HomeMy WebLinkAbout5.3 GrantLk (P-13212) DLA Vl1 ExhA 03-27-15 FINALDRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-1 March 2015
EXHIBIT A: PROJECT DESCRIPTION
1 Contents and Purpose of This Exhibit
Kenai Hydro, LLC (KHL), a wholly-owned subsidiary of Homer Electric Association, Inc.
(HEA), is filing this Draft License Application (DLA) for an original license for the Grant Lake
Hydroelectric Project (FERC No. 13212 [Project or Grant Lake Project]) under Part I of the
Federal Power Act.
Exhibit A of this DLA describes the proposed Project, including details about the Project
structures, the reservoir, turbines and generators, transmission lines, and any additional
equipment appurtenant of the Project.
2 General Project Description
The Grant Lake Hydroelectric Project would be a new 5-megawatt (MW) hydroelectric facility
on Grant Lake and Grant Creek near Moose Pass, Alaska. The new Project would divert water
from Grant Lake and deliver the flow to a powerhouse located near the outlet of the existing
Grant Creek natural, incised rock canyon. The Project would include the following major
components:
An intake structure in Grant Lake.
A tunnel extending from the lake intake to just east of the powerhouse.
A powerhouse with two Francis turbines providing an anticipated combined 5-MW
output. The maximum design flow will be approximately 385 cubic feet per second
(cfs).
Tailrace detention pond.
Switchyard with disconnect switch and step-up transformer.
An overhead transmission line.
A pole mounted disconnect switch where the transmission line intersects the main
power distribution line.
Ninety-one percent of HEA’s current generation needs (approximately 470,000 megawatt hour
(MWh)/year) are met via fossil fuel generation. In recognition of the importance to the
environment and the need to provide power for sustainable growth, HEA’s Board of Directors
adopted a policy (HEA Board Policy 505 – Renewable Portfolio Goal) that set a renewable
energy goal. The goal states that the cooperative will use best efforts to meet 22 percent of its
annual peak generation with renewable energy by 2018. Furthermore, the State of Alaska and
Legislature have adopted a renewable energy goal of 50 percent renewable energy by 2025.
Additionally, HEA would like to diversify its fuel mix and reduce its dependence on the
expensive natural gas supply (currently at $6.90/Mcf) available in the Cook Inlet Area. While
approximately 9 percent of HEA’s current generation needs are met through their stake in the
Bradley Lake Hydroelectric Project, the operation of the Grant Lake Project would provide an
additional 4 percent annually and represent HEA’s first fully-owned hydroelectric facility.
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-2 March 2015
3 Project Area and Vicinity
The proposed Grant Lake Project will be located near the community of Moose Pass, Alaska
(population 219) in the Kenai Peninsula Borough, approximately 25 miles north of Seward,
Alaska (population 2,693), and just east of the Seward Highway (State Route 9)(Figure A.3-1)1;
this highway connects Anchorage (population 291,826) to Seward. The Alaska Railroad
parallels the route of the Seward Highway, and is also adjacent to the Project area. Grant Lake is
located is in the mountainous terrain of the Kenai Mountain Range and has a normal water
surface elevation of 703 feet North American Vertical Datum of 1988 (NAVD 88) and surface
area of approximately 1,703 acres.
The proposed Project generating facilities will be located on Grant Creek, a natural outlet of
Grant Lake, which flows approximately one mile to Lower Trail Lake at elevation 469 feet
NAVD 88. The proposed Project lies within Section 13 of Township 4 North, Range 1 West;
Sections 1, 2, 5, 6, 7, and 18 of Township 4 North, Range 1 East; and Sections 27, 28, 29, 31, 32,
33, 34, 35, and 36 of Township 5 North, Range 1 East, Seward Meridian (U.S. Geological
Survey [USGS] Seward B-6 and B-7 Quadrangles). The surrounding geographic features, land
ownership, and proposed Project boundary are shown on the location map of Figure A.3-1.
1 The Project boundary alignment, in the vicinity of Grant Lake, follows the 703-foot contour line derived from
USGS-developed topographic data. Due to imprecision in the USGS topography, the Project boundary around
Grant Lake does not currently align with the USFS-developed aerial imagery presented in some of the Exhibit A and
Exhibit E figures. The Project boundary alignment will be refined as additional survey data of the Grant Lake
shoreline becomes available. The updated Project boundary is anticipated to align more precisely with USFS
imagery.
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-5 March 2015
4 Proposed Project Facilities
KHL was issued a preliminary permit to investigate a proposed hydropower development on
Grant Creek near the outlet of Grant Lake. The Grant Lake Project will consist of the Grant
Lake/Grant Creek development, an intake structure in Grant Lake, a tunnel, a surge chamber, a
penstock, a powerhouse, tailrace channel with fish exclusion barrier, access roads, a step-up
transformer, a breaker, an overhead transmission line, and a switchyard. The powerhouse will
contain two Francis turbine generating units with a combined rated capacity of 5 MW with a
maximum design flow of 385 cubic feet per second (cfs).
The general proposed layout of the Project is shown in Figure A.4-1. Specific proposed facility
characteristics are listed in Table A.4-1 and described in more detail in Sections 4.1 through 4.10
of this Exhibit. Individual proposed facility design drawings are provided in Exhibit F and
proposed locations of facilities within the Project boundary are shown in Exhibit G of this DLA.
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-6 March 2015
[This page intentionally left blank.]
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-9 March 2015
Table A.4-1. General characteristics of the proposed Grant Lake Project facility.
Number of Generating Units 2
Turbine Type Francis
Rated Generator Output
Unit 1 2.5 MW
Unit 2 2.5 MW
Total 5.0 MW
Maximum Rated Turbine Discharge
Unit 1 192.5 cfs
Unit 2 192.5 cfs
Total 385 cfs
Minimum Rated Turbine Discharge
Unit 1 58 cfs
Unit 2 58 cfs
Total 116 cfs
Turbine Centerline Elevation 526 ft NAVD 88
Normal Tailwater Elevation in Grant Creek at the confluence with the powerhouse and tailrace channel
Minimum 517 ft NAVD 88
Maximum 518.3 ft NAVD 88
Average Annual Energy 18,600 megawatt-hours (MWh)
Normal Maximum Lake Elevation 703 ft NAVD 88
Normal Minimum Lake Elevation 690 ft NAVD 88
Gross Head 184.7 ft
Net Head at Maximum Rated Discharge 171.7 ft
Grant Lake
Drainage Area 44.2 miles (mi)2
Surface Area 1,703 acres
Active/Net Storage Volume 18,790 ac-ft (elevation 703 to 690 feet NAVD 88)
Gross Storage Volume 251,920 ac-ft
Average Annual Natural Outflow 149,140 ac-ft
Average Annual Natural Outflow 206 cfs
Water Conveyance
Intake Intake structure at lake
Approximate dimensions of intake structure 25 ft x 38 ft
Invert Elevation 675 ft NAVD 88
Bypass Pipe for Instream Flows
Type Directional bore with HDPE liner
Length 900 ft
Diameter 18 in
DRAFT LICENSE APPLICATION EXHIBIT A
Table A.4-1, continued…
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-10 March 2015
Lower Pressure Pipeline
Type Welded steel
Length 200 ft
Diameter 48 in
Pressure Tunnel
Type 10-ft horseshoe
Length 3,300 ft
Velocity at Maximum Turbine Discharge 3.9 fps
Surge Chamber
Diameter 120 in
Base Elevation (preliminary) 680 ft NAVD 88
Top Elevation (preliminary) 785 ft NAVD 88
Penstock
Type Welded steel
Length 150 ft
Diameter 72 in
Tailrace
Type Open channel
Length 95 ft
Fish Exclusion Barrier
Type Picket barrier at tailrace outfall
Maximum Design Flow 385 ft
Tailrace Detention Pond
Approximate Acreage 5 acres
Approximate Capacity 15 ac-ft
Outlet Conveyance Length 200 ft
Powerhouse
Approximate Dimensions 50 ft x 100 ft x 30 ft high
Finished Floor Elevation 523 ft NAVD 88
Transmission Line
Type Overhead
Length Approximately 3.5 miles
Voltage 115 kilovolt (kV)
Powerhouse Access Road
Type Two-lane gravel surfacing with turnouts
Width 24 feet
Length One (1) mile from Seward Highway to powerhouse
Intake Access Road
Type Two-lane gravel surfacing with turnouts
Width 24 feet
Length One (1) mile from the powerhouse to the intake
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-11 March 2015
4.1. Grant Creek Diversion
The proposed Project consists of a reinforced concrete intake structure located on the south side
of the natural lake outlet. No structural modifications would be made to the existing lake natural
outlet. The Project will divert water up to a maximum of 385 cfs into the intake structure. When
the lake level exceeds the natural outlet of 703 feet NAVD 88, a maximum of 385 cfs will be
diverted into the intake structure and routed to the powerhouse. Flow in excess of 385 cfs would
pass over the natural outlet to Grant Creek.
4.2. Grant Lake Intake
The Project water intake would be a concrete structure located approximately 500 feet east of the
natural outlet of Grant Lake and adjacent to the shore. The intake structure consists of a
reinforced concrete structure extending from approximately elevation 675 NAVD 88 feet up to a
top deck elevation of 703 feet NAVD 88. The structure has an internal dimension of 38 feet by
15 feet. The structure includes intake trashracks, a selective withdrawal intake gates with wire
rope hoist, and a roller gate located on the water conveyance intake. The intake is divided into
three bays, each fitted with an intake gate to provide flexibility for delivering the full flow range
of 58 cfs to 385 cfs. The gate position within the water column will be set to deliver the required
water temperature to Grant Creek below the powerhouse. The roller gate would be 11 feet tall
by 11 feet wide and fitted with a wire rope hoist lift mechanism. Electrical power will be
extended from the powerhouse to the intake to operate the intake and isolation gates. Pressure
transducers will be installed to monitor the water level at the lake as well as within the intake
tower. An access bridge 16 feet wide would be installed from the lake shore out to the intake
structure.
The intake would allow for drawdown of Grant Lake to elevation 690 feet NAVD 88 thereby
creating approximately 18,790 acre-feet of active storage for the Project between elevations 703
feet NAVD 88 and 690 feet NAVD 88. The intake can be designed to allow the Project to draw
water near the surface at various levels of storage, if deemed necessary. The invert of the intake
would be at elevation 675 feet NAVD 88 to provide for adequate submergence to the tunnel.
A bypass pipe would extend from the intake structure to the base of the existing water fall in
Grant Creek. The installed pipe would be 900 feet long and approximately 18 inches in diameter
allowing the minimum flow ranging from 5 to 10 cfs to be released. A control gate would be
located within the intake structure to regulate and monitor the bypass flow releases.
4.3. Tunnel and Surge Chamber
The intake structure would connect to a tunnel extending to the Project powerhouse. The tunnel
would be approximately 3,300 feet long with a 10-foot-horseshoe shape. Drill and shoot
techniques would be used to construct the tunnel using an entrance portal at the powerhouse for
access. The lower 900 feet of tunnel would be constructed at a 15 percent slope. This section of
the tunnel will be concrete lined. The upper 2,400 feet of tunnel would be constructed at a 1
percent slope and would be unlined. This proposed arrangement provides a low pressure
hydraulic conduit in the upper tunnel reaches suitable for an unlined tunnel. A surge chamber is
located at the transition between the two tunnel slopes. This chamber is approximately 10 feet in
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-12 March 2015
diameter and would extend from the tunnel invert elevation of 650 feet NAVD 88 to the ground
surface at approximately elevation 790 feet NAVD 88. The surge chamber provides a non-
mechanical relief for hydraulic transients that could occur if a load rejection occurs at the
powerhouse. Rock anchors and shotcrete stabilization techniques would be used to stabilize the
tunnel where required. A rock trap would be located at the surge chamber location to collect
dislodged rocks from the unlined tunnel section.
The tunnel would transition to a 6-foot diameter steel penstock approximately 150 feet from the
powerhouse. The transition section would consist of a welded steel concentric structure which
transitions from the 10-foot tunnel section to the 72-inch diameter penstock. A steel liner would
extend from the downstream tunnel portal approximately 300 feet into the tunnel. The liner
would be installed within the exposed rock surface with grout pumped behind the liner to
provide an impermeable and structurally sound tunnel section. A similar steel tunnel liner
section would be installed at the connection to the intake structure for a total distance of
approximately 150 feet.
4.4. Penstock and Surge Tank
A 72-inch diameter steel penstock extends 150 feet from the downstream tunnel portal to the
powerhouse. The welded steel penstock would be supported on concrete pipe saddles along the
penstock route. The penstock would bifurcate into two 48 inch diameter pipes feeding each of
the powerhouse turbines. The penstock fitted with welded steel thrust rings would be encased in
concrete thrust blocks at the tunnel portal as well as the powerhouse. These thrust blocks would
be designed to resist the full hydraulic load associated with the Project operation. An interior
and exterior coating system would be applied to the penstock providing full corrosion protection.
An access manway would be provided on the exposed penstock section allowing access for
future inspection and maintenance.
4.5. Tailrace
The powerhouse draft tubes would connect to a tailrace channel located on the north side of the
powerhouse structure. The draft tubes would extend from a low point elevation of
approximately 509 feet NAVD 88 up to the tailrace channel invert elevation of 515 feet NAVD
88. The channel would continue to the east bank of Grant Creek. Each of the draft tubes will be
gated allowing the flow to be routed to the detention pond for spinning reserve. Isolation
bulkheads would be provided allowing dewatering of the draft tubes for inspection and
maintenance of the turbine. The tailrace channel would be trapezoidal in shape with a bottom
width of 43 feet, side slopes of 2H:1V and a channel depth ranging from 13 feet at the
powerhouse to 7 feet at the creek. A concrete structure would be constructed at the confluence
of the channel and Grant Creek. A picket-style fish barrier would be placed on this concrete
structure as well as provision for installation of stoplogs allowing the tailrace channel to be
dewatered for inspection and maintenance. The channel would be excavated from native
material and lined with riprap to provide a long term stable section. A staff gage and pressure
transducer will be placed in the channel to monitor the water level in the channel.
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-13 March 2015
4.6. Tailrace Detention Pond
An off-stream detention pond would be created to provide a storage reservoir for flows generated
during the rare instance when the units being used for emergency spinning reserve are needed to
provide full load into the electrical transmission grid. In this situation, the additional
powerhouse flows would be diverted into the detention pond and then released slowly back into
Grant Creek. It is anticipated that the discharge associated with a spinning reserve event would
be dispersed via the tailrace channel which flows into Grant Creek. The detention pond would
be located immediately south of the powerhouse and would have a capacity of approximately 15
acre-feet and a surface area of approximately 5 acres.
4.7. Powerhouse
The powerhouse would be located on the south bank of Grant Creek immediately west of the
downstream tunnel portal and adjacent to the detention pond. The powerhouse would consist of
a concrete foundation and a pre-engineered metal building superstructure. The building would
be approximately 100 feet long (east to west) and 50 feet wide (north to south). The penstock
would tie into the powerhouse on the south side and the tailrace channel on the north side of the
building. The building floor would be set at approximately elevation 523 feet NAVD 88 and the
centerline of the turbine runner at elevation 526 feet NAVD 88. The draft tube floor would be
set at elevation 509 feet NAVD 88 with an operating tailwater inside the draft tubes ranging from
518.0 feet to 519.3 feet NAVD 88.
Two horizontal Francis type turbine/generator units with a rated total capacity of 5,000 kilowatt
(kW) would be housed in the powerhouse structure. The powerhouse flow would range from a
maximum of 385 cfs to a minimum of 58 cfs with each turbine operating flow ranging from
192.5 cfs to 58 cfs. Associated mechanical and electrical equipment would include hydraulic
power units, turbine isolation valves, penstock drain, utility water system, lube oil system, oil
water separator, battery system, and heating, ventilating, and air conditioning (HVAC) system.
A control room housing the motor control center (MCC), communication rack, fiber optic panels,
computers, and related equipment would also be provided. The Project switchgear would be
located within the powerhouse. A standby generator, transformer, and fused pad mounted switch
assembly would be mounted on an enclosed switchyard located on the south side of the
powerhouse. Dewatering pumps would be provided to support dewatering of the turbine draft
tubes. A 30-ton bridge crane would be provided for equipment maintenance. The crane would
travel on rails mounted on the steel building support columns. An energy dissipation valve
would extend off the penstock and provide bypass flows into the Project tailrace.
4.8. Transmission Line/Switchyard
An overhead 115-kilovolt (kV) transmission line will extend from the powerhouse to the existing
115-kV transmission line located on the east side of the Seward Highway. In addition to
overhead transmission structures, the facilities would include a switchyard at the powerhouse
consisting of a 115-kV fused pad-mounted disconnect switch and a pad-mounted 115-kV GSU
transformer. The transmission line would run from the powerhouse parallel to the access road
where it would intersect Chugach Electric’s transmission line. The interconnection would have a
pole mounted disconnect switch.
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-14 March 2015
Wooden poles would be designed as tangent line structures on about 250-foot centers. Design of
the line would also incorporate the latest raptor protection guidelines. Collision avoidance
devices would be installed on the line at appropriate locations to protect migratory birds.
4.9. Appurtenant Facilities
The following pertinent mechanical and electrical equipment will be applicable to the Project:
Intake selective withdrawal intake gate
Intake trashrack system
Intake roller gate used to isolate the tunnel and downstream generation facilities
Control gate located on the bypass pipeline pipe
A 30-ton bridge crane in the powerhouse
Pumps located in the powerhouse used to dewater the draft tubes
Pressure transducers located throughout the project used to monitor the water level in the
reservoir, tunnel and trailrace, as well as pressures in the tunnel and penstock
Security cameras at the intake and powerhouse
Sanitary waste holding tank at the powerhouse
A power line extending from the powerhouse to the intake to supply electrical power to
the gates and trashrack
Temperature instrumentation at the intake structure and at various stream locations to
monitor water temperature
This equipment along with other identified miscellaneous mechanical and electrical equipment
will be developed during the final design and included in the construction documents.
4.10. Access Roads
The Project would require an access road to both the powerhouse located near the base of the
Grant Creek canyon and to the intake at Grant Lake. The access road would be used to construct
the Project and afterwards, to maintain the facilities. It is anticipated that the powerhouse would
be visited approximately once a week and the intake visited approximately once a month
beginning just after the ice melts and continuing until just before freeze up. The powerhouse
access road would be maintained year around. The intake access road would not be maintained
in winter.
The 24-foot wide access road would tie into the Seward Highway at approximately MP 26.9.
The route would travel eastward to cross Trail Lakes at the downstream end of the narrows
between Upper and Lower Trail lakes and then continue eastward to the powerhouse. This route
would be approximately one mile long. It would cross the Alaska Railroad (ARRC) tracks near
an existing railroad crossing for a private driveway. The road would cross the narrow channel
connecting Upper and Lower Trail lakes with an approximately a 110-foot-long single lane
bridge. This bridge is proposed as a clear span with the west abutment located on bedrock and
the east abutment on fill. The proposed route would avoid cuts and travel along the base of some
small hills on the south side of Grant Creek to the powerhouse. This proposed access road would
have one 90-degree crossing of the Iditarod National Historic Trail (INHT).
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-15 March 2015
The intake access road would be approximately one mile long, beginning at the powerhouse.
The road would ascend a 230-foot bluff to get to the top of the southern lip of the Grant Creek
canyon. A series of road switchbacks would be required to maintain a road grade of less than 8
percent. The road would then generally follow the southern edge of the canyon until it descends
to Grant Lake. A small parking area and turn-a-round area would be provided at the intake
structure. A 16-foot wide bridge will extend from the bank out to the intake structure.
The road would be gravel with a 16-foot top width. Maximum grade would be 8 percent.
Periodic turnouts would be provided to allow construction traffic to pass. Fifty-foot radius
curves would be used to more closely contour around the small steep hills of bedrock to limit the
extent of the excavation and the height of the embankments.
5 Project Lands
The proposed Project boundary as shown in Figure A.3-1 and in more detail in Exhibit G of this
DLA consists of 1,758.1 acres. The U.S. Forest Service (USFS) manages a total of 1,642.8 acres
(94 percent) of this total. USFS lands are part of the Chugach National Forest, which surrounds
most of Grant Lake. Alaska Department of Natural Resources (ADNR) owns the remainder of
land totaling 115.3 acres (6 percent).
Lands of the U.S. government to be used by the Project as shown on the Exhibit G Project
boundary drawings are tabulated below (Table A.5-1).
Table A.5-1. Tabulation of federal lands within the proposed Project boundary, by township, range and
section.
Location Owner/Agency Acreage Exhibit G Figure No.
AK T4N R1E S1 USFS 57.8 G-2
AK T4N R1E S2 USFS 57.8 G-2
AK T4N R1E S5 USFS 73.2 G-2
AK T4N R1E S6 USFS 68.0 G-2
AK T5N R1E S28 USFS 29.9 G-2
AK T5N R1E S29 USFS 180.6 G-2
AK T5N R1E S31 USFS 38.6 G-2
AK T5N R1E S32 USFS 318.1 G-2
AK T5N R1E S33 USFS 169.7 G-2
AK T5N R1E S34 USFS 320.2 G-2
AK T5N R1E S35 USFS 299.1 G-2
AK T5N R1E S36 USFS 29.8 G-2
Total Acreage: 1,642.8
DRAFT LICENSE APPLICATION EXHIBIT A
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 A-16 March 2015
[This page intentionally left blank.]