HomeMy WebLinkAbout200224-ELV_FLA_InitStmtElfin Cove Utility Commission
Crooked Creek and Jim's Lake Hydroelectric Project (P-14514)
Final License Application – Initial Statement Polarconsult Alaska, Inc.
February 2020 IS-1
INITIAL STATEMENT (pursuant to 18 CFR § 4.61(b))
BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION
APPLICATION FOR LICENSE FOR A MINOR WATER POWER PROJECT
(1) The Community of Elfin Cove Non Profit Corporation, DBA Elfin Cove Utility Commission
(ECUC), applies to the Federal Energy Regulatory Commission for a license for the
Crooked Creek and Jim’s Lake Hydroelectric Project (project), as described hereinafter.
ECUC previously held a preliminary permit for this hydropower site under P-14514.
(2) The location of the proposed project is:
State: Alaska
Borough (Alaska’s equivalent to a county): Unorganized Borough
(Sitka Recording District)
Nearest Community: Elfin Cove
Water Bodies: Crooked Creek and Jim’s Lake
(3) The exact name, address, and telephone number of the applicant are:
Community of Elfin Cove Non Profit Corporation, DBA Elfin Cove Utility Commission
P.O. Box 2
Elfin Cove, AK 99825
Tel: 907-239-2226
(4) The exact name, address, and telephone number of the authorized agents are:
Joel Groves Jim Wild
Polarconsult Alaska, Inc. c/o Elfin Cove Utility Commission
1503 W 33rd Ave #310 PO Box 2
Anchorage AK 99503 Elfin Cove, AK 99825
Tel: 907-258-2420 x204 Tel: 907-239-2222
e-mail: joel@polarconsult.net e-mail: jim.wild.ak@gmail.com
(5) The applicant is a domestic non-profit corporation, and is not claiming preference under
section 7(a) of the Federal Power Act.
(6)(i) The statutory or regulatory requirements of the State of Alaska, in which the project
would be located that affect the project as proposed with regard to bed and banks and
Elfin Cove Utility Commission
Crooked Creek and Jim's Lake Hydroelectric Project (P-14514)
Final License Application – Initial Statement Polarconsult Alaska, Inc.
February 2020 IS-2
the appropriation, diversion, and use of water for power purposes, and with respect to
the right to engage in the business of developing, transmitting, and distributing power
and in any other business necessary to accomplish the purposes of the license under the
Federal Power Act, are presented in Table IS-1.
Table IS-1 also lists approvals not required under the Federal Power Act, but which the
Applicant will seek if such approvals are helpful for efficient and timely project
development. It is the intent of the Applicant to continue to consult with permitting
agencies and comply fully with applicable Federal and State statutory and regulatory
requirements.
Table IS-1: Applicable Government Approvals for Project Activities
Permit or Approval Agency Statute or
Regulation Status
Permit to
Appropriate Public
Waters
Alaska Department of
Natural Resources
Alaska Statute (AS)
46.15
Application #LAS 29817 (Jim’s
Lake)
Application LAS 29818
(Crooked Creek)
Submitted August 22, 2014.
Fish Habitat Permit Alaska Department of
Fish and Game AS 16.05.871 - .901 Finding of no permit required
(ADFG 2014).
Section 404 Permit U.S. Army Corps of
Engineers
Federal Clean Water
Act, Rivers and
Harbors Act
Wetlands delineations
completed, Submittal of
application for Nationwide
Permit #17 is pending.
Cultural Resources
Preservation
Alaska State Historic
Preservation Office AS 41.35
Cultural Resources Survey and
Report completed, Section 106
consultation will be
coordinated with FERC licensing
process.
Special Use Permit
(SUP) U.S. Forest Service 36 CFR Chapter II
SUP application submitted June
26, 2014. Will be processed
after FERC license issued.
Certificate of Public
Convenience and
Necessity (CPCN) to
furnish electric
service.
Regulatory Commission
of Alaska AS 42.05
ECUC holds CPCN #701, issued
March 19, 2004. No further
action required for this project.
USFWS
Bald Eagle
Protection Act and
Migratory Bird
Treaty Act
Consultation and
compliance with
resource
protection laws. NMFS
Endangered Species
Act, Marine
Mammal Protection
Act
Part of the FERC licensing and
consultation process
Elfin Cove Utility Commission
Crooked Creek and Jim's Lake Hydroelectric Project (P-14514)
Final License Application – Initial Statement Polarconsult Alaska, Inc.
February 2020 IS-3
(6)(ii) The steps which the applicant has taken or plans to take to comply with each of the laws
cited above are listed in Table IS-1 under the column labeled “Status”.
(7) Brief Project Description
(7)(i) Proposed installed generating capacity 0.145 MW
(7)(ii) Check appropriate box:
existing dam unconstructed dam existing dam, major modified project
(8) Lands of the United States affected (shown on Exhibit G):
(Land Manager) (Name) (Acres)
(i) National Forest CRM, T42S, R55E, Section 36 E ½
CRM, T42S, R56E, Section 31 SW ¼
CRM, T43S, R55E, Section 1 NE ¼
CRM, T43S, R56E, Section 6 NW ¼
USS 2950, Lot 40A
2.30
2.08
1.03
8.47
0.10
(ii) Indian Reservation None. 0
(iii) Public Lands Under Jurisdiction of [any] None. 0
(iv) Other None. 0
(v) Total U.S. Lands 13.98
CRM: Copper River Meridian
R##E: Range ## East
T##S: Township ## South
USS: United States Survey
(8)(vi) Check appropriate box:
surveyed land unsurveyed land
Land within Elfin Cove town site is surveyed, National Forest land is unsurveyed.
(9) Construction of the project is planned to start within 60 months (5 years), and is
planned to be completed within 84 months (7 years), from the date of issuance of
license.