HomeMy WebLinkAboutR8 RE Fund Grant App_IndianRiver_TenakeeMain
GRANT APPLICATION
– FOR –
INDIAN RIVER HYDROELECTRIC PROJECT
SUPPLEMENTAL CONSTRUCTION FUNDING
SEPTEMBER 22, 2014
– SUBMITTED TO –
ALASKA ENERGY AUTHORITY
RENEWABLE ENERGY GRANT PROGRAM – ROUND IV
RFA #AEA-15003
– SUBMITTED BY –
CITY OF TENAKEE SPRINGS, ALASKA
P.O. BOX 52
TENAKEE SPRINGS, AK 99841
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 1 of 24 7/2/14
Application Forms and Instructions
This instruction page and the following grant application constitutes the Grant Application Form for
Round VIII of the Renewable Energy Fund. A separate application form is available for projects
with a primary purpose of producing heat (see RFA section 1.5). This is the standard form for all
other projects, including projects that will produce heat and electricity. An electronic version of the
Request for Applications (RFA) and both application forms is available online at:
http://www.akenergyauthority.org/REFund8.html.
• If you need technical assistance filling out this application, please contact Shawn Calfa, the
Alaska Energy Authority Grants Administrator at (907) 771-3031 or at scalfa@aidea.org.
• If you are applying for grants for more than one project, provide separate application forms
for each project.
• Multiple phases for the same project may be submitted as one application.
• If you are applying for grant funding for more than one phase of a project, provide
milestones and grant budget for each phase of the project.
• In order to ensure that grants provide sufficient benefit to the public, AEA may limit
recommendations for grants to preliminary development phases in accordance with 3 ACC
107.605(1).
• If some work has already been completed on your project and you are requesting funding
for an advanced phase, submit information sufficient to demonstrate that the preceding
phases are completed and funding for an advanced phase is warranted.
• If you have additional information or reports you would like the Authority to consider in
reviewing your application, either provide an electronic version of the document with your
submission or reference a web link where it can be downloaded or reviewed.
• In the sections below, please enter responses in the spaces provided, often under the
section heading. You may add additional rows or space to the form to provide sufficient
space for the information, or attach additional sheets if needed.
REMINDER:
• Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials
submitted to the Authority may be subject to disclosure requirements under the act if no
statutory exemptions apply.
• All applications received will be posted on the Authority web site after final
recommendations are made to the legislature.
• In accordance with 333 (b) Applicants may request trade secrets or proprietary company
data be kept confidential subject to review and approval by the Authority. If you want
information is to be kept confidential the applicant must:
o Request the information be kept confidential.
o Clearly identify the information that is the trade secret or proprietary in their
application.
o Receive concurrence from the Authority that the information will be kept confidential.
If the Authority determines it is not confidential it will be treated as a public record in
accordance with AS 40.25 or returned to the applicant upon request.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 2 of 24 7/2/14
SECTION 1 – APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
CITY OF TENAKEE SPRINGS dba TENAKEE SPRINGS ELECTRIC DEPARTMENT
Type of Entity: Fiscal Year End:
LOCAL GOVERNMENT July 31
Tax ID #
Tax Status: ☐ For-profit ☐ Non-profit ☐ Government (check one)
Date of last financial statement audit:
Mailing Address: Physical Address:
PO BOX 52 TENAKEE SPRINGS COMMUNITY BLDG.
TENAKEE SPRINGS, AK 99841 TENAKEE AVENUE
Telephone: Fax: Email:
907-736-2207 907-736-2207 citytke@gmail.com
1.1 APPLICANT POINT OF CONTACT / GRANTS MANAGER
Name: Title:
ARTHUR BLOOM HYDRO PROJECT MANAGER
Mailing Address:
PO BOX 52
TENAKEE SPRINGS, AK 99841
Telephone: Fax: Email:
907-736-2222 907-736-2207 artmbloom@gmail.com
1.1.1 APPLICANT ALTERNATE POINTS OF CONTACT
Name Telephone: Fax: Email:
X
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 3 of 24 7/2/14
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
☐ An electric utility holding a certificate of public convenience and necessity under AS 42.05, or
☐ An independent power producer in accordance with 3 AAC 107.695 (a) (1), or
☐ A local government, or
☐ A governmental entity (which includes tribal councils and housing authorities)
1.2 APPLICANT MINIMUM REQUIREMENTS (continued)
Please check as appropriate.
☐ 1.2.2 Attached to this application is formal approval and endorsement for the project by the
applicant’s board of directors, executive management, or other governing authority. If the
applicant is a collaborative grouping, a formal approval from each participant’s governing
authority is necessary. (Indicate by checking the box) * RESOLUTION ON AGENDA FOR SEPTEMBER COUNCIL MEETING, WILL BE PROVIDED WHEN
AVAILABLE
☐ 1.2.3 As an applicant, we have administrative and financial management systems and follow
procurement standards that comply with the standards set forth in the grant agreement
(Section 3 of the RFA). (Indicate by checking the box)
☐ 1.2.4 If awarded the grant, we can comply with all terms and conditions of the award as
identified in the Standard Grant Agreement template at
http://www.akenergyauthority.org/REFund8.html. (Any exceptions should be clearly noted
and submitted with the application.) (Indicate by checking the box)
☐ 1.2.5 We intend to own and operate any project that may be constructed with grant funds for
the benefit of the general public. If no please describe the nature of the project and who will
be the primary beneficiaries. (Indicate yes by checking the box)
X
X
X *
X
X
X
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 4 of 24 7/2/14
SECTION 2 – PROJECT SUMMARY
This section is intended to be no more than a 2-3 page overview of your project.
2.1 Project Title – (Provide a 4 to 7 word title for your project). Type in space below.
INDIAN RIVER HYDROELECTRIC PROJECT – CONSTRUCTION
2.2 Project Location –
Include the physical location of your project and name(s) of the community or communities that will
benefit from your project in the subsections below.
2.2.1 Location of Project – Latitude and longitude, street address, or community name.
Latitude and longitude coordinates may be obtained from Google Maps by finding you project’s
location on the map and then right clicking with the mouse and selecting “What is here? The
coordinates will be displayed in the Google search window above the map in a format as follows:
61.195676.-149.898663. If you would like assistance obtaining this information please contact
AEA at 907-771-3031.
The project is located on Indian River, approximately one mile east of Tenakee Springs in
Township 47 South, Range 63 East of the Copper River meridian. This project is located at
approximately 57.788d N, 135.193d W.
2.2.2 Community benefiting – Name(s) of the community or communities that will be the
beneficiaries of the project.
Tenakee Springs, its residents and businesses will benefit from this project.
2.3 PROJECT TYPE
Put X in boxes as appropriate
2.3.1 Renewable Resource Type
☐ Wind ☐ Biomass or Biofuels (excluding heat-only)
☐ Hydro, Including Run of River ☐ Hydrokinetic
☐ Geothermal, Excluding Heat Pumps ☐ Transmission of Renewable Energy
☐ Solar Photovoltaic ☐ Storage of Renewable
☐ Other (Describe) ☐ Small Natural Gas
2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply)
Pre-Construction Construction
☐ Reconnaissance ☐ Final Design and Permitting
☐ Feasibility and Conceptual Design ☐ Construction
X
X
X
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 5 of 24 7/2/14
2.4 PROJECT DESCRIPTION
Provide a brief one paragraph description of the proposed project.
Displace diesel generation of electricity for the City of Tenakee Springs with renewable
hydroelectric power. The City of Tenakee Springs is constructing a hydroelectric project on Indian
River. This will be a 180 kW low head, run-of-river plant displacing the use of 30,000 gallons of
diesel fuel annually, or 90% of annual electric utility diesel consumption. At least 6,500 additional
gallons of fuel oil can be displaced by heating public buildings with excess energy from the hydro
project.
The city successfully completed construction of Phase 1 of this project in June 2014, which
consisted of extending access roads and trails to the powerhouse and intake sites. Phase 2 will
commence this fall, which will construct the balance of the project. The final engineer’s cost
estimate exceeds the funds the city has available for this project, so the city is requesting
additional grant funds to ensure Phase 2 can be completed without disruption.
2.5 PROJECT BENEFIT
Briefly discuss the financial and public benefits that will result from this project, (such as reduced
fuel costs, lower energy costs, local jobs created, etc.)
The Tenakee Springs Electric Utility diesel generators use approximately 32,000 gallons of diesel
fuel per year. This project will eliminate 90+% of this annual fuel usage with hydroelectric power.
Additional fuel offsets can be achieved by replacing heating oil with electric heat. The proposed
project would help retain money within the community by stemming the outflow of money for
petroleum products and providing employment during construction and operation. Additional public
benefits would be less noise in the community (diesel generators would not be running most of the
time), less air pollution, less risk for environmental liability, lower cost electricity – especially for
commercial entities which currently pay very high rates, and potential expansion of economic base
(fish processing and washeteria).
2.6 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and
source of other contributions to the project.
The final engineer’s cost estimate for the project is $4,297,280. The city has existing funds of
$3,320,000, of which $578,349 was spent to complete Phase 1 construction, leaving $2,741,651 in
funds currently remaining for the project. Additional grant funds of $977,000 are requested to fully
fund Phase 2 construction of the project. The City will provide $280 cash match and the
city/residents may provide in-kind services as available and appropriate to facilitate project
completion.
2.7 COST AND BENEFIT SUMMARY
Include a summary of grant request and your project’s total costs and benefits below.
Costs for the Current Phase Covered by this Grant
(Summary of funds requested)
2.7.1 Grant Funds Requested in this application $ 977,000
2.7.2 Cash match to be provided $ 280
2.7.3 In-kind match to be provided $ as-needed
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 6 of 24 7/2/14
2.7.4 Other grant funds to be provided $ 3,320,000
2.7.5 Total Costs for Requested Phase of Project (sum of 2.7.1 through 2.7.4 $ 4,297,280
Other items for consideration
2.7.6 Other grant applications not yet approved none.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 7 of 24 7/2/14
Project Costs & Benefits
(Summary of total project costs including work to date and future cost estimates to get to a fully
operational project)
2.7.7 Total Project Cost
Summary from Cost Worksheet, Section 4.4.4, including
estimates through construction.
$ 4,526,280
2.7.8 Additional Performance Monitoring Equipment not
covered by the project but required for the Grant
Only applicable to construction phase projects
$ 0
2.7.9 Estimated Direct Financial Benefit (Savings)
The economic model used by AEA is available at
www.akenergyauthority.org/REFund8.html. This
economic model may be used by applicants but is not
required. Other economic models developed by the
applicant may be used, however the final benefit/cost
ratio used will be derived from the AEA model to ensure
a level playing field for all applicants.
$ 5,726,787
2.7.10 Other Public Benefit
If you can calculate the benefit in terms of dollars please
provide that number here and explain how you
calculated that number in Section 5 below.
No quantified benefit, see
section 5
SECTION 3 – PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include contact information, a resume
and references for the manager(s). In the electronic submittal, please submit resumes as separate
PDFs if the applicant would like those excluded from the web posting of this application. If the
applicant does not have a project manager indicate how you intend to solicit project management
support. If the applicant expects project management assistance from AEA or another government
entity, state that in this section.
Currently, the project manager is Arthur Bloom, an elected member of the city council (term ends
September 2014) and employee of the city (Hydroelectric Project Manager). Tenakee Springs
hired Polarconsult Alaska, Inc. to complete a feasibility study, conceptual design, permitting, final
design, and construction engineering for the project. Under this contract, Polarconsult is also
providing project manager support and guidance. No management assistance from AEA is
needed.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 8 of 24 7/2/14
3.2 Project Schedule and Milestones
Please fill out the schedule below. Be sure to identify key tasks and decision points in your project
along with estimated start and end dates for each of the milestones and tasks. Please clearly
identify the beginning and ending of all phases of your proposed project.
Milestones Tasks
Start
Date
End
Date
Issue Final Construction Drawings for
Agency Review
Final Construction Drawings, Engineer’s Cost
Estimate -- 9/22/14
Receive Agency Review Comments Agency Review Comments 9/22/14 10/6/14
Issue Final Construction Drawings for
Construction
Final Construction Documents
10/6/14 10/13/14
Select Vendors / Contractors and
Award Contracts
Contractor for Penstock Bench Construction
Turbine/Generator Vendor
Switchgear/Controls Vendor
Contractor for Balance of Construction 10/13/14 11/17/14
Construction Management Oversee contractor/vendor selection, manage
construction process for City 10/6/14 12/31/15
Construction Engineering / Inspection Site inspections, review contractor submittals,
change orders, pay requests, and duties as set forth in
construction / procurement contracts. 10/6/14 12/31/15
Phase 1 Construction Access roads and Trails (Completed) 9/1/13 7/15/14
Phase 2 Construction Balance of Project
Surveys Construction surveys, final as-built survey 11/1/14 12/31/15
Power Line Construct power line 11/1/14 7/31/15
Diversion/Intake/Fishpass Construct diversion/intake/fishpass 11/1/14 8/31/15
Penstock Construct penstock bench and penstock 11/1/14 6/30/15
Powerhouse Construct powerhouse 11/1/14 9/30/15
Turbine/Generator Furnish and install turbine/generator 11/1/14 10/31/15
Switchgear/Controls Furnish and install switchgear/controls 11/1/14 10/31/15
Startup / Commissioning Startup and commission plant 11/1/14 11/30/15
O&M Manual Provide final O&M manual to owner 11/1/14 12/31/15
Operations Reporting to AEA Provide annual operation reports to AEA 12/31/16 12/31/26
3.3 Project Resources
Describe the personnel, contractors, personnel or firms, equipment, and services you will use to
accomplish the project. Include any partnerships or commitments with other entities you have or
anticipate will be needed to complete your project. Describe any existing contracts and the
selection process you may use for major equipment purchases or contracts. Include brief resumes
and references for known, key personnel, contractors, and suppliers as an attachment to your
application.
The city’s existing project team, including Mr. Bloom and Tenakee’s consultant Polarconsult, has
successfully advanced the project through the completion of Phase 1 construction. For the
remainder of construction, the city and Polarconsult intend to work with Wilson Engineering based
in Juneau for assistance with site inspections and other services to help reduce mobilization costs
for engineers out of Anchorage, where Polarconsult is headquartered.
The City of Tenakee Springs will follow the methods set forth in its ordinances for procurement and
contractor / vendor selection processes during phase 2 construction.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 9 of 24 7/2/14
3.4 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status. Please
provide an alternative contact person and their contact information.
Tenakee’s Hydro Project Manager will provide regular reports to AEA on current project activities.
Construction reports will be issued on a monthly basis or more frequently as appropriate.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 10 of 24 7/2/14
3.5 Project Risk
Discuss potential problems and how you would address them.
This project utilizes proven technology and construction methods. All permits are in place, and
design is complete. The primary remaining risk on this project is construction risk, which would
most likely be manifested as increased construction cost.
The city has phased construction to first address the highest-risk construction activities and provide
time to adapt design for site conditions ascertained during construction. This strategy has been
successfully implemented over the past year with the completion of Phase 1 construction (project
access roads and trails) in summer 2014.
Phase 1 encountered challenging geotechnical conditions that resulted in final Phase 1 cost 12%
above the engineer’s cost estimate. Close coordination between the city, engineer, and contractor
enabled the city to adapt the plans and construct superior site access to the powerhouse than
provided in the original design. Geotechnical data obtained during Phase 1 construction has been
used to complete the Phase 2 project designs and prepare the final engineer’s cost estimate.
These design deliverables reflect current known geotechnical site conditions, and contain
appropriate contingencies for site geotechnical conditions.
The City and utility have a variety of options to handle future cost overruns on this project should
they occur. The two principal options are to seek additional grants or secure a loan that would be
repaid through future utility revenues.
3.6 Project Accountant(s)
Tell us who will be performing the accounting of this Project for the Grantee and include contact
information, a resume and references for the project accountant(s). In the electronic submittal,
please submit resumes as separate PDFs if the applicant would like those excluded from the web
posting of this application. If the applicant does not have a project accountant indicate how you
intend to solicit project management support.
The City employs a bookkeeper to manage city finances. The City’s engineering consultant and
hydro project manager also directly review all pay requests from construction contractors /
suppliers.
3.7 Financial Accounting System
Discuss the accounting system that will be used to account for project costs and whom will be the
primary user of the accounting system.
All construction pay requests are first routed to the Engineer, who reviews the request for
consistency with the construction contract and technical status and adequacy of work completed.
The engineer makes a recommendation for payment or revision of the pay request as appropriate.
The pay request then goes to the hydro project manager for review and approval, and is then
forwarded to the City’s bookkeeper for final processing. The city uses QuickBooks accounting
software.
3.8 Financial Management Controls
Discuss the controls that will be utilized to ensure that only costs that are reasonable, ordinary and
necessary will be allocated to this project. Also discuss the controls in place that will ensure that
no expenses for overhead, or any other unallowable costs will be requested for reimbursement
from the Renewable Energy Fund Grant Program.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 11 of 24 7/2/14
The cost review process for project construction is summarized in section 3.7 above. The city’s
engineer and hydro project manager are both familiar with the RE grant rules and will review
submittals for consistency with grant program rules before they are submitted to AEA.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 12 of 24 7/2/14
SECTION 4 – PROJECT DESCRIPTION AND TASKS
The level of information will vary according to phase(s) of the project you propose to undertake
with grant funds.
If some work has already been completed on your project and you are requesting funding for an
advanced phase, submit information sufficient to demonstrate that the preceding phases are
satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project. For pre-construction applications, describe
the resource to the extent known. For design and permitting or construction projects, please
provide feasibility documents, design documents, and permitting documents (if applicable) as
attachments to this application.
The hydro project will be a run-of-river project located between falls 4 and falls 2 on Indian River.
The project will have a design flow of 50 cfs, gross head of 64.5 feet, and installed capacity of 180
kW. The project will have a capacity factor of 76.2%, average total annual generation of 1,169,000
kWh, and would supply 90+% of Tenakee’s existing electric load of 427,000 kWh. The project
provides significant margin for load growth and/or space heating applications in the community.
The project design drawings, permits, and feasibility study have been submitted to AEA, and are
also available upon request. Permits issued for the project, final design drawings, and other
pertinent documents are included with this application in Attachment G.
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about the
number, size, age, efficiency, and type of generation.
Basic configuration of the existing system is 3 diesel electric generators; 2- 88kW peak and 1-
66kW peak capacity installed in 2007 by AEA Rural Power System Upgrade with new switchgear.
The existing system has an efficiency of about 13 kWh per gallon of fuel. Electricity is distributed
throughout the community via an overhead three phase distribution system.
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of
any impact the project may have on existing energy infrastructure and resources.
Tenakee currently relies 100% on diesel fuel for electric generation. Other energy resources
include gas/diesel for transportation (primarily for local boats / skiffs / ATVs), and a combination of
wood and fuel oil for space and water heating. Many residents use the geothermal hot springs /
bath house for bathing - the bath house is a focal point of the community.
This project will displace approximately 90% of the diesel fuel used for electricity generation.
Significant additional fuel oil or wood used for space heating can also be displaced by this project.
No transportation fuels are expected to be displaced, although electric ATVs / mopeds could be an
appropriate technology for Tenakee.
4.2.3 Existing Energy Market
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 13 of 24 7/2/14
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
Electricity is used in residential homes, commercial businesses, city buildings, streetlights, and
docks, and the school building. This project will have a profound beneficial impact by lowering
energy costs and making the use of electrical energy for heating of public buildings feasible.
Lower and more stable energy prices will tend to increase electrical demand on the system.
Commercial enterprises in Tenakee Springs particularly suffer under the current energy costs,
because they are not eligible for PCE subsidized rates. Lower energy costs will help to encourage
commercial activity in the community, which will tend to increase electrical demand.
4.3 Proposed System
Describe the system you are intending to develop and address potential system design, land
ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
• A description of renewable energy technology specific to project location
• Optimum installed capacity
• Anticipated capacity factor
• Anticipated annual generation
• Anticipated barriers
• Basic integration concept
• Delivery methods
The project is a run-of-river hydroelectric project with major elements listed below. Please also
reference the final design drawings included in Attachment G.
1. A concrete diversion / intake structure with a design headwater elevation of 124.0 feet and
design flow of 50 feet per second. The structure is co-located with an existing U.S. Forest
Service fish pass at the top of falls 4. The structure includes modifications to the fishpass to
maintain and enhance its functionality.
2. A 1,700 foot long, 36” diameter HDPE penstock installed on a bench down the east bank of
Indian River.
3. A powerhouse with a variable flow cross-flow turbine coupled to a three-phase synchronous
generator via a gear box speed increaser. Switchgear and controls will automatically dispatch
the hydro or diesel power plant based on water availability. The rated tailwater elevation is
59.5 feet, for total gross head of 64.5 feet and net operating head at full design flow of 55.7
feet.
4. 4,300 feet of new distribution voltage power line from the hydro power house to the city’s
existing distribution system near the small boat harbor.
The project’s installed capacity is 180 kW, with a capacity factor of 76.2%. Annual energy
generation capability is approximately 1,169,000 kWh. When the diesels need to run, the controls
will run them at optimal loadings to the extent practical to maintain high fuel economy and avoid
wet stacking or other adverse operating conditions.
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the project
or how you intend to approach land ownership and access issues.
The project will be located on a combination of city and state land, and access to the project is via
the city-owned log transfer facility and an existing US Forest Service logging road.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 14 of 24 7/2/14
1. The city has a long-term road use permit from the U.S. Forest Service authorizing use of the
logging road for project construction, operations and maintenance.
2. The city has an easement for the portions of the project located on state land (ADL 108047).
3. The city owns portions of the power-line route between the hydro powerhouse and harbor. A
utility easement will be dedicated and recorded for the power line once the line is installed and
an as-built survey has been completed.
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
• List of applicable permits
• Anticipated permitting timeline
• Identify and discuss potential barriers
All permits for the project are in place. Major permits are:
1. FERC Finding of Non-Jurisdiction (DI10-8-000)
2. Fish habitat permit (FH11-I-0125)
3. Water use permit (LAS 27836)
4. U.S. Corps of Engineers Environmental Permit (2010-0758 NWP-39)
5. State Land Easement for project lands (ADL 108047)
6. Road Use Permit from U.S. Forest Service
7. A SWPPP will be prepared and filed with ADEC prior to commencing Phase 2 construction
activities.
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will be
addressed:
• Threatened or endangered species
• Habitat issues
• Wetlands and other protected areas
• Archaeological and historical resources
• Land development constraints
• Telecommunications interference
• Aviation considerations
• Visual, aesthetics impacts
• Identify and discuss other potential barriers
This project is in the construction phase and all environmental issues have been addressed.
Threatened or endangered species. Consulted with applicable agencies, no affected species in
area.
Habitat issues. Fisheries issues addressed by Fish Habitat permit with in-stream flow reservations
and post construction monitoring requirements. Project includes enhancements to fish pass to
improve fish passage for coho salmon planted into Indian River by US Forest Service in late
1990s.
Wetlands. Project authorized by Corps of Engineers under Nationwide Permit 39.
Archeological. Cultural resources survey completed in 2012, project follows archeologist’s
recommendations for a finding of “no historic properties affected”.
Land development constraints. None applicable.
Telecomm Interference. None applicable.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 15 of 24 7/2/14
Aviation considerations. None applicable.
Visual, aesthetic impacts. Project site is not frequented by the public and is not visible from
commonly used vantage points – none applicable.
Other potential barriers. None.
4.4 Proposed New System Costs and Projected Revenues
(Total Estimated Costs and Projected Revenues)
The level of cost information provided will vary according to the phase of funding requested and
any previous work the applicant may have done on the project. Applicants must reference the
source of their cost data. For example: Applicants records or analysis, industry standards,
consultant or manufacturer’s estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of
the project. Cost information should include the following:
• Total anticipated project cost, and cost for this phase
• Requested grant funding
• Applicant matching funds – loans, capital contributions, in-kind
• Identification of other funding sources
• Projected capital cost of proposed renewable energy system
• Projected development cost of proposed renewable energy system
Total estimated construction cost is $4,297,280. Requested grant funding is $977,000. Existing
project funding in place is $3,320,000, of which $578,349 was spent to complete Phase 1
construction, leaving $2,741,651 in funds currently available for the project.
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by the
applicant.
(Note: Operational costs are not eligible for grant funds however grantees are required to meet
ongoing reporting requirements for the purpose of reporting impacts of projects on the communities
they serve.)
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
• Identification of potential power buyer(s)/customer(s)
• Potential power purchase/sales price - at a minimum indicate a price range
• Proposed rate of return from grant-funded project
Not applicable. All power will be sold to existing customers of Tenakee Springs Electric
Department. Utility rates will be based on utility operating costs with the hydro plant in service.
Existing rates are approximately $0.74/kWh. Projected fuel savings from the hydro project would
support reducing rates to approximately $0.43/kWh. Rates are set by the city council.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 16 of 24 7/2/14
4.4.4 Project Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered in
evaluating the project.
Please fill out the form provided below.
Renewable Energy Source Indian River
The Applicant should demonstrate that the renewable energy resource is available on a
sustainable basis.
Annual average resource availability. Run of River hydropower. plant capacity factor of 76.2%
Unit depends on project type (e.g. windspeed, hydropower output, biomass fuel)
Existing Energy Generation and Usage
a) Basic configuration (if system is part of the Railbelt1 grid, leave this section blank)
i. Number of generators/boilers/other Three diesel generators
ii. Rated capacity of generators/boilers/other 2 – 88 kW, 1 – 64 kW.
iii. Generator/boilers/other type --
iv. Age of generators/boilers/other All were commissioned in 2006. ~8 years old.
v. Efficiency of generators/boilers/other 13.3 kWh/gal, based on 2012-13 data.
b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank)
i. Annual O&M cost for labor $42,000 (estimated, total 2012-13 non-fuel expense of $83k)
ii. Annual O&M cost for non-labor $41,000 (estimated)
c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the
Railbelt grid, leave this section blank)
i. Electricity [kWh] 427,102 kWh (2012-13, PCE report)
ii. Fuel usage
Diesel [gal] 31,987 (2012-13, PCE report)
Other --
iii. Peak Load Approx 100 – 120 kW (estimated)
iv. Average Load 48 kW (2012-13, PCE report)
v. Minimum Load Approx 20 kW (estimated)
vi. Efficiency 13.3 kWh/gal (2012-13, PCE report)
vii. Future trends Recent trend is for flat load growth, future is projected to be flat to increasing
due to lower rates.
d) Annual heating fuel usage (fill in as applicable)
i. Diesel [gal or MMBtu] 6,500 gallons displaced by excess hydro electricity
1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric
Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 17 of 24 7/2/14
ii. Electricity [kWh] Unknown any usage is included in utility totals at c.i
iii. Propane [gal or MMBtu] Unknown.
iv. Coal [tons or MMBtu] None.
v. Wood [cords, green tons, dry tons] 24 cords per year (estimate)
vi. Other Unknown.
Proposed System Design Capacity and Fuel Usage
(Include any projections for continued use of non-renewable fuels)
a) Proposed renewable capacity
(Wind, Hydro, Biomass, other)
[kW or MMBtu/hr]
180 kW installed capacity – run of river hydro with 76.2%
capacity factor.
b) Proposed annual electricity or heat production (fill in as applicable)
i. Electricity [kWh] Approximately 1,169,000 kWh annually.
ii. Heat [MMBtu] --
c) Proposed annual fuel usage (fill in as applicable)
i. Propane [gal or MMBtu] --
ii. Coal [tons or MMBtu] --
iii. Wood or pellets [cords, green tons,
dry tons]
--
iv. Other --
Project Cost
a) Total capital cost of new system $4,297,280
b) Development cost $229,000 (design and permitting)
c) Annual O&M cost of new system $10,000 (incremental cost of hydro plant operations
and diesel plant operations). Other utility costs
assumed unchanged. $30,000 annual payment into
sinking fund for long-term hydro repair and
replacement costs.
d) Annual fuel cost $0 for water.
$9,900 for fuel for diesel generators.
Project Benefits
a) Amount of fuel displaced for
i. Electricity 30,000 gallons
ii. Heat 6,500 gallons
iii. Transportation None.
b) Current price of displaced fuel $4.78 gallon (2012-13 average)
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 18 of 24 7/2/14
c) Other economic benefits Improved function of fish passage at Indian River.
d) Alaska public benefits $150,000 annually in avoided utility fuel cost (at projected
2015 price), estimated 36,500 fewer gallons of fuel
products being shipped by barge through the waters of
Southeast Alaska to Tenakee Springs. Also projected
reduced annual PCE program expense of $52,500
($0.22/kWh x 238,739 eligible kWh).
Power Purchase/Sales Price
a) Price for power purchase/sale Estimated at $0.43/kWh, will depend on final project
cost, operations cost, and city council approval of
rates.
Project Analysis
a) Basic Economic Analysis
Project benefit/cost ratio $5.73M / $4.06M = 1.41 (R8 AEA/ISER Model)
Payback (years) $4.297M / $182,500 = simple payback 23.5 years at projected 2015
fuel prices (AEA/ISER model)
4.4.5 Impact on Rates
Briefly explain what if any effect your project will have on electrical rates in the proposed benefit
area. If the is for a PCE eligible utility please discuss what the expected impact would be for both
pre and post PCE.
The project will decrease the utility’s fuel expense by an estimated $150,000 annually (at projected
30,000 gallons x $5/gal cost). Impact to non-fuel costs are estimated at an increase of $10,000,
consisting of hydro plant operating costs and reduced diesel plant operating costs. Also setting
aside $30,000 annually for a sinking fund for the hydro plant, the net result is a projected savings
of $110,000 annually. This savings divided by total kWh sales of 360,337 (2012-13) results in
$0.31/kWh of potential rate reduction before PCE is considered, for a projected rate of $0.74 –
0.31 = $0.43/kWh.
With the above assumptions, the PCE subsidy level is projected to decrease from $0.47/kWh to
$0.22/kWh. This is based on the following utility expenses: sinking fund expense of $30,000; other
non-fuel expenses increasing $10,000 to $93,069; and continuing fuel purchase of $9,900; for total
expenses of $132,969. With flat demand of 360,337 kWh sales, these utility expenses are
$0.37/kWh sold. Subtracting the PCE base rate ($0.1482/kWh) and multiplying by 0.95 yields the
projected PCE subsidy level of approximately $0.21/kWh with the hydro project in service. The
eligible PCE rate is thus projected to decrease from $0.27/kWh (2013) to $0.43 – 0.21 =
$0.22/kWh.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 19 of 24 7/2/14
SECTION 5– PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings, and
how the people of Alaska will benefit from the project.
The benefits information should include the following:
• Potential annual fuel displacement (gallons and dollars) over the lifetime of the evaluated
renewable energy project
• Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price, RCA
tariff, or cost based rate)
• Potential additional annual incentives (i.e. tax credits)
• Potential additional annual revenue streams (i.e. green tag sales or other renewable energy
subsidies or programs that might be available)
• Discuss the non-economic public benefits to Alaskans over the lifetime of the project
1. Projected annual fuel displacement is 30,000 gallons for the diesel power plant and 6,500+
gallons by displacing heating oil. Annual value is $182,500 at projected 2015 prices.
2. Annual utility revenues are projected to be $155,000, based on projected flat sales of 360,337
kWh, and a base rate of $0.43/kWh.
3. The utility is not aware of any applicable tax credits related to this project.
4. The utility does not intend to pursue other revenue streams beyond electricity sales.
5. Non economic public benefits include:
(a) Less noise and air pollution in the community (diesel generators would not be running most of
the time) enhancing the health and quality of life for residents and making Tenakee a more
desirable place to live.
(b) reduced haulage and handling of 36,500+ gallons of petroleum products through the waters of
Southeast Alaska annually. Reduced potential for spills and environmental contamination.
(c) stable and more affordable electricity costs will also make Tenakee a more desirable place to
live, and will help to attract local economic activity such as tourism, fishing, etc. The hydro
combined with the hot springs will bolster the sustainability of the community for the long term.
(d) Commercial enterprises in Tenakee in particular will benefit from lower energy costs. Lower
energy costs will make local businesses such as stores, restaurants, and lodges more viable
and competitive and will increase Tenakee's sustainability and long term viability as a
community. Tenakee has struggled in recent years to attract and retain working families with
children to keep the local school open. Affordable energy, and the local economic activity it will
encourage and support, will help considerably in our long term efforts to help the community
thrive.
5.1 Public Benefit for Projects with Private Sector Sales
Projects that include sales of power to private sector businesses (sawmills, cruise ships, mines,
etc.), please provide a brief description of the direct and indirect public benefits derived from the
project as well as the private sector benefits and complete the table below. See section 1.6 in the
Request for Applications for more information.
Renewable energy resource availability (kWh per month) N/A
Estimated sales (kWh) N/A
Revenue for displacing diesel generation for use at
private sector businesses ($)
N/A
Estimated sales (kWh) N/A
Revenue for displacing diesel generation for use by the
Alaskan public ($)
N/A
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 20 of 24 7/2/14
SECTION 6– SUSTAINABILITY
Discuss your plan for operating the completed project so that it will be sustainable.
Include at a minimum:
• Proposed business structure(s) and concepts that may be considered.
• How you propose to finance the maintenance and operations for the life of the project
• Identification of operational issues that could arise.
• A description of operational costs including on-going support for any back-up or existing
systems that may be require to continue operation
• Commitment to reporting the savings and benefits
The city electric utility will be responsible for operation and maintenance of the hydro project once
it is completed. O&M costs would be covered by the utility’s electric rates and revenues. O&M
costs are estimated at $0.02 per kWh. The city also anticipates establishing a sinking fund for the
project funded from utility revenues to pay for long-term operating, maintenance, repair and
replacement expenses for the project.
Operational costs will include periodic cleaning of the diversion and intake structure (clearing logs
and debris), scheduled maintenance and overhauls of the turbines, generators, and ancillary
equipment and related hydro project operations such as seasonal adjustment of settings at the
intake to allow for winter vs. summer operations.
The City of Tenakee Springs commits to reporting the savings and benefits associated with the
Indian River Hydroelectric Project.
SECTION 7 – READINESS & COMPLIANCE WITH OTHER GRANTS
Discuss what you have done to prepare for this award and how quickly you intend to proceed with
work once your grant is approved.
Tell us what you may have already accomplished on the project to date and identify other grants
that may have been previously awarded for this project and the degree you have been able to
meet the requirements of previous grants.
The City of Tenakee Springs has been actively advancing this project through the study, permitting
and design process since 2009. This has included the successful completion of one prior hydro
study grant, completing permitting and design, and successfully completing Phase 1 of project
construction, which has provided easy access to the project site for prospective contractors and
improved understanding of geotechnical conditions, which was used to complete project designs
The city is looking forward to commencing Phase 2 construction and completing the project in
2015. The city anticipates starting procurement for long-lead items this fall.
SECTION 8 – LOCAL SUPPORT AND OPPOSITION
Discuss local support and opposition, known or anticipated, for the project. Include letters of
support or other documentation of local support from the community that would benefit from this
project. The Documentation of support must be dated within one year of the RFA date of July 2,
2014
The project is included in the Southeast Regional Integrated Resource Plan (IRP) prepared for
AEA in 2012. Several local entities have previously provided letters of support for the project,
which are included in Attachment B. Renewed support letters have been requested and will be
provided to AEA when available.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 21 of 24 7/2/14
SECTION 9 – GRANT BUDGET
Tell us how much you are seeking in grant funds. Include any investments to date and funding
sources, how much is being requested in grant funds, and additional investments you will make as
an applicant.
9.1 Funding Sources and Financial Commitment
Provide a narrative summary regarding funding source and your financial commitment to the
project
The City of Tenakee Springs is requesting a grant of $977,280 to complete construction of the
Indian River Hydroelectric Project. Since 2009, the Denali Commission, State of Alaska, and City
of Tenakee Springs have committed $354,000 in pre-construction funds and $3.32 million in
construction funds to complete this project. This includes $51,000 in matching funds and in-kind
contributions from the City of Tenakee Springs, plus significant additional in-kind contributions from
numerous residents of Tenakee Springs. The City Council has passed several unanimous
resolutions supporting this project over the past several years.
The city and its residents will continue to provide matching funds and in-kind services to see this
important project successfully completed.
9.2 Cost Estimate for Metering Equipment
Please provide a short narrative, and cost estimate, identifying the metering equipment, and its
related use to comply with the operations reporting requirement identified in Section 3.15 of the
Request for Applications.
Hydro plant switchgear specifications include the ability to export electronic reports that will meet
the requirements of section 3.15 of the RFA. Since this capability is to be integrated into the new
switchgear, no additional hardware cost is expected to meet this requirement. Automated export of
data from the switchgear to AEA may not be practical, but routine email of data files is readily
achievable.
Preparation of annual operating reports meeting the requirements of RFA Section 3.15 is
estimated to cost the utility $3,000 per year in staff time.
Renewable Energy Fund Round VIII
Grant Application - Standard Form
AEA 15003 Page 22 of 24 7/2/14
Applications MUST include a separate worksheet for each project phase that was identified in
section 2.3.2 of this application, (I. Reconnaissance, II. Feasibility and Conceptual Design, III. Final
Design and Permitting, and IV. Construction and Commissioning). Please use the tables provided
below to detail your proposed project’s budget. Be sure to use one table for each phase of your
project.
Milestone or Task
Anticipated
Completion
Date
RE- Fund
Grant
Funds
Grantee
Matching
Funds
Source of Matching
Funds:
Cash/In-kind/Federal
Grants/Other State
Grants/Other
TOTALS
Issue Final Construction
Drawings for Agency Review Sept 22, 2014 $0 $0 $0
Receive Agency Review
Comments Oct. 6, 2014 $0 $0 $0
Finalize, Phase 2 construction
issue bid documents Oct. 13, 2014 $3,000 $7,000 Exist. Funds/Cash / In-kind $10,000
Select vendors/contractors
and award contracts Nov. 17, 2014 $3,000 $7,000 Exist. Funds/Cash / In-kind $10,000
Construction Management Dec. 31, 2015 $32,000 $88,000 Exist. Funds/Cash / In-kind $120,000
Construction Engineering /
Inspection Dec. 31, 2015 $22,600 $103,400 Exist. Funds/Cash / In-kind $126,000
Phase 1 Construction
Access Roads and Trails July 15, 2014 $0 $564,880 (completed) $564,880
Phase 2 Construction Nov. 2014 –
Dec. 2015
Surveys Dec. 31, 2015 $8,000 $22,000 Exist. Funds/Cash / In-kind $30,000
Power Line Jul. 31, 2015 $108,400 $303,000 Exist. Funds/Cash / In-kind $411,400
Diversion, Intake, Fishpass Aug. 31, 2015 $168,000 $468,000 Exist. Funds/Cash / In-kind $636,000
Penstock Jun. 30, 2015 $285,000 $795,000 Exist. Funds/Cash / In-kind $1,080,000
Powerhouse Sep. 30, 2015 $98,000 $272,000 Exist. Funds/Cash / In-kind $370,000
Turbine / Generator Oct. 31, 2015 $73,000 $203,000 Exist. Funds/Cash / In-kind $276,000
Switchgear / Controls Oct. 31, 2015 $42,000 $118,000 Exist. Funds/Cash / In-kind $160,000
Construction Contingency Dec. 31, 2015 $118,000 $327,000 Exist. Funds/Cash / In-kind $445,000
Project Startup and
Commissioning Nov. 30, 2015 $14,000 $38,000 Exist. Funds/Cash / In-kind $52,000
O&M Manual Dec. 31, 2015 $2,000 $4,000 Exist. Funds/Cash / In-kind $6,000
Operations Reporting to AEA Dec. 31, 2026 Future utility rates
TOTALS $977,000 $3,320,280 $4,297,280
Budget Categories:
Direct Labor & Benefits $0 $0 $0
Travel & Per Diem $0 $0 $0
Equipment $99,126 $336,874 $436,000
Materials & Supplies $0 $0 $0
Contractual Services $61,840 $210,160 $272,000
Construction Services $714,862 $2,429,418 $3,144,280
Other $101,172 $343,828 $445,000
TOTALS $977,000 $3,320,280 $4,297,280