HomeMy WebLinkAbout5.1.1A Alsk Yukon Ec Corr Viability Analysis Memo_Final (3)INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 1
DATE: FEBRUARY 2, 2015 PROJECT: P.777
TO: File FILE: P:\P777\Working files\Dec 2014 - Jan
2015\February 2015
presentation\P777 - Financial
Feasibility - Interim Working Memo -
Feb 2, 2015.doc
CC: F. Pearson
FROM: C. Osler, H. Najmidinov & M. Pollitt-Smith
SUBJECT: Southeast Alaska & Yukon Economic Development Corridor: Financial
Feasibility Analysis - INTERIM WORKING MEMO
This draft memo provides the financial feasibility analysis (including related sensitivity analysis) for the
transmission interconnection between Southeast Alaska and Yukon.
1.0 BACKGROUND
The objective of the Southeast Alaska & Yukon Economic Development Corridor viability assessment (the
“Project”) is to determine the technical and financial conditions under w hich an electrical interconnection
between Yukon and Southeast Alaska would be viable, and to identify the most viable scenario that
represents the greatest net benefit to both governments.
The purpose of a transmission line such as the Project is to send electricity from one location to another
in order to supply electrical load requirements at the least cost. In summary, to be financially viable, the
transmission line to connect Southeast Alaska and Yukon requires the following conditions:
A demand for power (a sufficient load) at one end; and
A supply of power at the other end that can meet that demand on a cost competitive basis.
In the context of the Project, electricity moved over the interconnection is assumed to be used to
displace higher cost thermal generation. It is also recognized that there exists the potential for power to
move in both directions depending on load requirements and power availability.
In order to assess the viability of a potential transmission interconnection between Southeast Alaska &
Yukon, the financial feasibility analysis considered the specific conditions (loads, system reliability, other
potential uses of the corridor such as a telecommunications link) that would need to be present to make
development of such a corridor work.
Memorandum
Suite 500-280 Smith Street
Winnipeg, Manitoba
R3C 1K2
tel: (204) 942-0654
fax: (204) 943-3922
e-mail: intergroup@intergroup.ca
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 2
The financial feasibility analysis builds on the June 2014 workshop and background papers to define two
development scenarios for the Project (see Appendix A for summary) and the load and competitive
supply conditions provided at that time for this study, and on the technical feasibility analysis and cost
estimates that were subsequently developed (see below).
The overall viability assessment of the Project has progressed as follows:
On June 18, 2014, a one-day workshop (“June 2014 Workshop”) was held in Whitehorse by the
project team (including utilities and government) to assess conditions under which a
interconnection may be viable. Building upon known or previously established energy forecasts
and supply options, the following two "Development Scenarios" were defined in the workshop for
the purpose of the current viability assessment [see Appendix A of this memo for details - a key
finding of the Development Scenarios is that supplying the cruise ship load will be a fundament al
requirement for the viability of the transmission line under any reasonably realistic scenario ]:
o Scenario 1: Development with West Creek Hydro Generation; and
o Scenario 2: Yukon Surplus Hydro for Cruise Ship Loads
On December 17, 2014, a presentation was provided with a technical feasibility analysis for the
Project (“December 2014 Technical Presentation” and "Technical Feasibility Memorandum")
which identified technically feasible options for the transmission line and reviewed the West
Creek Hydro potential feasibility.
o The December 2014 Technical Presentation divided the transmission line into three
segments for the purpose of the design and routing. One route was selected for the
Skagway to US/Canada border segment (19 km) and the US/Canada border to Carcross
segment (81 km). The following options for transmission line routing were provided for
the Carcross to Whitehorse segment (70 km):
Option A: A new right of way generally following the South Klondike Highway
and with wooden H-poles;
Option B: Re-building and expanding existing ATCO right of way with a single -
pole wishbone transmission line and distribution under build; and
Option C: New right of way generally following White Pass & Yukon Route
railway with wooden H-Poles.
o The technical feasibility assessment also noted as follows regarding options for
undertaking or optimizing the Project :
The transmission line can be built with and without fiber optic cable;
Substation requirements and costs
Yukon: No new substation is required in Whitehorse, however, Riverside
Substation would require upgrades to accommodate the Project;
A new substation would be required in Skagway.
o The total length of the transmission line is estimated to be about 170 km (about 106
miles), including 151 km on the Canadian side of the border and 19 km on the Alaska
side of the border.
o The December presentation and Technical Memorandum also reviewed the West Creek
Hydro potential, including hydrology and power studies, review of site development
layouts, and review of environmental and regulatory issues associated with West Creek
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 3
Hydro development. As reviewed in Section 2.2 below, revised long term average energy
generation estimates and revised costs estimates were provided for West Creek Hydro. It
was also confirmed that development of this hydro project will likely require a minimum
of 10 years, i.e., the earliest that it potentially could be in service is about 2025.
o The December 2014 Technical Presentation concluded that from a technical perspective,
there are no significant issues associated with the transmission line design and routing,
electrical system compatibility, or West Creek hydro development that would suggest the
project is not feasible.
2.0 UPDATES TO FINANCIAL ASSESSMENT INFORMATION SINCE JUNE 2014
2.1 SKAGWAY-WHITEHORSE TRANSMISSION LINE COSTS
Transmission cost updates provided by Morrison Hershfield, in association with Dryden & LaRue, in
January 2015 show the transmission line costs estimated to be between $108.6 million and $145.8 million
(CAD, 2014$) depending on the Right of Way (ROW) selected and on whether the fibre option is included
or excluded. The fibre option adds about $19-$23 million to the cost transmission line, and apparently is
materially more costly than the current option1 to install fibre without use of the transmission line.
Further detail regarding updated transmission line costs is summarized in Appendix D.
For the purpose of the financial feasibility analysis the lowest cost Project option was considered as the
base case scenario for Project feasibility assessment (i.e., $108.6 million [CAD, 2014$] for Option A - new
ROW along Highway and without fibre). This is higher than the initially assumed cost used at the June
workshop (an assumed cost estimate of $84 million).
2.2 WEST CREEK HYDRO
West Creek Hydro cost updates provided to InterGroup by Morrison Hershfield , in association with Access
Consulting, indicate lower generation estimates and higher cost estimates for this project than the initial
assumptions used developed at the June workshop:
The December 2014 Technical Presentation provides updated analysis on West Creek Hydro
average generation. [Appendix B of this memo provides details of updated West Creek Hydro
generation estimates for the purpose of the financial feasibility analysis .]
The following updates regarding West Creek are noted:
o A long-term average generation output of 106 GW.h over the 15 years record of water
flows.
o Long-term average annual generation as follows:
Generation of about 55 GW.h over the summer months (from June 1 to
November 30); and
Generation of 50 GW.h in the winter months (December 1 to May 31).
o Based on the above updated generation estimates and the earlier load forecasts for the
Yukon grid (2030 forecast thermal generation with no mines, assuming no new
1 See Appendix D, which indicates cost in range of $9.5 million for fibre installation without use of transmission line.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 4
renewable generation on the grid) and the Cruise Ships, West Creek Hydro could
potentially displace about 25 GW.h/year of diesel generation otherwise required for the
Cruise Ships, and about 47 GW.h/year of long-term average thermal generation (likely
LNG supplied gas-fired generation) otherwise required for the Yukon grid (total thermal
generation displacement of 72 GW.h/year - with line losses assumed at 5%, this
corresponds to about 76 GW.h/year of West Creek Hydro generation or about 72% of
the estimated long term average West Creek Hydro capability of 106 GW.h/year).
Updated cost estimates for West Creek Hydro show higher capital cost s compared to what was
assumed in June 2014 Workshop (at that time assumed to be $140 million [$2014]). The
updated cost estimate for West Creek Hydro of $327 million Canadian dollars (2014$) is reviewed
in detail in Appendix C
3.0 DEVELOPMENT SCENARIOS - FINANCIAL FEASIBILITY ANALYSIS
The financial feasibility analysis assesses the viability of the interconnection Project under each of the two
Development Scenarios defined in the June 2014 workshop (see Appendix A), under the Base Case
assumptions (see Appendix E) as well as under the following sensitivities:
Impact of Changes in assumed Capital Costs;
Impact of Changes in assumed loads and power sales rates; and
Impact of Changes in assumed Average Cost of Capital (6.5% and 4.5%).
As reviewed in Appendix E, the financial feasibility analysis for each Development Scenario and sensitivity
assesses the potential recovery of Project costs through charges for electricity transmitted over the
interconnection. Assumed Project charge rates in this analysis are based on assumed market constraints
as well as estimated Project costs as reviewed below. In each case, constant dollar annual government
funding support required over the economic life is estimated if assumed charge rates are not expected to
recover estimated Project costs.
The analysis assumes, for simplicity, constant annual costs and revenues (over the assumed economic
lives) to reflect the preliminary nature of any assessment based on current information regarding the
interconnection Project and potential forecasts that affect Project feasibility:
Present value (PV) costs for the Project and West Creek Hydro stated as fixed annual
costs: As reviewed in Appendix E, PV costs for the Project and West Creek Hydro are each
stated in CAD, 2014$, including the assumed capital development cost and the assumed O&M
costs over the relevant economic life (55 years for the Project and 90 years for West Creek
Hydro).2 Annual PV costs are assumed constant [in CAD, 2014$] over the respective economic
lives (for the Base Case assumptions, at $4.649 million/year for the Project and $13.280
million/year for West Creek Hydro). This approach ignores normal utility rate recovery for such a
Project which requires higher annual costs at the outset that decline over the economic life.
Assumed constant annual generation, loads and sales rates: For simplicity, financial
feasibility is assessed based on assumed constant annual generation, loads and sales rates (in
real CAD, 2014$). This approach removes the complexities of varying annual forecasts over the
2 Under Base Case assumptions per Appendix E, the overall PV costs [CAD, 2014$] over the economic life are $115.4 million for the
Project and $373.0 million for West Creek Hydro.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 5
respective economic lives of the Project a nd West Creek Hydro, and assumes that the analysis is
conservative to the extent that Project use tends to improve over the economic life due to Yukon
grid load growth. If the Project proceeds, further feasibility analysis will be needed to confirm
that assumed conditions over the economic life will continue to sustain Project feasibility.
Lifecycle Cost of Energy (LCOE) in $/kW.h: LCOE costs for the Project or West Creek Hydro
reflect the respective PV annual costs divided by the relevant assumed constan t annual Project
load (i.e., electricity sales transmitted over the inter connection) or West Creek Hydro generation
sales used to displace thermal generation in Alaska and Yukon. See Appendix E for specifics for
Scenario 1 and Scenario 2.
Assumed West Creek Hydro sales rates (Scenario 1):
o Cruise Ship Sales: $0.27/kW.h (based on assumed Cruise Ship purchase power rate).
o Yukon Grid Sales: $0.139/kW.h (based on assumed sales of 47 GW.h/year and balance
of West Creek Hydro PV annual costs less assumed sale s revenues from Cruise Ships).
Assumed rates for electricity transmitted by the Project: The Project’s constant annual
charges [CAD, 2014$] for electricity transmitted are estimated as follows:
o Scenario 1:
Yukon Grid Sales to Cruise Ships: $0.140/kW.h (reflects the assumed Cruise
Ship purchase power rate of $0.27/kW.h less the assumed Yukon grid average
rate for summer sales of $0.13/kW.h for Scenario 1).
Purchase by Yukon from West Creek Hydro: two rates are estimated:
Maximum Rate for the Project: Yukon maximum rate for winter power
purchases ($0.165/kW.h for Scenario 1) less the applicable West Creek
Hydro sales rate to Yukon (based on annual West Creek Hydro annual
costs net of West Creek Hydro revenue from sales to Cruise Ships).
Residual Rate to recover LCOE: lesser of the Maximum Rate and the rate
needed to recover annual Project PV costs net of estimated revenues
from Yukon sales to Cruise Ships.
o Scenario 2:
Yukon Grid Sales to Cruise Ships: two rates are estimated:
Maximum Rate for the Project: $0.155/kW.h (reflects the assumed sales
rate to Cruise Ships of $0.27/kW.h, less the assumed Yukon grid average
rate charged for summer sales ($0.09/kW.h for Scenario 2).
Residual Rate to recover LCOE: lesser of the Maximum Rate and the rate
to recover annual Project PV LCOE costs ($0.155/kW.h for Scenario 2).
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 6
3.1 SCENARIO 1 ASSESSMENT - DEVELOPMENT WITH WEST CREEK HYDRO
GENERATION
Development Scenario 1 focuses on development of the Project transmission corridor to supply surplus
power from the proposed West Creek Hydro project near Skagway, Alaska to Whitehorse to displace
growing thermal generation required on the Yukon grid in winter months and to provide hydro power to
cruise ship loads in Skagway in summer months. Under this scenario the construction of the Project
would be timed such that it is available when the West Creek Hydro project is commissioned (i.e., the
scenario in effect assumes the Project is viable only with a West Creek Hydro project).
3.1.1 Development Scenario 1: Base Case Financial Feasibility Analysis
The Base Case financial feasibility analysis for Development Scenario 1 assumes that 47 GW.h/yr of West
Creek Hydro sales are transmitted to the Yukon grid during winter months and 5 GW.h/yr of Yukon
surplus hydro and backup LNG generation sales are transmitted to Alaska Cruise Ships during summer
months. Development Scenario 1 assumes Project in-service no sooner than 2025, and reflects forecast
loads for 2030 assuming no new mines connected to the Yukon grid (connection of new mine loads
would improve Project use, assuming no offsetting new renewable generation supply on the Yukon grid).
Table 1 provides the Base Case financial feasibility assessment of Scenario 1, including review of
assumed West Creek Hydro costs and revenues. Highlights include t he following:
LCOE for Project “sales” are $0.089/kW.h [CAD, 2014$], assuming annual sales transmitted over
the interconnection of 52 GW.h/year and annual PV costs of $4.649 million.
Estimated annual Project revenues are $1.925 million [CAD, 2014$], assuming $0.7 million
recovered for transmittal of 5 GW.h for Yukon summer sales to Cruise Ships and $1.225 million
recovered for transmittal of 47 GW.h for West Creek Hydro winter sales to the Yukon grid.
o Project revenues are constrained by the assumed high cost for West Creek Hydro
generation sales to Yukon, i.e. even after recovery of $6.75 million for summer sales to
Cruise Ships (25 GW.h at $0.27/kW.h), a rate of $0.139/kW.h is required to recover the
balance of West Creek Hydro PV annual costs [$6.53 mil lion] from the 47 GW.h of West
Creek Hydro winter sales to the Yukon grid.
o Based on the assumed Yukon grid maximum rate of $0.165/kW.h for power purchases
(assuming LNG generation displacement), only $0.026/kW.h remains to be charged for
Project transmission of 47 GW.h of West Creek Hydro winter sales to the Yukon grid.
The overall result is that Project viability for Scenario 1 under Base Case assumptions requires
external funding support [CAD, 2014$] equal to 59% of PV annual costs ($2.724 million/year).
Under these conditions, there is no PV Annual Surplus at Maximum Rates.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 7
Table 1: Development Scenario 1 – Financial Feasibility
Base Case Analysis [CAD, 2014$]
Intertie
Project
West Creek
Hydro
Economic Life (years)55 90
Cost of Capital (%/year)5.45%5.45%
Real Discount Rate (2%/yr inflation)3.38%3.38%
PV Costs (CAD, 2014$million)
Capital 108.612 327.036
O&M over economic life 6.783 45.923
Total 115.395 372.959
Annual Costs each year (CAD, 2014$million)$4.649 $13.280
Thermal Loads Displaced each year (GW.h/yr)
Cruise Ships 5.0 25.0
Yukon Grid 47.0 47.0
LCOE for sales (CAS, 2014$/kW.h)$0.089 $0.184
Sales Rate (CAD, 2014$/kW.h)
Cruise Ships purchase rate (displace diesel)0.27 0.27
Yukon av summer sale rate (w losses, LNG backup)0.13
Yukon max winter purchase rate (displace LNG)0.165
West Creek Hydro rate for winter sales to Yukon - 0.139
Intertie Use Rates [CAD, 2014$/kW.h])
Summer Sales to Alaska Cruise Ships
Assumed Rate ($/kW.h)0.140 0.27
Winter Sales to Yukon Grid
Residual Rate to recover LCOE ($/kW.h)0.026
Maximum Rate for Project ($/kW.h)0.026
Annual Revenues (CAD, 2014$million)
Alaska Cruise Ships thermal displacement 0.700 6.750
Yukon Grid thermal displacement (Residual Rate)1.225 6.530
Total Annual Revenues (Residual Rate)1.925 13.280
Total Annual Revenues (Maximum Rate)1.925
Unrecovered Annual Cost (CAD, 2014$million/yr)2.724 0.000
Percent of Annual Cost (%)59%0%
Funding Support Needed (CAD, 2014$million/yr)2.724
PV Annual Surplus at Max Rates (CAD, 2014$million/yr)0.000
Percent of Annual Cost (%)0%
Scenario 1 Base Case
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 8
3.1.2 Scenario 1: Financial Feasibility Sensitivity Analysis
Table 2 provides financial feasibility sensitivity analysis for Scenario 1, indicating the extent to which
estimated unrecovered PV annual costs vary from the $2.394 million estimated for the Base Case
assumptions. Highlights include the following:
Project Capital Costs: +/-15% variance has modest impact
West Creek Hydro Capital Costs: these cost estimates are subject to a wide range of possible
variance as reviewed in Appendix C, and cost reductions can have material impacts on financial
viability.
o A reduction of 10% from the Base Case cost reduces unrecovered PV annual costs to
$1.396 million;
o A reduction of 21% or more from the Base Case cost yields Project revenues adequate to
recover PV annual Project costs.
Cost of Capital: changes in cost of capital can have material impacts on financial feasibility:
o Increase of the nominal cost of capital to 6.5% [versus 5.45% in the Base Case]
increases unrecovered PV annual costs to $6.717 million;
o Reduction of the nominal cost of capital to 4.5% yields a PV Annual Surplus at Maximum
Rates of $0.642 million.
Power Sales Volumes: changes in power sales volumes can have material impacts o n financial
feasibility:
o Ability to displace 60 GW.h of Yukon thermal generation (versus 49 GW.h assumed in the
Base Case) reduces unrecovered PV annual costs to $0.579 million;
o In contrast, reductions in assumed loads sent to Yukon to 40 GW.h sales increases
unrecovered PV annual costs to $3.879 million;
o Removal of Cruise Ship loads for West Creek Hydro and Yukon sales increases
unrecovered PV annual costs to $9.184 million.
Power Sales Rates: changes in power sales rates [CAD, 2014$] can have material impacts o n
financial feasibility:
o Increase of the Yukon maximum rate for power purchase (reflects thermal fuel and O&M
costs displaced) to $0.20/kW.h [versus $0.165/kW.h in the Base Case] reduces
unrecovered PV annual costs to $1.079 million; reduction of this maximum rate to
$0.14/kW.h increases unrecovered PV annual costs to $3.899 million.
o Increase of the Cruise Ship rate for power purchase to $0.30/kW.h [versus $0.27/kW.h in
the Base Case] reduces unrecovered PV annual costs to $1.824 million; reduction of this
maximum rate to $0.24/kW.h increases unrecovered PV annual costs to $3.624 million.
In summary, Table 2 highlights the sensitivity of the Project financial feasibility analysis for Development
Scenario 1 to changes in specific Base Case assumptions. Combined changes in severa l of the identified
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 9
factors could increase or offset the sensitivities noted , e.g., at the assumed power sales rates and capital
costs, the Development Scenario 1 would recover PV Annual Costs with West Creek capital costs 15%
lower (at $278 million) and Yukon grid thermal displacement 5 GW.h/year higher (at 52 GW.h/year).
Table 2: Development Scenario 1 – Financial Feasibility
Sensitivity Analysis [CAD, 2014$]
Scenario 1 - Sensitivity Analysis
Unrecovered PV
Annual Costs
[CAD, 2014$
million/year]
PV Annual Surplus
at Maximum Rates
[CAD, 2014$
million/year]
Base Case Financial Feasibility 2.724 0.000
Project Capital Cost Variance:
Project Capital Cost +15% [$125 M]3.381 0.000
Project Capital Cost -15% [$92 M]2.068 0.000
West Creek Hydro Capital Cost Variance:
West Creek Capital Cost +25% [$409 M]6.044 0.000
West Creek Capital Cost -10% [$294 M]1.396 0.000
West Creek Capital Cost -21% [$258 M]0.000 0.065
West Creek Capital Cost -25% [$245 M]0.000 0.596
West Creek Capital Cost -50% [$163 M]0.000 3.916
Cost of Capital
Nominal cost of capital at 6.5% (real 4.41%)6.717 0.000
Nominal cost of capital at 4.5% (real 2.45%)0.000 0.642
Power Sales Volumes
WC sales ships 25 GW.h, Yukon 81 GW.h 0.000 2.886
WC sales ships 25 GW.h, Yukon 65 GW.h 0.000 0.246
WC sales ships 25 GW.h, Yukon 60 GW.h 0.579 0.000
WC sales ships 25 GW.h, Yukon 55 GW.h 1.404 0.000
WC sales ships 25 GW.h, Yukon 40 GW.h 3.879 0.000
WC sales ships 20 GW.h, Yukon 53 GW.h 2.384 0.000
WC sales Yukon 53 GW.h (No Cruise Ships)9.184 0.000
Power Sales Rates
Yukon grid max purchase rate $0.20/kW.h 1.079 0.000
Yukon grid max purchase rate $0.18/kW.h 2.019 0.000
Yukon grid max purchase rate $0.14/kW.h 3.899 0.000
Cruise Ship purchase rate 0.30/kW.h 1.824 0.000
Cruise Ship purchase rate 0.24/kW.h 3.624 0.000
Yukon grid summer sales rate $.165/kW.h 2.899 0.000
Yukon grid summer sales rate $.10/kW.h 2.574 0.000
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 10
3.2 SCENARIO 2 ASSESSMENT - DEVELOPMENT WITH YEC SUMMER HYDRO SURPLUS
AND SKAGWAY CRUISE SHIP LOADS
Development Scenario 2 focuses on development of the Project transmission corridor in advance of any
new hydropower developments in the Upper Lynn Canal area (such as West Creek hydro generation
project). The transmission corridor would be developed initially to transmit surplus summer power from
Whitehorse to Skagway to displace summer Cruise Ship diesel generation loads as soon as shore power is
available in Skagway.
3.2.1 Development Scenario 2: Base Case Financial Feasibility Analysis
The Base Case financial feasibility analysis for Development Scenario 2 assumes that 30 GW.h/year of
Yukon surplus hydro and backup LNG generation sales are transmitted to Alaska Cruise Ships during
summer months. Development Scenario 2 assumes Project in-service no sooner than 2020, and reflects
forecast loads for the 2020 to 2030 time period assuming no new mines connected to the Yukon grid
(connection of new mines could reduce surplus hydro supply and thereby reduce Project viability, unless
offsetting new renewable generation supp ly occurred on the Yukon grid).
Table 3 provides the Scenario 2 Base Case financial feasibility analysis. Highlights include the following:
LCOE for Project “sales” are $0.155/kW.h [CAD, 2014$], assuming annual sales transmitted over
the interconnection of 30 GW.h/year and annual PV costs of $4.649 million.
Estimated annual Project revenues at residual rates (i.e., residual rate charge to Cruise Ships to
recover LCOE) are sufficient to recover fully the Project PV annual costs. The key factor affecting
this recovery of PV annual costs is the margin between the estimated Yukon grid average rate for
summer sales ($0.09/kW.h) and the assumed Cruise Ships purchase power rate ($0.27/kW.h).
Under the Base Case assumptions, this margin is $0.18/kW.h, and thus exceeds the LCOE
threshold for the Project sales ($0.155/kW.h).3
Table 3 shows two rate revenues: "Residual rates" are limited to LCOE recovery, i.e.,
$0.155/kW.h; "Maximum rates" equal the full margin over grid rates ($0.18/kW.h).
The overall result is that Project viability under Scenario 2 and Base Case assumptions does not
require any government funding support, and the PV annual surplus revenue at maximum rates
[CAD, 2014$] equals 16% of PV annual costs ($0.751 million per year).
3 This feasibility analysis does not address how the "extra revenue in excess of costs and charge rates" (e.g., $0.025/kW.h in the
Base Case for Scenario 2) is allocated, e.g., reduced charge rate to Cruise Ships or increased Yukon grid rates for summer sales.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 11
Table 3: Development Scenario 2 – Financial Feasibility
Base Case Analysis [CAD, 2014$]
Base
Case
Intertie
Project
Economic Life (years)55
Cost of Capital (%/year)5.45%
Real Discount Rate (2%/yr inflation)3.38%
PV Costs (CAD, 2014$million)
Capital 108.612
O&M 6.783
Total 115.395
Annual Costs (CAD, 2014$million)$4.649
Thermal Loads Displaced (GW.h/yr)
Cruise Ships 30.0
LCOE for sales (CAD, 2014$/kW.h)$0.155
Sales Rate (CAD, 2014$/kW.h)
Cruise Ships purchase rate (displace diesel)0.27
Yukon av summer sale rate (w losses, LNG backup)0.09
Intertie Use Rates [CAD, 2014$/kW.h])
Summer Sales to Alaska Cruise Ships
Residual Rate to recover LCOE ($/kW.h)0.155
Maximum Rate for Project ($/kW.h)0.180
Annual Revenues (CAD, 2014$million)
Residual Rate revenues to recover LCOE 4.649
Maximum Rate revenues 5.400
Unrecovered Annual Cost (CAD, 2014$million/yr)0.000
Percent of Annual Cost (%)0%
Funding Support Needed (CAD, 2014$million/yr)0.000
PV Annual Surplus at Max Rates (CAD, 2014$million/yr)0.751
Percent of Annual Cost (%)16%
3.2.2 Scenario 2: Financial Feasibility Sensitivity Analysis
Table 4 provides financial feasibility sensitivity analysis for Scenario 2, indicating the extent to which the
PV annual surplus revenue at maximum rates varies from the $0.751 million estimated for the Base Case
assumptions. Highlights include the following:
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 12
Project Capital Costs: +/-15% variance has modest impact (PV annual surplus revenue is
reduced, but is still positive, with 15% increase in Project capital costs).
Cost of Capital: changes in cost of capital can have material impacts on financial feasibility:
o Increase of the nominal cost of capital to 6.5% [versus 5.45% in the Base Case] results
in unrecovered PV annual costs of $0.157 million;
o Reduction of the nominal cost of capital to 4.5% increases PV annual surplus revenues to
$1.510 million.
Power Sales Volumes: reductions in power sales volumes below the 30 GW.h/yr assumed in
the Base Case can have material impacts of financial feasibility:
o Reduction to 25 GW.h/yr removes the PV annual surplus revenue and results in
unrecovered PV annual costs of $0.149 million (3% of PV Annual Costs).
o Reduction to 20 GW.h/yr results in unrecovered PV annual costs of $1.049 million.
o In summary, each 5 GW.h/yr reduction in power sales volume reduces PV annual cost
recovery by $0.9 million or 19.4% of PV Annual Costs.
Power Sales Rates: changes in power sales rates [CAD, 2014$] can have material impacts of
financial feasibility:
o Increase of the Yukon grid average rate for summer sales (reflects mix of surplus hydro
and LNG fuel and O&M generation costs) to $0.15/kW.h [versus $0.09/kW.h in the Base
Case] results in unrecovered PV annual capital costs of $1.049 million, i.e., each
$0.03/kW.h increase in this average rate reduces Project annual cost recoveries by $0.9
million (assuming 30 GW.h/yr sales).
o Increase of the Cruise Ship rate for power purchase to $0.30/kW.h [versus $0.27/kW.h in
the Base Case] increases PV annual surplus revenues to $1.651 million; reduction of this
maximum rate to $0.24/kW.h results in unrecovered PV annual costs of $0.149 million.
The above analysis highlights the sensitivity of the Project financial feasibility analysis for Development
Scenario 2 to changes in specific Base Case assumptions. Combined changes in several of the above
factors could increase or offset the sensitivities noted. By way of example, at the assumed capital costs
the impact of two possible combined changes in sales volumes and rates is noted below:
Sales to Cruise Ships at 25 GW.h/year, purchase rate $0.25/kW.h, Yukon sale rate at
$0.12/kW.h: unrecovered PV Annual Cost at $1.399 million (30% of PV Annual Cost).
Sales to Cruise Ships at 20 GW.h/year: purchase rate $0.25/kW.h, Yukon sale rate at
$0.08/kW.h: unrecovered PV Annual Cost at $1.249 million (27% of PV Annual Cost).
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 13
Table 4: Development Scenario 2 – Financial Feasibility
Sensitivity Analysis [CAD, 2014$]
Scenario 2 - Sensitivity Analysis
Unrecovered PV
Annual Costs
[CAD, 2014$
million/year]
PV Annual Surplus
at Maximum Rates
[CAD, 2014$
million/year]
Base Case Financial Feasibility 0.000 0.751
Project Capital Cost Variance:
Project Capital Cost +15% [$125 M]0.000 0.094
Project Capital Cost -15% [$92 M]0.000 1.407
Cost of Capital
Nominal cost of capital at 6.5% (real 4.41%)0.157 0.000
Nominal cost of capital at 4.5% (real 2.45%)0.000 1.510
Power Sales Volumes
Summer sales to Cruise Ships 25 GW.h 0.149 0.000
Summer sales to Cruise Ships 20 GW.h 1.049 0.000
Summer sales to Cruise Ships 15 GW.h 1.949 0.000
Power Sales Rates
Yukon grid summer sales rate $0.15/kW.h 1.049 0.000
Yukon grid summer sales rate $0.12/kW.h 0.149 0.000
Yukon grid summer sales rate $0.06/kW.h 0.000 1.651
Cruise Ship purchase rate at 0.30/kW.h 0.000 1.651
Cruise Ship purchase rate at 0.24/kW.h 0.149 0.000
4.0 SUMMARY AND CONCLUSIONS
In order to assess the viability of a potential transmission interconnection between Southeast Alaska and
Yukon, a financial feasibility assessment was undertaken considering the specific conditions that would
need to be present to make the development of such a corridor work.
Initial Assessments Undertaken in June 2014
Initial assessments undertaken in June 2014 defined and confirmed two Development Scenarios for the
purpose of the feasibility assessment.
Scenario 1: Development with West Creek Hydro Generation; and
Scenario 2: Yukon Surplus Hydro for Cruise Ship loads.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 14
A key finding of the initial assessments undertaken in June 2014 was that supplying the cruise ship load
would be a fundamental requirement for the viability of the transmission line under any reasonably
realistic scenario.
Results of Financial Feasibility Assessment undertaken in January 2015
Building on the earlier analysis undertaken for the June 2014 workshop (including background papers)
and on the technical feasibility analysis and cost estimates subsequently developed, the financial
feasibility assessment indicates as follows for each of the development scenarios considered:
Project viability for Development Scenario 1: Under Base Case parameters Scenario 1 is
not viable without external funding support [CAD, 2014$] equal to 59% of present value (PV)
annual costs ($2.724 million/year). This assessment reflects the following:
o Higher capital cost estimates for the West Creek Hydro Project and lower average annual
generation estimates.
o Estimated Project revenues are constrained by the high cost for West C reek Hydro
generation sales to Yukon, and the maximum rate that YEC can pay for thermal
generation displaced by West Creek Hydro sales.
Project viability for Development Scenario 2: Under Base Case parameters Scenario 2 is
viable without government funding support, and the present value (PV) annual surplus revenue
at maximum interconnection use rates [CAD, 2014$] equals 16% of PV annual costs ($0.751
million per year). The key factors affecting the recovery of PV annual costs is the assumed
volume of summer sales (30 GW .h/year) and the assumed spread between the estimated Yukon
grid average rate for summer sales and the estimated Cruise Ships’ purchase power rate.
In summary, under Base Case conditions, proceeding with the Project on its own as per Scenario 2 is
financially feasible provided there is sufficient summer surplus hydro power and low cost thermal
generation backup (e.g., LNG) available in Yukon. Scenario 2 requires Cruise Ship loads of about 30
GW.h/year are available to be supplied with shore power in summer months at the power purchase rates
assumed in the Base Case. However, the Project is not currently financially viable with Scenario 1 Base
Case conditions due to the relatively high estimated cost of power delivered by West Creek Hydro under
the updated analysis.
Sensitivity analysis undertaken for each Development Scenario indicates that changes in power sales
volumes, power sales rates and the cost of capital can have a material impact on financial feasibility .
Changes in capital cost for the Project have only a modest impact. For Scenario 1, financial feasibility of
the Project is very sensitive to the development costs for West Creek Hydro .
The financial feasibility has assumed a cost of capital based on recent YEC experience, as well as Project
rates that are levelized over the Project economic life. Confirmation of specific financing and rate
arrangements for the Project would be required in order to confirm the Project's financial feasibility.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 15
Project viability under Scenario 2 is based upon a long-term opportunity to transmit surplus power during
the summer months from the Yukon grid to Skagway Cruise Ships. Sensitivity analysis confirms that
financial feasibility of the Project with the Scenario 2 Development Scenario is reasonably robust provided
that adequate Cruise Ship purchase power volumes and rates are confirmed prior to actual development.
In this regard, the following can be noted with regard to the likely sustainability of Yukon grid surplus
renewable energy generation and LNG backup generation capacity:
The Yukon grid tends to have surplus renewable generation in summer months due to low
average loads and excess renewable hydro generation. This is not expected to change in the
foreseeable future.
Although load growth on the Yukon grid by itself tends to reduce the summer renewable surplus
generation, future development of new renewable generation (to meet winter demands) is
reasonable to expect with ongoing load growth.
Access to summer sales in Alaska as assumed under Development Scenario 2 will enhance the
viability of new renewable generation on the Yukon g rid (to the extent that the Alaska sales
enhance use of the new renewable generation).
Development of the Project under Scenario 2 would also create specific new opportunities for
future hydro development in Southeast Alaska and northwest BC.
Backup LNG generation capacity on the Yukon grid is also likely to increase in future in step with
ongoing planned retirement of existing diesel generation units plus the need to increase backup
capacity due to ongoing increases in the winter peak load.
In conclusion, Development Scenario 2 offers conditions where the interconnection Project between
Yukon and Southeast Alaska would be financially viable, and would make sense to pursue in the near
term.
The next steps to proceed with Development Scenario 2 for the earliest potential in-service of the
interconnection Project (e.g., 2020) can be focused on confirming the relevant conditions, including the
following:
1. Confirmation of financial feasibility conditions, including:
a. arrangements as needed for adequate Cruise Ship purchase power volumes and rates to
be secured and supplied through shore power by 2020 and for a reasonable period
thereafter;
b. arrangements as needed to define basic provisions for securing Yukon Energy surplus
summer hydro and backup LNG genera tion, and the future adequacy of such generation
to supply the potential Cruise Ship loads (taking into account capacity related
requirements for multiple concurrent Cruise Ship loads); and
c. arrangements as needed to define basic provisions for the Project regarding ownership,
financing, basis for rate charges for interconnection use (and how these may change as
conditions change), and extent if any of government funding to support.
2. Confirmation of permitting and development requirements and timelines fo r the Project,
preparation of the required socio-environmental submissions, and finalization of feasibility cost
estimates based on the Project as defined for such submissions.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 16
APPENDIX A – SUMMARY OF JUNE 2014 WORKSHOP
The June 18, 2014 Workshop (and the related workshop memo of June 30, 2014) summarized the two
defined Development Scenarios and other key financial feasibility assessment information as set out
below. As per this stud's workplan, these Development Scenario parameters were "fixed" for the
remainder of this study.4
SCENARIO 1 – DEVELOPMENT WITH WEST CREEK HYDRO GENERATION
This development scenario is focused on development of the transmission corridor that wo uld supply
surplus power to Whitehorse from the proposed West Creek Hydro project near Skagway, Alaska in order
to displace growing thermal generation requirements on the Yukon grid in the winter months.
Scenario 1 - Development with West Creek Hydro Generation
Whitehorse, Yukon Skagway, Alaska
Need sufficient fossil fuel displacement opportunity Confirm West Creek Hydro volumes, timing and costs
Financial & Economics viability issues (beyond timing):Financial & Economics viability issues (beyond timing):
Expected cost savings from fossil fuel displacement Net power charges to cruise ships & sustainability of loads
Competitive renewable cost options (e.g., other hydro sites)Overall capital costs for new hydro & transmission
Supply security & charges for delivered West Creek hydro Financing, ownership and cost recovery arrangements
About 54 GW.h/yr from Alaska to Yukon
New loads needed on grid of 25-50 GW.h/yr to proceed
within next decade
About 134 GWh/yr generation, less 80 GW.h/yr June to
Nov (not needed in Yukon)
In summary:
Potential available generation from West Creek of 134 GW.h/year
o It was concluded that a reasonable assumption of time needed to develop the West
Creek hydro project (planning, permitting and construction) would be about 10 years.
o Available information for a 25 MW West Creek Hydro project estimates average
generation over 15 water years of record at 134 GW.h/yr (range of 110 to 160 GW.h/yr),
with about 80 GW.h on average from June 1 to November 30 (when the Yukon grid does
not typically have a fossil fuel generation requirement ), and approximately 9
GW.h/month on average for the remaining six months (with lowest generation in April
and May at about 7 GW.h/month). This represents a revised water management scheme
for West Creek to maximize winter energy generation.
Potential Summer Cruise Ship Load of 30 GW.h/Year
o The potential cruise ship load to be supplied from the West Creek Hydro project is
reviewed in section 1.1.2 of Background Paper #1 (Figures 6 and 7); this indicates that
about one-third (11 GW.h for total season) of the cruise ship load involves ships that can
4 However, input parameters such as Project costs and power production estimates have been updated as per the technical work
completed as part of the current study.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 17
currently connect to shore power (it is assumed that the balance could potentially be
converted in 1-2 years under economic conditions).
o A recent funding application estimated diesel generation cost per kW.h for cruise ships at
about 33.4 cents/kW.h (2017), including about 32.1 cents/kW.h fuel costs and 1.3
cents/kW.h operating and maintenance expenses.
Potential surplus power from West Creek Hydro project available to ship to Yukon to meet winter
load requirements of 54 GW.h/Year
o The most recent Yukon Energy (“YEC”) updated near-term grid load scenario forecasts5
indicate long-term average fossil fuel (diesel or LNG) generation requirement without any
new industrial loads or new renewable generation ranging from 2018 to 2026 at 31.4 to
55.0 GW.h/yr (with growing requirements thereafter); these requirements would increase
to the extent that DSM is less than assumed, and decrease to the extent that other
renewable generation is developed for the Yukon grid.
o YEC load forecast scenarios show that a potential new industrial load of 54 GW.h/yr in
2018 (Carmacks Copper) would increase fossil fuel generation requirements in the range
of 37-40 GW.h/yr for about 7.5 years. It was noted that updated information indicates
that this mine project is currently stalled.
SCENARIO 2 – DEVELOPMENT WITH YEC SUMMER HYDRO SURPLUS & SKAGWAY
CRUISE SHIP LOADS
This development scenario is focused on development of the transmission corridor in advance of any new
hydropower developments in the Upper Lynn Canal area (such as West Creek hydro generation project)
being developed. The transmission corridor would be developed to ship surplus summer power from
Whitehorse to Skagway to displace summer cruise ship diesel generation loads as soon as shore po wer is
available in Skagway.
Scenario 2 - Development with YEC Summer Hydro Surplus & Skagway Cruise Ship Loads
Whitehorse, Yukon Skagway, Alaska
Surplus Hydro (early June through September)Energy for Cruise Ships (early May through September)
Financial & Economics viability issues (beyond timing):Financial & Economics viability issues (beyond timing):
Charges for hydro power supplies Diesel cost saved by ships
Charges for LNG back up generation Shore power connection costs
Factors that reduce hydro surplus Factors that limit cruise ship diesel displacement volumes
Upper limit on viable transmission charges Competitive cost option (LNG generation at Skagway)
Assume up to about 34-38 GW.h surplus summer hydro
with current generation & loads - need LNG backup
About from 30 GW.h per season with peak load 6.5 to 32.5
MW in different weeks over the period
About 30 GW.h/yr from Yukon to Alaska
In summary:
5 Filed in December 2013 re: Application under Part 3 of PUA for Proposed Whitehorse Diesel-Natural Gas Conversion Project.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 18
Potential surplus generation of 34 to 38 GW.h/year is available in Yukon from early June to end
of September.
o Yukon Summer Surplus Hydro (Figure 2 in Background Paper #2) indicates that in 2018,
summer surplus hydro without new mine connections ranges from 34 to 38 GW.h with
average surplus per week ranging from 4 to 15 MW over the period; any new mine
connections would reduce this surplus over the summer period.
o Concerns were noted that capacity (MW) of surplus hydro range only from 4 to 15 MW to
supply cruise ship capacity requirements of 25 MW or more, and that YEC LNG
generation could be considered as backup subject to pricing arrangements.
o It was noted that Scenario 2, with its lower transmission loads relative to Scenario 1,
would not enable recovery of the full annual cost of the transmission line under normal
financing arrangements, i.e., this scenario would require some level of government
funding support (which will be assessed), and therefore the ultima te viability of the
project would presume either a future Scenario 1 or some other future cost effective
renewable supply would be developed to use the line to displace Yukon winter fossil fuel
generation.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 19
APPENDIX B – UPDATED WEST CREEK HYDRO GENERATION
The updated simulation for West Creek Hydro6 in Figure B-1 below shows the annual long term average
hydro generation capability for West Creek Hydro development at 106 GW.h for a 25 MW capacity plant,
including simulated monthly generation capability, based on 15 years of water records (1963-1977)7.
Figure B-1: West Creek Hydro Monthly Average Generation at 25 MW Capacity
0
2
4
6
8
10
12
14
16
18
20
0
5
10
15
20
25
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Average MW/monthGW.h/monthWest Creek Monthly Average Generation at 25 MW Capacity
Average Monthly GW.h Average Monthly MW
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
GW.h 9.7 9.4 9.4 6.2 5.4 7.0 7.8 10.6 13.2 6.8 9.9 10.2 105.6
Average
MW 13.2 12.9 12.8 8.5 7.4 9.6 10.7 14.5 18.1 9.3 13.5 13.9 12.0
As the table for Figure B-1 shows, updated long term average generation capability for West Creek Hydro
approximates 55 GW.h on average from June 1 to November 30 (when the Yukon grid does not typically
6 Based on “Review of West Creek Hydro Site – Viability Analysis of Southeast Alaska and Yukon Economic Development Corridor”
December 4, 2014 Memorandum prepared by Access. This information was also provided in the Morrison Hershfield December 11,
2014 "Technical Feasibility Memorandum."
7 Long-term average generation for 1963-1977 years. Figure 3 of the December 4, 2014 Memorandum prepared by Access shows
that generation ranges between about 87 GW.h/year (water year 1973) and about 131 GW.h (water year 1977).
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 20
have a fossil fuel generation requirement), and approximately 8.4 GW.h/month on average for the
remaining six months (with lowest generation in April and May at about 5.4 – 6.2 GW.h/month).
The West Creek Hydro power utilization estimates to displace thermal generation depend on a number of
conditions for 2025 (i.e., the earliest potential date for West Creek Hydro in service) and beyond. These
conditions cannot be predicted with any great confidence at this time. Some of these conditions include
Yukon grid and Cruise ship load levels and thermal generation requirements, water availability in a ny
specific year and whether or not all cruise ships are equipped with shore power connection (and whether
related shore facilities for connection are also installed on shore).
For the purpose of assessing the financial feasibility of the Southeast Yukon -Alaska interconnection
Project, the June workshop defined Development Scenario 1 assuming West Creek Hydro is developed.
The following analysis updates the assumed thermal generation displacement under Scenario 1, focusing
for convenience on such displacement in the initial years of the Project and of West Creek Hydro
operation (e.g., 2025 to 2030). To the extent that the Project is financially feasible based on thermal
displacement in these initial years, the situation will improve in subsequent years to the extent that
Yukon grid loads and thermal displacement opportunities increase without any concurrent reductions in
Cruise Ship loads.
Figure B-2 below updates the overlap of West Creek Hydro monthly generation (as updated) with YEC
thermal generation requirements and load estimates for Cruise Ships as provided in the June 2014
Workshop. As reviewed in the June 2014 workshop, YEC’s thermal generation forecasts as adopted for
this study are based on Yukon grid load and thermal generation forecasts provided in the December 2013
Yukon Energy Application under Part 3 of Public Utilities Act for the Proposed Whitehorse Diesel-Natural
Gas Conversion Project, assuming current renewable generation and licences on the Yukon grid, i.e., the
thermal generation forecasts exclude development of any new renewable generation sources and/or
changes to current licences8.
Considering the Yukon grid load forecast with no mine connections in 2030 (when West Creek Hydro
could potentially be in-service) Figure B-2 shows the following (assuming West Creek Hydro generation is
allocated first to displace Cruise Ship thermal generation):
West Creek Hydro can potentially displace about 47 GW.h of YEC long term average thermal
generation requirement during winter months, based on 2030 forecast Yukon grid loads
assuming no mine loads being connected to the grid 9 and an assumed 5% line losses on West
Creek generation. Higher thermal displacement would be feasible to the extent that any mine
loads were connected and/or non-mine load growth exceeded the assumed forecast (which
would be forecast to occur for years subsequent to 2030).
8 As noted at the June 2014 Workshop, development of smaller hydro enhancements on the Yukon grid may occur in near term
that would reduce thermal generation requirements (i.e., if Mayo Lake and Marsh Lake enhancements are assumed to proceed,
then diesel generation requirements would be reduced by 4 and 6 GW.h/year respectively). Gladstone is not expected to proceed in
near term, but were it to proceed it would materially reduce the diesel generation requirements on the Yukon grid. Other new
renewable projects may occur over the forecast period to 2030 - however, there are no specific plans at this time for specific new
renewable projects to be developed.
9 The Yukon grid load forecast for YEC was not extended beyond year 2030. In the table under Figure B-2, West Creek Hydro
generation for the months of January through April is fully utilized to displace YEC’s thermal generation at the assumed 2030 grid
load with no mine connected loads, and the West Creek generation is fully used in May for Cruise Ships and some contribution to
YEC generation. Figure B-2 indicates that August through October is the period when West Creek Hydro supply tends to be
underutilized at currently forecast loads, i.e., with the 2030 forecast sales to Yukon and Cruise Ships, unused West Creek
generation equals 29.9 GW.h with 26.9 GW.h occurring in August to December and 19.3 GW.h in August to October.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 21
At the same time, West Creek Hydro is shown to provide about 25 GW.h of energy required for
Cruise Ships during summer months; to allow for capacity constraints, it is assumed that West
Creek Hydro displaces only 75% of Cruise Ship thermal generation in June and July (and 80% in
August) and that the balance of the forecast 30 GW.h/year diesel load is displaced by Yukon grid
summer surplus hydro and/or backup YEC LNG generation10.
In sum, based on these load assumption, total sales of West Creek Hydro generation in 2030
would be about 72 GW.h/year [with about 5% losses this would require 76 GW.h West Creek
Hydro generation which is 72% of full West Creek Hydro utilization at 106 GW.h].
Consequently, for the purpose of the Scenario 1 financial feasibility analysis for the interconnection
Project, 72.0 GW.h/year of available energy from West Creek Hydro is estimated to be available to
displace thermal generation requirements for YEC and for Cruise Ships.
It is noted that the Figure B-2 estimates of West Creek Hydro generation for Cruise Ship and/or Yukon
grid loads are very preliminary. The estimates are developed without ability to simulate actual Yukon grid
and/or West Creek Hydro system operation to evaluate likely long -term average ability to use hydro
and/or LNG generation (and the required mix of these two generation sources) to displace the assumed
Cruise Ship diesel generation requirements and/or Yukon grid thermal generation requirements.
10 As noted in June 2014 Workshop, the Cruise Ship load demand can reach 25 MW when two or more large ships dock at the same
time; in this situation West Creek Hydro would likely not be able to meet the total load requirements for Cruise Ships. Under these
conditions, lower cost LNG generation from Yukon could be considered as backup generation, when required, subject to pricing
arrangements and capacity. The table under Figure B-2 also notes forecast Yukon grid summer surplus hydro under various future
load conditions and years – however, as noted in the June 2014 workshop papers (Background Paper #2, section 2.2), average MW
Yukon grid surplus hydro capacity during summer months tends to emerge only during June (at a low level), increasing to only 9 to
15 MW in August, i.e., more analysis is needed to assess capability to use surplus hydro (e.g., through use of daily storage) to meet
varying daily Cruise Ship peak MW requirements and the extent to which backup LNG generation would be required.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 22
Figure B-2: West Creek Monthly Average Generation, YEC Thermal Generation Requirements
and Cruise Ships Loads
0
5
10
15
20
25
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov DecGW.hWest Creek Average (GW.h)
YEC Base Case no Alexco 2025 (GW.h) -LTA
YEC Base Case no Alexco 2020 (GW.h) -LTA
Cruise Ships Load estimate based on 2014 Schedule
YEC Base Case 2030, no mine load (GW.h) -LTA
YEC thermal generation requirements for 2025 under Base Case
(no mine load, long-term average)
West Creek Hydro generation simulation,
average over 15 water years
Load Estimate for
Cruise Ships in Skagway
YEC thermal generation requirements for 2030
under Base Case (no mine load, long-term average)
YEC thermal generation requirements for 2020 under Base Case
(with Minto load, long-term average)
YEC thermal generation requirements for 2025 under Scenario A1
(with Carmacks Copper for half year, no other mine load, long -term average)
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Total
West Creek Simulated Generation
Average Annual over 15 Water Years 9.7 9.4 9.4 6.2 5.4 7.0 7.8 10.6 13.2 6.8 9.9 10.2 105.6
Cruise Ships - - - - 4.4 6.8 7.2 7.0 4.6 - - - 29.9
YEC Thermal Generation
Base Case no Alexco 2020 5.1 6.9 11.6 9.6 3.4 0.1 0.0 0.0 0.1 0.1 1.6 3.2 41.1
Base Case no Alexco 2025 5.8 8.0 13.5 10.7 3.5 0.1 0.0 0.0 0.0 0.1 1.8 3.5 46.8
Scenario A1 2025 9.0 13.2 20.5 15.7 6.6 0.7 0.0 0.0 0.0 0.1 1.7 3.4 71.0
Base Case no mines 2030 14.0 18.1 24.5 17.1 6.6 0.6 0.2 0.1 0.1 0.5 3.8 8.1 92.5
West Creek Thermal Displacement*
YEC Thermal Generation (2030)9.2 9.0 9.0 5.9 0.8 0.6 0.2 0.1 0.1 0.5 3.8 8.1 47.2
Cruise Ships Thermal Generation - - - - 4.4 5.0 5.4 5.6 4.6 - - - 25.0
Total Thermal Displacement 9.2 9.0 9.0 5.9 5.1 5.6 5.6 5.6 4.7 0.5 3.8 8.1 72.1
*
YEC Surplus Hydro
Base Case no Alexco 2020 - - - - 0.4 5.9 7.8 9.0 9.0 2.5 - - 34.6
Base Case no Alexco 2025 - - - - 0.4 6.3 8.4 9.6 9.4 2.5 - - 36.6
Scenario A1 2025 - - - - 0.0 2.4 8.2 9.5 9.1 2.4 - - 31.6
Base Case no mines 2030 - - - - 0.0 2.6 5.2 6.2 5.6 1.4 - - 21.1
Assumes: line losses at 5% on West Creek sales; West Creek Hydro generation allocated first to
displace Cruise Ship thermal generation; June-July sales at 75% [and August sales at 80%] of Cruise
Ship load due to West Creek capacity constraints.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 23
APPENDIX C – WEST CREEK HYDRO COST ESTIMATES
Table C-1 provides a summary of the updated West Creek Hydro construction cost estimates based on
the Memorandum prepared by Access11. As reviewed in the notes below, considerable uncertainty
remains in these cost estimates.
Table C-1: West Creek Updated Construction Cost Estimates
Item Costs
($000 US 1983)
Inflated Costs
($000 US 2013)
1 Preparatory Work 5,600 13,100
2 Damand Reservoir 44,500 104,100
3 Power Conduit 11,900 27,800
4 Power Plant 12,000 28,800
5 Switchyard and Transmission Line 4,300 10,100
Subtotal 78,200 183,200
Contingencies (25%) 19,600 45,800
Direct Construction Cost 97,800 229,000
Engineering and Owner Administration (15%) 14,700 34,400
Total Construction Cost 112,400 263,400
As shown in Table C-1, the updated cost estimate adjusted an earlier 1983 cost estimate (prepared for a
22.5 MW installed capacity) by inflating up to 2013$ value using the U.S. Annual Consumer Price Index
(134% increase in costs from 1983 to 2013). These estimates do not include socio-environmental
assessment, permitting and mitigation related costs which are estimated at about $13 million (US 2013$).
Based on these cost updates it is estimated that the total cost for West Creek Hydro would be about $327
million (CAD, 2014$) as per Table C-2 below.
Table C-2: West Creek Updated Cost Estimates
West Creek Hydro US CAD
$000 US $000 CAD
Total Construction Cost (2013$)263,400 305,544
Socio-Environmental Assessment, Permitting and Mitigation (2013$)13,000 15,080
Total Cost (2013$)276,400 320,624
Total Cost (2014$, assumed 2% inflation)281,928 327,036
11 “Review of West Creek Hydro Site – Viability Analysis of Southeast Alaska and Yukon Economic Development Corridor” December
4, 2014 Memorandum prepared by Access.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 24
Notes to Table C-1 and Table C-2:
1. Construction costs are high level estimates and are based on 1983 cost estimates for a 22.5 MW
plant capacity and inflated to a 2013$ value using the U.S. Annual Consumer Price Index (cost
estimate prepared by Access). An inflation factor of 134% was used to inflate costs from 1983 to
2013 (30 years). Access also notes that it is reasonable to expect project costs to range
anywhere between $200M US to $350M US depending on the selected installed capacity and the
final layout that is selected.
2. Access notes that in the 1983 cost estimates the power conduit and power plant it ems appear to
be low, and if the selected option is to build a power tunnel (instead of a penstock), construction
costs may increase as much as by $27.8 million (US).
3. Access also notes that if the installed capacity was optimized to match the available inflows in the
watershed, as discussed previously (in a 15 to 18 MW range), project costs could be reduced by
approximately 10% compared to the proposed 25 MW installed capacity.
4. Canadian dollar at $1 US = $1.16 CAD based on exchange rate as of January 2, 2 015 (Bank of
Canada).
5. The Southeast Alaska Integrated Resource Plan (Table 10-4) shows the estimated capital cost for
25 MW West Creek Hydro between $112 million and $168 million (US, 2011$).
6. The June 2014 Workshop noted that the cost estimate for West C reek Hydro was at $140 million
based on West Creek economic analysis provided as part of Renewable Energy Fund Round 6
Grant Application of the Municipality of Skagway before Alaska Energy Authority, 2012.
As reviewed in Appendix E, LCOE estimates for Wes t Creek Hydro were developed for the inter connection
Project feasibility analysis based on the $327 million CAD$2014 capital cost estimate, assumed annual
O&M costs [CAD$2014] at 0.5% of the capital cost estimate, and an economic life of 90 years.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 25
APPENDIX D – SKAGWAY – WHITEHORSE TRANSMISSION LINE COSTS
Table D-1 provides a summary of the interconnection Project transmission line costs as estimated by
Morrison Hershfield12.
Table D-1: Skagway – Whitehorse Transmission Line Costs (CAD, 2014$)
No Fibre With Fibre No Fibre With Fibre No Fibre With Fibre
$000 CAD $000 CAD $000 CAD $000 CAD $000 CAD $000 CAD
Transmission Line
Total 170 km
Alaskan portion 19 km
Canadian portion 151 km
Alaskan portion 32,453 34,055 32,453 34,055 32,453 34,055
Transmission Line 14,420 16,021 14,420 16,021 14,420 16,021
Substation 18,033 18,033 18,033 18,033 18,033 18,033
Canadian portion 76,160 93,587 90,405 111,750 85,478 104,060
Transmission Line 74,188 91,616 88,434 109,779 83,507 102,089
Substation Upgrade 1,971 1,971 1,971 1,971 1,971 1,971
Total Transmission Line 108,612 127,642 122,858 145,805 117,931 138,115
Option A New ROW along
Highway Option B ATCO ROW Option C New ROW along
railway
Note to the table:
1. Alaskan portion of the transmission line costs have been converted to Canadian dollar at $1 US =
$1.16 CAD based on exchange rate as of January 2, 2015.
As noted in Table D-1, transmission line costs are estimated to be between $108.6 million and $145.8
million (CAD, 2014$) depending on the Right of Way (ROW) option selected and on whether fibre options
are included or excluded.
The average cost per km of the transmission line is estimated to be higher on the Alaskan side (as shown
in Table D-2). Part of the higher costs is due to the exchange rate which is based on Bank of Canada
exchange rate on January 2, 2015 at $1.16 CAD = $1 US. For example, for Option B the cost for the
Alaskan side in US$ would be $0.654 million/km for no fibre option (compared to $0.586 million/km for
Canadian side), and $0.727 million/km for with fibre option (compared to $0.727 million/km for Canadian
side)13.
12 The cost estimates provided by Morrison Hershfield (January 2, 2015) for Canadian side was presented in Canadian dollars and
Alaskan side in US dollars. Alaskan portion of the transmission line costs have been converted to Canadian dollar at $1 US = $1.16
CAD based on exchange rate as of January 2, 2015.
13 By way of example, Southeast Alaska Integrated Resource Plan (SAIRP) provides analysis with relation to the potential
transmission connection between southeast Alaska communities, including connection of Haines to Juneau and it notes that the
project total cost would be about $244 million (2011$ US, SAIRP, page 12-36, Table 12-8) for 85.3 miles (the cost estimated to be
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 26
Table D-2: Skagway – Whitehorse Transmission Line Costs (CAD, 2014$)
No Fibre With Fibre No Fibre With Fibre No Fibre With Fibre
$000 CAD $000 CAD $000 CAD $000 CAD $000 CAD $000 CAD
Without substation cost
Alaskan portion 14,420 16,021 14,420 16,021 14,420 16,021
Canadian portion 74,188 91,616 88,434 109,779 83,507 102,089
Alaskan portion km 19 19 19 19 19 19
Canadian portion km 151 151 151 151 151 151
Alaskan portion $000/km 759 843 759 843 759 843
Canadian portion $000/km 491 607 586 727 553 676
Option A New ROW along
Highway Option B ATCO ROW Option C New ROW along
railway
As provided in Tables D-1 and D-2 above, the fibre options add about $19-$23 million to the cost of
transmission line. Based on information available from the Government of Yukon,14 the cost of installation
of fibre between Skagway and Whitehorse (as currently planned without use of the transmission line) is
estimated to be in the range of $9.5 million, which is much lower compared to fibre options added cost to
the transmission lines noted in the above tables. Accordingly, the financial feasibility analysis of the
interconnection Project does not consider further the fibre option.
Taking into account the above cost options, the lowest cost option (Option A) without fibre option is
assumed for the financial feasibility analysis to be the most economically feasible option compared t o the
other options provided in Table D-1. Accordingly, the Project capital cost of $108.6 million for Option A
(no fibre) is used for the Base Case feasibility analysis. In contrast, the most costly Project option without
fibre (Option B) is approximately 13% higher cost than Option A.
As reviewed in Appendix D, annual O&M costs for the interconnection Project are estimated at $1,608/km
or $273,300 per year (CAD, 2014$).
about $2.8 million/mile) of 69 kV transmission line (about 137 km). Table 12-1 of SAIRP provides generic costs of transmission line
which estimated to be about $0.446 million/mile when use wood poles and $0.481 million/mile when use steel poles.
14 Information from Department of Economic Development Government of Yukon.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 27
APPENDIX E – PROJECT FINANCIAL FEASIBILITY ANALYSIS: ASSUMPTIONS
In order to prepare the Base Case financial feasibility analysis for the Project the following assumptions
are used:
1. Capital Costs:
a. Interconnection Project capital costs for base case scenario at $108.6 million (2014$
CAD) (as per Table D1 of Appendix D, assuming Option A with no fibre option).
b. West Creek Hydro capital cost at $327 million (2014$ CAD) (as per Table C-2 of
Appendix C).
2. Annual Operating and Maintenance (O&M) costs:
Interconnection Project annual O&M costs assumed at $1,608/km or $273,300 per year
(CAD, 2014$); includes $1,407.6/km [2014$] brushing/cleaning for Canadian portion [151
km] based on YEC average cost for transmission lines 15, $2,051/km O&M [CAD, 2014$] for all
of the 19 km US portion, and $3,107/km added brushing/cleaning [CAD, 2014$] for the first
7 km only of the Alaskan portion of transmission line (based on Southeast Alaska Power
Agency experience).
West Creek Hydro annual O&M costs assumed at 0.5% of total cost consistent with YEC
Resource Plan analysis16. The O&M cost would be about $2.0 million for 2025. This is
comparable to the O&M expenses used in West Creek economic analysis (Skagway Round 6
Grant Application before Alaska Energy Authority, 2012) which assumed $2.3 million for
2025.
3. West Creek Hydro generation sales for Scenario 1 development estimated at 72 GW.h/year
(about 81 GW.h/year generation including line losses). As reviewed in Appendix B, this includes
about 47 GW.h YEC thermal generation displacements in 2030 and about 25 GW.h diesel
generation displacement for Cruise Ships17.
4. Project Economic Life - It is assumed that the project economic life for the interconnection
Project is 55 years and for West Creek Hydro is 90 years, based on experience with the most
recent developments for YEC [Mayo B Hydro assets amortize over a bout 90 years and CSTP 138
kV transmission line over 55 years].
5. Development Timeline - It is assumed that it would take a minimum 10 years to develop West
Creek Hydro with potential in-service date of 2025 for Scenario 1 and for Scenario 2 it is assumed
15 YEC’s 2012/13 GRA, response to CW-YEC-1-18 which shows $1,380/km.
16 YEC 20-Year Resource Plan: 2011-2030.
17 As reviewed in Appendix B, the thermal generation displacement will depend on load levels, new renewable projects in Yukon
(Mayo Lake, Marsh Lake, etc.) and other conditions. With about 5% line losses (i.e. 72 GW.h load at sales level and plus 5% for line
losses) would result in about 76 GW.h West Creek generation which is 72% of long-term average simulated generation capability of
106 GW.h/year.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 28
that the interconnection Project can be in-service at the earliest in 2020 (assumes about six years
for permitting and building)18.
6. Cost of Capital at 5.45%/year with inflation (nominal discount rate) and 3.38%/year excluding
inflation (real discount rate). The 5.45%/year nominal discount rate is consistent with YEC’s
latest average cost of capital used for the LNG Part 3 application analysis (assumes 60% debt at
3.6% average debt cost and 40% equity at 8.25% return) and comparable to the financial cost
used in West Creek economic analysis (Skagway Round 6 Grant Application before Alaska Energy
Authority, 2012) which assumed at 6%). The real discount rate of 3.38%/year assumes inflation
at 2%/year.
7. Annual inflation rate assumed at 2% [based on data from Department of Labor and Workforce
Development the annual change in CPI for Anchorage for the last five years (2009 -2013)
averages to 2.3%; based on data from Yukon Bureau of Statistics the annual change in CPI for
Whitehorse for the same period averages to 1.6%].
8. Interconnection Project Line Use assumed as follows (for the base case a simple constant
level of annual line use is assumed for each scenario over the 55 year economic life of the
Project):
a. Scenario 1: as reviewed in Appendix B, starting in 2025 to 2030 time frame, 47
GW.h/year sales in Whitehorse during winter months (as reviewed in Appendix B) from
49 GW.h/year generation at West Creek Hydropower (assumes 5% incremental line
loss); 5 GW.h/year sales in Skagway during summer months from 5.5 GW.h /year of
surplus hydro and/or LNG power generated on the Yukon grid (assumes 10% line loss).
b. Scenario 2: assuming Cruise Ship load of 30 GW.h/year is available and connected to
be displaced, starting in 2020 time frame, 30 GW.h/year sales in Skagway during
summer months from 33 GW.h/year of surplus hydro and/or LNG power generated on
the Yukon grid (assumes 10% line loss).
9. Sales rates for power purchases assumed as follows (CAD, 2014$) based on June 2014
Workshop information and assumptions:
a. Alaska Cruise Ship summer power purchases: assumed purchase power rate at
$0.27/kW.h (net of any land distribution cost charges) for power supplied to cruise ships
by YEC or West Creek Hydro (assumed at about 87% of ship diesel fuel and O&M cost
estimates provided at the June Workshop, ignoring conversion from US to CA dollars).19
b. YEC Yukon grid winter power purchases: assumed power purchase rate in the 2025
time period at $0.165/kW.h to displace thermal power generation (proxy for LNG thermal
18 As noted in June 2014 Workshop, the transmission project could require from 5.5 to 7.5 years to develop, including feasibility
assessments (up to 18 months), permitting and licensing (up to 24 months), and procurement and construction period (up to 36
months). Staged decision-making with could facilitate development at the earliest in about 5 years.
19 Background Paper #1, page 1-6: analysis by Municipality of Skagway (Round 6 Grant Application before Alaska Energy Authority,
2012) estimated the Cruise Ship diesel fuel and O&M cost at 33.4 cents/kW.h (US$) for 2016 (32.1 cents/kW.h fuel and 1.3
cents/kW.h O&M). This appears to reflect an estimate of about 31 c/kW.h (US$) in 2014$.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 29
fuel and O&M costs [CAD, 2014$], taking into consideration expectation that natural gas
prices escalate notably over that time period faster than general inflation)20.
c. YEC sales of summer power to Cruise Ships: assumed average power purchase
rate, excluding interconnection Project charges, as follows:
i. $0.13/kW.h for Scenario 1 YEC sales to Cruise Ships21; and
ii. $0.09/kW.h for Scenario 2 YEC sales to Cruise Ships, assuming no new mine
loads on the Yukon grid.22
10. PV Annual Costs (CAD, 2014$): based on the above assumptions, the PV annual costs for the
Project and West Creek Hydro are assumed as follows:
a. Interconnection Project: $115.385 million total PV costs, including $108.612 million
for capital development costs and $6.783 million PV costs for O&M over the 55 year
economic life (discounted at the real discount rate of 3.38%/yr). Annual PV costs of
$4.649 million assume constant annual real costs [in CAD, 2014$] over the economic life.
b. West Creek Hydro: $372.959 million total PV costs, including $327.036 million for
capital development costs and $45.923 million PV costs for O&M over the 90 year
economic life (discounted at the real discount rate of 3.38%/yr). Annual PV costs of
$13.280 million assume constant annual real costs [in CAD, 2014$] over the economic
life.
Financial Feasibility Analysis Approach
The financial feasibility analysis for each Development Scenario and sensitivity assesses the potential
recovery of Project costs through charges for electricity transmitted over the inter connection.
Assumed Project charge rates in this analysis are based on assumed market constraints as well as
estimated Project costs as reviewed below. In each case, constant dollar annual government funding
support required over the economic life is estimated if assumed charge rates are not exp ected to recover
estimated Project costs.
The analysis assumes, for simplicity, constant annual costs and revenues (over the assumed economic
lives) to reflect the preliminary nature of any assessment based on current information regarding the
20 YEC Part 3 LNG Application and related update evidence (Ex. B-13) during the YUB hearing indicated a 2015 estimated cost for
LNG delivered to Whitehorse from Delta BC (Vancouver) at 14.0 c/kW.h assuming A-train haul units and AECO gas price at
$4.5/MMBtu; assuming YEC gas-fired generation O&M cost at 1.5 c/kW.h, the 2015 incremental fuel and O&M cost estimate is 15.5
c/kW.h, with natural gas fuel cost representing 4.09 c/kW.h of this total. A 16.5 c/kW.h incremental fuel and O&M cost [2014$] in
2015 assumes an AECO natural gas fuel price (in 2014$) of about $5.85/MMBtu, i.e., gas price escalation (from the price assumed
for 2015) in real terms of about 30% over the time period to 2025. By way of reference, the NEB November 2013 Benchmark Price
forecast for Henry Hub gas price assumed real escalation of 32% for this price from 2015 to 2025.
21 Allows for about 60% of the sales using LNG generation for backup at the 16.5c/kW.h assumed fuel and O&M cost in 2015, and
the balance at an assumed charge of 5c/kW.h for surplus hydro, plus 10% line losses on all sales.
22 Allows for $0.08/kW.h from 2020 until after 2025 (and $0.106/kW.h by 2030) assuming about 20% of the sales using LNG
generation for backup at the 16.5c/kW.h assumed fuel and O&M cost in 2015 (40% by 2030), and the balance at an assumed
charge of 5c/kW.h for surplus hydro, plus 10% line losses on all sales.
INTERGROUP CONSULTANTS LTD. Interim Working Memo Page 30
interconnection Project and potential forecasts that affect Project feasibility.23 The following are key
elements in the financial feasibility analysis of the two development scenarios:
Present value (PV) costs for the Project and West Creek Hydro stated as fixed annual
costs: As reviewed in Appendix E, PV costs for the Project and West Creek Hydro are each
stated in CAD, 2014$, including the assumed capital development cost and the assumed O&M
costs over the relevant economic life (55 years for the Project and 90 y ears for West Creek
Hydro).24 Annual PV costs are assumed constant [in CAD, 2014$] over the respective economic
lives (for the Base Case assumptions, at $4.649 million/year for the Project and $13.280
million/year for West Creek Hydro). This approach ignore s normal utility rate recovery for such a
Project which requires higher annual costs at the outset that decline over the economic life.
Assumed constant annual generation, loads and sales rates: For simplicity, financial
feasibility is assessed based on assumed constant annual generation, loads and sales rates (in
real CAD, 2014$). This approach removes the complexities of varying annual forecasts over the
respective economic lives of the Project and West Creek Hydro, and assumes that the analysis is
conservative to the extent that Project use tends to improve over the economic life due to Yukon
grid load growth. If the Project proceeds, further feasibility analysis will be needed to confirm
that assumed conditions over the economic life will continue to sus tain Project feasibility.
Lifecycle Cost of Energy (LCOE) in $/kW.h: LCOE costs for the Project or West Creek Hydro
reflect the respective PV annual costs divided by the relevant assumed constant annual Project
load (i.e., electricity sales transmitted over the interconnection) or West Creek Hydro generation
sales used to displace thermal generation in Alaska and Yukon.
o Scenario 1:
Project LCOE: $0.089/kW.h [CAD, 2014$], assuming 52 GW.h/year sales
transmitted (47 GW.h/year sales to Yukon from West Creek Hydro and 5
GW.h/year sales to Cruise Ships from Yukon).
West Creek Hydro LCOE: $0.184/kW.h [CAD, 2014$], assuming 72 GW.h/year
sales from West Creek Hydro (47.0 GW.h to Yukon during winter, and 25.0 GW.h
to Cruise Ships during summer).
o Scenario 2:
Project LCOE: $0.155/kW.h [CAD, 2014$], assuming 30.0 GW.h/year sales
transmitted during summer from Yukon to Cruise Ships.
23 For example, forecasts for future Project and West Creek Hydro costs, Yukon and Cruise Ship loads, thermal generation available
to be displaced by the Project, and relevant charge rates for power supplies that may affect Project viability.
24 Under Base Case assumptions per Appendix E, the overall PV costs [CAD, 2014$] over the economic life are $115.4 million for the
Project and $373.0 million for West Creek Hydro.