HomeMy WebLinkAboutE2-200608-BurroCreek_2MW_HydroProbableCost(FINAL)2 MW BURRO CREEK HYDRO PROJECT POLARCONSULT ALASKA, INC. OPINION OF PROBABLE COST 5/31/2020 TASK ESTIMATED COST 2 MW PROJECT PERMITTING AND DESIGN $500,000 PHASE 1 CONSTRUCTION CONTRACTOR MOBILIZATION / DEMOBILIZATION $300,000 ACCESS ROADS AND TRAILS $1,500,000 PHASE 1 CONSTRUCTION TOTAL $1,800,000 PHASE 2 CONSTRUCTION CONTRACTOR MOBILIZATION / DEMOBILIZATION $300,000 DIVERSION AND INTAKE STRUCTURE $1,000,000 PENSTOCK (sized for upgrade to 7 MW)$2,900,000 POWERHOUSE (designed for upgrade to 7 MW)$800,000 TURBINE/GENERATOR/SWITCHGEAR/CONTROLS $2,100,000 ELECTRIC TRANSMISSION - ON SHORE BURRO CREEK $400,000 ELECTRIC TRANSMISSION - SUB CABLE TO SKAGWAY (sized for upgrade to 7 MW)$4,100,000 ELECTRIC TRANSMISSION - ON-SHORE CNXN TO APT/ FERRY DOCK $300,000 PHASE 2 CONSTRUCTION TOTAL $11,900,000 TOTAL CONSTRUCTION CONTRACT VALUE (PHASES 1 & 2)$13,700,000 CONSTRUCTION ADMINISTRATION / OVERHEAD CONTRACT MANAGEMENT / ADMIN 5%$700,000 CONSTRUCTION ENGINEERING 5%$700,000 CONTINGENCY 25%$3,400,000 PRE-CONSTRUCTION COSTS (Design and permitting from above)$500,000 TOTAL ADMINISTRATION / OVERHEAD COSTS $5,300,000 TOTAL ESTIMATED CAPITAL COST FOR 2 MW ON-PROPERTY HYDRO PROJECT $19,000,000 7 MW PROJECT PERMITTING AND 35% DESIGN $600,000 TOTAL $19,600,000 UNIT COST METRIC FOR 2 MW HYDRO PROJECT $9,500 PER KW COMPARABLE UNIT COST METRICS FOR RECENT ALASKA HYDRO PROJECTS Year Project MW Cost per kW 2008 Kasidaya Creek (Skagway, AK) (does not include submarine cable cost)3.0 $3,300 2010 Falls Creek (Gustavus, AK)0.8 $10,600 2012 Southfork Eagle River (Eagle River, AK)1.1 $2,700 2016 Allison Creek (Valdez, AK)6.5 $8,500 Note: Comparable project costs have not been adjusted for inflation.