HomeMy WebLinkAbout5.5 GrantLk (P-13212) DLA Vl1 ExhC 03-27-15 FINALDRAFT LICENSE APPLICATION EXHIBIT C
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 C-1 March 2015
EXHIBIT C: CONSTRUCTION SCHEDULE
1 Contents and Purpose of This Exhibit
Kenai Hydro, LLC (KHL), a wholly-owned subsidiary of Homer Electric Association, Inc.
(HEA), is filing this Draft License Application (DLA) for an original license for the Grant Lake
Hydroelectric Project (FERC No. 13212 [Project or Grant Lake Project]) under Part I of the
Federal Power Act.
Exhibit C of this DLA describes the proposed schedule for development of the Project. Because
no portion of the proposed Project consists of previously constructed, unlicensed water power
structures or facilities, 18 CFR §4.41(d)(3) does not apply (see below).
2 Construction Schedule
Construction of the Grant Lake Project will commence after the final issuance of a license from
FERC, currently anticipated to occur in December 2016. The pre-construction activities such as
equipment procurement and shop drawing preparation will begin at that time. Mobilization for
field construction activities will begin in April 2018. Construction work for the Project will
continue for 18 months followed by a two month startup and commissioning period.
Construction milestones and other significant events related to the proposed construction of the
Grant Lake Project are summarized in Figure C.2-1.
3 Commencement of Commercial Operation
Consistent with the schedule outlined in Figure C.2-1, commercial operation of the Project
would begin in January 2020.
4 Previously Constructed, Unlicensed Water Power Structures or Facilities
The regulation 18 CFR §4.41(d)(3) does not apply because no portion of the proposed Project
consists of previously constructed, unlicensed water power structures or facilities.
DRAFT LICENSE APPLICATION EXHIBIT C
Grant Lake Hydroelectric Project Kenai Hydro, LLC
FERC No. 13212 C-2 March 2015
[This page intentionally left blank.]
ID Task No. Task Name Start Finish1FERC LICENSINGFri 1/1/16Fri 12/30/162100FERC NEPA PreparationFri 1/1/16Wed 6/1/163110Issue Draft EA/EIS for Public CommentWed 6/1/16Wed 6/1/164120Public Comment PeriodWed 6/1/16Thu 9/1/165130Issue Final EA/EIS and License OrderThu 9/1/16Fri 12/30/166LAND ACQUISITION AND PERMITTINGWed 7/1/15Fri 3/31/177200Acquire Land and EasementsMon 8/3/15Wed 6/1/168205404 PermitWed 7/1/15Fri 3/31/179210USFS Special UseWed 7/1/15Fri 4/1/1610220EPA NPDES PermitWed 3/1/17Fri 3/31/1711FINAL ENGINEERING AND FERC PLANSFri 7/15/16Tue 1/30/1812300Geotechnical Field ExplorationsFri 7/15/16Fri 10/14/1613310Additional Topographic MappingFri 7/15/16Fri 10/14/1614320Prepare 50% Plans and SpecificationsMon 10/3/16Tue 1/31/1715330Prepare 90% Plans and SpecificationsWed 2/1/17Fri 6/2/1716340Prepare 100% Plans and SpecificationsFri 6/2/17Fri 9/1/1717350Issue Stamped/Signed Construction DocumentsWed 11/1/17Wed 11/1/1718360Prepare QCIPFri 9/1/17Wed 11/1/1719370Prepare Environmental PlansWed 2/1/17Fri 9/1/1720380Prepare Construction PlansFri 6/2/17Wed 11/1/1721390FERC Review and Approval to ConstructWed 11/1/17Tue 1/30/1822EQUIPMENT PROCUREMENTMon 10/3/16Tue 6/4/1923400Prepare Water‐to‐Wire Bid PackageMon 10/3/16Tue 1/3/1724410Bid PeriodMon 1/2/17Wed 3/1/1725420Review and Select VendorWed 3/1/17Mon 4/3/1726430Limited Award for Shop DrawingsWed 2/1/17Wed 2/1/1727440Shop Drawing Preparation and ApprovalThu 2/2/17Mon 7/3/1728450Notice to Proceed for FabricationMon 9/4/17Mon 9/4/1729460FabricationTue 9/5/17Wed 5/1/1930470ShippingWed 5/1/19Thu 5/30/1931480Delivery to SiteFri 5/31/19Fri 5/31/1932PRECONSTRUCTIONMon 9/4/17Mon 6/3/1933500Coordinate Turbine/Generator EquipmentMon 9/4/17Mon 6/3/1934510Shop Drawing PreparationThu 2/1/18Fri 6/1/1835520Early Material ProcurementThu 3/1/18Fri 6/1/1836530Prepare and Final Selection of SubcontractorsMon 4/2/18Tue 7/3/1837CONSTRUCTIONMon 4/2/18Tue 10/1/19381000MobilizationMon 4/2/18Tue 5/1/18391100Powerhouse Access RoadMon 4/30/18Wed 8/15/18401110 Clear and Grubbing AlignmentMon 4/30/18Mon 5/14/18411120 Construct Railroad CrossingMon 5/14/18Thu 6/14/18421130 Construct BridgeMon 5/14/18Tue 8/14/18431140 Construct Powerhouse Access RoadMon 7/2/18Wed 8/15/18441200Intake Access RoadMon 7/2/18Fri 9/28/18451210 Clear and Grubbing AlignmentMon 7/2/18Tue 7/31/18461220 Construct Intake Access RoadMon 7/16/18Mon 9/17/18471230 Construct Surge Shaft AccessFri 9/14/18Fri 9/28/18481240 Construct Tunnel Lower Portal AccessFri 8/31/18Fri 9/28/18491300Transmission LineThu 5/31/18Fri 9/28/18501310 Clear and GrubThu 5/31/18Fri 6/29/18511320 Install PolesMon 7/2/18Wed 8/15/18521330 String WireWed 8/15/18Fri 9/14/18531340 Tie to Existing TransmissionTue 8/14/18Fri 9/28/18541350 Drop Temporary Power Transformer @ PowerhouseFri 9/14/18Fri 9/28/18551360 Tie to New Powerhouse SubstationFri 9/14/18Fri 9/28/18561400TunnelFri 8/31/18Mon 9/2/19571410 Mobilize Tunnel SubcontractorFri 8/31/18Fri 9/28/18581420 Develop Lower Portal AccessFri 8/31/18Fri 9/28/18591430 Develop Lower PortalMon 10/1/18Thu 11/1/186/111/1AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFM20152016201720182019Figure C.2-1 Grant Lake Hydroelectric Project, FERC Project No. 13212, Project SchedulePage 1
ID Task No. Task Name Start Finish601440 Construct Tunnel to Lake Intake Vertical ShaftWed 10/31/18Fri 3/29/19611450 Install Tunnel Steel Liner InsertsMon 4/1/19Fri 5/31/19621460 Develop Intake Vertical Shaft ChamberMon 4/1/19Fri 5/31/19631470 Drill Low Flow Release MicroboreMon 6/3/19Tue 7/2/19641480 Construct Lined Tunnel SectionsMon 7/1/19Fri 8/30/19651490 Tunnel CompleteMon 9/2/19Mon 9/2/19661500Intake StructureMon 9/3/18Tue 10/1/19671510 Construct CofferdamMon 9/3/18Mon 10/1/18681520 Excavate Vertical Rock ShaftMon 4/1/19Fri 5/31/19691530 Construct Concrete Intake TowerMon 6/3/19Fri 8/2/19701540 Install GatesFri 8/2/19Fri 8/30/19711550 Remove Rock at IntakeMon 9/2/19Mon 9/30/19721560 Intake CompleteMon 9/30/19Mon 9/30/19731600PowerhouseWed 5/1/19Tue 10/1/19741610 Clear and GrubWed 5/1/19Tue 5/7/19751620 ExcavationWed 5/8/19Wed 5/15/19761630 Construct Concrete FoundationThu 5/16/19Mon 7/1/19771640 Erect Metal BuildingMon 7/1/19Wed 8/14/19781650 Install Bridge CraneFri 7/19/19Wed 8/14/19791660 Install Turbine‐Generator EquipmentMon 7/1/19Tue 9/17/19801670 Electrical InstallationMon 7/15/19Tue 9/17/19811680 Mechanical InstallationMon 7/15/19Tue 9/17/19821690 Balance of PlantThu 8/15/19Tue 10/1/19831700Construct SubstationMon 7/1/19Tue 10/1/19841710 ExcavationMon 7/1/19Wed 7/10/19851720 Construct Structure Concrete FoundationsWed 7/10/19Wed 8/14/19861730 Install Electrical EquipmentWed 8/14/19Fri 9/13/19871740 Complete Tie‐In to Transmission LineMon 9/16/19Tue 10/1/19881800Tailrace Channel and Fish BarrierWed 8/14/19Tue 10/1/19891810 Construct Cofferdam and DewateringWed 8/14/19Fri 8/30/19901820 Excavate Tailrace ChannelMon 9/2/19Tue 9/17/19911830 Construct Fish BarrierMon 9/2/19Tue 10/1/19921840 Remove CofferdamMon 9/30/19Mon 9/30/19931900Construct Detention PondTue 5/7/19Mon 7/29/19941910 Clear and GrubTue 5/7/19Mon 5/20/19951920 Install Dewatering SystemMon 5/20/19Fri 5/31/19961930 Excavate PondMon 6/3/19Fri 6/21/19971940 Construct Inlet StructureFri 6/21/19Mon 7/29/19981950 Construct Outlet StructureFri 6/21/19Mon 7/29/1999STARTUP AND COMMISSIONINGTue 10/1/19Wed 1/1/201004000Dry CommissioningTue 10/1/19Fri 11/1/191014100Wet CommissioningFri 11/1/19Fri 11/29/191024200Full Startup and DocumentationMon 12/2/19Fri 12/27/191034300Commercial Power ProductionWed 1/1/20Wed 1/1/20104PROJECT CLOSEOUTMon 9/2/19Fri 1/31/201055000Final O&M ManualsMon 9/2/19Tue 12/31/191065100As‐Constructed DrawingsFri 11/1/19Tue 12/31/191075200Final DocumentationMon 12/2/19Fri 1/31/201085300Project CompleteFri 1/31/20Fri 1/31/201/11/31AMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFMAMJJASONDJFM20152016201720182019Figure C.2-1 Grant Lake Hydroelectric Project, FERC Project No. 13212, Project SchedulePage 2