reliance on the diesel power plant.  This analysis assumes  utilization of excess hydro energy to provide interruptible heating systems for community  buildings and homes.  Further discussion on project costs and economic analysis may be found  in Section 4.0 and Appendices G and H.    1.3 PROJECT EVALUATION PROCESS  Hydroelectric development options for Knutson Creek were evaluated using an iterative  process to arrive at the recommended project. Initially, resource data for Knutson Creek were  collected and analyzed along with the community’s electric demand profile to identify several  initial project configurations for further evaluation. The resource data included stream  hydrology, site topography, and related information. Environmental and regulatory factors  were also considered in developing candidate project configurations. Data from the electric  utility were collected and analyzed to develop a model of the community’s electric demand  profile. These data were input to a generation dispatch model (GDM) to determine how much  prime electricity and interruptible electricity each project configuration would produce.   The electrical output for each project alternative was integrated with economic data comprised  of fuel costs, construction costs, operations and maintenance (O&M) costs, and financing  options to develop a BCR. The recommended project supplies the highest percentage of current  and projected future electrical demand (considering both prime demand and interruptible  energy services) while maintaining an acceptable BCR and satisfying expected environmental  constraints. This evaluation process is represented graphically on Figure 1‐1.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  3  Figure 1‐1 Feasibility Evaluation Process Flowchart  GENERATION DISPATCH MODEL Projects how much electricity is generated by diesel and hydro for each project configuration. Also projects excess energy generation. ELECTRICAL LOADS PCE & utility reports Utility load profile PROJECT RESOURCE DATA Knutson Creek hydrology Site topography Fisheries data LOAD PROFILE Prime power demand Potential interruptible energy loads ELIGIBLE HEATING LOAD Building inventory Climate data HYDROLOGY Flood magnitude Flow duration, timing and frequency ECONOMIC EVALUATION COMMUNITY NEEDS MET? BENEFIT/COST RATIO? ECONOMIC DATA Diesel fuel cost Excess energy value Financing plan RECOMMENDED PROJECT PROJECT COST DATA Design and permitting costs Project design approach Construction methods Construction cost estimate Operation and maintenance costs SURVEYS Gross head Pipe, power, access distances and alignments Property ownership ENVIRONMENTAL & REGULATORY CONSTRAINTS Aquatic resources Aesthetics Special restrictions GEOTECHNICAL ASSESSMENTS Stream diversion sites Civil infrastructure Project alignments COMMUNITY REVIEW AND FEEDBACK RESULTEVALUATION ANALYSISINPUT DATA ITERATIONS TO IMPROVE PROJECT PROPOSED PROJECT CONFIGURATION        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  4    1.4 CURRENT AND PREVIOUS STUDIES  1.4.1 1981 Regional Reconnaissance Study  In 1981, the U.S. Army Corps of Engineers (USACE) performed a regional study of potential  hydroelectric resources in southwest Alaska. As part of this study, the USACE looked at two  potential 100‐kW run‐of‐river projects in the area of Pedro Bay Village, one at Knutson Creek  and the other at Canyon Creek. Ultimately, the USACE concluded that neither project was  economical. Since then, however, improvements in technology and changes in the price and  usage patterns of other energy sources have made the prospect of developing a hydroelectric  project near Pedro Bay far more favorable.   1.4.2 2009 Regional Reconnaissance Study  In 2009, Polarconsult performed a reconnaissance study of potential hydropower resources in  the Pedro Bay area. This study looked at six potential sites: Knutson Creek, its three main  tributaries, Dumbbell Lake/Russian Creek, and Cottonwood Creek. Four of those sites, the main  fork of Knutson Creek and its three major tributaries, were selected as potentially viable sites  for hydropower development. The PBVC ultimately selected the main fork of Knutson Creek as  its preferred development site for continued investigation.   1.4.3 Current Feasibility Study  Between 2010 and 2012, Polarconsult engineers completed several trips to Pedro Bay to  conduct feasibility‐level field investigations of the Knutson Creek site.  Polarconsult personnel  were assisted by Mr. Ben Foss, the community's manager for this project, or other community  representatives on most field investigations. Field trips and activities completed are  summarized below.  October 10 ‐ 15, 2010 (Joel Groves, P.E., Gary Paulus, C.E.)  ● Installed a stream gauging station on Knutson Creek at RM 2.04 (lower station).  ● Measured discharge on Knutson Creek twice and on tributary R12 once.  ● Performed a reconnaissance of Knutson Creek to identify prospective access routes,  intake sites, and penstock routes.  ● Completed initial topographic surveys of the project area to determine the available  elevation drop for the project.                                                          2  This report references the unnamed major tributaries of Knutson Creek by which side of the creek they are on  looking upstream (“L” for left, “R” for right) and their numerical order of occurrence ascending the creek from  its mouth on Lake Iliamna.  Note that this “left/right” convention is opposite the “facing downstream”  convention customarily used in the natural sciences.  This standard was adopted to facilitate visualization of  these tributaries as viewed from Pedro Bay Village, as well as on maps oriented with north up.       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  5  February 4, 2011 (Gary Paulus, C.E.)  ● Measured discharge on Knutson Creek and downloaded lower stream gauging station  data.  April 4, 2011 (Joel Groves, P.E.)  ● Measured discharge on Knutson Creek and downloaded lower stream gauging station  data.  May 4‐5, 2011 (Joel Groves, P.E.)  ● Measured discharge on Knutson Creek and downloaded lower stream gauging station  data.  ● Completed additional topographic surveys of the project area and evaluated  powerhouse sites along the east and west banks of Knutson Creek.  November 15, 2011 (Gary Paulus, C.E.)  ● Installed a second stream gauging station on Knutson Creek near the mouth of tributary  L1 at RM 2.10 (upper station).  ● Measured discharge on Knutson Creek and downloaded lower stream gauging station  data.  April 19, 2012 (Joel Groves, P.E.; Mike Dahl, P.E.)  ● Measured discharge on Knutson Creek and downloaded lower stream gauging station  data.  July 20, 2012 (Joel Groves, P.E.)  ● Attempted to download upper stream gauging station data, but discovered it was  destroyed.  Attempted to measure discharge on Knutson Creek, but was unable to do so  due to unsafe conditions (high flow and velocity).  August 23‐25, 2012 (Bruce Barrett, Fisheries Biologist, and Joel Groves, P.E.)  ● Mr. Barrett conducted fish surveys of the project reach of Knutson Creek to assess fish  habitat, fish presence, and habitat utilization.    ● Mr. Groves installed new gauge hardware at the upper gauging station and reinforced  the station installation to reduce the likelihood of future hardware loss.  Attempted to  measure discharge on Knutson Creek, but was unable to do so due to unsafe conditions  (high flow and velocity).     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  6            This page intentionally blank.       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  7    2.0 COMMUNITY PROFILE  2.1 COMMUNITY OVERVIEW  Pedro Bay Village is an unincorporated community located at the east end of Iliamna Lake on  the Alaska Peninsula, within Township 4 South, Range 28 West of the Seward Meridian.  Its  geographic coordinates are 59 47’ 14” north and 154 6’ 22” west.  The community and project  site are both located within U.S. Geological Survey (USGS) quadrangle maps Iliamna D‐3 and D‐ 4.  The village is approximately 175 miles southwest of Anchorage and 90 miles west of Homer.   The community can be accessed by air or water, and barge service is seasonally available from  Naknek via the Kvichak River and from Homer via Williamsport and the Pile Bay Road.  Pedro  Bay is located in the Iliamna Recording District and the Lake and Peninsula Borough School  District.  Pedro Bay is located in a transitional climactic zone.  Average temperatures fall between 42  degrees Fahrenheit (F) and 62 F in the summer and 6 F and 30 F in the winter.  Extreme  temperatures range from  –50 F to 84 F.  Average annual precipitation is 35 inches, comprised  of 26 inches of rainfall and 64 inches of snowfall.  The population of Pedro Bay is approximately 42.  Most residents have seasonal employment in  the Bristol Bay fishery or in the local tourism industry.  The majority of residents also depend  upon fish and game (e.g., trout, salmon, bear, and moose) obtained through subsistence  hunting and fishing activities.  Pedro Bay has a federally recognized Alaska Native tribe,  organized as the PBVC.  Most of the houses in Pedro Bay are fully plumbed and utilize individual wells and septic  systems although Pedro Bay does maintain a community washeteria and some residents still  rely on honey buckets for waste management.  Honey bucket hauling services and septic  pumping services are provided by the PBVC, which also maintains the landfill and provides  electrical service.  Community services available in Pedro Bay include a school and a health  clinic, although the school was closed in fall of 2011 due to low enrollment.3  2.2  EXISTING ENERGY SYSTEM  2.2.1 Community Energy Overview  Pedro Bay has an isolated electrical system with no transmission interconnections to other  communities.  Pedro Bay relies 100% on diesel generation for electricity.  Diesel and other  petroleum fuels are delivered by barge or airplane several times annually.  Other local energy  usage includes diesel and gasoline fuels for transportation, wood and fuel oil for space and                                                          3 All information was complied from the ADCCED community profile for Pedro Bay Village.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  8  water heating, and propane gas for cooking and heating.  Table 2‐1 lists estimated annual fuel  consumption by type and purpose.  Table 2‐1 Estimated Community Energy Usage by Fuel Type and Purpose   Purpose (1) Fuel Estimated Annual Quantity Estimated Annual Cost (2)  Electric Diesel 22,000 gallons $118,800  Heating (3) Diesel/Fuel Oil 20,000 gallons $128,000  Heating (3) Wood 50 – 80 cords NA  Transportation Diesel/Gasoline 8,000 gallons $55,200  Total Hydrocarbon Fuels 50,000 gallons $302,000  NOTES:  (1)  Electric system data from PCE program and utility reports. Other fuel usage estimates based on the Pedro Bay Bulk Fuel  Consolidation and Upgrade Concept Design Report (Alaska Energy and Engineering, Inc. [AEE], 2003) and energy data  from the Alaska Energy Authority’s (AEA’s) 2010 Alaska Energy Plan Community Database,  http://www.akenergyauthority.org/alaska‐energy‐plan.html  (2)  Based on $5.40 per gallon for power plant fuel, $6.40 per gallon for heating fuel, $6.90 per gallon for transportation fuel.  (2012$).  (3) 25% of building heating needs is assumed to be met by wood and 75% by fuel oil.  Wood is assumed to be locally  harvested at no direct expense (only transportation fuel, labor, etc.).  2.2.2 Electric Utility Organization  Pedro Bay’s electric service is provided by the PBVC pursuant to Certificate of Public  Convenience and Necessity (CPCN) No. 662, which allows the PBVC to operate a public utility  for providing electric services in and around Pedro Bay Village.  The CPCN was issued in 2002 by  the Regulatory Commission of Alaska, which has exempted the PBVC from rate regulation  pursuant to the public interest exception included in Alaska Statute (AS) 42.05.711.4  PBVC  participates in the state’s Power Cost Equalization (PCE) program.  This program subsidizes  electrical rates for residences and community facilities served by eligible rural Alaska utilities.    2.2.3 Generation System  Pedro Bay's diesel power plant is located at the school.  The power plant has one 95‐kW diesel  generator and two 62‐kW diesel generators.  The school has a separate 62‐kW generator for  emergency power.  This fourth generator is not configured to feed the village power grid.  The  power plant switchgear is fully automatic with paralleling capability and uses a programmable  logic controller to match the generators to system load.  AEA upgraded the power plant  switchgear in 2012.5  The plant generates at 480 V single phase, which is stepped up to 7,200 V  for distribution with a 100‐kilovolt‐amp (kVA) transformer.  The 95‐kW generator set was  installed new in 2000, and the utility’s two 62‐kW gen sets were replaced in 2012 and 2013.   Installed generation equipment is listed in Table 2‐2.  The diesel plant is fitted with a waste heat                                                          4  The certificate and exemption were granted in RCA docket U‐89‐005, Order #4.  5  Switchgear upgrade design drawings dated January 19, 2012 (AEA, 2012c) and undated switchgear redlines.  (AEA, 2012d).     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  9  system that provides heat to the school. 6  AEA completed upgrades to the waste heat system in  2013.7  Table 2‐2 Existing Utility Generation Equipment  No. Equipment Prime Power  (kW)  Commissioned  Date  Total Hours  (November  2013)  Designated  Use  1 John Deere 6059 TFG01 Engine  Marathon Magnaplus Generator 95 kW 2000 NA Utility Peak  2 John Deere 4045 T150 Engine  Marathon Magnaplus Generator 62 kW  2012 NA Utility Base  3 John Deere 4045 T150 Engine  Marathon Magnaplus Generator 62 kW 2013 NA Utility Base  NA: not available.  2.2.4 Electrical Distribution System   Pedro Bay’s distribution system consists of a 7,200‐volt (V) single‐phase buried cable system.   There is also a significant amount of submarine cable running under Lake Iliamna to several  sites in the vicinity of the village.  There is a reactor installed on the system to compensate for  the capacitance of these cables and maintain an acceptable power factor on the electric  system. 8    2.2.5 Planned Upgrades  No upgrades are planned for the diesel power plant, bulk fuel facility, or distribution system.    2.2.6 Existing Load Profile  Total system electrical demand from 2003 to 2013 is presented on Figure 2‐1 and in Table 2‐3.  From 2003 to 2011, average wintertime demand was approximately 25 to 30 kW.  Average  summer‐time demand from 2003 to 2011 ranged from 20 to 25 kW.  Since the school closed in late 2011, seasonal variation in demand has decreased and demand is  now generally constant at approximately 16 to 20 kW year‐round.     Total generation from 2009 to 2011 (approximately 256,500 kilowatt‐hours [kWh] per year)  was approximately 5% lower than the average generation from 2004 through 2008                                                          6  Pedro Bay Power System Upgrade, Record Drawings, AEE, Inc., September 1, 2005.  7  Pedro Bay Heat Recovery Expansion Drawing Red‐Lines, AEE, Inc., September 21, 2013.  8  The system has two reactors, the reactor at the airport is currently energized.  Keith Jensen, Nov. 2013, personal  communication.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  10  0 10 20 30 40 50 60 70 80 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013Utility Generation (kW)Peak Monthly Generation (kW) Average Monthly Generation (kW) (approximately 269,000 kWh per year).  This decrease is attributed to conservation efforts and  sacrifices made by Pedro Bay ratepayers in response to the 51% increase in the price of  electricity that was implemented in late 2008 due to increasing fuel costs.    Since the school closed in late 2011, total generation has decreased significantly, with year‐ over‐year declines of approximately 10% occurring in 2011, 2012, and 2013 (year to date).   Total generation in 2012 was approximately 204,000 kWh, and total generation in 2013 is  estimated to be 180,000 to 190,000 kWh.      Figure 2‐1 Recent Monthly Peak and Average Power Generation             Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report  11 Table 2‐3 Recent Electric System Statistics Parameter  2003 (1) 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 (3) kWh Generated 102,314 249,083 295,974 272,211 264,939 262,759 256,409 256,677 226,927(2) 203,953 139,690 kWh for Station Service  (% of total generation) 5,257 (5.1%) 10,411 (4.2%) 14,239 (4.8%) 14,474 (5.3%) 12,112 (4.6%) 12,217 (4.6%) 12,222 (4.8%) 12,299 (4.8%) 11,718 (5.2%) 10,793 (5.3%) 9,698 (6.9%) kWh Sold 85,778 212,284 246,953 237,475 232,618 231,273 233,755 236,982 200,942 174,562 116,412 System Losses  (1 – (sold + station service)/generated) 11.02% 10.59% 11.75% 7.44% 7.63% 7.33% 4.07% 2.88% 6.32% 9.12% 9.72% Fuel Used (gallons) 10,403 23,349 22,552 19,454 20,325 23,458 21,018 21,673 19,514 20,583 14,035 Generation Efficiency  (kWh/gal) 9.8 10.7 13.1 14.0 13.0 11.2 12.2 11.8 11.6 9.9 10.0 Fuel Price (annual average) $2.24 $2.57 $2.74 $3.04 $5.06 $6.14 $4.60 $4.56 $5.23 $5.78 $5.91 Total Fuel Expense $23,321 $60,121 $61,798 $59,181 $102,886 $144,133 $96,669 $98,880 $102,132 $118,974 $82,989 Total Non‐fuel Expense $18,870 $41,233 $47,015 $41,811 $38,664 $44,833 $44,696 $53,855 $52,248 $34,539 $27,487 Total Utility Expense $42,190 $101,353 $108,814 $100,992 $141,550 $188,966 $141,365 $152,735 $154,380 $153,513 $110,476 Electric Cost per kWh $0.492 $0.477 $0.441 $0.425 $0.609 $0.817 $0.605 $0.645 $0.768 $0.879 $0.949 Utility Rate ($/kWh) $0.600 $0.600 $0.600 $0.600 $0.600 $0.600 $0.910 $0.910 $0.910 $0.910 NA Residential Rate with PCE  ($/kWh, annual average) (4) (4) (4) (4) (4) $0.262 (4) $0.424 $0.424 $0.466 $0.259 NA NOTES: All data are compiled from monthly PCE program records provided by the AEA (2012). (1) Records for 2003 include July through December only. (2)  Generation data for March 2011 are missing, and are estimated from kWh sales, powerhouse consumption, and line losses of 6.3%.     (3) Records for 2013 include January through September only. (4)  Older data not provided in the AEA database. kWh kilowatt‐hour NA not available.      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  12  2.2.7 Projected Future Load Profile   Community electrical demand is a function of population, electricity cost, and available income.  Commercial, industrial, and transient loads can also be major factors in total electrical demand.   In small Alaska villages with extremely high electric rates such as Pedro Bay Village, demand  often increases significantly in response to reduced electric rates. Reduced electric rates may  also encourage an increase in population over time, which can also cause an increase in  electrical demand.    The recommended 200‐kW hydro project provides significant capacity for future load growth.   As prime utility demand grows, some of the interruptible energy that is proposed to be  dispatched to building heating loads would instead be dispatched to prime loads.  Project  performance was evaluated for the following four load growth scenarios.   (1) 50% reduction in demand from current levels.  (2)  Continuation of existing demand.  (3) 200% increase from current levels.  (4) 400% increase from current levels.  Under the different load growth scenarios, total project output remains relatively constant, and  the portion of the project’s output that is used to supply prime demand varies.  These load  growth scenarios are discussed in greater detail in Section H.4 of Appendix H.   2.2.8 Population   The population of Pedro Bay in 2010 was 42, and the estimated 2011 population was 47.   Historically, the population of Pedro Bay has fluctuated somewhat from decade to decade but  has always remained below 70 (Table 2‐4). In the years for which population data are available,  Pedro Bay’s highest population figure was 65 in 1970. Its lowest population figure was 33 in  1980.  Population has been relatively stable since 1990, at approximately 46 +/‐ 10%.  Future  population in Pedro Bay is assumed to stay within the historic range and is expected to be  influenced by demographic trends (see Table 2‐5) and local economic opportunities.       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  13  Table 2‐4 Historic Population Data    Year Population 1  1950 44  1960 53  1970 65  1980 33  1990 42  2000 50  2010 42  2011 47 2  2012 42 2  Future Projection 30 to 70  NOTES:  (1)  Population data from decennial U.S. Census Bureau reports.  (2)  2011 population is estimated by the DCRA.    Table 2‐5 Local Demographics  Age Cohort (2010) Cohort Population  0 to 9 4  10 to 19 9  20 to 29 4  30 to 39 4  40 to 49 5  50 to 59 8  60 to 69 3  70 to 79 2  80+ 3  Total Population (2010) 42  Median Age (2010) 40  NOTE:  Data from 2010 Census.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  14  2.2.9 Income  Median household incomes for Pedro Bay, Alaska, and the United States are summarized in  Table 2‐6.  In 2010, household income in Pedro Bay was approximately 68% of household  income in Alaska.    Table 2‐6 Comparative Median Household Incomes  Population Group 1990 2000 2010  Pedro Bay Median Household Income as percentage  of Alaska Median Household Income NA NA 68%  Pedro Bay NA NA $40,750 1  Alaska $65,556 2 $69,021 2 $59,672 2  United States $49,950 2 $54,841 2 $50,831 2  NOTES:  (1) 2005‐2009 5‐Year estimate from Alaska Department of Labor and Workforce Development.  American Community  Survey.    Web http://labor.alaska.gov/research/census/  (2)  Data from U.S. Census Bureau, Table H‐8, 2011 version.  Amounts are in 2011 dollars.  NA:  Not Available.    2.2.10 Public Buildings and Housing Units  Major buildings in Pedro Bay Village are summarized in Table 2‐7.  The village’s building  inventory is a potential market for excess energy from the hydro project by adding interruptible  electric heating services to these buildings to offset fuel used by their existing heating systems.  Table 2‐7 Pedro Bay Building Inventory  Type of Building Estimated Quantity  Housing Units 33 (1)  Village Council Building (Meeting Hall, Washeteria) 1  Village Public Safety Officer (VPSO) Office 1  Church 1  School 2  Airport maintenance building 1  NOTE:  (1) Number of housing units recorded in the 2010 Census (U.S. Census Bureau, 2012). Pedro Bay Village has 33 housing units,  of which 19 are occupied, 13 are seasonally occupied, and 1 is vacant.  All housing units are assumed to be detached  single‐family dwellings.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  15  $0.00 $0.10 $0.20 $0.30 $0.40 $0.50 $0.60 $0.70 $0.80 $0.90 $1.00 $1.10 $1.20 $1.30 $1.40 $1.50 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013Energy Cost ($ per kWh)Non-Fuel Cost ($ per kWh) Fuel Cost ($ per kWh) Total Utility Costs ($ per kWh) Retail Electric Rate ($ per kWh) 2.2.11 Energy Market  Energy from a local hydroelectric project will be fed into the Pedro Bay Village electric system  to offset the need for diesel power generation. In addition, the hydroelectric project will often  generate energy in excess of electrical demand.  It is recommended that this excess energy be  made available on an interruptible basis to offset other local energy consumption for space and  water heating.   Fuel prices in Pedro Bay have increased significantly in recent years. The average price of fuel  was $2.68 per gallon in 2003‐2006, $4.27 per gallon from 2007‐2010, and $5.62 per gallon from  2011 to 2013.  This is an increase of 30% in the past 3 years, and 210% within the past decade.   The fuel, non‐fuel and total electricity costs in Pedro Bay are presented on Figure 2‐2.   Figure 2‐2 Recent Electric Utility and Electricity Costs            Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  16            This page intentionally blank.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  17    3.0 RECOMMENDED PROJECT   3.1 RESOURCE DESCRIPTION  The resource considered in this study is Knutson Creek, located immediately west of Pedro Bay  Village, and shown on Figures A‐1 and A‐2.  Knutson Creek is an approximately 7.5‐mile‐long   creek that drains a southwest‐facing basin measuring 37.11 square miles in area.  The basin is a  typical U‐shaped post‐glacial mountain valley aligned on a northeast – southwest axis and  measuring approximately 10 miles long by 3 to 4 miles wide.  It is ringed by mountains to the  east, north, and northwest that rise to elevations of approximately 2,200 to 4,600 feet, with the  highest peaks along the northeast perimeter of the basin.  The lowest elevation in the basin, at  the creek’s outlet to Lake Iliamna, is at an elevation of approximately 50 feet.  Lake Clark  National Park and Preserve abuts the northern drainage divide of the Knutson Creek basin.  Approximately 40% of the basin is vegetated.  The lower valley floor and lower mountain slopes  are vegetated by a mature mixed conifer and deciduous forest typical of southcentral Alaska.   Dominant species include white and black spruce, birch, and cottonwood.  Willow and alder  bushes become the dominant species above approximately 500 to 1,000 feet, eventually giving  way to open tundra above elevations of approximately 1,500 to 2,500 feet.    Knutson Creek’s headwaters are two alpine streams located at the northeast end of the basin.   From the confluence of these streams at approximately RM 7.5, Knutson Creek runs down the  center of the valley confined within an incised notch that is typically 300 to 1,000 feet wide and  50 to 100 feet deep.  In a few locations, Knutson Creek has carved a canyon with widths  narrowing to 150 feet.  The creek generally descends at a grade of 3% to 4% from RM 7.5 down  to approximately RM 1.5.  At this point, the creek leaves its confined corridor and emerges onto  an active alluvial cone for the remaining 1.5 miles to Lake Iliamna.  The grade along this lower  reach is approximately 1% to 2%.  Based on surface observations, bedrock is at or near the  surface along the reach from RM 1.5 to RM 7.5.  No bedrock is visible in the alluvial cone below  RM 1.5.   Knutson Creek is listed by the Alaska Department of Fish and Game (ADF&G) as anadromous  fish habitat. 9  Field surveys completed in August 2012 for this project by Alaska Biological  Consulting confirmed the presence of low numbers (~100 fish) of sockeye salmon in spawning  condition in the proposed bypass reach between RM 1.25 and RM 2.10, and the presence of  resident mountain Dolly Varden throughout the proposed bypass reach from RM 1.25 up to RM  2.70.  Fish surveys were not completed beyond these limits, but similarity of habitat conditions                                                          9  Knutson Creek is listed in the Atlas and Catalog of Waters Important to the Spawning, Rearing, and Migration  of Anadromous Fishes, maintained by the Alaska Department of Fish and Game.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  18  suggest Dolly Varden occur farther up and downstream.  Based on the August 2012 survey  results, anadromous habitat in the bypass reach is considered marginal.    Negotiating reasonable fish habitat permit conditions associated with this marginal habitat will  be very important to realizing the full benefits of this project.  Accordingly, Polarconsult  engaged with ADF&G early in the feasibility study, meeting with ADF&G staff in September  2010 and June 2011 to discuss the project, likely fisheries impacts and appropriate mitigation  measures.  Alaska Biological Consulting consulted with ADF&G staff in 2012 to discuss the  design of the fisheries survey and to understand the limiting resource conditions for sockeye in  the project area.  The fisheries report was provided to ADF&G in October of 2012.    The in‐stream flow reservations and associated project design elements presented in this  report are based on these consultations with ADF&G.  Fish habitat issues and the impacts of  habitat permit conditions are discussed in Sections E.2 and H.3 of the appendices, respectively.   Meeting records from the September 2010 and June 2011 meetings with ADF&G are included in  Appendix E as Attachments E‐1 and E‐2 respectively.  The Fisheries Surveys Report completed  by Alaska Biological Consulting is included as Attachment E‐3.    A stream gauging station has been measuring stream flow on Knutson Creek at RM 2.04 since  October 2010.  Based on station data, Knutson Creek at the proposed diversion site has a mean  annual flow of approximately 105 cubic feet per second (cfs), with an annual low flow of 7 to 20  cfs occurring in March and April, and seasonal high flows of approximately 1,000+ cfs.  Detailed  hydrology and gauging station information is presented in Appendix C and Attachment C‐1.   Technical aspects of Knutson Creek and the project area pertinent to the proposed project are  discussed in Appendix D.    3.2 OVERVIEW OF RECOMMENDED PROJECT  Polarconsult evaluated several run‐of‐river project configurations on Knutson Creek ranging in  installed capacity from 100 to 1,000 kW.  All of these configurations have the same diversion  and powerhouse locations, as these sites are well‐defined by the configuration of Knutson  Creek’s tributaries and the topography of the area.  Of these configurations, a project capacity  of approximately 100 to 250 kW is best‐suited to Pedro Bay’s long‐term needs.    The economic analysis presented in Section 4 and Appendix G of this report identify a 200‐kW  project as the most economic configuration, and the technical description presented in this  section is for a project of this size.  The actual installed capacity of the project, likely within the  100 to 250 kW range, should be determined once permit conditions are known and project  designs and cost estimates are more advanced.  The recommended project is a run‐of‐river hydroelectric project on Knutson Creek with an  intake at RM 2.59 and a powerhouse near RM 1.25, returning water to Knutson Creek at RM  1.10 via a 1,400‐foot‐long tailrace channel.  The recommended project has a 7,080‐foot‐long,  26‐inch‐diameter buried HDPE penstock, developing total gross head of 223.8 feet and net     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  19  head at full flow of 206.5 feet.  The recommended design flow is 18.25 cfs for an installed  generating capacity of 200 kW.  Technical details of the recommended project are listed in  Table 3‐1.  Each major component is discussed in greater detail in Section 3.4 and shown on the  conceptual design drawings in Appendix K.    The hydrology, topography, and geology of the project site clearly define the siting, routing, and  general configuration of the recommended project’s major features.  Design details of the  features as shown on the conceptual design drawings are subject to refinement as permit  conditions become known and additional site information is collected in the permitting and  design phase of project development.  The “optimal” design flow and installed capacity of the project are not clearly defined by site  conditions.  Knutson Creek has sufficient flow to support a significantly larger run‐of‐river hydro  project than the current village of Pedro Bay needs.10  Undersizing the hydro project would  sacrifice an opportunity to support future growth of the community at modest incremental  capital expense.  Oversizing the hydro project would result in unnecessary capital expense with  no benefit to the community and could also burden the community with increased O&M  expenses over the life of the project.  The challenge in selecting the project capacity is to weigh  these considerations evenly to arrive at an optimal project capacity.  Polarconsult’s analysis,  presented in Section H.2 of Appendix H, identifies a 200‐kW project as the most economic size.   This analysis should be revisited once project permit conditions have been finalized and designs  and capital cost estimates are more refined.    With the recommended project, Pedro Bay Village has an opportunity to displace a significant  portion of its heating fuel purchases by using hydro project capacity to supply energy to  community buildings and homes for heating purposes on an interruptible basis.  The  recommended project includes provisions to supply approximately 85% of the space heating  needs of community buildings and approximately 53% of the space heating needs of homes.   This will require refitting these buildings with additional electric services that can be  interrupted when needed to prioritize hydro generation capacity toward meeting electric utility  needs.  This will avoid unnecessary operation of the diesel power plant.    Figure 3‐1 presents hydro energy generated by the recommended project throughout a typical  year (2007) and shows how that energy is dispatched to meet utility system demand and  various interruptible electric heating services in the community.                                                              10   If a market existed for the full output of a run‐of‐river project on Knutson Creek, the optimal installed capacity  on a strictly economic basis (lowest $ per kWh for energy) is estimated at 800 to 1,200 kW.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  20  Table 3‐1 Technical Summary of Recommended Project   PROJECT FEATURES VALUE  Access Trails 16,400 feet  Primary Power Lines 9,900 feet  Communications Lines 18,000 feet  Basin Area Above Diversion Site (square miles) 29.17 square miles  Mean Annual Flow (cfs) 108 cfs  Minimum Flow (cfs) 13.3 cfs (average annual minimum flow)  6.8 cfs (extreme minimum flow)  Plant Design Flow (cfs) 18 cfs  Assumed In‐Stream Flow Reservation (ISFR) 6.6 cfs  Intake Headwater Elevation (ft) 398.5 feet  Powerhouse Finished Floor Elevation (ft) 178.0 feet  Normal Tailwater Elevation (ft) 174.7 feet  Gross Head (ft) 223.8 feet  Pipeline Length (ft)/Diameter (in) 7,080 feet of 26‐inch HDPE  Net Head at Full Flow (ft) 206.5 feet  Type of Turbine Single Crossflow Turbine (1)  Minimum Power Generation (kW) 50 kW (1)  Installed Capacity (kW) 200 kW  Plant Capacity Factor (2) 85.8%  Dam/Diversion Height (ft) 7 feet  Available Storage Volume (ac‐ft) none  ESTIMATED ANNUAL ENERGY GENERATION CHARACTERISTICS WITH RECOMMENDED HYDRO PROJECT  Total Existing Annual PBVC Load (kWh) 182,200 kWh    PBVC Utility Demand Supplied by Diesel (kWh) 8,100 kWh (4.4%)    PBVC Utility Demand Supplied by Hydro (kWh) 174,100 kWh (95.6%)  Total Annual Hydro Energy Generation (kWh) 1,503,700 kWh  Hydro Output used to Supply Existing PBVC Load (kWh)  174,100 kWh  Gross Excess Energy Available from Hydro (kWh) (3) 1,329,600 kWh  Gross Excess Hydro Energy Dispatched to   Community Buildings for Heating Applications (kWh) (4) 603,900 kWh  Gross Excess Hydro Energy Dispatched to   Homes for Heating Applications (kWh) (5) 486,400 kWh  Remaining Excess Energy Available from Hydro (kWh) 239,300 kWh  NOTES:  (1) The turbine configuration considered in this study is a single crossflow turbine, which typically has a minimum operating  threshold of 25% of rated output.  See Section H.1.1 for discussion of alternate turbine configurations that may warrant  consideration for this project.   (2) The amount of energy the project can produce with available water divided by the amount of energy the project could  produce operating at 100% output year‐round.  This is calculated with an assumed ISFR of 6.6 cfs.  (3) “Gross excess energy” means this is the energy generated at the hydro powerhouse, before system losses are subtracted.  (4) Includes 141,000 kWh dispatched to the school to make up for the loss of waste heat from the diesel power plant.    (5) See Appendix H for a full discussion of interruptible electric heating service analysis.  cfs  cubic feet per second HDPE  high‐density polyethylene kWh  kilowatt‐hour PBVC  Pedro Bay Village Council     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report  21 050100150200250Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2007Daily Energy Demand and Supply (Average Daily kW)Excess Energy Available from HydroHydro Energy Dispatched to Home Heating LoadsHydro Energy Dispatched to Community Building Heating LoadsDiesel Energy Dispatched to Meet Utility System DemandHydro Energy Dispatched to Meet Utility System DemandCurrent Utility System DemandUtility System Demand Met by DieselsCurrent Utility System DemandHydro Energy Dispatched to Community Building Heating LoadsHydro Energy Dispatched to Home Heating LoadsExcess Hydro EnergyUtility System Demand  Met by HydroFigure 3‐1 Typical Hydro Energy Output and Utilization, Recommended Project      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  22  3.3 DESCRIPTION OF PROJECT FEATURES  The descriptions of project features in this section are conceptual and are based upon review of  site conditions, construction costs, logistical considerations, long‐term maintenance and  operational considerations, and related factors.  In many cases, there are multiple viable  construction methods or design decisions that can be used.  In these cases, decisions will be  made in the design and permitting phase of the project as additional information on  environmental, regulatory, and technical constraints becomes available.  The recommended project has a design flow of 18.25 cfs and an installed capacity of 200 kW.   Conceptual design drawings for the recommended project are included in Appendix K of this  report.  3.3.1 Transmission Line  There are two logical routes and connection points for the hydro project to feed into the  existing Pedro Bay Village electric distribution system.  The preferred route is an approximately  9,900‐foot‐long route running from the hydro powerhouse along the hydro access road to the  airport access road, then following the airport access road east to the PBVC building,  connecting with the existing distribution system at transformer TX‐2 near the PBVC building.   The alternate route is an approximately 8,700‐foot‐long route running along the hydro access  road, then west along the airport access road to connect with the existing distribution system  at transformer TX‐20 at the airport maintenance building. 11  While the preferred route is longer than the alternate route, it provides a more direct  connection to the existing diesel powerhouse, which will result in increased system reliability.   It also runs by approximately 4,000 feet of potentially developable land along the airport access  road and would help facilitate future development of this property.  The preferred route is used  for all economic and other analyses in this study.  The transmission line can be either underground or overhead.  The village’s existing 7,200V  distribution system is entirely underground, and the terrain along the preferred transmission  line route appears suitable for installation of an underground line.  The cable can be direct‐ buried or buried in duct.    3.3.2 Controls and System Integration  The hydro project will have a dedicated communications circuit running between the hydro and  diesel powerhouses to coordinate operations and allow remote monitoring and operation of  the hydro project.  There will also be a dedicated communications circuit between the hydro  powerhouse and hydro intake.  This circuit will provide the hydro controls information about                                                          11  Transformer numbers taken from the Pedro Bay Distribution Upgrade Drawings (ADCCED, 1995).      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  23  the intake status, including availability of water for power generation.  It will also support  remote operation of gates and apparatus at the intake, as well as remote monitoring of the  intake.    The hydroelectric generator will be a single‐phase 480‐V synchronous machine.  It will normally  be the sole generation source for the village but will also be capable of paralleling with the  diesel generators when needed.  A pad‐mounted transformer will be located outside the hydro  powerhouse to step the voltage up to 7,200 V to connect with the existing electric distribution  system.  A manual disconnect and fuse will be located at the hydro powerhouse, enabling the  hydro powerhouse to be isolated from the distribution system for maintenance and repair.    The switchgear at both powerhouses will be modified to integrate operations.  Diesel  switchgear was upgraded by AEA in 2012 and 2013.  Under normal operation, the hydro plant  will carry the full system load and the diesel engines will be turned off in standby mode.  As  system load approaches the available capacity of the hydro, the switchgear will activate a diesel  engine to parallel with the hydro.  The diesel engine will be set at a base load to maintain  reasonable fuel efficiency and avoid wet‐stacking or other adverse operating conditions.          With this project, the utility’s diesel generators will be turned off for a significant amount of the  time.  This will extend the life of the diesels, reduce the frequency of diesel maintenance and  overhauls, reduce usage of consumables, and conserve fuel.  The existing waste heat system  that serves the school from the diesel powerhouse will be fitted with an interruptible electric  heating system to keep the standby diesel generator set(s) warm and to continue providing  heat to the school.    Interruptible electric heating services can be implemented in a number of ways.  This study  assumes that buildings are fitted with a second electric meter that includes a special relay  controlled by the hydro plant switchgear.  The switchgear incrementally closes these  interruptible meter relays when the hydro has excess generating capacity until interruptible  services are using all of the available excess energy.  This is a dynamic process, as total hydro  generation and prime utility load are constantly changing, and any given interruptible meter  may or may not have loads turned on when it is activated by the hydro plant switchgear.    A  load bank would also be installed at the hydro powerhouse to allow the hydro controller to  regulate system voltage and frequency without using the interruptible meters when necessary.   Communications between the hydro plant switchgear and interruptible meters can use several  different forms, including internet, radio link, dedicated wire, power line carrier, or grid  frequency modulation.   3.3.3 Access  Construction access to the hydro powerhouse will generally follow the existing all‐terrain  vehicle (ATV) trail that heads up Knutson Creek valley from the airport quarry (Figure A‐2).  The  proposed hydro powerhouse site is located approximately 5,800 feet from the existing airport     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  24  access road along the proposed hydro access road.  The conceptual designs show the access  road located slightly to the east of the existing ATV trail.  This alignment was selected to keep  the road as far away from Knutson Creek as possible to reduce the risk that future meanders of  Knutson Creek will wash out the access road.  There are no significant known constraints  regarding the final alignment of this road.    Access to the remainder of the hydro project will take one of two routes.  Heavy equipment for  construction and periodic maintenance will use a proposed 7,600 foot‐long access road from  the powerhouse to the intake, fording Knutson Creek above the powerhouse site at RM 1.30  and heading up the west side of Knutson Creek.  Constraints on use of the fording location will  be part of the Fish Habitat Permit issued by ADF&G for the project.  A separate trail will follow the penstock route up the east side of Knutson Creek.  This trail will  depart from the main access road approximately 600 feet above the powerhouse and continue  for 2,200 feet along the east side of Knutson Creek to a bridge crossing at RM 1.79.  It will then  rejoin the main access road approximately 3,700 feet below the diversion site.   3.3.4 Diversion and Intake Structures  Diversion Structure  The project diversion structure site is at an exposed bedrock sill located at RM 2.59 (see  Photographs B‐12 and B‐13).  The diversion structure will consist of a reinforced concrete wall  120 feet long and 0.5 to 7 feet tall.  This wall will serve to impound water enough to divert the  project flow through a horizontal slot on the west 20 feet of this wall into the intake structure.   Excess water will flow over the easterly 100 feet of the wall, which will serve as the main  spillway.  A short (0.25‐foot‐tall) step halfway along the 100‐foot‐long spillway will confine  lower flows to the west end of the spillway, discharging into the normal channel of Knutson  Creek.  Higher flows will spill over the full 100 feet of spillway.  A rock dike will extend from the  east end of the concrete spillway approximately 200 feet to the east side of the valley floor.   This dike will be designed to be overtopped by flood flows up to the estimated 500‐year flood  event of 2,500 cfs.  A similar dike will extend from the west end of the concrete spillway  structure approximately 240 feet to the west side of the valley floor.  The west dike will be  taller than the east dike and will not be overtopped by the estimated 500‐year flood event to  prevent flood damage to the intake, access road, work pad, penstock, and associated project  infrastructure located immediately downstream of the west dike.  Intake Structure  The intake structure will be a reinforced concrete structure located immediately downstream of  and adjacent to the west end of the concrete diversion structure.  The intake structure will  receive raw water and debris from the diversion impoundment and into the intake forebay, and  then direct this flow over a coanda effect‐type screen.  This screen will filter rocks, gravel, and  plant matter out of the water, with clean water collecting in the intake gallery beneath this     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  25  screen.  Filtered debris will be flushed off the screen and back to the main channel of Knutson  Creek by excess water flowing over the screen.  Filtered water will flow by gravity from the  gallery into the penstock and to the powerhouse.  The normal headwater elevation in the  intake gallery will be approximately 398.5 feet.  The diversion structure and intake structure will be fitted with gates to flush out accumulated  sediments and debris on an as‐needed basis.  These gates may be remotely operated from the  hydro or diesel powerhouse by the plant operator.  3.3.5 Penstock  The penstock will be a 26‐inch‐diameter HDPE pipe buried along the project access roads and  trails.  The penstock will be buried in the main access road for the first 3,700 feet below the  intake.  It will then depart the access road and cross to the east side of Knutson Creek via a 340‐ foot‐long bridge at RM 1.79.  This bridge will also support ATV, snow machine, or pedestrian  traffic to the intake.  The penstock then continues down the east side of Knutson Creek for  2,200 feet, rejoining the main access road 600 feet above the powerhouse.  A trail will be built  along the portion of the penstock route deviating from the main access road to provide access  for penstock construction and ATV access to the intake site for routine operation and  maintenance purposes.  Intake maintenance requiring heavy equipment will need to ford  Knutson Creek and use the construction access route along the west side of Knutson Creek.    The overall penstock length will be 7,080 feet.  At the full design flow of 18.25 cfs, head losses  along the penstock will be approximately 17.3 feet.  Most of the penstock will be low‐pressure  standard dimension ratio (SDR) 32.5 pipe.  The approximately 1,000 feet of penstock  immediately above the powerhouse will be higher‐pressure SDR 26 and SDR 21 pipe.  Power  and communications will be buried along the same route as the penstock to operate and  control equipment on the intake and diversion structures.  3.3.6 Powerhouse  The powerhouse will be a 20‐ by 24‐foot building with 10‐foot ceilings.  The building will include  an overhead gantry beam to move the turbine and generator.  The powerhouse will house the  turbine, generator, switchgear, and associated control systems for the project.  The turbine will  be a single crossflow‐type turbine, and the generator will be a single‐phase synchronous  machine.12  Finished floor elevation in the powerhouse will be 178 feet.  The tailrace finished  floor beneath the powerhouse will be 169.5 feet.  The normal tailwater elevation will be  approximately 174.7 feet, resulting in a gross project head of approximately 223.8 feet and a  net operating head at full design flow of approximately 206.5 feet.                                                            12  See Section H.1.1 in Appendix H for discussion of alternate turbine configurations that may be appropriate for  this project.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  26            This page intentionally blank.         Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  27    4.0 ECONOMIC ANALYSIS  To evaluate the economic benefits of the hydro project, a comparative analysis was performed  between a hydro project and future diesel generation costs without a hydro project.  Based on  this analysis, the hydro project is a lower‐cost power supply option for Pedro Bay Village than  continued purchase and consumption of diesel fuel, provided that the hydro project’s excess  energy is used for space heating on an interruptible basis.   Fitting buildings for interruptible  electric heating services is recommended to be an integral part of the hydro project in order to  realize the full project benefits.  This study conducted comparative analyses for a range of project capacities (100 to 1,000 kW).   Economic data for these alternate project capacities is presented in Section H.2 of Appendix H.  4.1 COST ESTIMATE FOR RECOMMENDED PROJECT  The cost estimate for the recommended project is presented in Table 4‐1.  This cost estimate  assumes the community contracts with a qualified construction firm to build the project.  Table 4‐1 Estimate of Total Installed Cost for Recommended Project (200 kW)  Cost Item Cost Estimate  (2012 $)  PRE‐CONSTRUCTION COSTS (STUDY, DESIGN, PERMITTING) $293,000  DIRECT CONSTRUCTION COSTS     Access Roads and Trails $370,000    Power and Communications Lines $375,000    Diversion and Intake Structures $259,000    Penstock $743,000  Building Conversions for Interruptible Electric Heating Service $310,000    Powerhouse $700,000    Shipping/Mobilization/Equipment $555,000  TOTAL DIRECT CONSTRUCTION COSTS $3,312,000  Construction Contingency (20%) $662,000  Construction Management/Administration $120,000  Construction Inspection/Engineering $115,000  ESTIMATED TOTAL INSTALLED COST $4,502,000     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  28  4.2 ECONOMIC EVALUATION OF RECOMMENDED PROJECT  The economic analysis of the hydro project was performed on a relative basis, using continued  operation of the diesel power plant as the reference case.  Estimates of major differential costs  were developed for the analysis, which included:  1) Annual costs for hydro project operation, maintenance, repair, and replacements,  2) Annual savings from reduced fuel usage, operations, and maintenance costs at the  diesel power plant,  3) Capital costs of the hydro project, and   4) Salvage value of the hydro project at the end of its life.  All of these expense items were considered over the 50‐year life of the project, and then  converted to present value amounts.  The present value of the project’s benefits and costs  (relative to continued use of the diesel power plant) were then compared to determine the  project’s estimated benefit‐cost ratio.  The electric utility’s general and administrative costs are  assumed to be constant for both cases, and so were not considered.  Similarly, the diesel power  plant will be needed for both cases, so capital outlays for the diesel plant beyond O&M savings  are also not considered.  Major assumptions used in the economic analysis of the project are  summarized in Table 4‐2.  These assumptions are discussed in greater detail in Appendix G.    Table 4‐2 Base Case Assumptions Used for Economic Analysis   Utility Assumptions Value  Annual Electric Demand 182,200 kilowatt‐hours (1)  Diesel Power Plant Fuel Efficiency 10.5 kWh generated per gallon (1)  Annual Utility Fuel Usage for Electricity Generation 17,352 gallons (1)  Per Gallon Fuel Cost to Utility $5.83 per gallon (2)  Total Annual Utility Fuel Costs $101,162  Utility Load Projections Flat at current load level (4)  Economic Model Assumptions   Hydro Project Salvage Value (Year 50) $0 (4)  Construction and Commissioning Year 2016 (4)  Project Financing Debt financing, Grant financing (5)    Debt term 30 years (4)    Debt interest rate 5% (6)    Real discount rate 3%  (4)  (1) Approximate annual average for the utility from 2011 to 2013, as determined from PCE program and utility records.  (2) 2012 fuel cost as estimated by the Institute of Social and Economic Research (ISER, 2012).  (4) Assumed value.  (5) The economic analysis for grant‐financed project used the economic model developed for the AEA’s Renewable Energy  Grant Program by ISER (Round 6 version, released July 2012) (AEA, 2012a).  (6) Assumed interest rate is based on the interest rate for the Sustainable Energy Transmission and Supply Development  Loan Program administered by the Alaska Industrial Development and Export Authority as of November 2013.  The Power  Project Fund also has an interest rate ranging from 0 to 6%.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  29  Two financing alternatives were evaluated for the project’s capital costs: (1) debt financing and  (2) grant financing.13  Table 4‐3 summarizes the annual costs and savings of the recommended  project for both debt‐ and grant‐based financing alternatives.    Table 4‐3 Summary of Economic Data for Recommended Project  Parameter  Values Used  for Economic  Analysis  ECONOMIC EVALUATION OF DEBT‐FINANCED PROJECT (Relative to continued diesel generation)  PROJECT BENEFITS    Annual Reduction in Utility Fuel Purchases due to Hydro Project 16,600 gallons  Annual Reduction in Heating Fuel Purchases due to Interruptible Electric Heating Services  24,200 gallons  Annual Savings from Avoided Diesel Plant Operating and Maintenance Costs $15,000  Salvage Value (at year 50) $0  PRESENT VALUE OF PROJECT BENEFITS $7,334,000 PROJECT COSTS   Estimated Total Installed Cost of Project (study, permitting, design, and construction) $4,502,000  Financed Project Cost $4,212,000  Annual Cost of Debt Servicing (for 30 years) $317,600  Estimated Annual Hydro Plant Operations, Maintenance, Repair and Replacement Costs   (for 50 years)  $29,000  PRESENT VALUE OF PROJECT COSTS  $6,234,000 BENEFIT‐COST RATIO (DEBT‐FINANCED PROJECT) 1.18 ECONOMIC EVALUATION OF GRANT‐FINANCED PROJECT  (Relative to continued diesel generation)  PRESENT VALUE OF PROJECT BENEFITS  $8,280,000  PRESENT VALUE OF PROJECT COSTS  $4,132,000  BENEFIT‐COST RATIO (GRANT‐FINANCED PROJECT)  2.00 NOTE:   See Appendix G (Section G.2) for assumptions used in the economic analysis and the project cost estimate. All dollar  amounts are in 2012 dollars.    Table 4‐3 assumes that most of the community buildings and homes in Pedro Bay Village are  fitted for interruptible electric heating services in order to use as much of the hydro project  output as possible.  The estimated cost of these conversions is included in the project’s total  installed cost estimate.  If the hydro project is instead used to supply only the existing electric  utility demand, the hydro project’s benefit‐cost ratio is much lower, at approximately 0.6 to 1.0  (depending on hydro project configuration and financing).  This underscores the importance of                                                          13  The grant‐financed scenario is developed using the economic model developed by ISER and used by AEA to  evaluate applications to the Renewable Energy Grant Program (ISER, 2012b).     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  30  using excess energy from the project with interruptible electric heating services, or a similar  beneficial application.  4.3 PROJECTED ELECTRICITY RATES WITH RECOMMENDED PROJECT  Table 4.4 presents estimated PBVC electric rates with the recommended project.  Three  potential rate scenarios are presented – two for a debt‐financed project, and a third for a grant‐ financed project.  Assumptions used to develop these estimated rates are discussed in Section  G.3 of Appendix G.    Table 4‐4 Estimated PBVC Electric Rates with Recommended Project  Estimated Electric Rates  Project Scenario Interruptible  Heating Service  (No PCE Subsidy)  Prime Energy Service  (Standard Service)  (Before PCE Subsidy)  Prime Energy Service with  PCE Subsidy (Residential and  Community Services Only) (1)  Debt‐Financed Hydro Project  (Discounted Rate for  Interruptible Heating Service) (2)  $0.198 per kWh $1.255 per kWh $0.255 per kWh  Grant‐Financed Hydro Project $0.065 per kWh $0.065 per kWh $0.065 per kWh   (no PCE subsidy)  Current Electric Rate  NA $0.910 per kWh $0.173 per kWh  Current Equivalent Cost of   Heating Fuel for Buildings $0.220 per kWh (3) NA NA  NOTES:  (1) Based on the fiscal year 2012 PCE base rate of $0.1342 per kWh and full funding for the PCE program.  The PCE program  reimburses the utility for up to 500 kWh per month per residential account and for certain community accounts.  The  subsidy level is 95% of the difference between the utility rate (up to $1.00 per kWh) and the base rate.  (2) If the hydro project is debt‐financed, a discounted interruptible service rate is necessary to provide a financial incentive  for ratepayers to convert to interruptible electric heating service.  A rate equal to a 10% discount from fuel oil prices is  assumed.  This results in a significant rate increase from existing rates for standard electric service.    (3) Based on an assumed heating equipment efficiency of 84%, $7.60 per gallon cost, and 140,000 btu/gallon heat content.  kWh kilowatt‐hour  NA not applicable  PCE Power Cost Equalization (program)  The estimated rates for a debt‐financed project presented in Table 4‐4 reveal a challenge with  debt‐financing for this project.  Interruptible energy rates must be competitive with heating oil  which limits the revenue from interruptible energy sales.  The resulting rates for prime energy  service must then cover the utility’s remaining costs, resulting in rates that are significantly  higher than existing rates.    This conundrum is a function of the particular debt parameters and energy usage patterns that  result from the recommended project configuration and economic evaluation assumptions, and  can be resolved through a combination of grants and/or low‐cost financing.  The electric rates  with a fully grant‐financed hydro project (6.5 cents per kWh for both interruptible and prime  energy services) represent the lower‐end of probable electric rates with the recommended     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  31  hydro project.  Rural utilities commonly use a combination of grants and low‐cost loans to  develop acceptable project economics.  With a fully grant‐financed hydro project, PBVC ratepayers would no longer qualify for PCE  subsidies as the electric rate would be too low.  With a debt‐financed project, PBVC ratepayers  would likely continue to receive PCE subsidies for eligible kWh usage.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  32  4.4 SENSITIVITY ANALYSIS  A sensitivity analysis was performed to determine how sensitive the economic analysis  conclusions are to variations in assumptions and input parameters.  The assumptions and  inputs reviewed and the results are summarized in Table 4‐5 for a debt‐financed project.  For  each variable, the input range considered, resulting range of BCR, and value that results in a  BCR of 1.00 are presented.  Generally, the BCR of a grant‐financed project is higher for a given  set of conditions, so evaluating debt‐financed conditions provides a more rigorous test of the  project’s economics.  Table 4‐5 Sensitivity Analysis Results (Debt‐Financed Project)  Parameter Base Case Value  (BCR of 1.18)  Range   Considered  Range of   Resulting BCR  Value for BCR of  1.00 (1)  Installed Cost $4,502,000  +/‐ 25% 0.95 – 1.54 $5,357,000  (+19%)  System load and   Growth trend  182,200 kWh  (No growth)  91,100 to 728,800 kWh  (– 50% to +400%) (2) 0.98 – 2.23 –45%  In‐Stream Flow  Reservation (ISFR) 6.6 cfs 0 to 20 0.86 – 1.29 14 cfs  Incremental Annual  Operations Costs $29,000/year +/‐ 50% 1.11 – 1.25 +260%  ($79,900/year)  Financing Rate 5% 0 to 8% 0.89 – 2.07 6.7%  Cost of Fuel (3) $5.83 per gallon ‐50% to 200% 0.62 – 2.30 –16%  ($4.89 per gallon)  Percent Utilization  of Excess Energy 82% 0% to 100% 0.51 – 1.34 63%  Environmental  Attributes Sales  Price  $0.00 per kWh $0.00 to $0.03 1.18 – 1.30 NA  NOTES:  (1) The feasibility‐level project cost estimate includes a 20% contingency on the construction cost.  (2)   Load growth cases assume a constant load over the project’s economic life at the stated percentage of existing annual  load.   (3) Range of fuel costs is applied to both power plant fuel and heating fuel.   BCR benefit‐cost ratio  NA Not applicable because variations in the parameter cannot result in a BCR of 1 or less.  Based on this analysis, the project economics are most sensitive to the following four  parameters:  (1) Percent utilization of excess energy,  (2) Cost of fuel,   (3) In‐stream flow reservations (ISFRs), and  (4) Installed cost.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  33  Percent Utilization of Excess Energy  Retrofitting public buildings and homes in Pedro Bay to receive interruptible excess energy  from the hydro project on an interruptible basis is critical to realizing the full economic benefits  of the project.  Analysis indicates that fitting seven community buildings and 33 homes for  interruptible electric heating is sufficient to use 78% of the excess energy available from the  recommended hydro project under existing utility load characteristics.  Without fully  developing this market for the project’s energy, the project’s benefits are significantly reduced.    Cost of Fuel  The project’s benefits are sensitive to the price of fuel.  Under the 100% debt‐financed  alternative for the project, the BCR is 1.00 at a 2012 fuel price of $4.89 per gallon. PBVC’s fuel  costs were less than this amount as recently as March 2011.  While the long‐term fuel cost is  considered unlikely to be below $4.89 per gallon in Pedro Bay, it is possible that prices will fall  below this level for a season or more in the early years that the project is operational.  In‐Stream Flow Reservations (ISFRs)  High ISFRs will reduce or eliminate the ability of the project to produce electricity during the  late winter months, reducing the project’s benefits without reducing the project’s costs.  If  possible, off‐site compensatory habitat should be constructed in lieu of ISFRs, or in exchange  for decreased ISFRs.    Installed Cost  Construction cost overruns on small hydroelectric projects such as that recommended for  Pedro Bay can significantly reduce the project’s benefits.  Proper project design and  construction management are both key to a successful on‐budget project.  An adaptive design  that can quickly address changing field conditions using on‐site materials, equipment, and labor  will help to control construction costs.  In addition, selecting a contractor with both local  experience and small hydro experience will help avoid problems during construction.  Using  force‐account construction with a capable superintendent instead of a contractor for all or  parts of the project can also be a good strategy to help the PBVC control construction costs.    Additionally, the challenging logistics and high transportation costs to Pedro Bay mean that  significant attention should be paid to early planning for the project.  Last‐minute shipping of  minor materials due to incomplete material take‐offs, extended lease terms of imported  construction equipment due to poor planning or unforeseen site conditions, and similar factors  can rapidly increase project costs.       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  34            This page intentionally blank.         Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  35    5.0 CONCLUSIONS AND RECOMMENDATIONS  The run‐of‐river hydroelectric project on Knutson Creek recommended in this report will supply  95.6% of Pedro Bay’s existing electrical demand in an average water year.  Additionally, it will  supply approximately 86% of the space heating needs of Pedro Bay’s community buildings, and  approximately 56% of the space heating needs of homes in the community.    At an estimated installed cost of $4,502,000, the recommended project as an estimated BCR of  1.18 to 2.00 compared to continued reliance on diesel fuel for electricity generation.  This BCR  range includes the significant space heating benefits the project is capable of supplying to the  community.  Indeed, using the project’s output for interruptible electric heating services is  critical to realizing the full benefits of the project.  These findings are based on an assumed ISFR of 6.6 cfs year‐round, equal to 50% of the average  annual low flow in Knutson Creek at the diversion site.  Project benefits improve with a lower  ISFR and decrease with higher ISFRs.  Accordingly, negotiating reasonable conditions for the fish  habitat permit for the project will directly impact the project’s benefits for the community.    Permit negotiations with the ADF&G should emphasize compensatory off‐site anadromous  habitat as mitigation for reducing flows in the bypass reach rather than establishing excessive  ISFRs for the marginal anadromous habitat in the bypass reach of Knutson Creek (See Appendix  E).  ISFRs in the bypass reach of Knutson Creek represent a direct trade‐off between providing  for the sustainability of Pedro Bay Village versus preserving marginal anadromous fish habitat in  the bypass reach of Knutson Creek.  Based on the findings of this study, continued development of the project is warranted as the  project can provide a significant long‐term benefit to Pedro Bay Village.  The next major steps  to develop the project are:  (1)  Initiate the permitting process for the project.  (a)  Prepare and file a Declaration of Intention with the Federal Energy Regulatory  Commission (FERC) to determine if the project falls under FERC jurisdiction.   This will influence the course of permitting for the project, and will also effect  the project’s life‐cycle costs.  (b) Continue consultations with ADFG regarding conditions associated with the  fish habitat permit.  Opportunities for off‐site mitigation, and on‐site  mitigation within the project tailrace, should be discussed with ADFG  personnel to maximize project benefits.  (2) Continue collecting hydrology data at the diversion, gauging station, and tailrace sites  along Knutson Creek, as well as at tributaries R1 and L1, to support efforts to secure a  fish habitat permit with reasonable conditions for the project.  (3)  Complete design of the project, which will include the following:       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  36  (a)  Analysis of optimal project capacity once permit conditions are known and  additional site information is available.  (b) More detailed analysis of existing space heating demand in Pedro Bay (e.g.,  fuel usage, building details) to refine the quantity of excess hydro energy that  can be dispatched to space heating loads and the extent of upgrades needed  to implement electric heating services.    (c)  Development of financing plans and rate schedules for standard electric  service and interruptible electric heating service to encourage conversion to  interruptible heating service and maximize project benefits to the community.  Figure 5‐1 provides the completed‐to‐date and anticipated future project schedule and  milestones.  Figure 5‐1 Project Development Schedule  2009 2010 2011 2012 2013 2014 2015 2016 ACTIVITY 12341234123412341234123412341234 Reconnaissance Study (Completed) Feasibility Study (Completed) Permitting FERC Non‐Jurisdiction Other Permitting and Authorizations Project Design Construction Plan Financing Plan Construction Project Commissioning Construction Phase Close‐out          Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  37  6.0 REFERENCES  Alaska Department of Commerce, Community, and Economic Development (ADCCED).  2012.  Pedro Bay.  Web site: http://www.commerce.state.ak.us /dca/commdb/CIS.cfm?  Comm_Boro_name=Pedro%20Bay   Alaska Department of Commerce, Community, and Economic Development (ADCCED).  Division  of Community and Regional Affairs. 1995.  Pedro Bay Distribution Upgrade Drawings.  March 20.   Alaska Department of Labor and Workforce Development.  American Community Survey.    Web  site: http://labor.alaska.gov/research/census/  Alaska Energy and Engineering, Inc. (AEE).  2003.  Pedro Bay Bulk Fuel Consolidation and  Upgrade Concept Design Report.   Alaska Energy and Engineering, Inc. (AEE).  September 7, 2005.  Pedro Bay Power System  Upgrade Record Drawings.     Alaska Energy and Engineering, Inc. (AEE).  2013.  Pedro Bay Heat Recovery Expansion Red Line  Drawings.  September 21, 2013.   Alaska Energy Authority (AEA).  2012a.  Renewable Energy Fund Round 6.  Web site:  http://www.akenergyauthority.org/RE_Fund‐6.html.  July.  Alaska Energy Authority (AEA).  2012b.  Power Cost Equalization.  Web site:  http://www.akenergyauthority.org/programspce.html     Alaska Energy Authority (AEA).  2012c.  Pedro Bay Easygen Upgrade Design Drawings,  Controlled Power, Inc. (#7443) and Alaska Energy Authority (PO RQ‐4071).  January 19,  2012.    Alaska Energy Authority (AEA).  2012d.  Undated red lines of August 12, 2004 Switchgear Design  Drawings, Controlled Power, Inc. (#5823) and Alaska Energy Authority (PO REG‐04‐230)  Provided by AEA on November 8, 2013.   Alaska Energy Authority (AEA).  2010.  Alaska Energy Plan Community Database.  Web site:  http://www.akenergyauthority.org/alaska‐energy‐plan.html     Institute of Social and Economic Research (ISER), University of Alaska Anchorage.  2012a.   Internal Publications Database Search.  Web site: http://www.iser.  uaa.alaska.edu/publications.php?id=1518      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  38  Institute of Social and Economic Research (ISER), University of Alaska Anchorage.  2012b.   Alaska Fuel Price Projections 2012‐2035.  ISER Working Paper 2012.1 and Microsoft  Excel Spreadsheet Price Model.  July.  U.S. Army Corps of Engineers (USACE).  2007.  Alaska Baseline Erosion Assessment: Erosion  Information Paper – Pedro Bay, Alaska.  October 19.    U.S. Census Bureau.  2010 Census.  Web site: http://2010.census.gov/2010census/  U.S. Geological Survey (USGS).  2003.  Estimating the Magnitude and Frequency of Peak  Streamflows for Ungaged Sites on Streams in Alaska and Conterminous Basins in  Canada: Water‐Resources Investigations Report 2003‐4188.  By Curran, Janet H.; Meyer,  David F.; and Tasker, Gary D.  USGS. 1973.  Surficial Deposits of the Iliamna Quadrangle, Alaska: Geological Survey Bulletin  1368‐A.  By Detterman, Robert L. and Reed, Bruce L.  USGS. 1980.  Stratigraphy, Structure, and Economic Geology of the Iliamna Quadrangle, Alaska:  A Comprehensive study of Mesozoic to Holocene Sedimentary, volcanic, and plutonic  rocks of the Iliamna Quadrangle.  Geological Survey Bulletin 1368‐B.  By Detterman,  Robert L. and Reed, Bruce L.      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report                 APPENDIX A – PROJECT MAPS       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  A‐1            This page intentionally blank.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  A‐2    Figure A‐1 Project Overview and Location Map        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  A‐3    Figure A‐2 Map of Recommended Knutson Creek Project        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  A‐4    Figure A‐3 Knutson Creek and Iliamna River Drainage Basins and Subbasins        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  A‐5              This page intentionally blank.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report       APPENDIX B – SITE PHOTOGRAPHS    Photograph    Title Page Nos.  Photograph B‐1 Exterior View of Existing Pedro Bay Diesel Power House........................B‐2 Photograph B‐2 Interior View of Existing Pedro Bay Diesel Power House........................B‐2 Photograph B‐3 Upper Gauging Station Looking Upstream..............................................B‐3 Photograph B‐4 Natural Outlet Control Structure at Upper Gauging Station...................B‐3 Photograph B‐5 View of Knutson Creek Reach at Lower Gauging Station........................B‐4 Photograph B‐6 View of Knutson Creek Lower Gauging Station.......................................B‐4 Photograph B‐7 View of Knutson Creek at River Mile 2.2, Looking Upstream..................B‐5 Photograph B‐8 View of Knutson Creek at River Mile 1.5, Looking Downstream.............B‐5 Photograph B‐9 View of Knutson Creek Downstream of Upper Gauging Station.............B‐6 Photograph B‐10 Oblique Aerial View of Lower Knutson Creek ..........................................B‐8 Photograph B‐11 Oblique Aerial View of Upper Knutson Creek..........................................B‐8 Photograph B‐12 Proposed Knutson Creek Diversion Site Looking Downstream...............B‐9 Photograph B‐13 Proposed Knutson Creek Diversion Site Looking Upstream..................B‐10 Photograph B‐14 Oblique View of Proposed Penstock Bridge Site Over Knutson  Creek ................................................................................................................B ‐10 Photograph B‐15 Elevation View of Proposed Penstock Bridge Site over Knutson  Creek ................................................................................................................B ‐11   Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  B‐1            This page intentionally blank.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  B‐2    Photograph B‐1 Exterior View of Existing Pedro Bay Diesel Power House    Polarconsult, July 21, 2009.      Photograph B‐2 Interior View of Existing Pedro Bay Diesel Power House    Polarconsult, July 21, 2009.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  B‐3  Photograph B‐3 Upper Gauging Station Looking Upstream  Polarconsult, April 19, 2012.    Photograph B‐4 Natural Outlet Control Structure at Upper Gauging Station     Polarconsult engineer Gary Paulus measuring stream flow in Knutson Creek at the upper gauging station site at  river mile 2.10.  The mouth of tributary “L1” is visible at far right.  Measured flow is 78.1 cfs.  Polarconsult, October 15, 2010.  View of upper gauging station at river  mile 2.10, looking upstream.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  B‐4  Photograph B‐5 View of Knutson Creek Reach at Lower Gauging Station    Stream gauging station installed October 12, 2010, at river mile 2.04.  The index bolt is an arbitrary elevation of  3.00 feet (to top of bolt).    Polarconsult, October 11, 2010.    Photograph B‐6 View of Knutson Creek Lower Gauging Station    Lower gauging station installed October 12, 2010, at river mile 2.04.  This view is taken from a cliff on the west side  of Knutson Creek.  The measured stream flow is approximately 83 cfs.  Polarconsult, October 14, 2010.  HDPE pipe housing  sensor and data logger  Download/charging  cable enclosure  Index bolt  Lower Gauging  Station Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  B‐5  Photograph B‐7 View of Knutson Creek at River Mile 2.2, Looking Upstream    View upstream from river mile 2.2 on Knutson Creek. This view shows representative creek grade, section, and bed  materials for the reach from river miles 2.1 through 2.5.  Polarconsult, October 13, 2010.    Photograph B‐8 View of Knutson Creek at River Mile 1.5, Looking Downstream    View downstream from river mile 1.5 on Knutson Creek. The creek section widens and grade decreases as it enters  the alluvial cone.    Polarconsult, October 11, 2010.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  B‐6  Photograph B‐9 View of Knutson Creek Downstream of Upper Gauging Station    Polarconsult engineer Gary Paulus measuring stream flow in Knutson Creek at the upper gauging station   site at river mile 2.10.  The lower gauging station is located just out of view on the east bank   downstream at photograph left.  Polarconsult, October 11, 2010.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  B‐7            This page intentionally blank.      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report  B‐8 Tributary ‘L1’Diversion SiteTributary ‘R2’ Tributary ‘R1’ Powerhouse Equipment Access Route Penstock BridgeLower Gauging StationUpper Gauging StationPhotograph B‐10 Oblique Aerial View of Lower Knutson Creek    Photograph B‐11 Oblique Aerial View of Upper Knutson Creek  Tributary ‘R1’PowerhouseEquipment Access Route Penstock RouteTailraceOblique aerial view looking west‐southwest over lower Knutson Creek from its mouth on Lake Iliamna up to approximately river mile 1.75.  The approximate locations of key project features are shown.    Polarconsult, April 26, 2012. Oblique aerial view looking west‐southwest over upper  Knutson Creek from approximately river mile 1.0 up to approximately river mile 3.0.  The approximate locations of key project features are shown.    Polarconsult, April 26, 2012.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report  B‐9  Photograph B‐12 Proposed Knutson Creek Diversion Site Looking Downstream  View of proposed Knutson Creek diversion site at RM 2.59 looking downstream (south‐southwest).  Polarconsult engineer Gary Paulus is standing on a bedrock outcrop that extends back toward the east bank and extends  under the creek channel.  The bedrock disappears beneath boulders and cobbles on the west bank of Knutson Creek. The red line traces the approximate bedrock contour.   Polarconsult, October 14, 2010.  ?  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report  B‐10 Photograph B‐13 Proposed Knutson Creek Diversion Site Looking Upstream  Photograph B‐14 Oblique View of Proposed Penstock Bridge Site Over Knutson Creek  View of proposed penstock bridge site over Knutson Creek from vicinity of east abutment.  The approximate penstock alignment is shown in dark red.   Polarconsult, May 5, 2011. View of proposed Knutson Creek diversion site at RM 2.59 looking upstream (north‐northeast).  Polarconsult engineer Gary Paulus is standing on a bedrock outcrop that extends back toward the east bank, and extends under the creek channel.  The bedrock disappears beneath boulders and cobbles on the west bank of Knutson Creek. Polarconsult, October 14, 2010.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report  B‐11 Photograph B‐15 Elevation View of Proposed Penstock Bridge Site over Knutson Creek  View of proposed penstock bridge site over Knutson Creek from upstream.  The approximate bridge location is shown in dark red. Polarconsult, May 5, 2011.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report            APPENDIX C – HYDROLOGY DATA    Section  Title Page Nos.  C.1 Available Hydrology Data......................................................................... C‐2  C.2 Stream Gauge Station Information.......................................................... C‐4  C.3 Flow Measurements and Station Calibration .......................................... C‐6  C.4 Knutson Creek Hydrology Data ............................................................... C‐8  C.5 Knutson Creek Hydrology Model........................................................... C‐12  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐1            This page intentionally blank.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐2  C.1 AVAILABLE HYDROLOGY DATA  Approximately 1.9 years of hydrology data have been collected at Knutson Creek.  Two gauging  stations have been installed at Knutson Creek; these are described in Section C.2.  This  appendix summarizes the hydrology data and analysis used for this study.  Appendix J provides  the daily stage and calculated flow data for both gauging stations in tabular form.  The collected hydrology information is used to determine the appropriate installed capacity of  the hydroelectric project, evaluate the expected performance of the project, and help  determine the magnitude of flood flows at Knutson Creek.  Moreover, this hydrology  information can help assess the effect the project may have on the natural environment.  Existing hydrology data are summarized in Table C‐1.  Flow measurements at the Knutson Creek  gauging stations are summarized in Table C‐2.  Hydrographs, stage‐discharge curves, flow  duration curves, and station notes for both gauges are included in this appendix.   Table C‐1 Summary of Hydrology Data for Knutson Creek  Location USGS  Gauge ID  Basin  Size  (square  miles)  Site  Elevation  (ft) (1)  Latitude(1)Longitude(1) Begin  Date End Date  Number  of Daily  Records(2)  Iliamna River 15300300 128 80 59d45’31” 153d50’41” 5/24/96 Current 5,936  Knutson Creek   Upper Gauge NA 30.0 310 59d49’11” 154d06’54” 11/10/11 Current(3) 2  Knutson Creek  Lower Gauge NA 33.1 300 59d49’09” 154d06’56” 10/12/10 Current(3) 555  NOTES:  (1) Coordinates for U.S. Geological Survey gauges are in North American Datum of 1927 (NAD 27). All other coordinates are  in NAD 83.  Knutson Creek gauging station elevations are in the project vertical datum.    (2) The record count for current gauging stations includes data through the most recent download of the Knutson Creek  gauges on August 25, 2012.   (3) Current status of both gauging stations is unknown.  Both stations were in good working order at Polarconsult’s last field  visit on August 25, 2012.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐3  Table C‐2 Flow Measurements at Knutson Creek and Tributaries  Date and Time Party Measured  Flow (cfs)  Measuremen t Quality  Stage at Upper  Gauging Station  (ft) (4)  Stage at Lower  Gauging Station  (ft) (5)  Method/Equipm ent  Knutson Creek Tributary “R1” (at 450’ elevation)  7/22/2009 13:45 Groves/Foss 43 Poor  –  –  Salt (2), (6)  10/14/2010 17:30 Groves/Paulus 3.7 Good –    –  Salt (2)  Knutson Creek Tributary “L1” (at mouth on Knutson Creek)  10/11/2010 16:00 Paulus/Groves 3.7 Very Poor –  –  CV (1), (6)  Knutson Creek at Upper Gauging Station  10/11/2010 15:30 Paulus/Groves 100.9 Good 2.16 1.53 CV (1)  10/15/2010 12:30 Paulus/Groves 78.1 Good 2.03 1.51 CV (1)  5/4/2011 11:50 Groves/Foss 51.3 Fair 1.83 1.40 CV (1)  4/19/2012 16:45 Groves/Dahl 32.8 Fair 1.63 1.30 Salt (2)  Knutson Creek at Lower Gauging Station  2/4/2011 11:45 Paulus/Foss 38.2 Fair –  1.21 Salt (2)  4/11/2011 14:30 Groves/Foss 10.2 Good 1.03 1.04 Salt (2)  7/20/2012 12:15 Groves 400 –  2.91 1.90 Visual estimate (3)  8/24/2012 15:30 Groves 200 –  2.50 1.65 Visual estimate (3)  NOTES:  (1) Current velocity (CV) stream flow method with Marsh‐McBirney Flo‐Mate™ 2000 Portable Velocity Flow at 40‐second  averaging interval.  Reported value is the average of two concurrent measurements unless otherwise noted.  (2) Sudden dose salt integration stream flow method with Hanna HI 9828 conductivity meter.  Reported value is the average  of two concurrent measurements unless otherwise noted.  (3) Flow conditions unsafe for current‐velocity measurement methods.  Velocity, depth, and width were partially measured  and/or estimated in order to estimate total flow.   (4) Creek stage is based on manual tapedown measurements from the top of a ¼‐inch bolt set in rock at the site.  The bolt  elevation is +4.70 feet.  The approximate point of zero flow for this station is 0.00 feet in this datum.  (5) Creek stage is based on manual tapedown measurements from the top of a ¼‐inch bolt set in rock at the site.  The bolt  elevation is +3.00 feet.  The approximate point of zero flow for this station is 0.00 feet in this datum.  (6) Only one measurement taken.  “– ”  Indicates data are not available.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐4  C.2 STREAM GAUGE STATION INFORMATION  Both the lower and upper gauging station sites were identified in October 2010 as good gauging  station locations.  The lower station has mediocre low‐flow stage resolution but is well‐ protected from high‐flow hazards and has a deep pool to protect the pressure and temperature  transducer (PTT) from freezing.  The upper station has superior low‐flow stage resolution but is  subject to high‐flow hazards and freezing conditions.  The history of both stations is described  in detail in this section.  C.2.1 Lower Knutson Creek Gauging Station  On October 12, 2010, Polarconsult installed a gauging station (the “lower gauging station”) at  RM 2.04 on Knutson Creek, at about the midpoint of the proposed project bypass reach (see  Figure A‐2).  This station was selected based on the perceived stability of the creek bed in the  immediate station vicinity, the relative protection from flood debris and velocities, its  accessibility from Pedro Bay Village for downloading and maintenance, and the presence of a  deep pool to protect the PTT from freezing during the winter months.    The lower gauging station is in a small, deep pool on the inside (east) bank of Knutson Creek  where it negotiates a series of sharp turns through a rock canyon.  The pool is on the periphery  of the creek bed at this location, with the main channel approximately 40 feet to the west and  approximately 4 feet below the pool elevation.  The outlet of this pool is controlled by a series  of 2‐ to 4‐foot‐diameter boulders well‐embedded in the creek bottom.  Flow is directed to this  pool year‐round by a series of cobble and boulder bars located approximately 100 feet  upstream (see Photographs B‐5 and B‐6).   Instrumentation at this gauging station is a model DCX‐ECO18VG vented PTT and data logger  manufactured by Keller America, Inc.  The PTT is programmed to measure water depth and  temperature at 30‐minute intervals, providing approximately 9.5 months of memory capacity.   The PTT is mounted within a 3‐inch‐diameter HDPE stilling tube fastened to two large boulders  on the stream bank with steel pipe clamps and rock bolts.  The PTT is secured within the stilling  tube with a 1‐inch‐diameter segment of polyvinyl chloride (PVC) tube.  The PVC tube is pinned  to the stilling tube to prevent vertical movement of the PTT.  At annual low‐flow conditions, the  PTT is immersed in approximately 1.3 feet of water.  The vent and data cable is routed through  liquidtite flexible metal conduit (LFMC) up to a nearby cottonwood tree, providing easy access  for download and charging.  The rechargeable battery is sufficient for 1+ years of operation on  a single charge.  The vertical datum for this station is the top of a ¼‐inch rock bolt drilled into one of the  boulders at the station.  The rock bolt is located approximately 4 feet upstream of the stilling  tube and PTT installation.  The top of the rock bolt is +3.00 feet in the station datum.  The  approximate point of zero flow for the pool outlet control is 0.00 feet in this datum.  This hardware has remained in service at this station without problems from October 12, 2010,  through the most recent download on August 25, 2012.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐5  C.2.2 Upper Knutson Creek Gauging Station   The upper gauging station is located immediately upstream of the mouth of tributary L1 at RM  2.10.  A ¼‐inch index bolt was installed on a bedrock outcrop at this station in October 2010 to  establish a vertical datum for the station.  The top of the bolt is +4.70 feet in the station datum.   The approximate point of zero flow for the station is 0.00 feet.  This station is approximately 300 feet upstream of the lower gauging station.  It was selected  based on the perceived stability of the creek bed in the immediate station vicinity and the good  outlet control, which consists of a string of well‐embedded boulders spanning the  approximately 40‐foot wide channel.  This station lacks an accessible pool and is subject to  inundation and high velocities during high‐flow events, which places any instrumentation  installations at risk.  This station also features one of the better locations for performing  current‐velocity measurements on Knutson Creek between approximately RM 1.00 and   RM 2.75.    Upon review of 2010‐11 winter stage data from the lower gauging station, instrumentation was  installed at the upper gauging station on November 10, 2011, to improve the low‐flow record  for Knutson Creek.  Instrumentation at this gauging station is a model DCX‐22VG vented PTT  and data logger manufactured by Keller America, Inc.  The PTT is programmed to measure  water depth and temperature at 30‐minute intervals.  At annual low‐flow conditions, the PTT is  immersed in approximately 0.8 feet of water.  The PTT was mounted directly in the stream,  clamped to a section of liquidtite flexible conduit (LFC).  The LFC was fastened to 20 feet of an  exposed rock outcrop and back to the east stream bank.  The vent tube/data cable was routed  through the LFC to a small enclosure mounted to a rock face on the stream bank (see  Photograph B‐3).  This installation survived the winter of 2011‐12, but the July 20, 2012, site  visit revealed that the PTT enclosure had been ripped away from the LFC by high flows.  The  enclosure was inaccessible under snowdrifts during the April 11, 2012, site visit, so the data  from this installation were lost.    A second DCX‐22VG was installed on August 24, 2012, to replace the lost instrumentation.  The  PTT/data logger installation was reinforced with a 2x4 anchored to bedrock, and the LFC was  reinforced with additional anchors to the bedrock.  Additionally, a 1/8‐inch steel cable was fixed  to the PTT and run through the LFC and anchored to bedrock to help prevent loss of the  PTT/data logger.  The DCX‐22VG is fitted with a non‐rechargeable battery with a 5‐year life.   Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐6  y = 1.3072e1.9943x R2 = 0.9984 0 50 100 150 200 250 300 350 400 450 500 0.00 0.50 1.00 1.50 2.00 2.50 3.00 3.50 Creek Stage (feet, station datum)Flow (cubic feet per second)Upper Station Rating Curve Expon. (Upper Station Rating Curve) (estimate) (estimate) C.3 FLOW MEASUREMENTS AND STATION CALIBRATION  The stage‐discharge curve for each gauging station has been developed by measuring flow in  Knutson Creek multiple times between October 2010 and August 2012 (Table C‐2).   Measurements at the upper or lower gauging stations are adjusted to the other station by  scaling the measured flow by the ratio of the basin areas above each station.    The existing flow measurements and calibrated sections of the stage discharge curves have  good confidence at low and medium flows (up to 100+ cfs), which are of primary interest for  hydropower assessment of Knutson Creek.  Additional high‐flow measurements would be  useful to increase confidence in the upper end of the stage‐discharge curves.  These data would  improve estimates of infrequent high‐flow events that have limited hydropower value but are  important for design of the diversion structure.   Stage‐discharge curves for each station are empirical best‐fit equations.  The stage‐discharge  curves are presented on Figure C‐1 and C‐2 for the upper and lower Knutson Creek gauging  stations, respectively.    Figure C‐1 Stage‐Discharge Curve for Knutson Creek Upper Gauging Station     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐7  y = 0.1152e4.3857x R2 = 0.9879 0 50 100 150 200 250 300 350 400 450 500 0.00 0.20 0.40 0.60 0.80 1.00 1.20 1.40 1.60 1.80 2.00 Creek Stage (feet)Flow (cubic feet per second)Lower Station Rating Curve Expon. (Lower Station Rating Curve) (estimate) (estimate) Figure C‐2 Stage‐Discharge Curve for Knutson Creek Lower Gauging Station      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐8  C.4 KNUTSON CREEK HYDROLOGY DATA  Hydrology data for the lower Knutson Creek gauging station are presented in this section.  No  hydrology data have been recorded at the upper station due to the loss of the first PTT (winter  2011‐12 data) in early summer 2012.  Data on the second PTT installed in August 2012 have not  been downloaded yet.  Figure C‐3 presents measured and recorded stage and temperature data at the lower gauging  station for the full period of record.  Figure C‐4 presents calculated and measured flow data at  the lower gauging station for the full period of record.  Calculated flow data on Figure C‐4 is  based on the stage‐discharge curve and equation presented on Figure C‐2.  Apparent ice‐ affected stage data, as determined by field observations, flow measurements, and concurrent  weather records, have been adjusted to provide an estimate of actual flow.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐9            This page intentionally blank.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.  November 2013 – Final Report  C‐10 -28-24-20-16-12-8-404812162024283236404448525610/1/10 11/12/10 12/24/10 2/4/11 3/18/11 4/29/11 6/10/11 7/22/11 9/2/11 10/14/11 11/25/11 1/6/12 2/17/12 3/30/12 5/11/12 6/22/12 8/3/12Water Temperature (F)0.751.752.753.754.755.75Creek Stage (ft, Lower Gauge Site Datum)Water Temperature (F)Water Temperature (F)Creek Stage, Recorded (ft)Creek Stage, Recorded (ft)Creek Stage, Manually Measured (ft)Creek Stage, Manually Measured (ft)05010015020025030035040045050010/1/10 11/12/10 12/24/10 2/4/11 3/18/11 4/29/11 6/10/11 7/22/11 9/2/11 10/14/11 11/25/11 1/6/12 2/17/12 3/30/12 5/11/12 6/22/12 8/3/12Knutson Creek Flow at Lower Gauge Station (cfs)Figure C‐3 2010‐2012 Knutson Creek Stage and Temperature Data               Figure C‐4 2010‐2012 Knutson Creek Flow Data  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.  November 2013 – Final Report  C‐11      This page intentionally blank.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐12  0 10 20 30 40 50 60 70 80 90 100 Jan 1 Feb 1 Mar 3 Apr 3 May 4 Jun 4 Jul 5 Aug 5 Sep 5 Oct 6 Nov 6 Dec 7Knutson Creek Flow at Intake Site (cfs)Flow at Proposed Intake Site, cfs Median Daily Flow Mean Daily Flow (Knutson Creek extended record based on gauged Knutson Creek flow Oct. 2010 - April 2011 and correlated Iliamna River flow 1996 - 2011) C.5 KNUTSON CREEK HYDROLOGY MODEL  Brailey Hydrological Consultants, Inc. (BHC) was contracted to analyze the 1.9 years of stream  flow data for Knutson Creek and concurrent flow data from the Iliamna River and develop an  extended record for Knutson Creek based on the 16.3 years of flow data for the Iliamna River.   The BHC report is included at the end of the feasibility study as Attachment C1.  The resulting  extended record provides an improved model of the expected variability of flows in Knutson  Creek that can be used for hydroelectric generation or that must be kept in the creek for  environmental reasons.  Using this extended record produces a better understanding of the  long‐term variability in performance of the hydro project in helping meet Pedro Bay’s energy  needs.  Figure C‐5 presents daily flow statistics for Knutson Creek based on the extended record.    Figure C‐5 Daily Flow Statistics for Knutson Creek Based on Extended Record    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐13  Figure C‐6 presents two flow duration curves for Knutson Creek.  One curve is based on flow  data for the lower gauging station and the second curve is based on the extended record for  Knutson Creek.    Figure C‐6 Flow Duration Curves for Knutson Creek at Proposed Intake Site      0 50 100 150 200 250 300 350 400 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100% Percent of Time Flow is Equalled or ExceededFlow at Intake Site (cfs)Flow Duration Curve for Intake Site, Based on Lower Gauge Data Flow Duration Curve for Intake Site, Based on Extended Record Design Flow for Recommended Project Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐14            ATTACHMENT C‐1   KNUTSON CREEK STREAMFLOW ANALYSIS REPORT  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  C‐15            This page intentionally blank.  Polar 1503 W Anch Attn:    Subje Dear  As pe for K data  meas occas of the the n statio transd   In ac devel comp uncor Bra Con rconsult Alas W. 33rd Aven horage,  Alask  M ect:  Kn Joel:  er my propos Knutson Cree has been r urements w sions during  e discharge m nearby Iliamn on transducer ducer record ccordance w loped using  pute uncorre rrected strea ailey Hyd nsultant ka, Inc.  nue, Suite 310 ka  99503  Mr. Joel Grove nutson Creek sal dated July ek near Pedro recorded at  ere conducte the period of measurement na River US r records sho ds show eleva Figure 1.   with USGS p ice‐free dis ected stream mflows were drologic ts 0  es, P.E.  k streamflow y 29, 2011, th o Bay, Alask the lower ed at the up f record.  Alt ts were cond GS station (N ow good agr ated stage rea Gaging Stat procedures f scharge mea mflows based e then corre c Septemb w analyses  is letter prov ka.  As show gaging stati pper flow me though ice af ucted during No. 1530030 reement with adings typica tion Location for winter f asurements,  d on the ic cted visually 3527 No Anchora 907‐248‐ dbrailey ber 13, 2011 vides the resu wn on Figure  ion since O easurement  ffect was not g the period  00).  Furtherm h field water al of ice effect ns, Knutson  flow estimat and the ice ce‐affected t y using weat orth Point D age, AK  995 ‐0058 phone y@alaska.net ults of stream 1, continuou October 2010 section (Figu t apparent in of ice affect d more, althou r level meas ts (Figure 2). Creek  tion, a ratin ‐free rating  transducer r ther data an rive  502  e  t  mflow analyse us water lev 0.  Discharg ure 1) on fiv n the field, tw designated fo ugh the lowe surements, th    ng curve wa was used t records.  Th d compariso es  el  ge  ve  wo  or  er  he    as  to  he  on    again estim   F   Using Iliamn with  provi   The f the ra nst provision mated streamf Figure 2.  Est g a linear reg na River, the that for the  ide a flow‐du foregoing ana ating curve fo nal winter flo flows are illu timated Dail O gression betw e period of r Iliamna Riv uration curve alyses includ or the lower K ow estimates ustrated on Fi ly Streamflo October 13, 2 ween estima record for lo ver (Figure 3) e (Figure 4).   de two weak Knutson cree s for USGS  igure 2.  ws on Knuts 2010 to April ated daily flo ower Knutso ).  The resul knesses that r ek station (Fi Station No.  son Creek an l 30, 2011  ows on lowe on Creek wa lting daily fl require furth igure 5).  Add Mr. Jo Sep 15300300.   nd the Iliamn er Knutson C as extended t lows were th her evaluation ditional stage oel Groves, P. tember 13, 201 Page The resultin na River,  Creek and th to correspon hen ranked t n.  The first  e‐discharge  E.  11  e 2  ng    he  nd  to  is        Figgure 3.  Exten Figure 4.  F nded Stream Flow‐Duratio   mflow Record, on Curve, Low , Lower Knu wer Knutson Mr. Jo Sep utson Creek  n Creek  oel Groves, P. tember 13, 201 Page   E.  11  e 3        meas condi disch   The s Knuts not b meteo Mem freeze   Than quest Since David Braile F urements ar itions above  harge measur second weak son Creek.  D be used (Fig orologic data morandum N e‐up, and at l k you for th tions or conce rely,  d E. Brailey  ey Hydrologi igure 5.  Prel re needed to 8.4 feet.  Fur rement, which kness that re Due to an app gure 2).  As a and comp o. 94.03 reco least once ev he opportunit erns.   ic Consultan liminary Rat o confirm thi rthermore, p h is generally equires furth parent loss o s a result, t parison again ommends str very six week ty to provide nts  ting Curve, L is relationsh peak annual f y considered her evaluatio of tracer, the s the winter fl nst USGS Sta reamflow me ks until break e these servi   Lower Knuts hip, which in flows are mo d the limit of r on are the es single winter flow estimat ation No. 15 easurements kup.    ices.  Please  Mr. Jo Sep son Creek  ndicates a ch ore than twi rating extens stimated win r flow measu tes are based 5300300.  US s as soon as  call should y oel Groves, P. tember 13, 201 Page hange in flow ce the highe sions.  nter flows o urement coul d entirely o SGS Technic possible afte you have an E.  11  e 4    w  st  on  ld  on  al  er  ny  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report          APPENDIX D – RESOURCE DATA AND ANALYSIS    Section  Title Page Nos.  D.1 Maximum Probable Flood........................................................................ D‐2  D.2 Review of Climate Effects on Hydropower Projects................................. D‐2  D.3 Geotechnical Considerations................................................................... D‐4      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐1           This page intentionally blank.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐2 D.1 MAXIMUM PROBABLE FLOOD  Determining the maximum probable flood for Knutson Creek is important for (1) designing the  in‐stream diversion structure at Knutson Creek so it can withstand flood flows, and (2)  designing the creek crossing, powerhouse, and other project features so they are not damaged  by flood events.  Existing data from the gauging station are compared with U.S. Geological  Survey (USGS) statistical models for southwest Alaska streams to develop initial estimates of  the 100‐year and 500‐year flood flows for Knutson Creek (USGS, 2003).  The USGS has developed statistical models to estimate the maximum probable floods for  streams in southwest Alaska. These models are developed based on stream gauging data  throughout the region and specific parameters for the drainage basin of the stream of  interest.14  The USGS model input parameters and estimated flood flows are summarized in  Table D‐1. The highest calculated flow in the extended record (1,500 cfs) is approximately 30%  greater than the estimated 15‐year flood flow based on the USGS model.  This is reasonable  agreement, given the accuracy of the USGS estimation method and the length of record at  these gauging stations.  The estimated 500‐year maximum probable flood flows are used for  the conceptual designs described in this feasibility study.  Table D‐1 Maximum Probable Flood at Knutson Creek  Parameter Knutson Creek Diversion Site  Basin Area (square miles) 29.2  Mean Annual Precipitation (inches) (1) 40  Percentage of Basin as Storage (lakes, ponds) 0%  Estimated 500‐year flood 2,423 cfs  Estimated 100‐year flood  1,803 cfs  Estimated 10‐year flood 1,027 cfs  Maximum Flow in Extended Record (15 years) 1,500 cfs  NOTE:  (1) Data are from source maps specified in the USGS Water Resources Investigation Report 2003‐4188 (USGS, 2003).     D.2 FLOOD HAZARDS  Upstream of RM 1.7, Knutson Creek is confined to its general course by bedrock topography.   Minor shifting within the valley floor is possible and appears to occur regularly, but these  meanders will not significantly impact the hydro project improvements.  Aside from the  diversion/intake structure, which is located at an exposed bedrock sill, the major project  features that are most exposed to flood or erosion hazards are portions of the upper intake  access road that are located along the westerly fringe of historic meander limits, and the  eastern‐most penstock bridge pier that is located within the historic meander limits.  These  project features will be designed to withstand these flood and scour hazards.                                                           14  See USGS Water Resources Investigation Report 2003‐4188 (USGS, 2003).  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐3 From RM 1.7 to its mouth on Lake Iliamna, Knutson Creek flows in an actively moving channel  over an alluvial cone.  In the early 1990s, Knutson Creek jumped its easterly bank in the vicinity  of RM 1.00 to 1.30 and flowed down to the airport, causing significant erosion of the runway.  A  berm was built along the original creek bank to restore the creek to its original and still current  channel (USACE, 2007).  The age of vegetation across much of the cone suggests that Knutson  Creek is not rapidly accreting large volumes of material in this area, however, the cone is not  significantly gullied and Knutson Creek’s history of channel shifting indicates the cone remains  subject to Knutson Creek’s meanders.    Given the history of the creek and the topography of the alluvial cone, it is conceivable that the  creek will experience major channel meanders during the 50‐year life of the hydro project.   Potential impacts of channel meanders to the hydro project are summarized below.  (1) Erosion of the equipment access road from station 66+00 to 86+00.  This road is built  on grade and could be easily rebuilt or moved using on‐site material if washed out in  a flood.  The precise road alignment or creek fording locations are not critical, and the  road can be readily adapted to future site conditions.  If a future Knutson Creek  channel developed along the west edge of the alluvial fan, the road grade off the  alluvial fan from station 86+00 to 88+00 could need to be relocated to a more  suitable location.  (2) Erosion or “stranding” of the tailrace.  By necessity, the tailrace channel crosses the  area where Knutson Creek flowed toward the airport in the 1990s.  A repeat of this  event would damage the tailrace.  Alternately, if Knutson Creek meandered to the  west, it could “strand” the tailrace, effectively lengthening the tailrace.  Corrective  action would depend on the nature of changes and the future location of Knutson  Creek.  The tailrace could be easily rebuilt or moved using on‐site material.  (3)  Erosion of the powerhouse site.  The powerhouse has been sited at the base of an  approximately 50‐foot‐tall embankment that marks the easterly edge of the alluvial  cone, and downstream of a 20‐foot‐tall terrace that has not been eroded by Knutson  Creek.  This location is well‐shielded from Knutson Creek meanders.  The presence of  mature birch and spruce trees in the powerhouse vicinity indicates that Knutson  Creek has not been in this area in at least several decades.  A meander toward the  powerhouse site would first jeopardize the airport, likely resulting in corrective action  to rechannelize Knutson Creek before it directly threatened the powerhouse site.  (4) Meander toward the hydro access road.  The hydro access road traverses the lower  easterly fringe of Knutson Creek’s alluvial fan.  A meander toward the hydro access  road would first jeopardize the airport, resulting in corrective action to rechannelize  Knutson Creek away from this area before it threatened the hydro access road.      From 2010 to 2012, Knutson Creek eroded approximately 5 feet of the east bank from  approximately RM 1.25 to RM 1.30 – the same general area of the breach in the early 1990s.   This project will help prevent future erosion along the east side of Knutson Creek by improving  access to this area.  Improved access will allow for increased monitoring of bank erosion and  will help facilitate timely corrective actions to keep Knutson Creek in its existing channel.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐4 D.2 REVIEW OF CLIMATE EFFECTS ON HYDROPOWER PROJECTS  Long‐term climate trends can affect precipitation, temperature, snowpack, evapo‐transpiration,  and related hydrological processes, changing the amount and timing of discharge in local  streams and therefore the amount of energy that a hydro project can generate.   Because the proposed design flow for this project is a relatively small fraction of the mean  annual flow in Knutson Creek, these climate effects are not likely to impact project  performance significantly over its 50‐year design life.    D.3 GEOTECHNICAL CONSIDERATIONS  Review of surface conditions suggests that bedrock is unlikely to be encountered along most of  the power line route between the village and the hydro powerhouse site.  This route should be  easily trenched for installation of the underground power and communications lines using  conventional equipment and methods.  It is noted that bedrock outcrops do occur in the village  and it is possible that bedrock be encountered along the power line route.  The hydro access road to the powerhouse can be readily graded and shaped from on‐site  materials.  Use of non‐organic on‐site material may be appropriate for the finish course of the  road prism given the low volume of traffic along the road.    Based on surficial observations, bedrock is unlikely to be shallow enough at the powerhouse  site to be of use for the powerhouse foundation.  The location at the top of Knutson Creek’s  alluvial cone and the surficial geology suggest that the powerhouse site will likely be a poorly  sorted and fairly course aggregate deposited by Knutson Creek.  Test pits are recommended to  verify subsurface conditions at the powerhouse site.  The first bedrock outcrops occur along Knutson Creek approximately ½‐mile upstream of the  powerhouse site, and continue upstream to the diversion site.  Bedrock is inferred to be at or  near the surface throughout this area based on these occurrences.  In the immediate vicinity of  the creek, surficial deposits consist of poorly sorted sands, gravels, cobbles, and boulders, with  the largest boulders measuring 6+ feet.  An excavator in the 40,000 to 60,000‐pound class fitted  with a thumb can efficiently manage most of the boulders in the project work areas.    Bedrock may be encountered along the penstock route, and may require blasting in a few areas  in order to achieve sufficient burial of the pipe.  In most areas, it will be more cost effective to  import additional fill than to excavate, rip, or blast the rock.  Rock is expected to be shallower  along the upper portion of the penstock route along the west side of Knutson Creek.  Blasting  could be necessary in the vicinity of the junction between the penstock and the access road,  where the penstock traverses a saddle area.  Bedrock is exposed at the diversion site.  The exposed rock appears to be a competent and  suitable foundation material for a low diversion structure.  Subsurface flow underneath the  diversion structure should be minimal because of the presence of this rock.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐5 D.3.1 Area Geomorphology  The Knutson Creek project is located in either the southern extents of the Alaska Range, or  northern extent of the geographically contiguous Aleutian Range, depending on the  nomenclature used by various source documents.   The project is located on the northwestern  side of this mountain range which extends from the Alaska Range to the northeast (in the  vicinity of Skwentna and Rainy Pass), and runs southwest, following the west shore of Cook  Inlet and continuing down the southern side of the Alaska Peninsula before transitioning into  the Aleutian Islands.    Bedrock Geology  Bedrock geology of the Iliamna Quadrangle was mapped by the USGS in the late 1960s and  1970s, and is shown for the project vicinity in Figure D‐1 (USGS 1980).  The Knutson Valley and  surrounding mountains are formed from an intrusive pluton of quartz monzonite that has been  tentatively assigned a late Cretaceous age.  The quartz monzonite is a massive coarse‐grained  light‐gray prophyritic rock.  Samples considered typical of the formation contain approximately  24 percent quartz, 25 percent orthoclase, 46 percent plagioclase, 4 percent hornblende, and  minor accessory minerals.   Quartz diorite and granodiorite are present in adjacent formations,  and may occur in bedrock of the project area as  well. (USGS, 1980)  Numerous surface presentations of bedrock are visible in Knutson Creek and rock outcrops  along the creek.  The material typically has widely‐spaced joints, and appears very competent.   Most of the boulders, cobbles and sand grains in Knutson Creek are of this same parent rock in  various stages of weathering and decomposition.    Surficial Geology  Surficial geology of the Iliamna Quadrangle was mapped by the USGS in the late 1960s, and is  shown for the project vicinity on Figure D‐2 (USGS 1973).  Surficial geology in the project area is  predominately flood plain alluvium and alluvial cones in the immediate vicinity of Knutson  Creek.  The access road to the powerhouse, powerhouse site, tailrace, and intake site are  located in such areas.  Portions of the penstock route and intake access road located on  benches above Knutson Creek are in areas that include talus and rubble deposits from the  surrounding mountain slopes.  Surface presentations of these features suggest the deposits and  the up‐gradient source terrain are all currently vegetated and stable.  Most of the mass  movements that created these deposits are attributed to past glaciation or immediate post‐ glacial periods.        The project is located in a region of sporadic permafrost.  Most permafrost occurrences in the  region are characterized as relict permafrost surviving from the colder climate of the last  glaciation (USGS, 1973).  The southern aspect and typical surficial geology of the immediate  project area are not favorable to permafrost, but isolated occurrences are possible.     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐6 Figure D‐1 Bedrock Geology of the Project Area                                                Detail from Plate 1, USGS Geological Bulletin 1368‐B (USGS, 1980)    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐7 Figure D‐2 Surficial Geology of the Project Area                                              Detail from Plate 1, USGS Geological Bulletin 1368‐A (USGS, 1973)  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐8 D.3.2 Tectonics and Volcanism  The project site is located midway between two major area faults.  The Lake Clark fault, which is  likely a splay of the Castle Mountain fault system, is located approximately 26 miles northwest  of Knutson Creek, and runs in a northeast – southwest direction.  The Bruin Bay fault, which  generally traces the western shore of Cook inlet, is located approximately 26 miles southeast of  Knutson Creek and also runs in a northeast – southwest direction.  The Bruin Bay fault in the  vicinity of the project probably has not moved since Oligocene time (23+ million years ago)  (USGS, 1980).  The Cottonwood Creek canyon, immediately north of Pedro Bay Village and  normally oriented to the major axis of Knutson Valley, has been identified as a minor local  lineament that may represent a fault, fracture, or joint system (USGS, 1980).    Design of project features in accordance with building codes and accepted engineering practice  is adequate to address seismic activity in the project area.  Several active volcanoes are located in the general vicinity of Knutson Creek.  These include  Fourpeaked, Augustine, Redoubt, and Spurr Volcanoes, all of which have erupted in the past  two decades.  The closest of these is Augustine, which is approximately 35 miles southeast of  Knutson Creek.    The only notable potential hazard to the project from these volcanoes is ash fall.  A significant  ash fall in the Knutson Creek basin could result in suspended ash flowing in Knutson Creek,  which may not be removed by the intake structure.  The abrasiveness of the ash could cause  accelerated wear of the turbine’s water surfaces, shortening its useful life.  Also, airborne ash  entering the hydro powerhouse through inadequately filtered ventilation systems could  damage the generator, switchgear, or controls.  More severe ash falls would compound these  problems and likely create others as well.  A test pit on Pedro Mountain in the project vicinity encountered three significant ash layers ½  to one inches thick within 20 inches of the ground surface, with the most recent being an  approximately ¾‐inch thick layer from the 1912 eruption of Katmai / Novarupta Volcano. (USGS,  1973).               Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  D‐9           This page intentionally blank.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report          APPENDIX E – ENVIRONMENTAL CONSIDERATIONS    Section  Title Page Nos.  E.1 THREATENED AND ENDANGERED SPECIES......................................................................E‐2 E.2 FISHERIES AND WILDLIFE.................................................................................................E ‐2 E.3 WATER AND AIR QUALITY................................................................................................E ‐5 E.4 WETLAND AND PROTECTED AREAS.................................................................................E ‐5 E.5 ARCHAEOLOGICAL AND HISTORICAL RESOURCES...........................................................E‐6 E.6 LAND DEVELOPMENT CONSIDERATIONS.........................................................................E‐6 E.7 TELECOMMUNICATIONS AND AVIATION CONSIDERATIONS ..........................................E‐6 E.8 VISUAL AND AESTHETIC RESOURCES...............................................................................E ‐6 E.9 MITIGATION MEASURES..................................................................................................E ‐6 Attachment E‐1 September 22, 2010 Meeting Record   Attachment E‐2 June 9, 2011 Meeting Record   Attachment E‐3 Fisheries Survey Report        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  E‐1            This page intentionally blank.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  E‐2  E.1 THREATENED AND ENDANGERED SPECIES   The U.S. Fish and Wildlife Service and National Marine Fisheries Service were contacted about  this project.  Both agencies confirmed that the project area is not listed as critical habitat for  any threatened or endangered species.    E.2 FISHERIES AND WILDLIFE   The project does not significantly affect upland habitat areas, so no wildlife impacts are  expected.    Because the proposed project would partially dewater anadromous and resident fish habitat,  Polarconsult consulted with ADF&G at the beginning of the feasibility study to scope out the  resource studies and environmental restrictions that would apply to the project to protect fish  habitat.  Polarconsult met with Ronald Benkert of ADF&G on September 22, 2010, and met  again with Ronald Benkert, Monte Miller, Jason Mouw, and Stormy Haught on June 9, 2011.   ADF&G indicated that the project could be permitted, and the key issues would be the level of  study warranted to define fisheries impacts and the proper design of mitigation measures to  protect or compensate for habitat impacts.  Records of these meetings are included as  Attachments E‐1 and E‐2 to this appendix.      In 2012, Polarconsult contracted with Alaska Biological Consulting, Inc. (ABC) to complete an  assessment of fisheries resources in Knutson Creek that may be affected by the hydro project.   ABC conducted more in‐depth consultations with ADF&G in the summer of 2012, contacting  ADFG personnel (including Dr. Robert Piorkowski, Slim Morstad, Fred West, and Jason Dyle)  regarding design of the fisheries survey performed at Knutson Creek in August 2012, and also  consulting with biologists Slim Morstad (ADF&G) and Dr. Thomas Quinn (University of  Washington) regarding the limiting resources for sockeye production in the Iliamna Lake  system.  ABC’s full report is included at the end of this section as Attachment E‐3.  Key findings  are summarized below.  The lower portion of Knutson Creek up to approximately RM 2.1 is anadromous habitat for  Sockeye salmon, and the entire reach of Knutson Creek under consideration for this project is  resident habitat for Dolly Varden.    The project will seasonally reduce flow in approximately one mile of anadromous habitat, from  the proposed tailrace discharge at RM 1.1 upstream to the limit of anadromous habitat at RM  2.1.  The project will significantly reduce flow in the bypass reach of Knutson Creek (50%  reduction or more) from approximately mid‐November through mid‐April.  Flow reductions of  approximately 90% would occur from approximately mid‐January to early April.  During the  summer and fall (approximately mid‐April to mid‐November), flow reductions would be minor  to negligible (less than 30% flow reduction).  See Figure E‐1.  Flow would be maintained in Knutson Creek by tributary flow from numerous minor drainages  and the two major tributaries R1 and L1.  Tributary L1 discharges to the bypass reach at RM 2.1,  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  E‐3  above anadromous habitat, and Tributary R1 discharges to the bypass reach at RM 1.3,  approximately 0.2 miles upstream of the tailrace.  The drainage subbasins for these tributaries  are shown on Figure A‐3.  Subbasin drainage areas are tabulated in Table E‐1.  Figure E‐1  presents flow at the top of anadromous fish habitat under natural conditions, with the hydro  project without in‐stream flow reservations (ISFR)s, and with the 6.6 cfs year‐round ISFR  assumed in this study.  Without any ISFRs, the recommended hydro project is able to meet 100% of existing utility  demand year‐round.  The 6.6 cfs ISFR assumed for this study reduces that performance to  94.5% year‐round, meaning that the utility would still need to purchase and burn approximately  1,200 gallons of fuel annually.  The present value of this fuel expense over 50 years is  approximately $200,000.  The 6.6 cfs ISFR also reduces the amount of excess energy that can be  used by interruptible electric heating services, increasing the amount of heating fuel burned in  Pedro Bay Village for space heating.  This is estimated at 3,300 gallons of heating fuel annually.   The present value of this fuel expense over 50 years is approximately $570,000, resulting in a  total present worth of the 6.6 cfs ISFR estimated at $770,000.       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  E‐4  Table E‐1 Areas of Knutson Creek Subbasins  Subbasin Subbasin Area (square miles)  Subbasin as  Percentage of  Diversion Subbasin  Total Upstream  Basin Area  (square miles)  Above hydro project diversion   (RM 2.59 to headwaters) 29.17 100% 29.17  Hydro project diversion to Tributary L1   (RM 2.10 to 2.59) 0.74 2.6% 29.91  Tributary L1   (enters Knutson Creek at RM 2.10)  3.16 10.8% 33.07  Tributary L1 to Tributary R1   (RM 2.10 to RM 1.30) 0.77 2.6% 33.84  Tributary R1   (enters Knutson Creek at RM 1.30) 1.67 5.7% 35.51  Tributary R1 to hydro project tailrace   (RM 1.30 to RM 1.10) 0.19 0.6% 35.70  Hydro project tailrace to Lake Iliamna   (RM 1.10 to 0.00) 1.41 4.8% 37.11  Total Knutson Creek drainage (at Lake Iliamna) 37.11 126% 37.11  E.2.1 Anadromous Habitat  It appears that most of the anadromous habitat in the project’s bypass reach is marginal.  ABC  estimated the productivity of this one‐mile reach of Knutson Creek to be approximately 100  returning adult salmon, which may or may not successfully spawn in the bypass reach.  By  comparison, the lower mile of Knutson Creek below the project and shores of Knutson Bay  support many 1,000s of sockeye salmon.  Off‐site mitigation appears to be a good option for  addressing impacts to anadromous habitat in the bypass reach.  Two options suggested by ABC  include construction of additional highly productive fish ponds near the airport or constructing  the project tailrace channel to provide replacement habitat.   E.2.2 Resident Habitat  Dolly Varden are present throughout the proposed bypass reach of Knutson Creek.  ABC  concluded that suggested off‐site compensatory habitat proposed to mitigate impacts to  anadromous habitat would also address impacts to resident fish habitat.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  E‐5  0 10 20 30 40 50 60 70 80 90 100 Jan 1Feb 1Mar 3Apr 3May 4Jun 4Jul 5Aug 5Sep 5Oct 6Nov 6Dec 7Knutson Creek Flow at RM 2.1(Top of Anadromous Habitat) (cfs)Proposed Design Flow, cfs Existing Mean Daily Flow Bypass Flow with 6.6 cfs ISFR Bypass Flow with no ISFR Figure E‐1 Estimated Knutson Creek Flow at RM 2.1 (Top of Anadromous Habitat)                            ISFR: in‐stream flow reservation    RM: river mile    cfs: cubic foot per second  E.3 WATER AND AIR QUALITY   The project will not negatively impact water or air quality.  By reducing diesel combustion in  Pedro Bay, the project will improve local air quality.  By reducing the amount of fuel shipped to  Pedro Bay for power generation, the project will also incrementally reduce the risk of fuel spills  that could degrade water quality.  E.4 WETLAND AND PROTECTED AREAS  The diversion and intake structures are by necessity located within the ordinary high water  mark of Knutson Creek.  The creek bed at the proposed diversion structure is a combination of  exposed bedrock, cobbles, and boulders.    The penstock route passes near some wetland terraces between approximately station 16+00  and 26+00 and may have some unavoidable wetland impacts.  Other project features do not  pass through significant wetland areas although some small unidentified wetlands may exist  along the proposed routes.  Many of these small wetland areas can likely be avoided in final  design once they are identified.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  E‐6  E.5 ARCHAEOLOGICAL AND HISTORICAL RESOURCES  No archeological or historical resources are known to exist in the project area.  E.6 LAND DEVELOPMENT CONSIDERATIONS  The proposed access road to the powerhouse site will provide improved vehicular access to  undeveloped property north of the airport.  The proposed power line route will extend electric  service to undeveloped property along the airport access road, as well as undeveloped property  along the hydro access road up to the powerhouse site.  These improvements will help to  reduce the cost of developing this land.  Some of this land may be subject to flood hazards from  Knutson Creek.  E.7 TELECOMMUNICATIONS AND AVIATION CONSIDERATIONS  The project will not affect telecommunications or aviation.  E.8 VISUAL AND AESTHETIC RESOURCES  The project will not be visible from popular vantage points on the ground surrounding Pedro  Bay Village.  The only vantage point from which the project will generally be visible is from the  air.  E.9 MITIGATION MEASURES  Based on current information, total wetlands impacted by this project will likely be under ½  acre.  No mitigation is expected to be necessary for this acreage of wetlands impact.    The project will reduce flow in the bypass reach of Knutson Creek by 50% and more during the  winter months (approximately mid‐November through mid‐April).  This will impact resident and  anadromous fish habitat in Knutson Creek.    Mitigation options for these potential impacts include a minimum ISFR for the anadromous  portion of the bypass reach of Knutson Creek, construction of off‐site compensatory habitat to  make up for lost habitat in Knutson Creek, or payment as mitigation as allowed in AS 16.05.851.   These options are discussed in greater detail in the fisheries report included as Attachment E‐1  to this appendix.    Based on available information, it appears that construction of compensatory habitat is the  most appropriate mitigation measure for this project.  ISFRs would decrease generation  capacity during the winter months, when the need for affordable energy in Pedro Bay is  greatest.  Similarly, annual payments would place undue financial stress on the community.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix E              This page intentionally blank.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix E        ATTACHMENT E‐1   POLARCONSULT MEETING RECORD  SEPTEMBER 22, 2010 MEETING WITH ADF&G    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix E            This page intentionally blank.  polarconsult alaska, inc. ENGINEERS - SURVEYORS - ENERGY CONSULTANTS specializing in energy conservation systems CONVERSATION RECORD DATE: PROJECT: TIME: September 22, 2010 10002-Pedro Bay Feas 9:00 AM CONTACT: COMPANY: Ron Benkert Adfg PHONE#: FAX#: Taken By: 267-2113 Joel Groves SUBJECT: Knutson Creek Hydro SUMMARY: Met w/ Ron at his office to review proposed project. Existing data: ADFG had field crews in the area this summer, they may have done more fish studies on Knutson Creek. Not sure, as they are focused on studies related to Pebble road work, and the road is down in known habitat on Knutson. He will check and see and let me know. Their consultants are still in the QA/QC phase and hadn’t released data. He wasn’t sure what the upper limit of fish habitat was, if it was the designated limit at 200’ elevation contour or if that was just how far past studies had looked. He had requested the data to see what the basis of the existing habitat delineation is. On the project, he said that the winter flows were critical to rearing in the habitat reach, and 80% retained in-stream flow would be a safe number for permitting. Could do less in the final permitting, 60%, 70%, but would need more studies or analysis to demonstrate this would be acceptable to fish habitat. 20% is likely not viable. Would need more fish studies to better determine the upper limit of habitat. Main question to be answered is if the intake area is habitat. If so, then fish screens at the intake would be necessary. He pointed out that negative fish trapping results weren’t always conclusive. They’ve seen some creeks where fish are intermittently present, and may come and go from year to year. I mentioned our intent to install a gauge, he said this would be useful data, as well as more pictures of the project area and the habitat in Knutson Creek in the project vicinity. Also discussed tributary ‘R1’. He concurred that it would likely be easier to permit, based on the apparent higher gradient and presumed lack of fish habitat. This would still need to be verified with trapping. He noted that R2 and HDR both are familiar with the area for fish work. Also mentioned that ballpark numbers for dolly varden and sculpin are that they are not present in creeks above 20% grade. Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix E        ATTACHMENT E‐2   POLARCONSULT MEETING RECORD  JUNE 9, 2011 MEETING WITH ADF&G      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix E            This page intentionally blank.  polarconsult alaska, inc. ENGINEERS - SURVEYORS - ENERGY CONSULTANTS specializing in energy conservation systems CONVERSATION RECORD DATE: PROJECT: TIME: June 9, 2011 10002 3:45 PM CONTACT: COMPANY: Ron Benkert Adfg PHONE#: FAX#: Taken By: Joel Groves SUBJECT: Knutson Creek Fish Issues & Project Update SUMMARY: Meeting with Ron Benkert (RB), ADFG Habitat. Also present were: Stormy Haught (SH) Jason Mouw (JM) (regional sport fish) Monty Miller (MM) (statewide hydropower coordinator) Joel Groves (JG) provided a brief overview of polarconsult, other hydro projects currently underway at Polarconsult. JG provided overview of project history, current phase and status of study, current development concept and configuration. Discussed existing habitat limit. JG stated that the habitat limit indicated in the Fish Atlas did not seem to have a physical barrier, although there was a potential barrier in the canyon. There is little apparent valuable habitat above this point, but if fish can make it here, they can probably keep going upstream. MM asked about jurisdiction, JG opined that the project was not likely under FERC jurisdiction. MM felt that it would be because the fisheries resource is Bristol Bay sockeye, which has a clear interstate commerce status. RB stated key issues for habitat: screens at the intake (1 mm) and tailrace, and minimum flows in the bypass reach. Intake screen is a big challenge and cost, icing in particular is an issue. This is all in flux until some firm data on the resource are available. Habitat mapping, fish trapping, etc. RB requested that future hydrographs be linear, not log, so they are easier to interpolate. Told him that once the hydrology study is done, will provide a better characterization and presentation of proposed flow regimes. Current data is interim. JG mentioned the fish present in fens on the west side of the alluvial fan (far side of Knutson Creek from village). MM speculated that these fens could be hydraulically connected to Knutson Creek, and at risk from a diversion. JG clarified that he observed the fens to be directly fed by surface drainage from the bluffs along the west edge of the alluvial fan. A surface connection to the main channel of Knutson Creek wasn’t polarconsult alaska, inc. ENGINEERS - SURVEYORS - ENERGY CONSULTANTS specializing in energy conservation systems observed, but probably existed downstream where the fens presumably exit to Knutson Creek or perhaps directly to the lake. JG did not hike down to these areas. JM provided an overview of the typical assessment process: 1. Habitat mapping to understand what is out there. 2. Habitat utilization to understand what is using the habitat. Spatial and temporal. 3. Transects and similar analysis to understand what impacts dewatering the habitat reaches may have on fisheries. Unclear at this time how far down this progression the study would need to go. If field work indicates little spawning habitat, then less study, and so on. RB stated that ADFG was unable to do any trapping or field work in support of this project. They might be able to do some work under contract, but he wasn’t sure (potentially less costly than a contract biologist). JM mentioned that University of Washington has been doing work on Knutson Creek for years, and may have some data that is pertinent to this project. Contacts are Tom Quinn and Dan Schlinder. Preliminary assessment is that this project looks doable, but need field data and analysis to make a final determination. Talked about timing of in stream work. Generally, the window is 6/1 to 7/15. Earlier JVs are out-migrating, and later adults are in-migrating. This would pertain to equipment fording of the creek. Intake work would have to occur in March/April to avoid high water. Intake area would be dewatered so no fish impacts expected. Mentioned bridge crossing, said that expected to keep supports above OHW to avoid flood hazards, so habitat permit may not be necessary. (?) indicated that standard guidance for minor creek crossings was 48” dia culvert or provide 1.2x bank full width in culvert or under bridge. Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix E        ATTACHMENT E‐3   FISHERIES SURVEY REPORT    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix E            This page intentionally blank.       Technical Report No. 12-011 __________________________________________________________ A Fisheries Survey of Upper Knutson Creek Associated with Potential Hydroelectric Development for Pedro Bay, Alaska by Bruce M Barrett September 2012 ________________________________________________________________________________ Alaska Biological Consulting PO Box 322 Lakeside, MT 59922-0322 Tel: 406-844-3453 E-mail: alaskabiol@yahoo.com 1 INTRODUCTION Knutson Creek, an inlet stream of Iliamna Lake on the northeast end, is designated as an anadromous fish stream under Alaska Statute 16.05.870 (Figure 1). The stream lies northwest of the community of Pedro Bay, Alaska and is being considered as a potential hydroelectric energy source for the village by the council. Polarconsult Alaska, Inc. is conducting the feasibility study. The proposed project calls for diverting approximately 10-20 cfs of water from Knutson Creek at RM 2.6 and returning the diverted flow at RM 1.2. The need for an alternative energy source for Pedro Bay Village is evident with diesel selling at $6.90/gallon and electricity at 91 cents/kwh there (personal communication, Ben Foss). Lower Knutson Creek is occupied by anadromous and resident fishes based on ADF&G’s Catalog of Waters Important for Spawning, Rearing, and Migration of Anadromous Fishes (2012). The species listed are: Dolly Varden and slimy sculpin (resident fishes) and sockeye salmon (anadromous fish). To properly evaluate the potential impact to fisheries resources from construction and operation of a small-scale hydro power facility on Knutson Creek, it is essential under Alaska Title 16 statutes to determine the extent of resident and anadromous fish use within the proposed project reach (RM 1.2- RM 2.6) and also the level of use by subsistence and recreational fishers. This report is intended to serve that purpose. OBJECTIVES The objectives of this study were: 1. Determine fish presence by species and their approximate distribution in upper Knutson Creek from about RM 1.2 to 2.7 (approximately 1.5 miles); 2. Determine average fish size by species in the study reach, excluding sculpin and adult sockeye salmon; 3. Classify the general stream characteristics within the study reach; 4. Determine whether upper Knutson Creek is used by local residents for subsistence and/or sport fishing; 5. Identify potential fish mitigation alternatives. METHODS A standard salmon escapement survey was conducted on foot with the observer using polarized glasses and a tally counter. Counts (live fish and carcasses) by species were recorded per ¼ mile stream reach beginning at approximately RM 1.25 and extending upstream to RM 2.7 (Figure 2). The upper most point of observed adult salmon presence was documented by GPS. Ten standard minnow traps were deployed at multiple locations in upper Knutson Creek with one in a tributary near its Knutson Creek confluence and seven traps within the proposed main-stem project reach and two about 0.2 miles further upstream (above the proposed hydro-intake) in the area of a tributary confluence (Figure 2). Average fishing time per trap was 6.4 h (range: 0.9-21.5 h). Trap bait consisted of sockeye salmon (Oncorhynchus nerka) roe provided by a Pedro Bay sport-fishing lodge. Each trap was baited with two sections of roe (approx. 20 g/each) individually secured in a cheesecloth wrap. All baits were disinfected by a 10-m soak time in 1/100 Betadyne, and each trap site was a low velocity location, typically behind boulders along the stream bank. All traps deployed were weighted with one or two medium size cobble and secured by a line attached to the shore. Trap locations were identified by GPS and flagged for visual identification. 2 Fish captured were confirmed by species in accordance with Pacific Fisheries of Canada (1973). A total of 129 Dolly Varden (Salvelinus malma) from the traps were measured for FL (tip of snout to fork-of tail, mm). Two larger caught Dolly Varden were examined for maturity. Rearing fish presence was also evaluated by visually inspecting low velocity near-shore bank areas and pools in secondary mainstem flow channels between the powerhouse area and the proposed hydro-intake on the creek’s right side (looking upstream). The left (west) side of Knutson Creek was not assessable due to stream flow conditions. Fish sampling was conducted incompliance with an ADF&G issued collection permit (SF2012-266), and field assistance was provided by Vern Jensen while logistical support at Pedro Bay was given by Ben Foss and daughter. RESULTS Resident Fish A total of 256 Dolly Varden (DV) were captured in 10 minnow traps deployed for 58 hours in the study area, and all traps produced a catch (Tables 1-2; Figure 3). The DV captured were considered resident fish given size and sexual maturity. The average FL measured was 11.9 mm (4.7”) and the range was 5.8- 19.3 mm (2.3- 7.6”; Tables 3-4). Of two DV sampled for maturity, both were found to be sexually mature (Figure 4.) No other resident fish species were caught or observed in Knutson Creek with the exception of approximately six young-of-year (YOY) fish which were likely sculpin (Cotus sp.) in an elevated flow channel off the left side of Knutson Creek mainstem between trap sites #1 and #2 (RM 1.6-1.7). These YOY fish, visually judged to be juvenile sculpin, were approximately 20 mm in length and displayed a darting type swimming motion when disturbed. At several trap locations, “small” size fish were readily visible and particularly at trap sites T-1 and #9 both of which had a tributary influence. Likewise in many other low velocity areas of the main-stem, “small” fish were readily visible including the reach sampled above the proposed hydro-intake. Based on trap catches and visual assessment, all were considered to be DV. Further, where traps were set at these locations, “small” sized fish were observed entering the traps within minutes of their placement and as defined earlier, all trap-caught fish were DV. Anadromous Fish The upper limit for anadromous fish in Knutson Creek is approximately RM 2.04 as defined in ADF&G’s Catalog of Waters Important for Spawning, Rearing, and Migration of Anadromous Fishes (2012). On August 23, 2012 a total of 43 adult sockeye salmon were counted above RM 1.25 under ideal survey conditions (Tables 2 and 5). Of these, 40 were alive and three were carcasses, one of which was bear-killed (Figures 5-6). All but one of the 40 live fish were either paired or aggregated and all were in spawning condition. Most of the adult sockeye counted were in the immediate area of trap site #2 and split into two aggregates, both within 3 meters of the bank and holding over sandy-gravel substrate in relatively low velocity areas. The furthest adult sockeye salmon observed in Knutson Creek was as at RM 2.1, at a site about 4 meters below the lower gaging station. The sighting was limited to a single male in spawning condition and represents a slightly higher stream location than previously known (ADF&G 2012). No juvenile salmon were caught in any of the 10 minnow traps, indicating their absence in Knutson Creek upstream of about RM 1.25 (Table 2). 3 Fisheries Use Upper Knutson Creek (above RM 1.25) supports minimal bear use based on the low number of adult sockeye observed. Only one bear-killed salmon carcass was found, and there was no evidence of any regular bear-trails, and one scat was observed (Figure 6; 2.5-d of observation (8/23-25/12)). Two (>50yrs/old) male Pedro Bay residents were queried on the communities’ dependence on upper Knutson Creek for subsistence use. Both reported that the upper stream is not currently used nor has it been used in the past. They indicated that the lower river near the lake below RM 0.5, and mainly the river mouth provides recreational and subsistence fishing. General Habitat Observations The stream bed in the proposed project reach is comprised of moderate sized granite cobbles, boulders, and course sands, in order of abundance. No silt deposits were observed and cobble embeddedness was minimal at an estimated maximum of 5% in the near-shore (0-50cm depth). Mainstem water clarity was excellent, fully transparent. While not specifically measured the OHW channel width was visually estimated to average about 1.5x of the stream width in most areas. Knutson Creek water temperature was 45F at trap site #5 (8/23/12; 1227 hrs), and 48F in the tributary at trap site T-1, and 49.5F in a backwater channel of the same tributary where an estimated 40-50 DV in the 7-15 cm FL range were readily visible at the time of trap placement (8/23/12; 0952hrs; Figure 7). Stream gradient was estimated to be about 2-3% in the project reach except for 5-6 % where the stream passes through a canyon at RM 2.0. While no barrier falls were noted several areas from trap site 2 upstream supported a series of cascades with two to four ft. of vertical drop each (e.g. Figures 8-9) that were commonly sparse of fish resting and/or holding areas. While the vertical drops would not likely impede the assent of pre-spawning condition adult salmon, they appeared formidable enough to retard most spawning condition adults such as observed in the area of trap sites #1 and #2. DISCUSSION Fisheries Knutson Creek supports adult sockeye salmon and resident DV in the reach proposed for hydro-electric development. As compared to lower Knutson Creek and the lake-shoals off its stream mouth, the upper stream provides minimal sockeye spawning habitat and use. Peak escapement counts in the lower river and Knutson Bay average about 600 (yrs. 2002-11) and 96,000 (yrs. 2007-11) sockeye salmon, respectively (Morstad, 2012). An estimate of the total 2012 sockeye escapement for the hydro-electric reach can be made by expanding the peak count of 40 live fish by a factor of 2.47 as derived from peak aerial counts and weir and tower escapement numbers from other sockeye systems (Eggers et. al. 2012). Total escapement within the boundaries of the hydro-sockeye salmon project amounts to an estimated 99 sockeye salmon. DV are present throughout the study reach and evidence is that the upper stream offers both rearing and spawning habitats. The former is based on high trap catch numbers and sight observations while the later is based on two sexually mature DV sampled from trap #6 measuring 15.2cm and 15.7 cm (6 and 6.2 inches). The lateral tributaries flowing into Knutson Creek provide DV rearing habitat also as some of the highest minnow trap catches were in and around the mouths of two sampled tributaries. While DV are relatively abundant and well distributed in the project area, they are small in size based on an average 12cm FL (4.7 inches) and are not known to support any fishery (subsistence or sport). 4 The absence of any juvenile salmon in the minnow traps set in upper Knutson Creek was not unexpected particularly for juvenile sockeye fry which typically rear in lakes, sloughs, and ponds where a strong zooplankton forage base exists such as Iliamna Lake (Hart 1973). Any fry produced from stream- spawning sockeye salmon would expectedly descend into Iliamna Lake after emerging in the spring. Because Coho salmon are not known to spawn in Knutson Creek (ADF&G 2012), and adult Coho salmon are not common in either Knutson Bay or Pedro Bay of Iliamna Lake, per local knowledge, explaining why juvenile Coho fry were not caught in Knutson Creek above RM 1.2. Mitigation The first question for mitigation consideration is what level of impact might the proposed project have on fish migration, and spawning and rearing habitats from RM 1.2 to RM 2.6, and further what if any opportunities might be available to mitigate potential impacts? Resident Fish It is unlikely that summer rearing habitat for DV would be adversely impacted. From site observations and trapping most if not all of the rearing occurs within the near-shore (<5 m) where water velocity is manageable. With early May through early October flows in Knutson Creek are expected to be in the 80- 300cfs range (pers. com. Joel Groves), a withdrawal of 15-20 cfs at the intake should have no measurable impact on DV movement and/or rearing during that time irrespective of tributary inputs in the RM 2.6 - 2.1 reach. In winter months, the water withdrawal would reduce mainstem flow likely enough to assume that any eggs or spawn incubating in the mainstem would be lost due to dewatering and freezing. Also some pool areas where DV typically overwinter would likely be reduced or lost particularly in the ½ mile reach between RM 2.6 and 2.1 or the area between the intake and tributary “L1” (Figure 1). Because resident DV are not migrating in the winter, fish passage would not be an issue nor would it be in the spring through fall months when there would be more mainstem flow at RM 2.6 then needed for power generation. While DV would be impacted by the proposed project, the impact level should be negligible considering the amount of habitat upstream and downstream of the project reach. However , compensation in the form of replacement habitat could easily be achieved as a byproduct of anadromous fish, specifically sockeye salmon, mitigation opportunities as addressed below. Anadromous Fish Since sockeye salmon currently spawn above the proposed powerhouse site, albeit in relatively low numbers, some fisheries losses would likely occur if nearly all of the Knutson Creek main-stem flow were divereted for power use during the late fall and winter months. This is under the assumption that the upper stream currently provides suitable spawning conditions for successful egg incubation. The impact would be from reduction of the wetted channel width resulting in redds freezing and causing egg mortality. Naturally, this may already be occurring as the sockeye spawning observed was near the edges of the stream in relatively low velocity and in shallow areas which would make the fertilized eggs susceptible to mortality as mainstem flow naturally decreases with freeze-up. Further, it is not unlikely that most of the sockeye counted in the survey were stray fish produced from lower spawning areas. With thousands of fish spawning in Knutson Bay, a minor level of straying could well explain the presence of 43 adult sockeye salmon in the project reach. University of Washington studies indicate that localized straying does occur and between major Pedro Bay pond groups, sockeye salmon straying averages about 4% (Quinn et. al. 2012). Replacement salmon spawning habitat could be developed offsite at Pedro Bay. Several natural groundwater fed ponds are in and around the village that provide sockeye salmon spawning and some DV rearing. The ponds are relatively shallow (about 26 cm (10.2 inch) average depth) and extensively used by brown and black bears for feeding. Pond P1 as partially shown in Figure 10 and described in Quinn et. al. (2012) extends to within 20 feet of a primary Pedro Bay service road (Figure 1). Land setback from the pond by about 10+ yards could be excavated to a depth of about 5-6 feet to create a small (800ft2) auxiliary pond that when connected by a culvert (30-36 inch dia.) to Pond P1 would provide spawning area for about 5 200 sockeye salmon based on a reported average spawner density in Pond P1 of 0.4 m2 (Quinn et. al. 2012). An excavator and other resources are available at Pedro Bay Village to perform the work, and access would be a non-issue including water quality and sedimentation if standard safeguards are followed. This would include excavating the pond without a connection to Pond P1 until all fill material including the banks of the new pond are well vegetated. The conduit connection would follow and be performed using silt barriers and other standard water-quality control methods. An alternate mitigation proposal is to construct a spawning channel at the tailrace discharge. The design would be dependent upon where the power house is sited, but overall there should be ample ground to provide about 1,000ft 2 of spawning area as replacement habitat for about 100 sockeye salmon in upper Knutson Creek (assumes average spawning density of 1 female/2 m2 in Bristol Bay streams (Groot and Marcolis 1991)). The advantage of a spawning channel is flow stability and less erosion than the creek’s mainstem. Further, a spawning channel would provide direct onsite mitigation therein lessening the impact to upper Knutson Creek sockeye salmon, assuming that sockeye production is occurring in the stream’s upper reaches which may not be the case, for reasons addressed earlier. LITERATURE CITED Alaska Department of Fish and Game. 2008, updated 2012. Catalog of waters important for spawning, rearing, and migration of anadromous fishes. ADF&G, Sport Fish Div., Juneau, AK. Eggers, D., Munro, A., and Volk, E., 2012. Estimating escapement of western Alaska sockeye salmon for wassip reporting groups, 2006 to 2008. Tech. Doc. 18, Western Alaska Salmon Stock Identification Program, ADF&G, Juneau, AK. Groot, C. and Margolis L. 1991. Pacific salmon life histories. UBC Press, Vancouver, BC. Hart, J.L. 1973. Pacific fishes of Canada. Bull. 180; Fish. Res. Bd. Canada. Morstad, Steve. 2012. ADF&G salmon escapement survey database ,download June 23, 2012. ADF&G, Div. Comm. Fish., King Salmon, AK. Ouinn, Thomas P. Jr., Gosse, D., and Schtickzelle N., 2012. Population dynamics and synchrony at fine spatial scales: a case history of sockeye salmon (Oncorhynchus nerka) population structure in Alaska, USA. Can. J. Fish. Aquat. Sci. 69: 297–306. ` 6 Table 1. Summary of minnow trap catch results in total number of fish, and average hourly catch by location, date, and species, Knutson Creek, near Pedro Bay, 2012. TRAP Dates Total TOTAL CATCH Avg. Hourly # LOCATION Fished Hours DOLLY other Catch VARDEN Dolly Varden T-1* N 59 48.786 8/23/2012 7.77 39 0 5.0 W 154 07. 361 1 N 59 48.846 8/23/2012 6.75 71 0 10.5 W 154 07. 341 2 N 59 49.069 8/23/2012 5.72 34 0 5.9 W 154 07. 039 3 N 59 49.146 8/23/2012 4.90 6 0 1.2 W 154 06. 889 4 N 59 49.172 8/23/2012 4.00 34 0 8.5 W 154 06. 850 5 N 59 49.195 8/23/2012 3.47 19 0 5.5 W 154 06. 870 6 N 59 49.204 8/23/2012 2.65 14 0 5.3 W 154 06. 789 7 N 59 49.507 8/24/2012 0.87 17 0 19.5 W 154 06. 502 8** N 59 49.598 8/23/2012 0.38 1 0 2.6 W 154 06. 403 8/24/2012 **1 0 ** 9 N 59 49.598 8/23/2012 0.22 6 0 27.3 W 154 06. 403 8/23-24/2012 21.25 14 0 0.7 TOTALS 57.98 256 0 Average 8.4 * Site in lateral tributary 50yds upstream of Knutson Cr. confluence ** Trap dislodged from site found x-wise in stream 7 Table 2. Fish catch numbers by species using a standard minnow trap by location, Knutson Creek, an Iliamna Lake inlet stream near Pedro Bay Village, August 23-24, 2012. TRAP CATCH # LOCATION DATE TIME DOLLY other Notes VARDEN **T-1 N 59 48.786 8/23/2012 0952 hrs Elv. 210 ft. W 154 07. 361 **Side channel of right-bank tributary (R1) 50 yds above Knutson Cr. confluence; trib. water temp.: 48F; side channel: 49.5F Bank veg.: alder and willow, dense Stream bed: cobble 90%, 10% boulder 8/23/2012 1738 hrs.39 0 surface vel: 2.4 ft/sec approx. Trib.input to main stem about 2% volume 1 N 59 48.846 8/23/2012 1022 hrs ELV: 243ft. W 154 07. 341 Right-bank trap set behind large boulder Sockeye adults: 17 live & 1 carcass (bear kill) in immediate area; spawning Excellent survey conditions; water clear 8/23/2012 1723 hrs.71 0 All spawning w/i < 10ft. of stream bank 2 N 59 49.069 8/23/2012 1106 hrs Elv. 277 ft. W 154 07. 039 Right-bank set Alder/willow & cottonwood bank veg. Trap in 18" depth Sockeye adults: 22 live, 2 carcasses counted between trap site 1& 2; spawning 8/23/2012 1649 hrs.34 0 3 N 59 49.146 8/23/2012 1138 hrs Elv. 294 ft. (est.) W 154 06. 889 Loc. at lower stream gage station Set behind bank boulder; 20inch depth Right-bank set Boulder (5ft dia.) and cobble bed 8/23/2012 1630 hrs. 6 0 Sockeye adult: 1 live 4m downstream 4 N 59 49.172 8/23/2012 1205 hrs Elv. 304 ft. W 154 06. 850 Loc. at upper (2nd) gage station Boulder/ cobble bed Trap depth: 18 in. 8/23/2012 1605 hrs 34 0 Site across from left-side trib. (L1), approx 5% of mainstem flow 5 N 59 49.195 8/23/2012 1227 hrs Elv. 309 ft. W 154 06. 870 Water temp: 50F Trap depth: 18 in. Bank veg: alder(50%) and willow (50%) Bed: Boulder cobble w/ course sand in eddies Right-bank set 8/23/2012 1555 hrs 19 0 6 N 59 49.204 8/23/2012 1247 hrs Elv. 356 ft. W 154 06. 789 Right-bank set behind table boulder (6X2X12ft.) Bank veg: alder(50%) and willow (50%) 8/23/2012 1526 hrs 14 0 DV 6.0 and 6.2in. (fl) mature male & female 8 Table 2. Page 2 of 2. TRAP CATCH # LOCATION DATE TIME DOLLY other Notes VARDEN 7 N 59 49.507 8/23/2012 1334 hrs Elv. 384 ft. W 154 06. 502 Bank veg: alder(50%) and willow (50%) Right-bank set Bed: cobble/boulder/ course sand Trap depth: 15in. 8/24/2012 1128 hrs * * Trap clasp sprung catch lost; trap baited/reset 1220 hrs 17 0 8 N 59 49.598 8/23/2012 1417 hrs ELV. 402 ft; immediately below right-side trib. (R2) W 154 06. 403 1440 hrs 1 0 trap depth:16 in. Right-bank set 8/24/2012 1142 hrs 1 0 8/24/12: Trap found 3yd. downstream cross- wise in current making trap unfishable. 9 N 59 49.598 8/23/2012 1415 hrs Elv. 403 ft. W 154 06. 403 8/23/2012 1428 hrs 6 0 Upstream of proposed hydro-intake Immediately above rt.-side trib. (R2) Trib: adds approx. 20-30% of mainstem flow 8/23/2012 1440 hrs * * reset trap; bank veg.: 60% willow, 35% alder, 2-5% spruce 8/24/2012 1155 hrs 14 0 Right bank set; 20 inch depth 9 Table 3. Sampled fork lengths (cm) of Dolly Varden captured, by selected minnow trap, in upper Knutson Creek, an Iliamna Lake inlet stream near Pedro Bay Village, 8/23-24/2012. Specimen Trap Trap Trap Trap Trap Trap Trap Number # 2 # 3 # 4 # 5 # 6 # 8 # 9 1 6.4 11.9 8.6 14.2 10.4 15.9 15.2 2 10.2 10.9 10.7 15.2 14.2 11.4 14.2 3 9.9 14.0 10.2 11.9 13.7 13.2 4 10.9 12.7 11.4 10.7 11.9 12.2 5 10.4 13.7 12.7 14.7 12.7 11.2 6 9.7 12.4 12.2 15.0 9.9 11.2 7 10.9 11.9 13.5 9.7 13.0 8 11.7 13.2 11.7 10.2 11.4 9 6.9 12.7 13.5 10.9 12.7 10 13.2 11.7 11.9 7.4 17.0 11 7.4 16.3 8.9 12.4 13.5 12 9.9 11.7 15.0 11.4 16.8 13 9.4 13.2 11.2 15.2 11.4 14 12.2 19.3 10.9 15.7 15.0 15 11.2 13.7 11.7 12.4 16 15.5 13.0 11.4 12.2 17 14.5 11.7 12.2 12.4 18 11.7 11.4 10.2 13.7 19 5.8 13.7 5.8 12.7 20 12.2 14.7 14.7 21 11.7 15.5 22 12.4 13.2 23 13.0 11.9 24 11.4 9.4 25 10.2 8.6 26 10.9 9.1 27 9.4 12.2 28 10.7 11.7 29 8.6 11.9 30 10.9 12.2 31 8.9 12.7 32 10.2 7.4 33 15.5 9.1 34 8.9 12.7 10 Table 4. Selected length (FL) statistics on Dolly Varden sampled on upper Knutson Creek, an Iliamna Lake inlet stream near Pedro Bay Village August 23-24, 2012. Sample Size Mean Median Range Standard (n)cm inches cm inches cm inches deviation (mm) 129 11.9 4.7 11.9 4.7 (5.8 - 19.3)(2.3 - 7.6) 2.3 Table 5. Salmon escapement survey of upper Knutson Creek , by species, from RM 1.25 to RM 2.7, August 23, 2012. River Mile Reach Survey Sockeye Salmon other Start End Conditions Live Dead Total Live Dead Total 1.25 1.50 Excellent 17 1 18 0 0 0 1.50 1.75 Excellent 4 1 5 0 0 0 1.75 2.00 Excellent 18 1 19 0 0 0 2.00 2.25 Excellent 1 0 1 0 0 0 2.25 2.50 * 0 0 0 0 0 0 2.50 2.70 Excellent 0 0 0 0 0 0 Total 40 3 43 0 0 0 * Survey conditions were excellent, however only about 30% of the reach was visible due to access. 11 Figure 1. Map of Knutson Creek with proposed hydro-project identified, and Pedro Bay Village, and Pedro Pond P1 shown (Map Courtesy of Polarconsult Alaska). 12 Figure 2. Map of upper Knutson Creek from approximately RM 1.2 to RM 2.8 with fish trap sites and proposed hydro-project location identified (Map Courtesy of Polarconsult Alaska). 13 Figure 3.Typical trap catch of “small” but abundant Dolly Varden in upper Knutson Cr., trap #6, 8/23/12. Figure 4. Mature male and female Dolly Varden, upper Knutson Creek, 8/23/2012. 14 Figure 5. Sockeye salmon spawning in upper Knutson Creek at trap site 2, 8/23/12. Figure 6. Sockeye salmon carcass (bear killed), upper Knutson Creek, 8/23/12. 15 Figure 7. Knutson Cr. tributary ‘R1’, Trap site T-1 (left of Vern Jensen, Pedro Bay resident), 50 yds. above Knutson Cr. confluence and approx. 90 yds below proposed powerhouse site, 8/23/12. Figure 8. Upper Knutson Creek, approx. 50yds below lower flow gage site, 8/25/12. 16 Figure 9. Upper Knutson Creek, downstream view, trap site #8, 200m above proposed intake, 8/23/12. Figure 10. Sockeye salmon spawning in the upper end of Pedro Bay Pond P1, 8/25/12. Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix F            APPENDIX F – PERMITTING INFORMATION      Section  Title Page Nos.  F.1 Federal Permits........................................................................................ F‐2   F.2 State of Alaska Permits............................................................................ F‐2  F.3 Local Permits............................................................................................ F‐4   F.4 Other Permits and Authorizations........................................................... F‐5   Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  F‐1            This page intentionally blank.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  F‐2  F.1 FEDERAL PERMITS  F.1.1 Federal Energy Regulatory Commission (FERC)  The Federal Energy Regulatory Commission (FERC) has jurisdiction over hydroelectric projects  that meet certain criteria. Generally, these criteria include:  (1) The project is located on navigable waters,  (2) The project is located on federal land,  (3) The project affects interstate commerce, or  (4) The project is part of an interstate electrical grid.  None of the information identified by this study indicates the project meets any of these  criteria.  The project reach does receive an estimated 100 adult sockeye salmon, which are part  of the 2 to 10 million escapement on the Kvichak River and Iliamna Lake system.  However, it is  not established that these sockeye successfully spawn in the project reach, and they constitute  a negligible percentage (0.001 to 0.005%) of the Kvichak River escapement.  Accordingly, the  project should not fall under FERC jurisdiction.  A Declaration of Intention will need to be filed  with the FERC in the permitting phase of the project to verify this jurisdictional analysis.    F.1.3 U.S. Army Corps of Engineers (USACE) Permits  The diversion structure, intake structure, tailrace, and other features of the recommended  project will be located within waters of the United States; therefore, permits from the USACE  will be required.  Additionally, some project features or mitigation efforts may impact wetlands,  which will also require a USACE permit.  The project may be eligible for a Nationwide Permit  #17 for hydro projects, #39 for commercial and institutional developments, or others. If the  project cannot be permitted under a Nationwide Permit, an individual permit will need to be  obtained instead.   F.1.4 U.S. Environmental Protection Agency   A stormwater pollution prevention plan will be required for construction of the project.   F.1.5 Federal Aviation Administration   The recommended project will not have any features likely to present a hazard to aviation.   F.2 STATE OF ALASKA PERMITS  F.2.1 Alaska Department of Natural Resources (ADNR) Permits  F.2.1.1 Coastal Zone Consistency Review   The State of Alaska does not currently have a Coastal Zone Management Program.   Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  F‐3  F.2.1.2 Land Authorizations   None of the project area is on state land.    F.2.1.3 Tidelands Permits   No tidelands permits are needed for the project.  F.2.1.4 Material Sale Agreement  Not applicable.  Material sources likely to be used for this project are not state‐owned.   F.2.1.5 Water Use Permit/Water Rights  The project will need to obtain water rights from the Alaska Department of Natural Resources  (ADNR).  F.2.2 Alaska Department of Fish and Game (ADF&G) Permits  F.2.2.1 Fish Habitat Permit  The project will need to obtain a fish habitat permit from the ADF&G.  The fish habitat permit  will include in‐stream flow reservations (if any), mitigation requirements, restrictions on  construction activities near and below the ordinary high water mark of Knutson Creek, and  authorization for constructing a creek fording location on Knutson Creek for construction and  on‐going maintenance access to the upper penstock and diversion / intake site.  F.2.3 Alaska Department of Transportation and Public Facilities Permits  Not applicable.  F.2.4 Alaska Department of Environmental Conservation (ADEC) Permits  F.2.4.1 ADEC Wastewater or Potable Water Permits  Not applicable.  F.2.4.2 Solid Waste Disposal Permit   Not applicable.   F.2.4.3 Air Quality Permit and Bulk Fuel Permit  Not applicable.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  F‐4  F.3 LOCAL PERMITS  The project is located within the Lake and Peninsula Borough.  A development permit will be  required from the Lake and Peninsula Borough for the project.    F.4 OTHER PERMITS AND AUTHORIZATIONS  F.4.1  Material Sales  Locally sourced aggregate material for the project will need to be purchased from the Pedro  Bay Corporation and/or Bristol Bay Native Corporation.  An existing quarry at the airport is  likely a suitable material source for road building and related construction work for this project.    F.4.2 Site Access  Property rights for the project footprint will need to be secured in the form of leases,  easements, and right of ways as appropriate.  The land in the project area is owned by Pedro  Bay Corporation.  Some land in the project area is being held by the Alaska Department of  Commerce, Community, and Economic Development (ADCCED) Division of Community and  Regional Affairs (DCRA) in trust for a future Pedro Bay municipal government.  The PBVC may  be able to secure some or all of the required project lands from these trustee holdings.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  F‐5            This page intentionally blank.               Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix H            APPENDIX G – COST ESTIMATES AND ECONOMIC ANALYSIS      Section  Title Page Nos.  G.1 Project Cost Estimate............................................................................... G‐2   G.2 Economic Analysis and Assumptions....................................................... G‐2  G.3 Estimated Utility Electric rates with Recommended Project................... G‐7  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐1            This page intentionally blank.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐2  G.1 PROJECT COST ESTIMATE   The total estimated installed cost of the recommended project is presented in Table G‐1.  The  estimated costs in Table G‐1 assume the project is contracted out for construction.  Table G‐1 Cost Estimate for Recommended Project   Cost Item Cost Estimate  (2012 $)  PRE‐CONSTRUCTION COSTS (DESIGN, PERMITTING) $293,000  DIRECT CONSTRUCTION COSTS     Access Roads and Trails $370,000    Power and Communications Lines $375,000    Diversion and Intake Structures $259,000    Penstock $743,000    Building Conversions for Interruptible Electric Heating Service $310,000    Powerhouse $700,000    Shipping/Mobilization/Equipment $555,000  TOTAL DIRECT CONSTRUCTION COSTS $3,312,000    Construction Contingency (20%) $662,000    Construction Management/Administration $120,000    Construction Inspection/Engineering $115,000  ESTIMATED TOTAL INSTALLED COST $4,502,000    G.2 ECONOMIC ANALYSIS AND ASSUMPTIONS  Table G‐2 presents the life‐cycle economic analysis of the benefits and costs of the  recommended project.  Assumptions used in developing the economic analysis summarized in  Table G‐2 are described in this section.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐3  Table G‐2 Economic Analysis of Recommended Project  NOTES: All dollar values are in 2012 dollars.  All present value calculations assume the project’s first year of operations is 2016  and are presented as 2012 dollars.    (1) Future prices for power plant and heating fuel in Pedro Bay use the fuel price projections developed by the Institute of  Social and Economic Research (ISER) for the Alaska Energy Authority (AEA) (July 2012).    (2) Gross excess energy is the energy generated at the powerhouse before system losses are subtracted.  (3) Capital cost estimate includes a budget for retrofitting building electrical and mechanical systems to receive interruptible  electric heating service.    (4) The benefits, costs, and benefit‐cost ratio for a grant financed project are calculated using the ISER economic model  developed for the AEA’s Renewable Energy Grant Program Round 6 (July 2012).    Parameter  Recommended  Project   (200 kW)  ECONOMIC EVALUATION OF DEBT‐FINANCED PROJECT (Relative to continued diesel generation)   PROJECT BENEFITS   Total Annual PBVC Prime Load Supplied by Hydro 174,100 kWh  Resulting Reduction in Utility Fuel Purchases (5) 16,600 gallons  Annual Value of Savings from Reduced Power Plant Fuel Use (first year of operation) (1) $96,780  Annual Value of Savings from Avoided Diesel Plant Operating and Maintenance Costs $15,000  Salvage Value (at year 50) $0  Present Value of Power Plant O&M and Fuel Savings Over 50 Years $3,185,000  Gross Excess Hydro Energy Dispatched to Interruptible Electric Heating Services (2) 1,090,300 kWh  Resulting Reduction in Heating Fuel Purchases 24,200 gallons  Annual Value of Savings from Reduced Heating Fuel Use (first year of operation) (1) $136,500  Present Value of Heating Fuel Savings Over 50 Years $4,149,000  PRESENT VALUE OF PROJECT BENEFITS  $7,334,000  PROJECT COSTS   Estimated Total Installed Cost of Project (study, permitting, design, and construction) (3) $4,502,000  Financed Project Cost $4,212,000  Annual Cost of Debt Servicing (for 30 years) $317,600  Estimated Annual Operating, Maintenance, Repair, and Replacement Cost for Hydro  Plant (for 50 years) $29,000  PRESENT VALUE OF PROJECT COSTS  $6,234,000  BENEFIT‐COST RATIO (Debt‐Financed Project) 1.18  ECONOMIC EVALUATION OF GRANT‐FINANCED PROJECT  (Relative to continued diesel generation)  PRESENT VALUE OF PROJECT BENEFITS (4)  $8,280,000  PRESENT VALUE OF PROJECT COSTS  (4) $4,132,000  BENEFIT‐COST RATIO (Grant‐Financed Project) (4) 2.00 Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐4  G.2.1 Estimated Annual Project Costs  G.2.1.1 General, Administrative, Operation, and Maintenance Expenses  Typical general and administrative costs for a utility like PBVC range from $15,000 to $25,000  per year.  This annual expense covers activities such as meter reading, customer service,  managing the utility’s business affairs, etc.  These costs will not significantly change if the  means of energy generation changes from diesel to hydro or a combination of the two.   Typical non‐fuel O&M expenses for a utility like PBVC are also in the range of $15,000 to  $25,000 per year.  This annual expense includes the costs of lube oils, filters, and other  consumables for the diesel generators, maintenance labor, and similar costs that are generally  related to the running time of the diesel engines.  A significant portion of these costs will be  avoided with the recommended hydro project.   The hydroelectric project will have additional O&M costs. This includes additional labor costs  for monitoring and maintaining the hydro systems as well as direct expenses for parts and  consumables.  Annual O&M costs for the recommended project will be approximately $10,000  to $20,000 per year.  This will include activities such as plant inspections, maintenance, routine  parts replacement, and trail maintenance costs.   G.2.1.2 Repair and Replacement  Most of the hydroelectric project systems and components have a very long useful life.  The  intake, penstock, powerhouse, switchgear, turbine/generator, and power line all are expected  to have useful lives of 30 to 50 years or more.  Some components will require periodic repair or  replacement.  Components such as pumps, actuators, some control system components and  sensors, and bearings are assumed to have a useful life of 5 to 10 years.  The water turbines  may need an overhaul after about 15 to 25 years.  The average annual expense for repair and  replacement is estimated at $8,000 for the recommended project.   G.2.1.3 Taxes  Because the PBVC is a not‐for‐profit entity, no tax liability is considered.   G.2.1.4 Insurance  It is assumed that the PBVC’s existing insurance policies will be adequate for the hydroelectric  project. No additional annual costs are allocated for insurance.   G.2.1.5 Financing  Two financing options are considered for the project: (1) debt financing and (2) grant financing.   A combination of these methods may also be used.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐5  Debt Financing  For debt financing, the entire construction cost of the project is assumed to be commercially  financed for a 30‐year term at 6% interest.  Loan origination costs of 3% are assumed for items  such as application fees and loan guarantee fees.  State or federal loan programs can lower  PBVC’s borrowing costs for the project below market rates, which would reduce annual debt  payments, enabling PBVC to lower electric rates in the community.  Grant Financing  State or federal grants can help reduce the amount of capital PBVC needs to borrow for the  project.  Such grants would enable PBVC to further lower electric rates in the community.  BCRs  for a fully‐grant financed project are developed using the economic model developed for the  Alaska Energy Authority’s (AEA’s) Renewable Energy Grant Program by the Institute of Social  and Economic Research (ISER). 13    G.2.2 Estimated Project Revenues and Savings  G.2.2.1 Direct Fuel Displacement  The recommended hydro project will significantly reduce the amount of diesel fuel PBVC  consumed for electricity generation. Fuel savings are calculated using recent operating  efficiency and fuel costs for PBVC’s diesel power plant of 12.4 kWh per gallon, and the future  fuel price forecast for Pedro Bay prepared for the AEA by the ISER, which starts at $6.47 per  gallon in 2016. 15  Transportation diesel fuel in Pedro Bay cost $6.90 per gallon in the summer of  2012. 16  G.2.2.2 Excess Energy  In addition to reducing diesel fuel usage at the power plant, the recommended hydro project  also generates a significant amount of excess energy that is available on an interruptible basis.  This study assumes this energy is dispatched on an interruptible basis to space heating  applications in community buildings and homes.    The economic model for dispatch of this excess energy assumes that 12% of the gross available  excess energy is consumed by the hydro load governor system, station service, and incremental  energy losses on PBVC’s distribution system.  The remaining 88% is available as net energy  metered to interruptible utility customer loads such as space heating and water heating  applications at a special rate.  Annually, 124,000 kWh of this net excess energy (141,000 kWh  gross at generation) is allocated to the school to replace the existing waste heat it currently  receives from the diesel power plant.  This energy will also keep the diesel power plant and                                                          15  Alaska Fuel Price Projections 2012‐2035.  ISER Working Paper 2012.1 and Microsoft Excel Spreadsheet Price  Model (ISER, 2012).   16  Personal Communication with Mr. Ben Foss.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐6  engines warm so they are ready to provide backup power should the hydro plant trip off line.   All of the remaining net excess energy is assumed to be made available to interruptible  services, displacing heating fuel that is consumed with an assumed average efficiency of 84%.   The value of this displaced heating fuel is factored into the economic analysis.  G.2.2.3 Environmental Attributes  The environmental attributes (EA) of the recommended project can be marketed nationwide to  earn PBVC additional revenue.  The project’s EAs would be sold on the voluntary market, where  pricing for EAs varies.  Prices were as high as $0.02 per kWh before the financial crisis of 2008.   Since 2008, prices on the voluntary market have stabilized around $0.001 per kWh.   For several years, there has been an effort at the federal level to implement mandatory  purchase of EAs.  Such legislation would likely expand the market and stabilize the pricing for  EAs.  It is unknown if or when such legislation would take effect, or what the final terms of such  legislation will be.   While EAs from the project are an additional potential revenue stream for PBVC, at current  rates, the cost to “certify” the project to sell EAs would likely exceed the revenue from sale of  the EAs.  Accordingly, no revenue from EAs is assumed in the base case of the economic  evaluation.   G.2.2.4 Indirect and Nonmonetary Benefits  The recommended hydroelectric project offers significant indirect and nonmonetary benefits in  addition to direct economic benefits.  These other benefits include:  ● Reduced air pollution (nitrogen oxide [NOx], sulfur oxide [SOx], particulates, and  hydrocarbons) due to decreased operation of the diesel power plant  ● Reduced noise in Pedro Bay when the diesel plant is turned off.   ● Reduced risk of oil spills due to decreased throughput and handling of fuel.   ● More stable energy prices. With a hydro plant, PBVC’s electricity rates will be largely  insulated from the increasingly volatile world oil prices.   ● Secondary benefits arising from the availability of plentiful hydroelectricity with a stable  price.  This will increase the affordability of living and doing business in Pedro Bay and  will help to increase the long‐term viability of the community.  An example of such a  secondary benefit is an increase in the population of school‐age children, helping the  village to reopen the school and ensuring that school enrollment exceeds district and  state thresholds for state funding year‐to‐year.  ● Economic multipliers due to the fact that a greater percentage of the utility's revenues  will be retained in the local community for labor instead of paying external entities such  as fuel suppliers.   Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐7  ● Local training and experience with small hydroelectric projects. To the extent that local  residents choose to be involved in construction, maintenance, and operation of the  hydroelectric project, they will learn a unique set of skills.  These skills will become  increasingly useful as Alaska continues to develop its local hydroelectric resources.   G.3 ESTIMATED UTILITY ELECTRIC RATES WITH RECOMMENDED PROJECT  There are numerous pricing models that electric utilities can adopt, and a detailed discussion of  those models is beyond the scope of this report.  This section provides a simple analysis of  estimated utility costs and rate requirements under basic financing scenarios for the  recommended project.  Because the recommended project assumes significant energy sales on  an interruptible basis, potential rates include interruptible energy sales.  Table G‐3 summarizes  estimates electric rates with the recommended project under debt‐ and grant‐financing  scenarios.  Table G‐3 projects an electric rate of between 6.5 and 125.5 cents per kWh for normal electric  service and 6.5 and 19.8 cents for interruptible electric service, depending on how the  recommended project is financed.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐8  Table G‐3 Estimated Electric Rates with the Recommended Project  Parameter Recommended  Project (200 kW)  ESTIMATED ENERGY PERFORMANCE OF RECOMMENDED PROJECT  Total Annual PBVC Prime Load Supplied by Diesel (kWh) 8,100 kWh  Total Annual PBVC Prime Load Supplied by Hydro (kWh) 174,100 kWh  Total Annual PBVC Prime Load (kWh, at generation) 180,200 kWh  Total Hydro Energy Dispatched to Supply PBVC Prime Load (kWh) 174,100 kWh  Total Gross Excess Hydro Energy Available (kWh) (1) 1,329,600 kWh  Gross Excess Hydro Energy Dispatched to Interruptible Electric Heating Services (kWh) 1,090,300 kWh  Percentage of Community Building Heating Needs Supplied by Hydro Energy (2) 86%  Percentage of Home Heating Needs Supplied by Hydro Energy (2) 56%  Remaining Excess Hydro Energy (kWh) 239,300 kWh  Total Annual Hydro Generation (kWh) 1,503,700 kWh  ESTIMATED ELECTRIC RATES WITH DEBT‐FINANCED HYDRO PROJECT  Estimated Total Installed Cost of Project (study, permitting, design, and construction) $4,502,000  Financed Project Cost $4,212,000  Annual Cost of Debt Servicing $317,600  Annual Utility Fuel Cost $4,200  Annual General and Administrative Cost $20,000  Annual Hydro Plant Operations, Maintenance, Repair and Replacement Cost $29,000  Annual Diesel Plant Operations and Maintenance Cost $5,000  Operating Margins (Contingency) $15,000  Annual Revenue Requirement $390,800  Electric Service Type Sales Volume (kWh) Estimated Rate ($/kWh) Annual Revenue  Prime Energy Services 160,150 $1.255 $201,040  Interruptible Heating Services 958,400 $0.198 $189,760  Total  1,118,550  $390,800  ESTIMATED ELECTRIC RATES WITH GRANT‐FINANCED HYDRO PROJECT  Annual Revenue Requirement (3) $76,400  Electric Service Type Sales Volume (kWh) Estimated Rate ($/kWh) Annual Revenue  Prime Energy Services 160,150 $0.065 $10,410  Interruptible Heating Services 958,400 $0.065 $72,710  Total  1,118,550  $78,470  CURRENT ELECTRIC RATE (FOR COMPARISION) $0.91 per kWh  CURRENT EQUIVELENT COST OF HEATING FUEL FOR BUILDINGS $0.22 per kWh  NOTES:  All dollar values are in 2012 dollars.  PBVC load and hydro performance based on assumptions detailed in Appendix H.   Economic assumptions are detailed in Appendix G.2.  (1) Gross excess energy is the energy generated at the powerhouse before system losses are subtracted.      (2) See Section H.2.3 for discussion of the assumptions used for interruptible electric heating services.  (3) Same revenue requirement as for the debt‐financed project but without the debt servicing cost  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  G‐9            This page intentionally blank.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  Appendix H            APPENDIX H – TECHNICAL ANALYSIS       Section  Title Page Nos.  H.1 Hydro Project Modeling........................................................................... H ‐2  H.2 Project Sizing Analysis.............................................................................. H‐8  H.3  Evaluation of In‐Stream Flow Reservations........................................... H‐12  H.4 Different Utility Load Scenarios............................................................. H ‐13  H.5 Load Growth Scenarios.......................................................................... H‐12    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  H‐1            This page intentionally blank.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  H‐2  H.1 HYDRO PROJECT MODELING   The primary analytical tool used to evaluate various hydro project configurations and load cases  for this feasibility study is a generation dispatch model (GDM). A GDM takes in the technical  parameters of the proposed generation systems (both hydro and diesel), resource availability,  and utility loads, and then simulates operation of the proposed integrated system to determine  how a given hydro project configuration performs.  H.1.1 Generation Dispatch Model (GDM)  The GDM developed for this feasibility study runs at a one‐day time step and is used to assess  seasonal and annual variations in the performance of various project configurations.  Use of a  shorter time step was not warranted because the hydro resource and proposed project  capacity are both sufficient to carry 100% of Pedro Bay’s existing peak electric load.  At this  level of study, short‐term fluctuations in load and water availability are not significant factors  for the hydro project proposed for Pedro Bay.  At each time step, the model evaluates (1) utility load and (2) available water in Knutson Creek.   If there is sufficient water to supply all of the utility load, the hydro generator is dispatched to  meet 100% of load.  If additional water and generating capacity are available, this additional  energy is dispatched to interruptible loads.  If there is insufficient water to supply all of the  utility load, the diesel power plant is dispatched to supply all or a portion of the utility load.  At  the next time step, this analysis is repeated.  Inputs used to develop and run the model are  described in Table H‐1.  The model assumes a single crossflow turbine is installed at the hydro powerhouse.  When  utility load drops below the minimum operating threshold of the turbine, interruptible loads or  a dump load at the powerhouse are energized to increase load and continue turbine operation.   For project configurations with higher design flows or substantial in‐stream flow reservations  (ISFRs), the model shuts the hydro project down when there is insufficient water to operate the  turbine at minimum levels.  17  When the GDM calls for the diesel generator(s) to operate, each generator is loaded to a  minimum of 40% of rated output, regardless of the deficit between utility load and hydro  output.  Thus, if utility load is 70 kilowatts (kW) and available hydro output is 60 kW, PBVC’s 62‐ kW diesel generator will run at 25 kW (40%), and hydro output will be curtailed from 60 kW to  45 kW.  The remaining 15 kW of potential hydro output can be dispatched to interruptible  loads.                                                            17  Other turbine configurations can achieve higher partial‐flow efficiency than a single crossflow turbine.  A series  of pump turbines, or a combination of pump turbines and a smaller crossflow could be appropriate at Knutson  Creek.  Final turbine selection should occur during final design, once permit conditions and project capacity have  been determined.  These alternate configurations are expected to have slightly increased energy output,  resulting in improved project benefits than those estimated by this study.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  H‐3  The GDM also monitors utility load and hydro plant availability for opportunities to dispatch  unused hydro plant capacity to interruptible electric heating services for heating buildings in  Pedro Bay.  To accurately evaluate these opportunities, generalized building heating demand  was input to the model to estimate how much excess hydro energy could be used for heating  buildings and how much of a buildings’ total energy requirements could be served by  interruptible electric heating services.  Assumptions used for this analysis are discussed in detail  in Section H.2.3.  Table H‐1 Generation Dispatch Model Variables, Inputs, and Outputs  MODEL INPUT DATA   Input Range of Values Evaluated Value Used for  Recommended Project  Hydro Project Design Flow (cfs) 10 to 88 cfs  (See Section H.2) 18.25 cfs  Knutson Creek Flow at Diversion  (cfs)  Extended record for Knutson Creek based on  hydrology data for Knutson Creek and  Iliamna River.   Same  In‐Stream Flow Reservations 0 to 13.3 cfs at diversion site  (See Section H.3) 6.6 cfs at diversion site  PBVC System Demand (kW)  Daily estimate derived from National  Renewable Energy Laboratory (NREL) village  load model and PBVC utility records.  (See Section H.4)  182,200 kWh annual demand  Turbine Efficiency Curve Standard crossflow turbine efficiency curve,  with peak water‐to‐wire efficiency of 62%. Same  Project Head, Penstock Lengths,  Physical Parameters  Based on field measurements and system  design flows. Same  Building Data  Square footage and thermal efficiency  estimated from aerial photographs and site  visits.   Same  Climate Data Average monthly heating degree‐days for  Iliamna, Alaska. Same  PBVC Diesel Generator Sizes  Based on existing installed equipment. Same  MODEL OUTPUT DATA  PBVC Demand supplied by hydro (daily kWh)  PBVC Demand supplied by diesel (daily kWh)  Excess hydro energy available for interruptible loads (daily kWh)  Excess hydro energy dispatched to heat community buildings (daily kWh)  Percentage of community building heating needs met by hydro energy  Excess hydro energy dispatched to heat homes (daily kWh)  Percentage of home heating needs met by hydro energy    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report  H‐4    H.1.2 Load Patterns and Load Model  Table H‐2 presents average historical PBVC load data and the simulated load data input to the  GDM. Recent PBVC operating data presented in Table 2‐3 and Figure 2‐1 (from PCE reports and  PBVC records) was used to determine characteristic loads, and the simulated load model was  developed using a village load simulator tool developed by the National Renewable Energy  Laboratory (NREL). 18    Table H‐2 Actual and Modeled Electric Demand   Parameter Typical PBVC Load (1) PBVC Load Model    Peak Load (kW) ~70 47    Average Load (kW) 21 to 30 21  Total Annual Energy Generation (kWh) 180,000 to 296,000 182,200  NOTE:  (1) Based on 2003 to 2013 annual utility system records compiled from PCE program and PBVC records.    H.1.3 Model Results  Average daily hydro performance and PBVC load over a typical year (2007) are shown on Figure  H‐1.  Figure H‐2 shows the annual variations in hydro performance from 1996 to 2011. The data  shown on Figure H‐2 correspond to the extended water records for Knutson Creek and the  range of annual system performance tabulated in Table H‐3.                                                           18  The Alaska Village Electric Load Calculator, NREL/TP‐500‐36824, NREL, Golden Colorado, Sept. 2004.  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report   H‐5 050100150200250Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec2007Daily Energy Demand and Supply (Average Daily kW)Excess Energy Available from HydroHydro Energy Dispatched to Home Heating LoadsHydro Energy Dispatched to Community Building Heating LoadsDiesel Energy Dispatched to Meet Utility System DemandHydro Energy Dispatched to Meet Utility System DemandCurrent Utility System DemandUtility System Demand Met by DieselsCurrent Utility System DemandHydro Energy Dispatched to Community Building Heating LoadsHydro Energy Dispatched to Home Heating LoadsExcess Hydro EnergyUtility System Demand  Met by HydroFigure H‐1 Typical Daily Performance of Recommended Hydro Project              Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report   H‐6 050100150200250May 96 May 97May 98 May 99May 00May 01May 02May 03 May 04May 05 May 06May 07 May 08May 09May 10Daily Energy Demand and Supply (Average Daily kW)Excess Energy Available from HydroHydro Energy Dispatched to Home Heating LoadsHydro Energy Dispatched to Community Building Heating LoadsDiesel Energy Dispatched to Meet Utility System DemandHydro Energy Dispatched to Meet Utility System DemandCurrent Utility System DemandUtility System Demand Met by Diesels (RED)Current Utility System Demand (BLACK LINE)Utility System Demand Met by Hydro (BRIGHT BLUE)Hydro Energy Dispatched to Community Building Heating Loads (DARK BLUE)Hydro Energy Dispatched to Home Heating Loads (MEDIUM BLUE)Excess Hydro Energy (LIGHT BLUE)Figure H‐2 Annual Performance Of Recommended Hydro Project (1996 through 2011)     Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   H‐7  Table H‐3 Expected Range of Annual Performance for Recommended Project  Expected Annual Hydro Generation  Energy Performance Parameter Minimum  (1999)(1) Average Maximum  (2001) (1)  Total Annual PBVC Prime Load Supplied by Diesel (kWh)  (Diesel as % of total prime supply)  35,200  (22.3%)  8,100  (4.4%)  0  (0.0%)  Total Annual PBVC Load Supplied by Hydro (kWh)  (Hydro as % of total prime supply)  147,000  (77.7%)  174,100  (95.6%)  182,200  (100.0%)  Total Annual PBVC Prime Load (kWh at Generation) 182,200 182,200 182,200  Total Hydro Energy Dispatched to Supply PBVC Prime Load 147,000 174,100 182,200  Total Gross Annual Excess Hydro Energy Available (kWh) (2) 1,110,100 1,2329,600 1,504,600  Gross Excess Hydro Energy Dispatched   to Community Building Interruptible Heating Services  (kWh)   (Percentage of heating load supplied by hydro)  451,000  (64%)  603,900  (86%)  702,200  (100%)  Gross Excess Hydro Energy Dispatched   to Home Interruptible Heating Services (kWh)  (Percentage of heating load supplied by hydro)  423,600  (49%)  486,400  (56%)  563,100  (65%)  Remaining Excess Hydro Energy (kWh)  236,100 239,300 239,300  Total Annual Hydro Generation (kWh)  (Percent of average year)  1,257,100  (83.6%)  1,503,700  (100%)  1,686,800  (112.2%)  NOTES:  (1) Utility load is uniform for all years in the simulation, but water availability in Knutson Creek is based on the extended  hydrological record, and varies from year to year.  The years in parentheses reflect the calendar year for the reported  project performance.  (2) Gross excess energy is the energy generated at the powerhouse before system losses are subtracted.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   H‐8  H.2 PROJECT SIZING ANALYSIS    H.2.1 Introduction  Knutson Creek has sufficient flow to support a significantly larger run‐of‐river hydro project  than is needed to supply the PBVC electric system’s current load, which has a peak demand of  approximately 70 kW.  Undersizing the hydro project will sacrifice an opportunity to support  future growth of the community or serve other energy demands in the community at modest  incremental capital expense.  Oversizing the hydro project will result in unnecessary capital  expense that results in no benefit to the community and can also burden the community with  increased operations and maintenance (O&M) expenses over the life of the project.  The  challenge in selecting the project capacity is to weigh these considerations evenly to arrive at  the “optimal” project capacity.  This section presents Polarconsult’s sizing analysis, which  identifies a 200 kW project as the most economical installed capacity.    This project capacity analysis should be revisited once project permit conditions are finalized  and project designs and cost estimates are more refined to verify that a 200‐kW project is  “optimal” for Pedro Bay.  A range of project configurations was evaluated using the GDM to determine which hydro  project configuration best supplies PBVC’s existing electric load while providing for future load  growth and interruptible energy usage, without unduly impacting project economics.  The  primary criteria for this evaluation was displacement of diesel fuel used for generating  electricity and heating fuel for space and water heating in buildings.    Table H‐4 lists the range of project parameters that were evaluated using the GDM to assess (1)  the amount of diesel generation displaced by each project configuration and (2) the amount of  excess energy each configuration produced.  Findings for key technical parameters are  discussed in the following sections.  Table H‐4 Range of Project Design Parameters Considered and Recommended Values  Parameter (1) Range Considered Recommended Project  Hydro Project Installed Capacity 100 to 1,000 kW 200 kW  Hydro Project Design Flow 9 to 88 cfs 18.25 cfs  NOTE:  (1) Related project parameters were also modified in conjunction with the parameters listed.  For example, the penstock  diameter was varied with design flow to maintain acceptable head losses.    Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   H‐9  H.2.2 Results of Sizing Analysis  Table H‐5 summarizes the economics for each of the project configurations considered in this  study using debt‐based financing and grant‐based financing.  With deployment of interruptible  energy services in the community, the recommended 200‐kW project results in the highest BCR  for the project of 1.18 on a debt‐financed basis and 2.00 on a grant‐financed basis. 19                                                          19  Debt based financing assumes the entire capital cost is financed over 30 years at 5% interest.  Grant based  financing is calculated using the financial model developed for AEA by ISER for the Renewable Energy Grant  Program (Round 6 version, released in July 2012).  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.   November 2013 – Final Report   H‐10 Table H‐5 Economic Evaluation of Hydro Project Configurations Hydro Project Configuration (Installed Capacity) Parameter 100 kW 150 kW 200 kW 250 kW 500 kW 1,000 kW ENERGY PERFORMANCE OF PROJECT  Total Hydro Energy Dispatched to Supply PBVC Prime Load (kWh) 180,200 175,100 174,100 171,300 153,900 122,600 Total Gross Excess Energy Dispatched to Interruptible Heating Services (1, 2) 641,700 932,100 1,090,400 1,167,300 1,153,000 978,500 Remaining Excess Hydro Energy 0 61,500 239,200 469,900 1,796,000 3,790,700 TOTAL ANNUAL HYDRO GENERATION 821,900 1,168,700 1,503,700 1,808,500 3,101,900 4,891,800ECONOMIC EVALUATION OF DEBT‐FINANCED PROJECT (Relative to continued diesel generation) PROJECT BENEFITS       Avoided Utility Diesel Purchases (gallons) (3) 17,200 16,700 16,600 16,300 14,700 11,700 Avoided Heating Fuel Purchases (gallons) (3) 12,800 20,200 24,200 26,200 25,800 21,400 Estimated Savings, Avoided Diesel O&M $15,000 $15,000 $15,000 $15,000 $15,000 $15,000 PRESENT VALUE OF PROJECT BENEFITS  $5,480,000 $6,665,000 $7,334,000 $7,632,000 $7,279,000 $6,013,000 PROJECT COSTS       Estimated Total Installed Cost of Project  (4) (permitting, design, and construction) $4,195,000 $4,380,000 $4,502,000 $4,816,000 $5,783,000 $6,871,000 Estimated Annual Operating, Maintenance, Repair, and Replacement Cost for Hydro Plant $21,600 $23,300 $29,000 $30,600 $37,400 $46,800 PRESENT VALUE OF PROJECT COSTS $5,665,000 $5,947,000 $6,234,000 $6,684,000 $8,111,000 $9,754,000 BENEFIT‐COST RATIO (Debt‐Financed Project) 0.97 1.12 1.18 1.14 0.90 0.62ECONOMIC EVALUATION OF GRANT‐FINANCED PROJECT (Relative to continued diesel generation) (5) ESTIMATED PRESENT VALUE OF PROJECT BENEFITS  $5,979,000 $7,523,000 $8,280,000 $8,148,000 $7,560,000 $6,202,000 ESTIMATED PRESENT VALUE OF PROJECT COSTS  $3,851,000 $4,021,000 $4,132,000 $4,420,000 $5,304,000 $6,300,000 BENEFIT‐COST RATIO (Grant‐Financed Project) 1.55 1.87 2.00 1.66 1.43 0.98NOTES: All present value calculations assume the project’s first year of operations is 2016 and all cost are in 2012 dollars.  Detailed assumptions are explained in Section G.2. (1) Gross excess energy is the energy generated at the powerhouse before system losses are subtracted.     (2) See Section H.2.3 for discussion of the assumptions used for interruptible electric heating services. (3) Future prices for power plant and heating fuel in Pedro Bay use the fuel price projections developed by ISER for the AEA.   (4) Project cost estimate includes a budget for retrofitting building electrical and/or mechanical systems to receive interruptible electric heating service.   (5) Estimated benefits, costs, and benefit‐cost ratio for a grant‐financed project are calculated using ISER economic model developed for the AEA Renewable Energy Grant Program Round 6 (July 2012).      Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   H‐11  H.2.3 Analysis Methodology for Heating Applications  Electric heating applications would be implemented on an interruptible basis, meaning that  normal electric demand would have a priority over electric heating demand.  When total  demand approaches available hydro generating capacity, heating loads would be interrupted  without warning by a central controller to avoid activating the diesel power plant.  This  operating scheme is desirable because using diesel‐fired electricity to heat buildings is less  efficient (and more costly) than using fuel oil to directly heat the building.  The analysis first considered serving public and community buildings, such as the PBVC building,  Village Public Safety Officer (VPSO) office, school, and church.  Once these heating loads were  served, significant excess energy remained, so additional service to private homes and buildings  was evaluated.  The analysis assumes the 33 homes identified in the 2010 U.S. Census are fitted  for electric heat.  Nineteen of these homes are assumed to be occupied and heated year‐round,  and the remaining 14 are assumed to be occupied and heated from June 1 to September 30.    The relative benefits of just serving community buildings versus community buildings and  homes were reviewed, and in all cases serving homes resulted in an increased BCR.  Project  scenarios that consider interruptible heating service also include building mechanical system  retrofits as part of the total project cost.  The village distribution system and individual electric  services are assumed to be adequate to handle the increased load of heating service.  Building heating loads were estimated using average monthly climate data for Iliamna, Alaska  (11,030 annual heating degree‐days at 65 F).  The approximate square footage of each of the  community buildings was estimated from aerial photographs and site visits, and a unit heating  load was developed for each building based on these criteria.  For homes, a generic model was  developed using similar methods.  The resulting heating loads are summarized in Table H‐6.  Table H‐6 Heating Loads for Community Buildings and Homes  Parameter  School PBVC  Building Church VPSO Office House  Estimated Square Footage 5,500 5,600 5,600 3,600 1,200  Estimated Unit Heating Load     (Btu per hour‐degree F‐Sq.Ft) 0.32 0.45 0.40 0.40 0.40  Calculated Heating Load      (Btu/hour‐degree F) 1,760 2,520 2,240 1,440 480  Annual MMbtus 465.9 667.1 593.0 381.2 127.1  Efficiency of Mechanical  Equipment (assumed) 84% 84% 84% 84% 84%  Efficiency of Electric  Distribution System 87.9% 87.9% 87.9% 87.9% 87.9%  Gallons of Fuel Oil to Serve  Space Heating Load 3,960 5,670 5,040 1,480 1,080  Gross Hydro Energy Required  to Serve 100% of Building  Space Heating Load (kWh)  155,300 222,300 197,600 127,000 42,400  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   H‐12  In some cases, the total amount of heating fuel displaced by interruptible electric heating  services is greater than the total amount of heating fuel used by the community (Table 2‐1).   More detailed analysis of actual heating fuel usage and heating patterns in the community is  needed to determine the cause of this discrepancy.  It is likely that the discrepancy is due to a  combination of several factors, such as a greater portion of heating needs being met with wood  than the assumed 25%, more seasonally occupied homes than assumes, and / or setting  thermostats lower to reduce heating costs.       H.3 EVALUATION OF IN‐STREAM FLOW RESERVATIONS   Because part of the proposed bypass reach in Knutson Creek is anadromous fish habitat, and  the entire bypass reach is resident fish habitat, it is likely that ADF&G will require an ISFR to  maintain minimum flow in the bypass reach of Knutson Creek.  An ISFR will affect hydro project  operations and performance primarily in the late winter months, when flow is lowest.    Construction of off‐site compensatory habitat is preferable to an ISFR for the project, but an  ISFR is a likely permit condition.  ISFR requirements will not be known until PBVC completes  permit negotiations with ADF&G for the project.  Five hypothetical ISFRs were evaluated to determine the impacts of ISFRs on the performance  of the recommended hydro project and other project capacities considered by this study.  The  ISFRs and project impacts are summarized in Table H‐7.  To provide a realistic forecast of hydro project performance, all analyses of hydro project  performance in this report assume an ISFR of 6.6 cfs unless stated otherwise.    Table H‐7 Impacts of In‐Stream Flow Reservations on Hydro Performance  Hydro Project Capacity and   Percent of Current PBVC Load Supplied by Hydro Project  In‐Stream  Flow  Reservation  (ISFR)  ISFR as Percentage   of Annual Low Flow  at Diversion Site (1) 100 kW 150 kW 200 kW 250 kW 500 kW 1,000 kW  0 cfs (no  reservation) 0% 100% 100% 100% 100% 98.6% 78.2%  4.0 cfs 30% 100% 99.5% 99.2% 98.7% 89.1% 70.8%  6.6 cfs 50% 97.6% 94.7% 94.0% 92.5% 82.6% 68.6%  10 cfs 75% 89.4% 87.4% 87.1% 84.8% 77.0% 63.6%  13.3 cfs 100% 82.6% 80.8% 80.3% 78.8% 71.4% 59.8%  NOTE:  (1)  The annual low flow is the extended record median daily flow at the intake site, which is 13.3 cfs on April 2nd   (see Figure C‐5).   Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   H‐13  H.4 DIFFERENT UTILITY LOAD SCENARIOS  Performance of the recommended hydro project under different PBVC loads was evaluated  using the GDM for the following load growth cases:  (1) Annual load at 50% of 2008‐2010 load,  (2)  Annual load at 30% of 2008‐2010 load (actual load in 2013),  (3) PBVC load in 2008‐2010 (base case),  (4)  Annual load at 200% of 2008‐2010  load, and  (5) Annual load at 400% of 2008‐2010  load.  There is a significant amount of excess energy from the hydro project under all load growth  cases.  The amount of excess energy decreases as utility load increases.  Under the 400% load  growth case, there is only 573,200 kWh of excess energy available (38.1% of total hydro  generation).  Interruptible electric heating services are able to put most of this excess energy  (81% to 97%) to beneficial use under all load growth cases.   Table H‐8 Annual Performance of Recommended Project under Load Growth Cases  Expected Annual Hydro Generation  Energy Performance Parameter 50% Load  Reduction  Existing  PBVC Load  (Base Case)  +43%  Load  Growth (2)  +285%  Load   Growth (2)  +570%  Load   Growth (2)  Total Annual PBVC Prime Load Supplied by Diesel (kWh)  (Diesel as % of total prime supply)  7,900  (8.7%)  8,100  (4.4%)  14,200  (5.5%)  33,900  (6.5%)  109,500  (10.5%)  Total Annual PBVC Load Supplied by Hydro (kWh)  (Hydro as % of total prime supply)  83,200  (91.3%)  174,100  (95.6%)  245,800  (94.5%)  486,100  (93.5%)  930,500  (89.5%)  Total Annual PBVC Prime Load (kWh at Generation) 91,100 182,200 260,000 520,000 1,040,000  Total Hydro Energy Dispatched to Supply PBVC Prime Load 83,200 174,100 245,800 486,100 930,500  Total Gross Annual Excess Hydro Energy Available (kWh) (1) 1,420,500 1,329,600 1,257,900 1,017,600 573,200  Gross Excess Hydro Energy Dispatched   to Community Building Interruptible Heating Services  (kWh)   (Percentage of heating load supplied by hydro)  620,300  (88.3%)  603,900  (86.0%)  594,900  (84.7%)  549,100  (78.2%)  377,100  (53.7%)  Gross Excess Hydro Energy Dispatched   to Home Interruptible Heating Services (kWh)  (Percentage of heating load supplied by hydro)  519,500  (60.1%)  486,400  (56.3%)  458,000  (53.0%)  356,700  (41.3%)  181,500  (21.0%)  Remaining Excess Hydro Energy (kWh)  280,700 239,300 205,000 111,800 14,600  Total Annual Hydro Generation (kWh) 1,503,700 1,503,700 1,503,700 1,503,700 1,503,700  NOTES:  (1) Gross excess energy is the energy generated at the powerhouse before system losses are subtracted.      (2) 43%, 285%, and 570% load growth cases correspond to the base case, 200%, and 400% load growth cases in the November  2012 draft report.  The headings have been revised to reflect the new base case load based on current PBVC system load in  2012 ‐13.        Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report              APPENDIX I – DRAFT REPORT REVIEW COMMENTS AND RESPONSES         Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   I‐1            This page intentionally blank.    polarconsult alaska, inc. 1503 West 33rd Avenue, Suite 310 Anchorage, Alaska 99503-3638 Phone: (907) 258-2420 FAX: (907) 258-2419 M EMORANDUM November 27, 2013  Page 1 of 9  DATE: November 27, 2013   TO: John Baalke, Tribal Administrator, Pedro Bay Village Council  FROM: Joel Groves, Project Manager, Polarconsult   SUBJECT: Response to AEA Review Comments on Knutson Creek Hydroelectric Feasibility  Study and Summary of Other Major Revisions to Final Report  CC: Final Report Appendix I   The Client Review Draft of the Knutson Creek Hydroelectric Feasibility Study Final Report was  provided to the Alaska Energy Authority (AEA) on November 12, 2012.  The AEA provided  comments on October 21, 2013.      AEA comments and Polarconsult responses are summarized below.  As appropriate, AEA’s  comments have been incorporated into the final release of the Knutson Creek Hydroelectric  Feasibility Study Final Report, dated November 2013.    AEA Comments Received October 21, 2013 (Polarconsult responses in BLUE)  The feasibility study recommends a 200 kW run‐of‐river hydroelectric project on the main stem  of Knutson Creek. The project would have a design flow of 18.25 cfs, intake at river mile 2.59  and a powerhouse near river mile 1.25. The project reach would affect 1 mile of anadromous  habitat. Total generation is estimated at 1,503,700 kWh, of which 16% would be used to meet  94% of electrical demand and 70% would be used for interruptible space heating. Generation  considers a 6.6 cfs of in‐stream flow requirements to maintain fish habitat.     1) We are concerned with the recommendation of a project with a bypass reach that affects  anadromous salmon habitat. Knutson Creek is listed for sockeye presence and spawning in  the anadromous waters catalog. Permitting such a project will be lengthy and will require  more fisheries studies than what was done during this feasibility study. It does not appear  ADF&G was consulted on the methodology for the most recent fisheries study. The stream  also contains resident Dolly Varden throughout. In‐stream flow requirements for fish  passage will be required if the project is permitted and that amount is currently unknown.  ADF&G will have to be consulted and make a determination. It is also unknown if the  project falls under FERC jurisdiction. It may not be worth the time and money to try and  permit a project that may receive permitting requirements that make it unfeasible.  Polarconsult met with ADFG twice over the course of the feasibility study to solicit ADFG’s  input on the feasibility of the project, discussing fish‐related issues and identifying  appropriate measures that may be required to accommodate fish that are present within  the project’s bypass reach.  The first meeting was with Ronald Benkert on September 22,  2010, and the second with Ronald Benkert, Monte Miller, Jason Mouw, and Stormy  Haught on June 9, 2011.      P OLARCONSULT M EMORANDUM    November 27, 2013  Page 2 of 9  Additionally, Polarconsult’s fisheries subconsultant Alaska Biological Consulting (ABC)  held further consultations with ADFG in 2012.  ABC consulted with ADFG personnel  (including Dr. Robert Piorkowski, Slim Morstad, Fred West, and Jason Dyle) regarding  design of the fisheries survey performed at Knutson Creek in August 2012.  Biologists Slim  Morstad and Dr. Thomas Quinn (University of Washington) were also consulted regarding  the limiting resources for sockeye production in the Iliamna Lake system.      Lastly, ADFG Headquarters, Sport Fisheries Division, and Commercial Fisheries Division  were each provided copies of the Knutson Creek Fisheries Report (ABC Technical Report  12‐011) in October 2012.     These meetings and consultations have been referenced in the main narrative at Section  3.1, and the meeting records and appropriate correspondence have been added to  Appendix E of the Final Report.    ADFG personnel consulted on this project have indicated that the project can be  permitted.  Field surveys to date have quantified potential impacts and identified  potential mitigation measures.  The proposed in‐stream flow reservations and associated  findings in the feasibility study are based on these discussions with ADFG.  Additional  consultations with ADFG would occur in the permitting phase of the project to finalize  mitigation measures that are acceptable to both PBVC and ADFG.      In the June 2011 meeting, ADFG’s Mr. Miller was of the opinion that the presence of  sockeye within the bypass reach would be sufficient basis for FERC jurisdiction on the  basis of interstate commerce.  However, subsequent field surveys in 2012 determined  that the bypass reach receives only approximately 100 spawning sockeye, out of a total  sockeye escapement for the Kvichak River system of 2 to 10 million.1  It is doubtful that  0.001 to 0.005 percent of a significant interstate commerce activity is sufficient basis for  FERC to assert jurisdiction over the project.      Polarconsult agrees with AEA that the question of FERC jurisdiction is important to the  project’s economic feasibility (both in controlling development costs and life‐cycle  costs/benefits), and recommends that one of the first tasks in the permitting phase of  development be to file a Declaration of Intention with the FERC to determine project  jurisdiction.      Polarconsult also agrees with AEA that continued close consultation with ADFG is  appropriate to insure that environmental constraints on the project do not unduly reduce  its economic benefits to Pedro Bay.  Further consultations would occur under the  permitting phase of project development.     2) We question the recommendation for off‐site mitigation. We do not know of any project in  recent past that has been permitted by ADF&G that allowed off‐site mitigation for a salmon                                                          1  Fishery Manuscript Series No. 12‐04.  Review of Salmon Escapement Goals In Bristol Bay, Alaska, 2012.  ADFG,  November 2012. Table 3, Page 24.  Knutson Creek is a tributary of the Kvichak River.  P OLARCONSULT M EMORANDUM    November 27, 2013  Page 3 of 9  stream. Can you provide an example and the permitting process in regard to cost and time  to complete for such a project? Additionally, since there is much question regarding ADF&G  permitting, Pedro Bay should contact ADF&G and share the feasibility study for their  thoughts to see if it can be permitted as proposed. Monte Miller is the hydro coordinator  for ADF&G and his contact information is attached.   Offsite mitigation is an option under Alaska Title 16 including AS 16.05.871 and 16.05.841.  The legislative intent is to ensure no net loss of anadromous fisheries habitat and  production, and through Title 16 laws there is considerable latitude to mitigate for  anadromous fish habitat impacts by a variety of avenues.     Offsite mitigation under Title 16 is quite common for a variety of projects.  One recent  example is the Chuniisax Creek Hydroelectric Project in Atka, which became operational  in December 2012.  A deterioriated culvert blocking anadromous fish passage on Dancing  Creek in Atka was replaced as off‐site mitigation for project impacts to pink salmon  habitat in Chuniisax Creek downstream of the hydro project.  Offsite mitigation was also  recently used on the Trunk Road improvement project in the Mat‐Su Borough.  Again,  culvert replacements (on Wasilla Creek and Carneti Creek) were used to mitigate fisheries  impacts along the Trunk Road corridor.      3) Table ES‐2: Shows 15.5% supplied by diesel plant as well as 94.5%. Perhaps this is a typo.  This was a typo and has been corrected.      4) Annual kWh generated has dropped from 264,000 in 2008 to 185,000 in 2013.  This is a 30%  decrease in five years, which reflects the closing of the school in November of 2010.  Table  ES‐2 in the report assumes 260,000 kWh of electricity generated.  Figure 2‐1, Figure 2‐2, and Table 2‐3 have been updated to include the latest available  utility data.  Annual generation decreased by approximately 10% (year‐over‐year) in 2011  and 2012, and 2013 is on track for a similar decrease.  These decreases can reasonably be  attributed to the school’s closure in fall 2011 and related impacts.      Negative load growth trends are addressed in the sensitivity analysis included in Section  4.4 of the report.  While the trends reflected by this loss of load are concerning, the  project’s benefit‐cost ratio remains favorable under current conditions.  It is hoped that  the reduced energy costs resulting from the hydro project would help to reverse the  declining population in Pedro Bay, allowing the school to reopen and utility load to  increase.  It is noted that Pedro Bay’s population decreased from 65 in 1970 to a low of 33  in 1980, after the energy crises of the 1970s.  By 2000, the population had rebounded to  50.  A similar or perhaps more pronounced effect could result from the hydro project.        5) The amount of hydro assumed to be used for heating purposes equals the heating value of  36,000 gallons of diesel, which is significantly more than the 26,870 gallons shown in table  ES‐2.  The school building and teacher housing are no longer heated according to the school  district, so those heating loads should not be included in the analysis.  P OLARCONSULT M EMORANDUM    November 27, 2013  Page 4 of 9  Polarconsult’s assumptions used to estimate heating fuel displaced by excess hydro  energy are described in Appendix G, Section G.2.2.2, and are restated below:    1,052,900 kWh    Excess hydro energy dispatched to heating loads   x 0.879     combined distribution system losses and energy used by hydro load governor   x 3,414 btu/kWh  convert to btus   / 140,000 btu/gal convert to gallons heating oil   / 0.84      account for efficiency of typical combustion appliance.  26,870    gallons of fuel oil displaced.     Please note that the excess hydro and displaced fuel oil quantities above are no longer  current as the analysis in the final report has been revised to reflect current PBVC system  load (182,200 kWh) instead of 2008‐2011 load of 260,000 kWh.      As‐builts of the powerplant heat recovery expansion dated September 21, 2013 indicate  that the waste heat service to the school remains in service and the waste heat service to  the teacher housing has been disconnected.    Polarconsult understands that the PBVC is obligated to provide heat to the school building  with waste heat from the diesel powerplant.  141,000 gross kWh (part of the total gross  kWh of excess hydro energy) was budgeted to honor this obligation.  No excess hydro  energy was specifically allocated to teacher housing in the study.  Given that teacher  housing is configured to receive waste heat from the diesel powerplant, this load could  easily be served by the hydro plant if needed.    6) Section 2.0 Community Profile: The school has been closed. It doesn’t appear this has been  considered in the analysis? How does this affect the project benefits? I imagine with the  school closed it does consume near the electricity as when it was open, which would reduce  the hydro project benefits. In a small community the school can be the largest electric and  heat consumer. Has the clinic been closed too?  The report narrative has been revised to acknowledge closure of the school in fall 2011.   The clinic is still open as of November 2013.       7) Section 2.2 Existing Energy System: The switchgear was just upgraded by AEA.  The diesel powerplant upgrades completed by AEA in 2012 & 2013 have been added to  the narrative of Section 2.2.    8) Section 2.2.4 Electrical Distribution System: The distribution system includes a substantial  portion in the lake which causes reactive power.  There are reactors installed for power  factor correction.  These may need to be upgraded or replaced if the load increases  significantly.  The narrative in Section 2.2.4 has been revised to mention the reactor and system  capacitance associated with the underground cable and submarine cable distribution  system.   The need for rebalancing the system’s reactance and related matters would be  P OLARCONSULT M EMORANDUM    November 27, 2013  Page 5 of 9  considered in the design phase of the project.  The system has two reactors, but only the  reactor at the airport is currently energized.2    9) Section 2.2.5 Planned Upgrades: According to the 2012 RPSU survey, the two 58kW gensets  have 37k and 42k hours on them.  They will need to be overhauled or replaced.  The two smaller gen sets were replaced in 2012 and early 2013.  The narrative in Section  2.2.5 has been modified to reflect this.3      10) Section 2.2.6 Existing Load Profile: Normally, for northern communities we see higher  winter demands than in the summer. It sounds like this is not the case in Pedro Bay. What is  the higher summer demand attributed to?  Before mid‐2011, typical winter‐time utility generation was roughly 25% higher than  typical summer‐time utility generation.  Since mid‐2011, generation has been nearly flat  year‐round.  The Section 2.2.6 narrative has been revised appropriately.       11) Section 2.2.6 Existing Load Profile: Attributes the decrease in total generation in 2009 and  after to conservation efforts and sacrifices. Closing of the school would have a huge impact  on generation needs and this should be noted.  The school closure in 2011 has been added to the narrative in Section 2.2.6.    12) Table 2‐3: 2011 and 2012 data needs to be updated.  Table 2‐3 and Figure 2‐1 have been updated to include more recent electric system data.    13) Section 2.2.8 Population: With the school closing how has that effected population?  The narrative in Section 2.2.8 has been modified to discuss the school closure.  Table 2‐4  has been revised to include the most recent available population estimates.      14) Figure 2‐2: Why do non‐fuel costs go from approximately 30 cents/kWh to 90 cents/kWh in  Figure 2‐2 on the far right?  This may be an error, and isn’t reflected in PCE data.  The non‐fuel costs in Figure 2‐2 are calculated from monthly PCE data (monthly non‐fuel  expenses divided by monthly total kWh sales) provided by the AEA.  The charted value for  October 2011 just reflects higher‐than‐normal non‐fuel costs for that month.      15) Figure 3‐1: Why does the figure show similar home heating loads in Jun‐Aug as in Oct‐Nov?  The analysis methodology for heating applications is explained in Appendix H, Section  H.2.3.  In summary, of the 33 homes identified in the 2010 Census, 19 are assumed to be  occupied year‐round and 14 are assumed to be only seasonally occupied (June 1 to  September 30).  So while the per‐building heating load is lower during the summer  months, the total number of buildings being heated during the summer increases from 19  to 33, resulting in a similar total residential heating load year‐round.                                                              2  Personal communication with Keith Jensen, PBVC Utility Manager, Nov. 2013.  3  Personal communication with Keith Jensen, PBVC Utility Manager, Nov. 2013.  P OLARCONSULT M EMORANDUM    November 27, 2013  Page 6 of 9  16) Section 3.3.3 Access: Knutson Creek is an anadromous stream and will require ADF&G  habitat permits for any vehicles fording the river, during construction and periodic  maintenance. This should be clarified.  The narrative at Section 3.3.3 and Appendix F Section F.2.2 has been revised to clarify this  point.    17) Section 3.3.5 Penstock: Overall penstock length is estimated at 7,080’ and it is  recommended that the portion of the penstock route deviating from the main access road  will be finished as an ATV trail. This may not be suitable for construction. Installing 2,500’ of  penstock with light equipment is not feasible.  The narrative at Section 3.3.5 was not intended to imply this trail will only be constructed  as an ATV trail and has been revised for clarity.  The trail will be developed as needed to  support installation of the penstock.  Post construction, this route will only be suitable for  ATV access to the intake, as the penstock bridge will not be rated for larger vehicles.   Whether the construction trail is left in place or finished as an ATV trail is a detail to be  worked out with the relevant stakeholders in the permitting and design phase of the  project.      18) Section 4.1 Cost Estimate: Believe this number to be a bit low. For example, $191,000 for  16,400’ of access roads and trails does not seem reasonable based on recently bid hydro  projects. Mobilization costs may actually be twice than the estimate. Lastly, power and  communication lines cost estimate seem light. Rural overhead power lines along existing  roads typically cost $250k‐$500k/mile, and this is a two‐mile buried line. Buried line  typically costs about twice what overhead line costs.  Polarconsult has reviewed the project cost estimate and concurs that the line item  estimates for the power line and road construction in the draft report were low.  The  project cost estimate and economic analysis have been revised throughout the final  report.    Bid costs for rural projects are notoriously variable, and heavily depend on how the  project is structured for bid and which construction firms bid on the project.  The cost  estimate implicitly assumes that the project is organized in an efficient manner, managed  by individuals experienced in the unique logistics of rural Alaska projects, and  competitively bid by a range of qualified contractors.      Available information indicates that geotechnical conditions at the project site are  favorable for road construction.  Most of the site is underlain by an aggregate alluvial fan,  which is assumed to be suitable for road construction by shaping on‐site material with  minimal import or processing of material.  As construction equipment capable of building  these roads is available in Pedro Bay, road construction appear suitable for completion  under force account with direct hire of qualified operators.      As mentioned in Section 3.3.1, the powerline route appears suitable for overhead or  underground construction.  Existing lines in Pedro Bay are underground and the  P OLARCONSULT M EMORANDUM    November 27, 2013  Page 7 of 9  community prefers underground lines where feasible, so this practice was followed for  the conceptual designs.      AEA’s suggested cost metric of $250,000 to $500,000 per mile for rural overhead power  lines is applicable to three‐phase four‐wire 7.2/12.47 kV power lines.  As Pedro Bay is a  single‐phase system, this cost metric is not directly applicable.  The cost of rural single  phase overhead lines is approximately 75% that of comparable three phase lines, inferring  an appropriate cost metric of $187,500 to $375,000 per mile.4  The upper end of this cost  range is applicable for lines with adverse geotechnical conditions – such as warm silty  permafrost soils – that require driven steel piling to support the wood poles.   Geotechnical conditions along the power line alignment in Pedro Bay appear suitable for  direct burial of poles.  Accordingly, AEA’s suggested cost metric results in an expected cost  for an overhead power line extension of $187,500 per mile, or $351,500 for the power line  extension to the hydro powerhouse.  At the current level of study, this cost estimate is  applicable for an overhead or underground power line.         19) Section 4.1 Cost Estimate: Does the proposal include the cost of upgrading the entire  distribution system, service entrances and house electrical and heating systems to allow for  electric heating?  The $310,000 estimate ($362,000 found in appendix) only mentions  building conversions.  A distribution system analysis may be needed to determine the  capacity of the existing power lines and transformers, and the cost of any needed upgrades.  The budget item for interruptible electric heating services includes installation of a dual  meter base, interruptible service main panel, wiring, and installation of electric heating  equipment.  It did not include upgrade of the utility service lines or utility distribution  system.     The existing village distribution system is assumed to have cables with at least #2 copper  conductor, which is adequate to transmit the full 200 kW (~30 amperes) output of the  proposed hydro project.  If individual distribution transformers or service lines are  undersized for the additional load of electric heating, the electric heating capacity  installed at that location could be restricted to the capacity of the service, or the service  could be upgraded.     20) Section 4.2 Economic Evaluation: The base case analysis uses 260,000 kWh demand, while  PCE FY13 data shows 185,000 kWh generated (29% less) and 155,000 sold (40% less).  The sensitivity analysis in Section 4.4 addresses the impacts of variations in load from the  260,000 kWh used for the study.  Because PBVC’s system load has decreased  approximately 30%, the report has been revised where appropriate to acknowledge this  decreased load and discuss how it impacts the project economics.                                                              4  Comparative costs and cost factors for rural overhead power lines from HVDC Transmission System for Rural  Alaskan Applications, Phase II Prototyping and Testing, Final Report.  Polarconsult Alaska, Inc. May 2012.  Table  B‐1 and associated narrative.  P OLARCONSULT M EMORANDUM    November 27, 2013  Page 8 of 9  21) Section 4.2 Economic Evaluation: The grant‐financed economic analysis scenario may be  valuable to Pedro Bay but is not relevant to AEA’s decision making.  No action taken.  The ‘grant‐financed’ economic analysis scenario uses the economic  model developed by ISER and used by the AEA to evaluate grant applications submitted to  the Renewable Energy Grant Program.  This has been clarified in the main report  narrative.    22) Page B‐8. Photos appear to be identical.  Photograph B‐11 has been replaced with the correct photograph.    23) Table C‐1. Please clarify what Note 2 is referring to.  Table C‐1 Note 2 has been revised.    24) We understand Pedro Bay would like to displace as much diesel fuel as possible; and, unless  there is a reason to assume a sudden change in the trend towards lower electric loads over  time, justifying this project based on higher electric load is not reasonable. With the school  closing and the decrease in population that usually follows it may be more feasible to  permit and design a smaller project that does not affect salmon habitat. There are hydro  projects that operate in conjunction with a diesel plant and have been shown to be feasible.  They contribute to a portion of the community’s generation requirements and still provide  beneficial savings. This may be something that can work for Pedro Bay.  The report narrative has been revised to clarify the report findings with regard to installed  capacity.  A project with installed capacity in the range of 100 to 250 kW is best‐suited to  meet the village’s long‐term energy needs, and the economic analysis identified a 200‐kW  project as the most economic installed capacity.  The project capacity should be finalized  only after permit conditions are known, and project designs and cost estimates are more  refined.    Projects within the 100 to 250 kW range are technically viable on Knutson Creek.  Smaller  projects within this range would reduce, not avoid, partial dewatering of resident and  anadromous fish habitat and the associated habitat impacts.  Smaller project capacities  provide modest capital cost and negligible O&M cost savings.  As detailed in Table H‐5,  downsizing the project from 200 kW to 100 kW reduces the estimated installed cost by  approximately 7% (estimated installed cost decreases from $4.5M to $4.2M).  This is  because many of the project costs, such as for pre‐construction work, mobilization,  shipping, power line, diversion structure, and access roads, do not change with the  decreased project size.  The only significant savings come from reduced costs for the  penstock, powerhouse, and turbine/generator.    The current decrease in population is consistent with past fluctuations in Pedro Bay’s  population, and it is probable that the village’s population will continue to track future  economic opportunities in the region.  A significant and permanent reduction in electricity  costs from the hydro project will have a clear positive influence on the local economy, and  may result in a rebound in population and utility load.  It is not clear that a major  P OLARCONSULT M EMORANDUM    November 27, 2013  Page 9 of 9  community asset with a 50+ year useful life should be sized based on a 2‐3 year transient  trend in the local population and utility load.  Polarconsult is not aware of any village  hydro project in Alaska that has proven to be over‐sized over the course of its useful life.      In consideration of these factors, Polarconsult recommends that Pedro Bay proceed with  design and permitting of a 200 kW project, and revisit the matter of installed capacity  once permit conditions are known and designs are more advanced.  At that time, the  benefit‐cost ratio of various configurations should be calculated and the appropriate  project capacity should be selected.  Based on available information, it appears that  appropriate installed capacity will be in the range of 100 to 250 kW.     OTHER SIGNIFICANT REPORT REVISIONS  1.  The draft report incorrectly included displaced heating fuel for the school building as part of  the total heating oil displaced by the project through interruptible electric heating services.   The school building is currently heated from a waste heat system at the diesel power plant,  and the PBVC is obligated to provide heat to the school.  Accordingly, electric heating at the  school displaces waste heat rather than fuel oil, and is not a project benefit.  Tables and  narrative throughout the report have been revised to reflect this.      2. Because of the significant decrease in system load that occurred while this report was under  preparation and review, Polarconsult has revised the analysis and final report to reflect the  estimated annual utility load for 2013 of approximately 182,200 kWh, which reflects an  approximately 30% decrease from the 260,000 kWh annual system load that was used in  the draft report.  All figures, tables, and narratives reflect this revised system load.       Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report              APPENDIX J – TABULAR HYDROLOGY DATA           Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   J‐1            This page intentionally blank.  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 10/12/2010 23 1.55 1.56 1.59 118 34.40 35.74 37.04 (2) 10/13/2010 48 1.53 1.54 1.56 94 32.79 33.99 35.97 10/14/2010 48 1.51 1.53 1.54 91 31.83 33.25 35.25 10/15/2010 47 1.50 1.52 1.54 91 31.87 33.51 35.38 10/16/2010 48 1.51 1.52 1.53 99 34.24 35.76 36.88 10/17/2010 48 1.51 1.54 1.57 100 36.45 37.19 38.02 10/18/2010 48 1.53 1.54 1.57 103 36.59 37.52 38.76 10/19/2010 48 1.52 1.55 1.58 109 37.30 38.07 39.59 10/20/2010 48 1.55 1.56 1.58 118 37.30 37.96 39.31 10/21/2010 48 1.57 1.69 1.82 127 37.37 37.88 38.14 10/22/2010 48 1.63 1.66 1.73 136 36.92 37.86 39.31 10/23/2010 48 1.58 1.62 1.64 119 37.14 37.85 38.89 10/24/2010 48 1.56 1.58 1.61 112 36.79 37.39 38.24 10/25/2010 48 1.55 1.57 1.59 102 35.90 36.65 37.50 10/26/2010 48 1.53 1.55 1.56 96 35.97 36.81 38.31 10/27/2010 48 1.51 1.53 1.57 115 35.02 35.95 36.91 10/28/2010 48 1.55 1.57 1.61 96 35.25 35.85 36.79 10/29/2010 48 1.51 1.53 1.57 84 34.99 35.63 36.72 10/30/2010 48 1.49 1.50 1.52 78 33.28 34.59 35.58 10/31/2010 48 1.47 1.48 1.50 76 32.06 33.30 34.73 11/1/2010 48 1.47 1.48 1.49 71 34.33 34.81 35.25 11/2/2010 48 1.45 1.46 1.47 68 34.01 34.51 35.22 11/3/2010 48 1.44 1.45 1.47 64 33.88 34.76 35.71 11/4/2010 48 1.43 1.44 1.46 60 32.62 33.37 34.40 11/5/2010 48 1.41 1.43 1.44 56 31.46 32.82 34.01 11/6/2010 48 1.40 1.41 1.43 52 31.53 32.23 33.42 11/7/2010 48 1.38 1.39 1.41 53 31.43 31.60 32.03 11/8/2010 48 1.40 1.62 1.74 51 31.43 31.47 31.51 11/9/2010 48 1.44 1.63 1.93 51 31.40 31.45 31.51 11/10/2010 48 1.39 1.41 1.47 50 31.43 31.66 32.65 11/11/2010 48 1.36 1.38 1.40 46 32.75 33.33 34.10 11/12/2010 48 1.35 1.36 1.37 46 32.39 33.36 34.53 11/13/2010 48 1.35 1.36 1.37 44 32.59 33.18 33.51 11/14/2010 48 1.34 1.35 1.36 44 32.82 33.51 34.23 11/15/2010 48 1.34 1.36 1.46 44 31.43 31.68 32.85 11/16/2010 48 1.47 1.75 1.90 41 31.37 31.45 31.51 11/17/2010 48 1.12 1.22 1.47 38 31.39 31.46 31.53 11/18/2010 48 0.85 0.93 1.10 38 31.42 31.49 31.52 11/19/2010 48 0.97 1.35 2.05 39 31.40 31.47 31.52 11/20/2010 48 1.85 2.19 2.41 44 31.42 31.46 31.52 11/21/2010 48 1.37 1.49 1.89 52 31.43 31.50 31.57 11/22/2010 48 1.36 1.41 1.47 64 31.46 31.64 31.93 11/23/2010 48 1.47 1.67 1.86 76 31.90 33.59 35.22 11/24/2010 48 1.60 1.68 1.86 90 34.73 35.02 35.32 11/25/2010 48 1.50 1.56 1.62 79 31.40 32.65 34.80 11/26/2010 48 1.48 1.49 1.51 86 31.40 31.46 31.50 11/27/2010 48 1.49 1.51 1.53 77 31.47 31.89 32.49 11/28/2010 48 1.47 1.59 1.88 73 31.40 31.66 32.59 11/29/2010 48 1.88 2.12 2.42 70 31.38 31.44 31.51 11/30/2010 48 1.91 2.17 2.50 66 31.39 31.44 31.49 12/1/2010 48 2.02 2.27 2.55 63 31.38 31.44 31.51 12/2/2010 48 2.13 2.31 2.57 60 31.39 31.44 31.49 12/3/2010 48 2.07 2.48 3.25 57 31.39 31.44 31.49 12/4/2010 48 2.26 2.77 3.27 54 31.39 31.46 31.52 12/5/2010 48 1.44 1.68 2.25 48 31.40 31.48 31.57 12/6/2010 48 1.40 1.42 1.44 46 31.43 31.49 31.57 November 2013 ‐ Final Report Appendix J Page J‐1  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 12/7/2010 48 1.39 1.40 1.41 45 31.43 31.49 31.56 12/8/2010 48 1.37 1.39 1.41 42 31.43 31.47 31.49 12/9/2010 48 1.36 1.37 1.38 40 31.40 31.46 31.49 12/10/2010 48 1.32 1.34 1.37 40 31.40 31.46 31.53 12/11/2010 48 1.32 1.35 1.38 40 31.43 31.47 31.53 12/12/2010 48 1.34 1.35 1.37 39 31.43 31.48 31.53 12/13/2010 48 1.34 1.35 1.36 36 31.46 31.50 31.56 12/14/2010 48 1.31 1.33 1.35 33 31.43 31.48 31.53 12/15/2010 48 1.30 1.31 1.32 32 31.46 31.50 31.56 12/16/2010 48 1.29 1.30 1.32 33 31.46 31.51 31.56 12/17/2010 48 1.28 1.30 1.32 32 31.43 31.52 31.56 12/18/2010 48 1.29 1.29 1.31 33 31.46 31.53 31.56 12/19/2010 48 1.29 1.30 1.31 32 31.49 31.56 31.63 12/20/2010 48 1.28 1.29 1.31 30 31.56 31.62 31.69 12/21/2010 48 1.27 1.28 1.29 29 31.56 31.62 31.66 12/22/2010 48 1.26 1.27 1.28 28 31.53 31.61 31.69 12/23/2010 48 1.25 1.26 1.27 28 31.53 31.60 31.63 12/24/2010 48 1.25 1.26 1.27 27 31.56 31.63 31.69 12/25/2010 48 1.24 1.25 1.27 26 31.60 31.65 31.69 12/26/2010 48 1.24 1.24 1.25 25 31.63 31.69 31.76 12/27/2010 48 1.23 1.23 1.24 24 31.66 31.76 31.86 12/28/2010 48 1.22 1.23 1.24 24 31.69 31.78 31.83 12/29/2010 48 1.22 1.23 1.24 24 31.79 31.96 32.19 12/30/2010 48 1.22 1.23 1.26 28 31.76 32.23 32.49 12/31/2010 48 1.24 1.26 1.30 37 31.53 31.98 32.52 1/1/2011 48 1.24 1.34 1.44 53 31.43 32.02 32.82 1/2/2011 48 1.39 1.45 1.48 40 31.43 31.52 31.69 1/3/2011 48 1.36 1.42 1.57 49 31.63 32.36 33.21 1/4/2011 48 1.41 1.46 1.53 28 31.83 32.56 32.85 1/5/2011 48 1.36 1.38 1.41 22 32.39 32.63 32.89 1/6/2011 48 1.20 1.31 1.36 21 31.40 31.73 32.65 1/7/2011 48 1.14 1.18 1.22 21 31.39 31.45 31.49 1/8/2011 48 1.18 1.23 1.31 20 31.39 31.43 31.46 1/9/2011 48 1.29 1.38 1.45 20 31.40 31.43 31.47 1/10/2011 48 1.42 1.47 1.54 20 31.40 31.43 31.50 1/11/2011 48 1.38 1.46 1.51 19 31.37 31.43 31.50 1/12/2011 48 1.28 1.35 1.47 19 31.40 31.43 31.49 1/13/2011 48 1.31 1.45 1.54 19 31.40 31.44 31.50 1/14/2011 48 1.17 1.25 1.46 18 31.39 31.44 31.49 1/15/2011 48 1.17 1.23 1.30 18 31.36 31.43 31.49 1/16/2011 48 1.05 1.14 1.27 18 31.39 31.45 31.49 1/17/2011 48 1.21 1.34 1.44 18 31.40 31.44 31.50 1/18/2011 48 1.09 1.27 1.46 17 31.36 31.44 31.53 1/19/2011 48 1.46 1.55 1.62 17 31.37 31.43 31.47 1/20/2011 48 1.62 1.70 1.81 17 31.40 31.46 31.51 1/21/2011 48 1.49 1.71 1.83 16 31.40 31.49 31.57 1/22/2011 48 1.30 1.37 1.48 16 31.40 31.47 31.57 1/23/2011 48 1.31 1.34 1.35 14 31.40 31.51 31.60 1/24/2011 48 1.27 1.30 1.34 16 31.49 31.75 32.12 1/25/2011 48 1.25 1.27 1.28 16 32.12 32.57 32.95 1/26/2011 48 1.25 1.26 1.28 15 31.63 32.15 32.52 1/27/2011 48 1.24 1.25 1.27 14 31.43 31.73 32.32 1/28/2011 48 1.22 1.24 1.26 13 32.29 32.64 32.88 1/29/2011 48 1.21 1.22 1.24 12 32.72 32.91 33.11 1/30/2011 48 1.19 1.20 1.22 11 32.88 32.98 33.11 1/31/2011 48 1.18 1.19 1.20 11 32.92 33.03 33.15 November 2013 ‐ Final Report Appendix J Page J‐2  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 2/1/2011 48 1.18 1.19 1.19 11 32.61 32.80 33.08 2/2/2011 48 1.17 1.18 1.19 11 32.05 32.40 32.55 2/3/2011 48 1.17 1.17 1.18 11 31.99 32.20 32.35 2/4/2011 48 1.15 1.17 1.19 11 31.39 31.64 32.12 2/5/2011 48 1.15 1.16 1.18 12 31.46 31.83 32.22 2/6/2011 48 1.16 1.16 1.17 12 31.82 32.58 33.11 2/7/2011 48 1.15 1.16 1.17 17 32.42 32.83 33.24 2/8/2011 48 1.17 1.21 1.23 16 32.75 33.03 33.21 2/9/2011 48 1.17 1.20 1.22 12 32.91 33.17 33.38 2/10/2011 48 1.15 1.17 1.19 11 31.43 32.16 32.88 2/11/2011 48 1.11 1.40 1.70 11 31.36 31.43 31.47 2/12/2011 48 1.31 1.48 1.60 11 31.37 31.42 31.47 2/13/2011 48 1.57 1.85 2.10 10 31.37 31.43 31.48 2/14/2011 48 1.99 2.31 2.59 10 31.35 31.43 31.49 2/15/2011 48 2.61 2.91 3.07 10 31.37 31.43 31.47 2/16/2011 48 1.24 1.80 2.97 10 31.39 31.47 31.60 2/17/2011 48 1.17 1.19 1.23 10 31.43 31.50 31.60 2/18/2011 48 1.17 1.18 1.20 9 31.46 31.51 31.56 2/19/2011 48 1.16 1.16 1.17 10 31.46 31.51 31.59 2/20/2011 48 1.15 1.15 1.16 10 31.49 31.56 31.62 2/21/2011 48 1.14 1.15 1.16 10 31.56 31.61 31.69 2/22/2011 48 1.12 1.14 1.14 10 31.52 31.62 31.69 2/23/2011 48 1.13 1.13 1.14 10 31.59 31.75 31.95 2/24/2011 48 1.13 1.13 1.13 11 31.79 32.01 32.28 2/25/2011 48 1.12 1.14 1.15 10 31.75 31.95 32.28 2/26/2011 48 1.12 1.13 1.14 10 31.43 31.57 31.79 2/27/2011 48 1.11 1.12 1.13 10 31.43 31.55 31.69 2/28/2011 48 1.11 1.11 1.12 10 31.49 31.55 31.66 3/1/2011 48 1.11 1.11 1.12 9 31.52 31.59 31.69 3/2/2011 48 1.10 1.11 1.11 9 31.52 31.62 31.72 3/3/2011 48 1.10 1.10 1.11 9 31.52 31.61 31.69 3/4/2011 48 1.10 1.10 1.10 9 31.52 31.62 31.72 3/5/2011 48 1.09 1.10 1.10 9 31.52 31.66 31.75 3/6/2011 48 1.09 1.09 1.10 9 31.66 31.77 31.99 3/7/2011 48 1.09 1.09 1.10 9 31.92 32.16 32.38 3/8/2011 48 1.09 1.09 1.09 9 31.99 32.17 32.35 3/9/2011 48 1.08 1.08 1.09 9 31.85 32.08 32.25 3/10/2011 48 1.08 1.08 1.09 8 31.72 31.95 32.12 3/11/2011 48 1.07 1.08 1.08 9 31.62 31.83 31.99 3/12/2011 48 1.07 1.07 1.08 9 31.59 31.75 31.89 3/13/2011 48 1.07 1.07 1.07 8 31.56 31.72 31.89 3/14/2011 48 1.06 1.07 1.07 8 31.59 31.72 31.85 3/15/2011 48 1.06 1.06 1.07 8 31.66 31.82 31.99 3/16/2011 48 1.06 1.06 1.06 8 31.72 31.90 32.05 3/17/2011 48 1.05 1.06 1.06 8 31.62 31.84 32.09 3/18/2011 48 1.05 1.06 1.06 8 32.02 32.34 32.65 3/19/2011 48 1.05 1.05 1.06 8 32.15 32.42 32.65 3/20/2011 48 1.05 1.06 1.06 8 32.38 32.61 32.88 3/21/2011 48 1.04 1.05 1.05 8 32.55 32.77 32.95 3/22/2011 48 1.04 1.04 1.05 8 32.68 32.86 33.04 3/23/2011 48 1.04 1.04 1.05 8 32.75 32.95 33.21 3/24/2011 48 1.04 1.04 1.05 8 32.75 32.98 33.31 3/25/2011 48 1.03 1.04 1.05 8 32.68 33.01 33.41 3/26/2011 48 1.03 1.04 1.04 8 32.68 32.98 33.34 3/27/2011 48 1.03 1.03 1.04 8 32.28 32.68 33.08 3/28/2011 48 1.03 1.03 1.04 8 32.12 32.59 33.01 November 2013 ‐ Final Report Appendix J Page J‐3  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 3/29/2011 48 1.03 1.04 1.04 9 32.71 33.03 33.37 3/30/2011 48 1.03 1.04 1.05 8 32.84 33.12 33.57 3/31/2011 48 1.03 1.03 1.04 8 32.19 32.60 32.98 4/1/2011 48 1.02 1.03 1.03 8 31.89 32.48 33.08 4/2/2011 48 1.02 1.03 1.04 9 32.68 32.89 33.17 4/3/2011 48 1.03 1.04 1.06 9 32.78 33.06 33.41 4/4/2011 48 1.03 1.03 1.04 8 32.98 33.15 33.47 4/5/2011 48 1.02 1.03 1.03 8 32.52 32.83 33.04 4/6/2011 48 1.01 1.02 1.03 11 31.49 32.05 32.48 4/7/2011 48 1.02 1.06 1.10 10 31.92 32.56 33.01 4/8/2011 48 1.04 1.05 1.06 10 32.65 33.06 33.80 4/9/2011 48 1.03 1.04 1.05 9 32.58 32.98 33.37 4/10/2011 48 1.03 1.03 1.04 9 32.65 32.88 33.08 4/11/2011 46 1.02 1.03 1.03 9 32.65 32.90 33.27 4/12/2011 48 1.02 1.02 1.03 9 32.22 32.67 33.27 4/13/2011 48 1.01 1.02 1.03 9 31.62 32.35 33.08 4/14/2011 48 1.01 1.02 1.02 9 31.66 32.48 33.27 4/15/2011 48 1.01 1.02 1.04 10 32.32 33.11 34.00 4/16/2011 48 1.02 1.04 1.06 11 32.45 33.23 34.10 4/17/2011 48 1.05 1.06 1.09 14 32.48 33.23 34.06 4/18/2011 48 1.08 1.10 1.12 16 32.48 33.22 34.13 4/19/2011 48 1.11 1.12 1.16 19 32.52 33.24 34.16 4/20/2011 48 1.14 1.16 1.18 21 32.35 33.22 34.26 4/21/2011 48 1.16 1.18 1.19 25 32.38 33.15 34.07 4/22/2011 48 1.17 1.21 1.27 55 32.62 33.15 33.67 4/23/2011 48 1.27 1.38 1.52 79 31.60 32.15 32.55 4/24/2011 48 1.43 1.48 1.61 76 31.67 32.69 34.10 4/25/2011 48 1.43 1.48 1.52 57 32.36 33.66 35.84 4/26/2011 48 1.36 1.41 1.49 44 33.02 33.67 34.73 4/27/2011 48 1.32 1.35 1.38 43 33.21 34.91 38.14 4/28/2011 48 1.32 1.34 1.37 45 33.18 33.91 34.66 4/29/2011 48 1.31 1.35 1.41 55 33.84 34.89 36.29 4/30/2011 48 1.39 1.41 1.44 55 33.78 34.96 36.88 5/1/2011 48 1.38 1.41 1.45 57 33.41 35.40 38.30 5/2/2011 48 1.38 1.41 1.45 57 32.42 35.32 40.55 5/3/2011 48 1.40 1.42 1.44 60 33.65 35.63 38.56 5/4/2011 48 1.39 1.42 1.48 69 34.37 35.91 39.49 5/5/2011 48 1.42 1.46 1.51 83 32.85 35.90 40.36 5/6/2011 48 1.45 1.50 1.59 87 33.15 36.17 41.23 5/7/2011 48 1.48 1.51 1.57 82 33.32 35.94 39.43 5/8/2011 48 1.47 1.50 1.53 99 34.66 36.14 38.33 5/9/2011 48 1.50 1.54 1.63 116 34.92 37.09 40.78 5/10/2011 48 1.53 1.58 1.63 106 34.10 37.18 41.96 5/11/2011 48 1.52 1.55 1.60 105 33.05 36.73 41.96 5/12/2011 48 1.52 1.55 1.64 125 33.12 37.20 42.94 5/13/2011 48 1.55 1.59 1.66 132 33.74 37.72 43.13 5/14/2011 48 1.58 1.60 1.65 110 35.58 36.68 38.27 5/15/2011 48 1.54 1.56 1.59 114 35.12 37.37 40.81 5/16/2011 48 1.55 1.57 1.61 133 35.90 37.75 40.30 5/17/2011 48 1.56 1.60 1.71 200 35.87 37.92 41.03 5/18/2011 48 1.67 1.70 1.76 223 35.48 37.93 41.74 5/19/2011 48 1.67 1.72 1.81 307 35.91 38.01 40.94 5/20/2011 48 1.73 1.80 1.88 224 35.61 36.56 38.31 5/21/2011 48 1.68 1.72 1.79 219 35.29 37.58 41.83 5/22/2011 48 1.66 1.72 1.90 285 35.48 37.96 42.28 5/23/2011 48 1.71 1.78 1.88 240 35.88 37.16 38.47 November 2013 ‐ Final Report Appendix J Page J‐4  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 5/24/2011 48 1.69 1.74 1.80 221 36.13 37.30 38.76 5/25/2011 48 1.67 1.72 1.80 265 35.87 38.21 42.34 5/26/2011 48 1.67 1.76 1.89 364 35.42 38.67 42.38 5/27/2011 48 1.74 1.86 1.99 418 36.34 38.67 43.23 5/28/2011 48 1.82 1.90 2.01 351 35.59 37.89 41.39 5/29/2011 48 1.74 1.83 1.97 413 35.91 38.09 41.49 5/30/2011 48 1.82 1.91 2.04 35.88 39.18 44.41 (1) 5/31/2011 48 1.92 2.01 2.19 36.59 37.82 39.25 (1) 6/1/2011 48 1.96 2.09 2.24 445 36.14 37.06 38.19 6/2/2011 48 1.85 1.98 2.14 35.29 39.01 44.56 (1) 6/3/2011 48 1.92 1.99 2.18 463 36.56 38.26 41.84 6/4/2011 48 1.83 1.93 2.02 424 36.63 37.58 38.70 6/5/2011 48 1.83 1.88 1.96 372 36.43 38.42 41.42 6/6/2011 48 1.78 1.84 1.91 399 35.46 38.54 41.80 6/7/2011 48 1.81 1.87 1.98 448 37.63 39.81 43.68 6/8/2011 48 1.83 1.91 1.97 415 37.41 39.05 40.91 6/9/2011 48 1.83 1.88 1.95 452 37.28 39.32 41.33 6/10/2011 48 1.85 1.90 1.99 428 37.86 39.25 41.36 6/11/2011 48 1.82 1.89 1.95 441 37.37 38.76 40.34 6/12/2011 48 1.81 1.88 1.93 392 38.18 39.46 41.13 6/13/2011 48 1.82 1.86 1.92 383 37.83 39.39 41.13 6/14/2011 48 1.79 1.85 1.90 322 37.86 39.62 42.47 6/15/2011 48 1.74 1.81 1.86 346 37.73 40.42 44.02 6/16/2011 48 1.74 1.82 1.89 353 37.89 40.93 45.09 6/17/2011 48 1.76 1.83 1.92 316 38.05 41.72 46.88 6/18/2011 48 1.76 1.80 1.86 318 38.21 41.45 44.90 6/19/2011 48 1.76 1.80 1.90 426 39.86 40.75 41.77 6/20/2011 48 1.81 1.88 1.94 475 39.31 40.45 41.90 6/21/2011 48 1.88 1.95 2.04 430 39.05 40.30 42.19 6/22/2011 48 1.81 1.90 2.00 387 38.76 40.28 42.69 6/23/2011 48 1.79 1.85 1.94 430 37.34 41.94 47.85 6/24/2011 48 1.82 1.89 1.99 430 40.37 42.86 46.20 6/25/2011 48 1.82 1.89 1.99 416 40.17 41.46 42.76 6/26/2011 48 1.82 1.88 1.96 477 40.17 42.84 46.38 6/27/2011 48 1.90 1.96 2.04 463 40.91 42.21 44.34 6/28/2011 48 1.86 1.93 2.02 391 39.51 40.22 41.40 6/29/2011 48 1.80 1.85 1.90 385 39.24 42.12 47.69 6/30/2011 48 1.81 1.85 1.91 377 40.72 43.20 46.88 7/1/2011 48 1.80 1.84 1.90 360 41.32 43.86 47.41 7/2/2011 48 1.78 1.83 1.90 320 41.36 42.58 44.05 7/3/2011 48 1.77 1.81 1.86 291 41.10 43.64 47.44 7/4/2011 48 1.76 1.79 1.81 288 41.87 43.04 44.81 7/5/2011 48 1.74 1.78 1.86 354 41.10 44.61 49.71 7/6/2011 48 1.78 1.83 1.89 312 42.73 45.36 49.16 7/7/2011 48 1.75 1.80 1.87 256 42.09 43.54 45.03 7/8/2011 48 1.72 1.76 1.80 304 41.68 43.56 46.72 7/9/2011 48 1.73 1.80 1.86 288 42.22 43.08 44.12 7/10/2011 48 1.74 1.78 1.82 295 41.90 43.07 44.56 7/11/2011 48 1.75 1.84 1.99 463 42.76 44.11 45.16 7/12/2011 48 1.88 1.93 2.01 328 42.00 42.92 44.25 7/13/2011 48 1.76 1.81 1.90 259 40.94 42.42 44.40 7/14/2011 48 1.73 1.76 1.80 256 41.45 42.35 43.45 7/15/2011 48 1.73 1.76 1.79 239 41.42 43.51 46.88 7/16/2011 48 1.70 1.74 1.78 264 42.91 44.11 46.82 7/17/2011 48 1.71 1.76 1.89 317 42.82 43.69 44.65 7/18/2011 48 1.76 1.81 1.91 265 42.28 43.61 45.75 November 2013 ‐ Final Report Appendix J Page J‐5  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 7/19/2011 48 1.74 1.76 1.79 243 42.28 45.12 49.71 7/20/2011 48 1.69 1.74 1.78 228 42.76 46.54 51.59 7/21/2011 48 1.69 1.73 1.79 197 44.31 46.23 48.56 7/22/2011 48 1.67 1.70 1.73 273 44.47 47.27 51.53 7/23/2011 48 1.69 1.80 2.00 440 45.47 47.29 50.21 7/24/2011 48 1.84 1.91 2.00 472 43.52 44.75 46.01 7/25/2011 48 1.88 1.94 2.03 452 43.14 44.14 45.57 7/26/2011 48 1.85 1.92 1.98 414 41.90 44.07 45.60 7/27/2011 48 1.81 1.87 1.92 351 43.04 45.00 47.91 7/28/2011 48 1.78 1.83 1.89 286 43.93 45.27 47.20 7/29/2011 48 1.74 1.78 1.82 269 43.87 45.75 47.97 7/30/2011 48 1.73 1.77 1.81 242 44.84 45.55 46.35 7/31/2011 48 1.72 1.74 1.79 240 44.28 45.25 46.72 8/1/2011 48 1.71 1.74 1.77 378 44.53 45.64 46.76 8/2/2011 48 1.76 1.90 1.98 427 45.32 46.21 47.45 8/3/2011 48 1.83 1.88 1.95 398 45.00 46.25 47.73 8/4/2011 48 1.81 1.97 2.14 471 43.90 45.01 46.07 8/5/2011 48 1.88 1.96 2.04 450 41.87 43.12 44.56 8/6/2011 48 1.85 1.98 2.17 41.58 42.38 43.24 (1) 8/7/2011 48 1.94 2.04 2.13 464 41.52 43.03 44.97 8/8/2011 48 1.87 1.93 2.02 474 42.00 42.66 43.27 8/9/2011 48 1.90 2.01 2.15 450 41.78 43.09 45.23 8/10/2011 48 1.87 1.98 2.13 465 42.63 44.68 47.88 8/11/2011 48 1.88 1.94 2.00 457 42.54 45.27 48.78 8/12/2011 48 1.86 1.91 1.95 391 43.93 45.23 46.51 8/13/2011 48 1.78 1.86 1.95 327 44.68 46.50 49.09 8/14/2011 48 1.76 1.81 1.88 259 45.69 47.03 49.34 8/15/2011 48 1.72 1.76 1.80 215 42.69 46.13 50.23 8/16/2011 48 1.68 1.72 1.75 189 43.58 46.92 50.79 8/17/2011 48 1.64 1.69 1.73 180 45.44 47.29 49.37 8/18/2011 48 1.65 1.68 1.71 238 46.13 46.95 47.72 8/19/2011 48 1.68 1.74 1.83 259 45.78 46.35 46.79 8/20/2011 48 1.71 1.76 1.83 202 44.68 45.99 47.51 8/21/2011 48 1.67 1.70 1.76 191 44.53 46.08 48.07 8/22/2011 48 1.67 1.69 1.72 178 43.99 45.18 46.07 8/23/2011 48 1.65 1.67 1.70 163 43.39 44.58 47.22 8/24/2011 48 1.63 1.65 1.67 167 41.96 43.29 44.40 8/25/2011 48 1.64 1.66 1.68 152 43.48 45.01 47.07 8/26/2011 48 1.61 1.64 1.67 140 43.99 46.13 49.27 8/27/2011 48 1.59 1.62 1.64 128 43.45 45.23 46.47 8/28/2011 48 1.58 1.60 1.61 119 42.31 45.64 50.20 8/29/2011 48 1.56 1.58 1.60 117 43.20 45.85 48.93 8/30/2011 48 1.57 1.58 1.60 242 45.15 46.43 48.31 8/31/2011 48 1.58 1.74 1.84 189 45.19 45.97 47.35 9/1/2011 48 1.65 1.69 1.75 188 42.97 45.06 47.44 9/2/2011 48 1.65 1.69 1.72 181 44.18 45.03 46.10 9/3/2011 48 1.64 1.68 1.71 169 44.02 45.25 46.54 9/4/2011 48 1.64 1.66 1.69 154 43.93 45.24 47.22 9/5/2011 48 1.60 1.64 1.66 142 42.69 44.23 45.59 9/6/2011 48 1.60 1.62 1.65 154 43.42 44.77 46.16 9/7/2011 48 1.61 1.64 1.72 374 43.99 45.22 46.95 9/8/2011 48 1.72 1.86 1.97 256 44.12 45.14 46.66 9/9/2011 48 1.72 1.75 1.80 213 40.98 43.72 47.60 9/10/2011 48 1.68 1.71 1.75 191 42.98 44.52 46.98 9/11/2011 48 1.66 1.69 1.72 181 43.64 44.63 46.57 9/12/2011 48 1.65 1.68 1.70 178 43.77 44.77 46.19 November 2013 ‐ Final Report Appendix J Page J‐6  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 9/13/2011 48 1.64 1.67 1.78 400 43.89 45.07 47.07 9/14/2011 48 1.80 1.87 1.96 388 43.62 44.51 46.01 9/15/2011 48 1.80 1.93 2.06 444 43.14 43.71 44.72 9/16/2011 48 1.84 1.91 1.99 385 42.16 43.53 45.28 9/17/2011 48 1.80 1.85 1.90 295 42.00 43.17 44.94 9/18/2011 48 1.73 1.79 1.83 250 41.13 42.82 45.16 9/19/2011 48 1.72 1.75 1.79 237 41.87 42.75 43.93 9/20/2011 48 1.69 1.74 1.78 287 42.00 43.28 45.19 9/21/2011 48 1.71 1.78 1.83 254 42.38 43.54 45.47 9/22/2011 48 1.74 1.76 1.81 228 41.93 43.32 45.09 9/23/2011 48 1.70 1.73 1.77 238 40.11 42.17 44.24 9/24/2011 48 1.68 1.74 1.81 241 41.00 41.87 43.14 9/25/2011 48 1.71 1.74 1.78 217 40.14 41.75 43.77 9/26/2011 48 1.69 1.72 1.75 199 38.92 40.71 44.43 9/27/2011 48 1.68 1.70 1.73 183 38.02 39.75 42.66 9/28/2011 48 1.65 1.68 1.72 165 37.63 39.32 41.03 9/29/2011 48 1.63 1.66 1.69 149 37.69 39.41 41.42 9/30/2011 48 1.62 1.63 1.66 141 36.56 38.56 40.91 10/1/2011 48 1.60 1.62 1.65 138 39.05 40.26 42.02 10/2/2011 48 1.59 1.62 1.64 160 39.31 40.42 41.80 10/3/2011 48 1.58 1.65 1.72 136 39.50 40.22 41.39 10/4/2011 48 1.59 1.61 1.63 153 37.30 39.29 41.86 10/5/2011 48 1.57 1.64 1.72 172 38.02 39.17 40.20 10/6/2011 48 1.63 1.66 1.74 164 38.02 39.60 41.42 10/7/2011 48 1.63 1.66 1.68 154 38.95 40.18 41.67 10/8/2011 48 1.62 1.64 1.66 139 38.27 39.45 41.16 10/9/2011 48 1.59 1.62 1.65 126 36.62 38.31 40.39 10/10/2011 48 1.57 1.59 1.62 114 35.65 37.34 39.47 10/11/2011 48 1.55 1.57 1.60 104 34.60 36.04 38.34 10/12/2011 48 1.53 1.55 1.58 107 33.19 34.92 36.66 10/13/2011 48 1.54 1.56 1.59 206 36.10 37.50 38.95 10/14/2011 48 1.59 1.70 1.85 210 38.14 38.80 39.63 10/15/2011 48 1.68 1.71 1.76 171 37.63 38.81 39.95 10/16/2011 48 1.64 1.66 1.70 147 35.48 36.37 37.85 10/17/2011 48 1.61 1.63 1.65 134 33.62 34.84 36.72 10/18/2011 48 1.59 1.61 1.63 122 33.52 34.71 36.56 10/19/2011 48 1.57 1.59 1.62 116 32.26 33.92 35.91 10/20/2011 48 1.56 1.58 1.59 112 33.97 35.54 37.56 10/21/2011 48 1.56 1.57 1.60 102 36.75 37.43 38.66 10/22/2011 48 1.53 1.55 1.57 101 35.25 36.25 37.79 10/23/2011 48 1.52 1.55 1.58 121 35.67 36.92 38.24 10/24/2011 48 1.54 1.59 1.64 356 35.74 37.13 38.27 10/25/2011 48 1.66 1.90 2.12 242 36.62 37.75 38.31 10/26/2011 48 1.70 1.74 1.82 187 34.11 34.94 36.40 10/27/2011 48 1.66 1.68 1.71 173 34.86 36.05 37.27 10/28/2011 48 1.65 1.67 1.69 150 36.10 36.88 38.27 10/29/2011 48 1.61 1.64 1.67 125 35.68 36.49 37.66 10/30/2011 48 1.57 1.59 1.63 118 32.03 33.31 35.81 10/31/2011 48 1.56 1.58 1.61 104 31.93 33.29 34.66 11/1/2011 48 1.51 1.55 1.58 110 31.30 32.68 33.91 11/2/2011 48 1.51 1.71 1.86 118 31.34 31.38 31.44 11/3/2011 48 1.50 1.56 1.81 97 31.37 32.06 33.12 11/4/2011 48 1.50 1.53 1.56 90 31.83 33.16 34.04 11/5/2011 48 1.49 1.52 1.59 80 31.34 31.78 32.72 11/6/2011 48 1.47 1.49 1.51 75 31.37 31.74 32.49 11/7/2011 48 1.47 1.82 2.25 70 31.34 31.39 31.45 November 2013 ‐ Final Report Appendix J Page J‐7  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 11/8/2011 48 2.25 2.42 2.58 65 31.32 31.38 31.46 11/9/2011 48 1.53 2.50 2.91 63 31.33 31.39 31.54 11/10/2011 48 1.42 1.43 1.52 57 31.60 32.50 33.19 11/11/2011 48 1.40 1.41 1.43 53 31.36 32.32 32.95 11/12/2011 48 1.38 1.40 1.42 55 31.40 32.19 32.59 11/13/2011 48 1.39 1.41 1.43 52 31.30 31.45 31.99 11/14/2011 48 1.38 1.39 1.43 48 31.33 31.71 32.16 11/15/2011 48 1.33 1.62 1.86 34 31.30 31.36 31.43 11/16/2011 48 1.09 1.15 1.29 34 31.29 31.36 31.39 11/17/2011 48 1.08 1.27 1.43 34 31.33 31.37 31.47 11/18/2011 48 1.34 1.63 1.88 34 31.31 31.37 31.41 11/19/2011 48 1.52 1.71 1.83 34 31.34 31.38 31.44 11/20/2011 48 1.35 1.39 1.51 34 31.36 31.41 31.47 11/21/2011 48 1.25 1.31 1.36 34 31.33 31.40 31.43 11/22/2011 48 1.24 1.30 1.35 38 31.33 31.39 31.43 11/23/2011 48 1.30 1.32 1.34 36 31.36 31.42 31.46 11/24/2011 48 1.29 1.31 1.33 34 31.40 31.43 31.46 11/25/2011 48 1.28 1.29 1.31 31 31.40 31.44 31.49 11/26/2011 48 1.26 1.28 1.29 32 31.40 31.43 31.49 11/27/2011 48 1.26 1.28 1.30 32 31.40 31.43 31.49 11/28/2011 48 1.27 1.29 1.30 32 31.49 31.64 31.79 11/29/2011 48 1.28 1.28 1.30 32 31.83 32.22 32.65 11/30/2011 48 1.27 1.28 1.29 31 32.59 33.02 33.24 12/1/2011 48 1.26 1.28 1.29 31 32.36 32.68 33.08 12/2/2011 48 1.26 1.27 1.31 31 33.05 33.22 33.35 12/3/2011 48 1.27 1.33 1.41 31 32.03 32.78 33.48 12/4/2011 48 1.36 1.42 1.49 31 31.53 32.21 32.75 12/5/2011 48 1.32 1.33 1.36 31 31.93 32.21 32.59 12/6/2011 48 1.30 1.31 1.32 31 31.63 32.16 32.69 12/7/2011 48 1.29 1.30 1.32 31 32.09 32.55 33.21 12/8/2011 48 1.29 1.30 1.32 31 33.15 33.47 33.74 12/9/2011 48 1.27 1.29 1.30 31 32.09 32.88 33.11 12/10/2011 48 1.26 1.28 1.29 34 31.43 31.85 32.26 12/11/2011 48 1.27 1.30 1.32 33 31.96 32.39 32.85 12/12/2011 48 1.27 1.29 1.31 54 31.33 31.97 32.29 12/13/2011 48 1.10 1.36 1.58 62 31.33 31.37 31.43 12/14/2011 48 1.26 1.37 1.74 30 31.33 31.62 32.32 12/15/2011 48 1.26 1.27 1.28 30 32.32 32.76 33.15 12/16/2011 48 1.26 1.27 1.28 30 33.02 33.15 33.28 12/17/2011 48 1.26 1.27 1.28 55 33.11 33.34 33.51 12/18/2011 48 1.28 1.40 1.47 43 31.63 32.39 33.44 12/19/2011 48 1.32 1.35 1.37 37 32.19 32.58 32.92 12/20/2011 48 1.30 1.32 1.33 34 31.89 32.49 33.02 12/21/2011 48 1.29 1.30 1.31 34 31.66 32.36 32.78 12/22/2011 48 1.28 1.66 1.84 34 31.31 31.36 31.56 12/23/2011 48 1.34 1.47 1.70 34 31.33 31.36 31.40 12/24/2011 48 1.20 1.56 1.87 34 31.30 31.36 31.43 12/25/2011 48 1.12 1.16 1.21 36 31.29 31.36 31.40 12/26/2011 48 1.22 1.31 1.35 43 31.30 31.36 31.43 12/27/2011 48 1.31 1.35 1.38 46 31.33 31.35 31.43 12/28/2011 48 1.34 1.37 1.39 41 31.30 31.34 31.40 12/29/2011 48 1.29 1.33 1.41 33 31.30 31.36 31.43 12/30/2011 48 1.28 1.29 1.31 32 31.33 31.39 31.43 12/31/2011 48 1.27 1.28 1.29 35 31.36 31.40 31.46 1/1/2012 48 1.28 1.30 1.32 33 31.36 31.41 31.49 1/2/2012 48 1.32 1.35 1.38 40 31.36 31.42 31.46 November 2013 ‐ Final Report Appendix J Page J‐8  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 1/3/2012 48 1.38 1.40 1.41 39 31.40 31.43 31.49 1/4/2012 48 1.38 1.39 1.41 39 31.40 31.46 31.49 1/5/2012 48 1.37 1.39 1.41 37 31.43 31.48 31.53 1/6/2012 48 1.37 1.38 1.39 36 31.49 31.52 31.56 1/7/2012 48 1.37 1.38 1.39 35 31.53 31.64 31.76 1/8/2012 48 1.34 1.37 1.39 34 31.60 31.74 31.86 1/9/2012 48 1.35 1.36 1.37 41 31.60 31.70 31.79 1/10/2012 48 1.36 1.40 1.55 33 31.56 31.66 31.76 1/11/2012 48 1.34 1.35 1.38 29 31.69 31.79 31.86 1/12/2012 48 1.30 1.33 1.34 30 31.43 31.56 31.83 1/13/2012 48 1.32 1.34 1.35 29 31.46 31.54 31.66 1/14/2012 48 1.32 1.32 1.34 28 31.53 31.58 31.63 1/15/2012 48 1.31 1.32 1.33 28 31.56 31.61 31.69 1/16/2012 48 1.30 1.31 1.33 27 31.56 31.62 31.66 1/17/2012 48 1.30 1.31 1.32 26 31.60 31.63 31.69 1/18/2012 48 1.29 1.30 1.31 26 31.60 31.68 31.73 1/19/2012 48 1.29 1.30 1.31 25 31.60 31.65 31.73 1/20/2012 48 1.29 1.30 1.30 25 31.60 31.66 31.73 1/21/2012 48 1.28 1.29 1.30 24 31.53 31.57 31.66 1/22/2012 48 1.27 1.28 1.30 24 31.53 31.60 31.73 1/23/2012 48 1.27 1.28 1.29 23 31.73 31.87 31.99 1/24/2012 48 1.26 1.27 1.28 22 31.86 31.93 31.99 1/25/2012 48 1.25 1.26 1.27 21 31.76 31.81 31.89 1/26/2012 48 1.25 1.26 1.27 21 31.66 31.72 31.79 1/27/2012 48 1.24 1.25 1.26 21 31.53 31.59 31.66 1/28/2012 48 1.24 1.25 1.26 20 31.49 31.55 31.63 1/29/2012 48 1.24 1.25 1.25 20 31.56 31.73 31.93 1/30/2012 48 1.23 1.24 1.25 18 31.93 32.10 32.29 1/31/2012 48 1.19 1.21 1.24 22 32.22 32.37 32.52 2/1/2012 48 1.18 1.20 1.21 22 32.06 32.30 32.55 2/2/2012 48 1.17 1.19 1.21 21 31.63 31.96 32.39 2/3/2012 48 1.17 1.18 1.19 20 31.52 31.70 31.79 2/4/2012 48 1.13 1.18 1.22 22 31.52 31.58 31.66 2/5/2012 48 1.18 1.20 1.24 25 31.59 31.79 31.96 2/6/2012 48 1.21 1.22 1.24 21 31.66 31.96 32.19 2/7/2012 48 1.17 1.19 1.21 20 32.22 32.45 32.62 2/8/2012 48 1.16 1.18 1.23 26 32.06 32.62 32.92 2/9/2012 48 1.19 1.24 1.26 20 31.63 32.00 32.36 2/10/2012 48 1.15 1.17 1.20 18 32.32 32.66 33.11 2/11/2012 48 1.14 1.15 1.16 16 32.52 32.73 32.84 2/12/2012 48 1.12 1.13 1.15 16 32.25 32.48 32.71 2/13/2012 48 1.11 1.12 1.13 15 31.79 32.11 32.42 2/14/2012 48 1.10 1.11 1.12 14 31.72 31.95 32.28 2/15/2012 48 1.06 1.10 1.14 16 31.56 31.72 31.92 2/16/2012 48 1.11 1.12 1.13 15 31.79 32.14 32.45 2/17/2012 48 1.10 1.11 1.11 14 32.15 32.43 32.75 2/18/2012 48 1.09 1.10 1.11 14 32.28 32.50 32.71 2/19/2012 48 1.09 1.10 1.11 14 32.48 32.71 32.98 2/20/2012 48 1.09 1.10 1.11 14 32.28 32.61 32.84 2/21/2012 48 1.09 1.09 1.10 14 31.89 32.18 32.58 2/22/2012 48 1.08 1.09 1.10 13 31.79 32.10 32.25 2/23/2012 48 1.08 1.08 1.09 13 31.46 31.68 31.85 2/24/2012 48 1.06 1.08 1.13 14 31.33 31.41 31.49 2/25/2012 48 1.07 1.10 1.12 14 31.36 31.59 31.79 2/26/2012 48 1.05 1.09 1.11 13 31.52 31.84 32.05 2/27/2012 48 1.04 1.08 1.09 14 31.43 32.05 32.32 November 2013 ‐ Final Report Appendix J Page J‐9  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 2/28/2012 48 1.01 1.09 1.16 20 31.36 31.40 31.43 2/29/2012 48 1.11 1.18 1.22 20 31.36 31.42 31.49 3/1/2012 48 1.11 1.17 1.22 13 31.39 31.55 31.66 3/2/2012 48 1.07 1.09 1.10 13 31.62 31.73 31.82 3/3/2012 48 1.06 1.07 1.08 12 31.49 31.66 31.75 3/4/2012 48 1.06 1.07 1.08 13 31.43 31.49 31.56 3/5/2012 48 1.06 1.07 1.08 12 31.43 31.57 31.69 3/6/2012 48 1.06 1.06 1.07 12 31.66 31.95 32.19 3/7/2012 48 1.05 1.06 1.07 12 32.09 32.29 32.61 3/8/2012 48 1.05 1.06 1.07 12 32.02 32.21 32.35 3/9/2012 48 1.04 1.06 1.06 12 31.46 31.65 32.02 3/10/2012 48 1.04 1.05 1.06 12 31.39 31.52 31.72 3/11/2012 48 1.05 1.06 1.07 13 31.39 31.49 31.62 3/12/2012 48 1.05 1.07 1.08 12 31.43 31.49 31.59 3/13/2012 48 1.05 1.07 1.09 11 31.43 31.53 31.62 3/14/2012 48 1.04 1.05 1.06 11 31.49 31.60 31.69 3/15/2012 48 1.04 1.04 1.05 11 31.49 31.63 31.72 3/16/2012 48 1.03 1.04 1.04 11 31.59 31.69 31.85 3/17/2012 48 1.02 1.03 1.05 11 31.43 31.52 31.66 3/18/2012 48 1.02 1.04 1.07 12 31.43 31.49 31.59 3/19/2012 48 1.05 1.06 1.07 12 31.43 31.51 31.62 3/20/2012 48 1.05 1.06 1.08 12 31.43 31.50 31.59 3/21/2012 48 1.05 1.06 1.07 12 31.39 31.50 31.59 3/22/2012 48 1.04 1.05 1.06 12 31.46 31.52 31.62 3/23/2012 48 1.02 1.06 1.10 12 31.43 31.49 31.56 3/24/2012 48 1.03 1.06 1.10 10 31.46 31.54 31.66 3/25/2012 48 1.02 1.03 1.04 10 31.49 31.62 31.82 3/26/2012 48 1.02 1.02 1.03 10 31.59 31.84 32.05 3/27/2012 48 1.02 1.03 1.05 12 31.99 32.15 32.35 3/28/2012 48 1.04 1.06 1.08 12 32.05 32.38 32.78 3/29/2012 48 1.05 1.06 1.08 11 32.52 33.00 33.70 3/30/2012 48 1.04 1.05 1.07 11 32.32 33.05 33.90 3/31/2012 48 1.03 1.03 1.05 10 32.58 33.23 33.90 4/1/2012 48 1.02 1.03 1.03 10 32.91 33.38 33.80 4/2/2012 48 1.02 1.03 1.03 10 32.91 33.45 34.29 4/3/2012 48 1.02 1.02 1.03 10 32.09 32.73 33.27 4/4/2012 48 1.01 1.02 1.03 15 32.25 32.80 33.24 4/5/2012 48 1.02 1.11 1.16 12 31.82 32.26 33.17 4/6/2012 48 1.05 1.07 1.10 11 31.89 32.61 33.44 4/7/2012 48 1.04 1.05 1.05 11 32.35 33.18 34.10 4/8/2012 48 1.03 1.04 1.06 11 32.55 33.06 33.70 4/9/2012 48 1.03 1.04 1.05 11 32.68 33.45 34.32 4/10/2012 48 1.03 1.04 1.05 11 33.01 33.77 34.68 4/11/2012 48 1.03 1.04 1.05 11 32.35 33.57 34.88 4/12/2012 48 1.03 1.04 1.05 11 32.88 33.84 34.91 4/13/2012 48 1.03 1.05 1.06 13 32.81 33.93 35.21 4/14/2012 48 1.05 1.07 1.10 19 33.44 34.09 34.85 4/15/2012 48 1.10 1.17 1.24 26 33.21 33.74 34.46 4/16/2012 48 1.21 1.24 1.26 29 32.95 34.06 35.73 4/17/2012 48 1.23 1.26 1.28 33 33.31 34.31 35.90 4/18/2012 48 1.27 1.29 1.31 34 33.18 34.29 36.03 4/19/2012 46 1.28 1.29 1.31 35 32.75 34.53 36.81 4/20/2012 48 1.29 1.30 1.33 36 32.85 34.47 36.74 4/21/2012 48 1.29 1.31 1.33 33 33.15 33.89 34.75 4/22/2012 48 1.26 1.29 1.34 41 33.31 35.27 38.40 4/23/2012 48 1.32 1.34 1.37 42 33.54 34.91 37.30 November 2013 ‐ Final Report Appendix J Page J‐10  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 4/24/2012 48 1.33 1.35 1.37 47 32.69 34.89 38.40 4/25/2012 48 1.35 1.37 1.40 55 32.72 34.99 38.56 4/26/2012 48 1.38 1.41 1.45 66 32.92 35.08 38.78 4/27/2012 48 1.42 1.45 1.48 73 33.19 35.14 38.69 4/28/2012 48 1.44 1.47 1.51 78 33.94 35.41 37.72 4/29/2012 48 1.47 1.49 1.52 83 33.84 35.57 38.11 4/30/2012 48 1.48 1.50 1.53 79 33.65 35.41 38.33 5/1/2012 48 1.46 1.49 1.51 68 32.79 34.59 38.14 5/2/2012 48 1.44 1.45 1.47 63 32.03 34.76 38.75 5/3/2012 48 1.43 1.44 1.45 60 33.48 35.78 38.62 5/4/2012 48 1.41 1.42 1.44 60 34.37 36.14 39.43 5/5/2012 48 1.41 1.43 1.45 64 34.37 36.36 39.72 5/6/2012 48 1.42 1.44 1.46 74 34.53 36.55 39.62 5/7/2012 48 1.45 1.48 1.53 82 34.73 36.80 40.71 5/8/2012 48 1.47 1.50 1.53 73 34.27 35.48 37.53 5/9/2012 48 1.45 1.47 1.49 76 33.74 35.46 37.46 5/10/2012 48 1.46 1.48 1.50 75 33.94 36.19 39.88 5/11/2012 48 1.46 1.48 1.49 70 33.81 35.73 38.69 5/12/2012 48 1.45 1.46 1.48 68 34.20 36.35 39.72 5/13/2012 48 1.44 1.45 1.47 67 33.71 36.39 40.04 5/14/2012 48 1.44 1.45 1.46 71 33.48 36.31 39.72 5/15/2012 48 1.44 1.47 1.52 89 33.81 37.51 42.91 5/16/2012 48 1.48 1.52 1.60 130 33.65 37.42 42.94 5/17/2012 48 1.56 1.61 1.68 167 34.79 37.45 42.24 5/18/2012 48 1.63 1.66 1.69 159 33.91 36.39 40.78 5/19/2012 48 1.62 1.65 1.67 158 34.86 36.68 39.27 5/20/2012 48 1.62 1.65 1.68 183 34.90 36.90 39.24 5/21/2012 48 1.65 1.68 1.75 234 34.83 37.42 41.35 5/22/2012 48 1.68 1.74 1.84 329 34.73 37.08 40.59 5/23/2012 48 1.74 1.83 1.93 394 34.83 36.91 41.26 5/24/2012 48 1.80 1.85 1.93 440 34.35 36.16 39.63 5/25/2012 48 1.84 1.89 1.96 385 35.03 36.04 37.86 5/26/2012 48 1.80 1.85 1.92 364 34.61 35.74 36.85 5/27/2012 48 1.80 1.84 1.93 442 35.16 36.88 40.34 5/28/2012 48 1.83 1.89 1.93 425 35.16 36.10 37.70 5/29/2012 48 1.83 1.88 1.93 426 34.77 36.60 39.31 5/30/2012 48 1.83 1.88 1.93 396 34.87 36.59 38.67 5/31/2012 48 1.81 1.86 1.91 413 34.77 36.97 39.95 6/1/2012 48 1.81 1.87 1.95 457 34.38 37.39 41.71 6/2/2012 48 1.86 1.91 1.96 499 35.20 36.84 40.30 6/3/2012 48 1.91 1.99 2.08 464 34.70 36.45 40.02 6/4/2012 48 1.89 2.00 2.08 475 34.48 35.84 37.31 6/5/2012 48 1.88 1.95 2.06 474 33.98 37.10 41.40 6/6/2012 48 1.88 1.94 2.02 34.64 37.23 41.46 (1) 6/7/2012 48 1.98 2.05 2.20 35.52 37.22 39.99 (1) 6/8/2012 48 1.95 2.05 2.17 455 34.61 35.76 36.92 6/9/2012 48 1.89 1.97 2.06 495 35.36 36.95 40.05 6/10/2012 48 1.91 1.97 2.08 482 34.80 36.90 39.60 6/11/2012 48 1.88 1.94 1.98 35.59 36.93 38.54 (1) 6/12/2012 48 1.91 1.98 2.05 486 35.52 36.22 36.92 6/13/2012 48 1.90 1.98 2.08 35.49 36.33 37.25 (1) 6/14/2012 48 2.02 2.12 2.35 35.39 37.29 40.88 (1) 6/15/2012 48 2.04 2.13 2.50 34.58 37.19 41.07 (1) 6/16/2012 48 1.97 2.07 2.18 34.87 38.15 42.63 (1) 6/17/2012 48 2.02 2.14 2.53 35.49 37.93 42.86 (1) 6/18/2012 48 1.92 2.17 2.52 451 35.56 36.45 37.41 November 2013 ‐ Final Report Appendix J Page J‐11  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 6/19/2012 48 1.89 2.03 2.15 416 35.82 37.06 38.54 6/20/2012 48 1.86 2.06 2.17 36.18 38.02 41.14 (1) 6/21/2012 48 1.97 2.17 2.78 35.75 38.68 42.95 (1) 6/22/2012 48 2.05 2.31 3.15 451 36.18 38.77 43.12 6/23/2012 48 1.89 2.35 2.96 200 35.96 38.54 42.23 6/24/2012 48 1.18 2.22 2.80 329 36.24 37.17 37.86 6/25/2012 48 1.81 2.10 2.49 474 36.18 37.10 38.38 6/26/2012 48 1.90 2.02 2.14 460 36.63 37.29 38.51 6/27/2012 48 1.87 1.93 2.01 459 36.63 38.34 40.43 6/28/2012 48 1.85 1.92 2.01 466 37.18 38.06 39.47 6/29/2012 48 1.85 1.93 1.99 479 37.08 38.72 41.96 6/30/2012 48 1.89 1.96 2.06 462 37.02 39.78 44.00 7/1/2012 48 1.88 1.94 2.03 451 37.66 39.15 40.98 7/2/2012 48 1.84 1.90 1.97 402 37.76 38.47 39.47 7/3/2012 48 1.79 1.86 1.92 460 37.34 38.23 39.31 7/4/2012 48 1.84 1.94 2.11 475 37.21 38.55 40.21 7/5/2012 48 1.88 1.98 2.11 462 36.92 38.86 41.49 7/6/2012 48 1.87 1.92 1.99 451 37.41 39.37 41.39 7/7/2012 48 1.84 1.90 1.95 499 37.63 40.10 43.33 7/8/2012 48 1.91 1.98 2.04 463 37.99 38.71 40.30 7/9/2012 48 1.85 1.91 1.97 428 37.50 39.50 42.67 7/10/2012 48 1.83 1.88 1.96 443 36.73 39.49 42.06 7/11/2012 48 1.86 1.99 2.13 431 38.76 39.33 40.28 7/12/2012 48 1.86 2.00 2.15 426 38.15 39.18 40.66 7/13/2012 48 1.81 1.90 1.99 450 37.76 39.69 41.42 7/14/2012 48 1.84 1.93 2.03 433 39.37 40.17 41.84 7/15/2012 48 1.88 1.96 2.03 451 38.54 39.26 40.21 7/16/2012 48 1.84 1.90 1.98 415 38.47 39.53 40.94 7/17/2012 48 1.80 1.87 1.93 399 37.66 41.45 47.07 7/18/2012 48 1.80 1.87 1.94 425 39.18 42.88 47.91 7/19/2012 48 1.80 1.89 1.97 444 40.46 41.71 43.68 7/20/2012 48 1.84 1.95 2.13 496 39.89 42.33 46.29 7/21/2012 48 1.91 2.09 2.21 41.01 41.52 42.29 (1) 7/22/2012 48 1.95 2.06 2.14 498 39.67 40.78 41.94 7/23/2012 48 1.91 1.99 2.06 457 40.40 41.03 41.74 7/24/2012 48 1.86 1.93 2.02 418 39.89 41.87 45.13 7/25/2012 48 1.81 1.89 2.03 498 39.63 43.38 48.51 7/26/2012 48 1.91 1.96 2.03 420 42.06 44.26 47.73 7/27/2012 48 1.82 1.88 2.00 419 41.49 42.75 44.06 7/28/2012 48 1.81 1.89 1.95 429 41.36 44.17 48.38 7/29/2012 48 1.87 2.06 2.34 272 42.03 42.96 44.60 7/30/2012 48 1.66 2.18 2.43 40.08 41.61 43.72 (1) 7/31/2012 48 1.95 2.02 2.17 39.64 41.79 43.81 (1) 8/1/2012 48 2.05 2.15 2.22 41.37 42.15 42.92 (1) 8/2/2012 48 2.03 2.27 2.83 40.02 40.61 41.88 (1) 8/3/2012 48 1.96 2.13 2.42 39.99 41.00 42.45 (1) 8/4/2012 48 1.99 2.04 2.11 40.24 40.83 41.43 (1) 8/5/2012 48 1.93 1.98 2.06 467 39.99 42.09 45.19 8/6/2012 48 1.87 1.93 2.00 418 39.98 43.27 47.85 8/7/2012 48 1.84 1.87 1.95 339 42.28 43.68 45.32 8/8/2012 48 1.77 1.82 1.86 297 41.65 44.39 48.47 8/9/2012 48 1.75 1.79 1.84 296 42.31 45.11 48.90 8/10/2012 48 1.75 1.79 1.83 259 44.08 45.26 46.95 8/11/2012 48 1.71 1.76 1.81 236 43.14 46.02 50.45 8/12/2012 48 1.70 1.74 1.78 222 43.01 46.48 51.13 8/13/2012 48 1.67 1.72 1.77 232 44.24 47.32 51.47 November 2013 ‐ Final Report Appendix J Page J‐12  Pedro Bay Village Council Knutson Creek Hydroelectric Feasibility Study Polarconsult Alaska, Inc. Recorded Stage (ft, station datum)Water Temperature (F) DATE Record Count Daily Minimum Daily Mean Daily Maximum Calculated Mean Daily Flow Daily Minimum Daily Mean Daily Maximum Notes 8/14/2012 48 1.70 1.73 1.78 218 45.47 47.41 49.96 8/15/2012 48 1.69 1.72 1.76 203 45.41 46.89 49.53 8/16/2012 48 1.67 1.70 1.77 174 44.50 45.53 46.72 8/17/2012 48 1.62 1.67 1.72 195 43.39 45.22 47.51 8/18/2012 48 1.60 1.69 1.88 269 42.59 44.15 45.16 8/19/2012 48 1.71 1.76 1.88 231 43.58 44.30 45.35 8/20/2012 48 1.67 1.73 1.79 173 42.63 44.25 46.07 8/21/2012 48 1.63 1.66 1.71 149 41.23 43.61 45.60 8/22/2012 48 1.59 1.63 1.66 218 41.29 43.64 45.66 8/23/2012 48 1.64 1.72 1.77 210 43.17 44.31 46.19 8/24/2012 48 1.65 1.71 1.76 241 42.50 43.34 44.65 8/25/2012 17 1.72 1.74 1.76 238 42.98 43.31 43.71 (3) Notes: 2. Gauge hardware installed. 3. Most recent station data download. 1. Stage value is outside the calibrated range of the stage-discharge curve for the station, so a calculated flow value is not reported. Flow is estimated to exceed 500 cfs. November 2013 ‐ Final Report Appendix J Page J‐13  Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report              APPENDIX K – CONCEPTUAL DESIGN DRAWINGS           Pedro Bay Village Council  Knutson Creek Hydroelectric Feasibility Study  Polarconsult Alaska, Inc.    November 2013 – Final Report   K‐1            This page intentionally blank.      398.5 FEETHEADWATER ELEVATION DIVERSION SPILLWAY ELEVATION 401.5 FEET 174.7 FEETTAILWATER ELEVATION 223.8 FEETTOTAL PLANT GROSS HEAD 18.25 CFSDESIGN FLOW 206.5 FEETFULL FLOW DYNAMIC HEAD 26" Ø PENSTOCK LENGTH 7,080 FEET FULL FLOW HEAD LOSS 17.3 FEET 200 KWRATED POWER OUTPUT POWERHOUSE FINISH FLOOR ELEVATION 178.0 FEET *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** 21 28 33 32292017 16 *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION ***GENERAL LOCATION OF PROJECT FEATURES LAND STATUS *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** ***11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION ***SUMMARY OF DIVERSION AND INTAKE OPERATING STAGES (CONCEPTUAL) *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION *** *** 11/9/2012 CONCEPTUAL DRAWINGS ***FOR PERMITTING AND PLANNING PURPOSES ONLY*** NOT FOR CONSTRUCTION ***EXISTING DIESEL POWER PLANT INFORMATION GENSET #1 #2 #3 kW / kVA 95 / 119 62 / 62 62 / 62 PF 0.8 1.0 1.0 1800 1800 1800 RPM ENGINE SET JOHN DEERE 6069 TFG01 JOHN DEERE 4045 T150 JOHN DEERE 4045 T150 GENERATOR MAGNAPLUS 432PSL6212 MAGNAPLUS 363PSL1607 MAGNAPLUS 363PSL1607 DATA FROM GENSET NAMEPLATES, 2009