Loading...
HomeMy WebLinkAboutLPBWoodBoilerBudgetITEM COST NOTES Personnel $15,000.00 Operators  -­‐  100  hours Laborers  -­‐  50  hours Project  Lead  -­‐  30  hours Subcontractors $8,000.00 Electrical  and  Plumbing Equipment $2,500.00 Boiler  &  Heating  Equipment $50,000.00 The  Garn  Jr.  Unit  $14,000 The  Chemical  Treatment  Pkg  $500 Shipping  from  Minnesota  to  Villages  $8,000 Misc.  Supplies  $7,500 Metal  Stud  Frame  &  Insulation  -­‐  opt.  $20,000 $75,500.00 Markup  (O/H  &  P)  20%$15,100.00 Contingency  @  10%$7,550.00 Total  for  1  community $98,150.00 Independent  Proposal  Reviewer  &  Project  Inspector $15,000.00 Grand  Project  Total  for  PTA,  NON,  and  PDB $309,450.00 Lake  and  Peninsula  Wood  Boiler  Construction  Project Master  Budget AEA  Renewable  Energy  Fund  Round  VIII  Application