HomeMy WebLinkAboutAirlift Testing of PS 13-1 10.30.14 Draft_CP Pilgrim Hot Springs Flow Testing
PS 13 -1 Air Lifted Flow Testing September 15 -17, 2014
Prepared by: Dick Benoit, Chris Pike and Gwen Holdmann
October 7, 2014
INTRODUCTION
The Alaska Center for Energy and Power (ACEP) led an extensive geothermal exploration effort at Pilgrim
Hot Springs between 2010 and 2014. During this time period, a variety of geophysical surveys were
conducted in conjunction with drilling efforts that took place during the summers of 2011, 2012, and
2013. The efforts culminated in the drilling of a large diameter well capable of high flow rates in the fall
of 2013. Flow testing of this well, called PS 13-1, during September 2014 was the first time that
controlled flow rates greater than the naturally occurring artesian rates were sustained and measured at
the site. Previous testing had investigated the subsurface temperatures but had not closely examined
the aquifer’s production capability. Downhole temperatures and pressures were measured in PS 13-1
while the well was flowing at 60 gpm, and while the well was airlifted at rates of 172 gpm and 300 gpm.
The pressure changes that were measured led researchers to conclude that the well has the ability to
sustainably provide thermal fluid for on-site power generation and district heating applications.
FLOW TESTING OF PS 13-1
Well PS 13-1 was briefly flow tested twice with air lifting assistance between Sept. 15 and 17, 2014. The
airlift was accomplished utilizing thin wall 1” diameter aluminum tubing with a dispersion head on the
bottom and a small Atlas Copco trailer mounted rental compressor rated at 100 PSI and 185 CFM. This
hardware was supplied by Howard Trott of Potelco. A six inch Krohne magnetic flow meter (magmeter),
supplied by ACEP, was used to measure the flow rates. The surface equipment is shown on Figure 1.
The 5” diameter dispersion head was backed up with 1/8 inch aircraft cable to prevent accidental loss of
the downhole equipment in the well. The air water mixture flowed into the first tank on Figure 1 with
considerable turbulence. As the water flowed into the second tank there was no turbulence and the
tank provided adequate head to push the water through the magmeter and out a 240 foot-long 6” PVC
pipeline to the flow through hot spring pond.
The first airlift only lasted about an hour as the flow was limited by a constriction in the flow line
downstream of the second tank. Expansion of the flow line caused a short flexible hose to partially
collapse and reduce the flow rate out of the second tank. This first test was more of a test of the
equipment than a test of the resource. The aluminum tubing was run to a depth of 40 feet below the
top of the standpipe (29 feet below ground level). The average air lift flow rate during the first test was
172 gpm and the magmeter readings were confirmed by measuring that it took 18 seconds to fill a 55
gallon drum in the discharge of the pipeline into the flow through hot springs pond. This equates to 183
gpm. Pumping at a higher air rate increased the flow rate to 177 gpm but resulted in the water bubbling
out the top of the wellhead standpipe.
Once the well was being airlifted and the
wellhead appeared to be stable a Kuster
tool was run to a depth of 30 m below
the top of the master gate with the
heavier aircraft cable used as a backup in
case the small 1/16 inch diameter cable
normally used on the reel was cut. The
Kuster tool was run into the well for a
little over a half hour before the air was
cut off. Once the air was cut off the well
resumed its natural artesian flow at 55
gpm and the Kuster tool remained
hanging in the well overnight to record
the pressure buildup. There was no wing
valve on the flow line to allow the well to
be shut-in with the aluminum tubing and
Kuster tool hanging in the well.
On the morning of Sept. 16 some
additional parts were obtained in Nome
and the flow line was modified to remove
the constriction. The aluminum tubing in
the well was deepened from 40 to 72’
below the top of the standpipe on the
wellhead (61 feet below ground level).
This depth was about the maximum
practical depth for one person on a large
A frame ladder to raise and lower the
downhole equipment. It also was the
maximum depth to also allow use of the
on hand larger diameter aircraft cable to
hold and protect the Kuster tool.
In the second test there was adequate
confidence to run the Kuster tool into the
well under artesian flow conditions
before starting the air lift. The air
volume was quickly increased in 3 steps
to find the maximum air lift rate that
would not flow water out the top of the wellhead. This flow rate was about 300 gpm. The highest flow
rate reported briefly by the magmeter was about 350 gpm. The 300 gpm air lifted flow rate was held for
about 7.5 hours, until the air compressor was almost out of diesel fuel at 0100 hours on Sept. 17. After
the compressor was shut off the well continued to flow artesian until after the Kuster tool was retrieved
late in the morning on Sept. 17. The downhole hardware was pulled out of the well on the morning of
Sept. 17 as Howard Trott had to fly out of Nome that evening.
Figure 1. Surface equipment utilized for airlift of PS 13-1. The
magmeter is in the silver spool between the black and white
parts of the flow line. The black heavy large diameter hose
serving as a standpipe on the top of the wellhead was
needed to prevent water from flowing out the top of the
wellhead. The clamp holding the aluminum tubing is visible
on top of the standpipe. The blue hoses are the air lines
coming from the trailer mounted air compressor.
Figure 2. Downhole pressure and temperature record during the two air lifts of PS 13-1.
Figure 3. Downhole pressure and temperature record just before and after stopping the
first air lift at 1902 hours.
The air lifting increased the scatter in the pressure and temperature data as compared to the unassisted
artesian flow (Figures 2 and 3). During the first air lift it is unclear if there was any decline trend in the
downhole pressure. The first 15 minutes of downhole data indicate a decline but perhaps this was
simply the tool equilibrating to the downhole conditions (Figure 3). During the second 15 minutes there
is no evident decline. At 7 pm the amount of air being pumped was increased for 2 minutes to assess
the plumbing system at higher flow rates and was then shut off (Figure 3). The amount flowing through
the meter increased by only about 5 gpm to 177 gpm but water was occasionally spilling out the top of
the wellhead. There was a constriction in the soft 6 inch hose between the two tanks that was limiting
the flow that could go through the meter.
The downhole flowing temperatures were measured below the air injection depth and therefore can not
be cooled by the air injection, as the surface measured temperatures were. The maximum downhole
temperature measured during the first airlift was 78.28 oC (Figure 3). Immediately upon shutting off the
air, the temperature took a 0.2 oC decline and then quickly climbed for the next 13 minutes to its
maximum value of 78.8 oC and then quickly cooled. The temperature was down to 77.1 oC when the tool
was removed the following morning and showed a range of 1.7 oC during this logging. During the air lift
the temperatures slightly increased. After the air lifting ceased the bulk of the temperature change
occurred. First with a short 0.2 oC decrease that was probably related to the short increased volume air
lift. Then there was a 0.8 oC increase followed by a long decline until temperatures were about 1 oC
lower than during the airlifting. During this decline the well was flowing under natural artesian
conditions. This variation of temperatures with flow rates demonstrates that there is more than one
Figure 4. Downhole pressure and temperature record just before and after stopping the second air
lift at 1902 hours.
feed zone for this well with differing temperatures. Higher temperatures coincide with higher flow
rates.
A similar response was seen upon stopping the second airlift (Figure 4), however this response lacked
the sharp initial drop in temperature as seen at the end of the first airlift (Figure 3).
The maximum temperature recorded after stopping the second airlift was 79.8 oC or 1.0 oC hotter than
seen after stopping the first airlift (Figure 2). After the second airlift was finished the artesian flowing
tempeature declined to 76.95 oC, about 0.25 oC cooler than seen after the the end of the first airlift.
All of this temperature variability points to a fairly complex interplay between two or more feed zones
with differing temperatures. This led to a very detailed flowing log being run on the morning of Sept. 18
before the well was shut in and the artesian flow was stopped. This artesian flowing log and a static log
run on Sept. 7, 2014 show some of the details of the fluid entry points (Figure 5).
The flowing SMU log shows multiple sharp reversals in temperature gradient between depths of 56 and
67 m which define all the possible fluid entry points. The top of the screen in the wells is at 57.3m which
is in good agreement with the flowing temperature log. Due to the minimal divergence between the
flowing and static logs between depths of 65 and 67 m, any fluid entry points in that interval are suspect
as the temperature readings were not very stable in that and shallower intervals. The deepest
significant fluid entry is at a depth near 65 m and the shallowest major entry as defined by temperature
is near 60 m. All of the defined fluid-entry tempeatures are between 77.02 and 77.18 oC on the flowing
20
25
30
35
40
45
50
55
60
65
70
76.2 76.4 76.6 76.8 77 77.2 77.4 77.6 77.8 78
Depth (meters)Temperature C
PS 13-1 Sept. 2014 Static and Flowing SMU Logs
PS 13-1 9-7-14 Static SMU
PS 13-1 9-18-14 Flowing SMUCemented CastingSolid CasingWell Screen
Figure 5. Detailed flowing and static logs from PS 13-1 run in Sept. 2014 with precision SMU logging
equipment. The flowing log depths were increased by 1.4m to have exactly the same bottom hole depth
as the static log as this is the most important part of the hole for this discussion.
log. However the static temperatures in this interval range from 77.4 to 77.7 oC. During the airlifting
temperatures as high as 78.25 to 79.3 oC were measured which had to come from shallower depths in
the well, perhaps as shallow as 35 or 40 m. This fluid would then have to flow down the outside of the
uncemented 14” casing and enter the screened interval between 57.3 and 72.5 m. The maximum
temperature measured during the airlifting operations was the 79.8 oC spike shortly after ceasing the air
lift. This is only 0.18 oC hotter than the maximum measured tempeature of 79.62 oC during the static log
prior to flowing the well. Thus we now have a good idea as to the origin of the fluid producing the
temperature spike.
It was decided that during the air lift the internal wellbore conditions were probably too severe for the
small SMU tool and its delicate electrical cable. The primary use of the Kuster tool was for the pressure
monitoring so it was not moved during the airlifting. However, during any future air lifting a traversing
Kuster survey should be run.
Four major flow rate changes were monitored with downhole pressure changes in PS 13-1 during
September 2014. The first was done on Sept 15, prior to the airlifting and involved opening up the well
so it could artesian flow. During this flow the rate is somewhere between 60 and 75 gpm as it was
measured with a 5 gallon bucket. Three major flow rate changes were monitored during the airlifting
with the Kuster tool downhole (Figure 2, Table 1) and the magmeter providing the flow rate data. The
first was the cessation of the first airlift, the second was the start of the second airlift, and the third was
the end of the second airlift. All of these changes had natural artesian flow either before or after. None
of the changes involved the larger change in going from a static condtion to the airlift.
TABLE 1 PRODUCTIVITY DATA
Start Artesian
Flow
Stop First Airlift Start Second Airlift Stop Second Airlift
Starting Flow Rate 0 172 65 300
Ending Flow Rate 60 – 75? 55 300 60?
Change in Flow Rate 60 – 75? 117 235 240
Pressure Before
Change
103.40 38.27 46.45 39.4
Pressure After
Change
100.46 43.54 37.91 48.23
Change in Pressure 2.94 5.27 8.54 8.83
Productivity
(gpm/psi)
20.4 – 25.5 22.2 27.5 27.2
The productivity measurement involving the lowest flow rate and smallest downhole pressure change
was between 20.4 and 25.5 gpm/psi. The next largest flow rate change was at the end of the first airlift
and it produced a productivity value of 22.2 gpm/psi, the same as the average value of the cessation of
artesian flow. The two largest flow rate changes at the start and stop of the second airlift give virtually
identical and higher productivity values of 27.5 and 27.2 gpm/psi. These are quite encouraging as the
well did not give lower productivity values as higher flow rate changes occurred. This indicates that the
well is capable flow at significantly higher rates. However, it does not indicate that the temperatures
seen during testing are sustainable over the long term.
The pressure record in PS 13-1 shows a 2 psi increase after 2230 hours (figure 2). This is a reflection of
the thin cable holding the tool breaking and the tool moving part of a meter downhole until it was held
by the thicker aircraft cable. It turned out to be very useful to back up the support for the Kuster tool.
TEMPERATURE AND PRESSURE MONITORING IN PS 13-2
Two hours after the first airlift a Kuster tool was hung in well PS 13-2 near a depth of 30m to monitor its
downhole temperature and pressure for a few days during the expected longer and more voluminous
second airlift. This PS 13-2 record is exceptionally complex for a well that was not flowing (Figure 6).
The start and stop of the second airlift is marked by sharp pressure changes of about 0.2 psi. There was
no net longer-term pressure change between the pressure prior to the airlift and pressures near the end
of the monitoring period.
During the airlift there was a curious temperature increase and decline that requires a much deeper
understanding of the hydrology to try to explain (Figure 6). Equally large or larger temperature changes
occurred when the airlift was not in progress.
70
70.5
71
71.5
72
72.5
73
42
42.2
42.4
42.6
42.8
43
43.2
43.4
43.6
43.8
44
9/15/2014 12:009/16/2014 0:009/16/2014 12:009/17/2014 0:009/17/2014 12:009/18/2014 0:009/18/2014 12:00Temperature CPressure (psig)Date and Time
PS 13-2 Monitoring Sept. 15-18, 2014 During 300 gpm Airlift of PS 13-1
Pressure
Start 300 gpm air lift
Stop 300 gpm airlift
Temperature
Resume 60 gpm artesian flowFlowing 60 gpm artesian
Figure 6.
TEMPERATURE AND PRESSURE MONITORING IN PS 13-3
A Kuster tool was also hung in PS 13-3 after the first airlift to document the downhole pressure and
temperature changes (Figure 7). This record shows a sharp 0.2 psi reaction to both the start and stop of
the airlift. There is no longer-term net pressure change from the start of monitoring to the end. There
was a tiny .05 oC temperature rise associated with the higher flow that did not reverse after the airlift.
There are also three tiny temperature spikes that occur after 8 pm very close to one day apart that are
not understood.
HISTORIC HOT SPRINGS TEMPERATURE MONITORING
A small Hobo brand temperature monitoring probe was placed in the discharge area in the historic hot
spring pool at Pilgrim Hot Springs during the testing of the wells. The pool is located 750 feet northeast
of well PS13-1. During the testing period, the sensor was placed in the northwest corner of the pool
about 2 feet below the water surface (figure 8).
78
78.1
78.2
78.3
78.4
78.5
78.6
78.7
78.8
78.9
79
51
51.1
51.2
51.3
51.4
51.5
51.6
51.7
51.8
51.9
52
9/15/2014 12:009/16/2014 0:009/16/2014 12:009/17/2014 0:009/17/2014 12:009/18/2014 0:009/18/2014 12:00Temperature CPressure (psig)Date and Time
PS 13-3 Sept 15-18, 2014 Monitoring During 300 gpm Airlift of PS 13-1
Pressure
Start 300 gpm Air lift
Stop 300 gpm Air Lift
Temperature
Resume 60 gpm artesian flowFlowing 60 gpm artesian
Flowing
300 gpm
Figure 7.
Figure 8.
Researchers Chris Pike and Dick Benoit also used a presision temperature measuring probe owned by
Southern Methodist University to measure the maximum temperatures in the pool. This was done by
inserting the probe several inches into the sandy bottom of the pool and recording the temperatures.
The maximum temperature of 73 °C (163 °F) was encountered in the extreme eastern edge of the pool.
The water temperature of the pool was monitored between September 9th and September 18th 2014
with a brief interuption during the early morning hours of September 16th to download data. During the
time that the temperature was being recorded, the hot spring pool was being used by the public for
soaking and relaxation activities. ACEP staff member Chris Pike monitored the temperature probe on a
nightly basis to ensure that it was still in position. There was a brief period on September 12th when the
probe was removed from the spring. The data collected show that the pool temperature varied for
unknown reasons and mostly stayed between 100 and 110 degrees F (figure 9).
During the 300 GPM flow testing, the pool temperature dropped. It did not stabalize and begin to rise
again until after air lifting pumping was stopped. During this time period, the pool dropped to its
coolest recorded temperature, below 94 degrees F (figure 9). Further testing is needed to draw a
difinitive correlation between the temperature of the hot spring pool and the flow of the wells, however
the pumping of water from the shallow thermal aquifer likely impacts the flow of hot water that flows
into the pool.
CONCLUSIONS
The PS 13-1 well was successfully airlifted for over 7 hours at an average rate of 300 gpm. This probably
represented about the largest flow that could have been achieved with the available equipment.
Repeated productivity measurements with flow rate changes of 60 to 240 gpm all gave values of 20.4 to
27.5 gpm/psi which indicates a good productive well. It is encouraging that the productivity values
associated with the higher flow rates had the highest values. During the airlift most of the fluid must
have entered the wellbore in the main shallow thermal aquifer and flowed down the blank casing to
enter the screened part of the well below 57.3m.
The airlift test impacted the nearby PS 13-2 and PS 13-3 wells with a 0.2 psi pressure decline. There
apparently also were temperature impacts but these are not convincingly explicable with the available
data.
90
92
94
96
98
100
102
104
106
108
110
9/9/14 0:009/10/14 0:009/11/14 0:009/12/14 0:009/13/14 0:009/14/14 0:009/15/14 0:009/16/14 0:009/17/14 0:009/18/14 0:00Temperature (°F)Pilgrim Hot Springs Hot Pool Temperatures During
Well Testing
PS13-3 Flowing ~ 60 GPM Artesian PS13-1 Flowing ~60 GPM Artesian
PS13-1 Flowing 300 GPM PS13-1 Flowing 172 GPM
Erroneous Data Hourly Hot Pool Temeprature (°F)
Figure 9.