HomeMy WebLinkAboutGrantApplication7 REV - Adak WindRenewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Application Page 1 of 22 7/2/2013 SECTION 1 – APPLICANT INFORMATION Name (Name of utility, IPP, or government entity submitting proposal) City of Adak, Alaska Type of Entity: Local Government Fiscal Year End: June 30, 2013 Tax ID # 920175821 Tax Status: For-profit Non-profit X Government ( check one) Date of last financial statement audit: Council Certified Financials FY 12 Mailing Address PO Box 2011 Adak, AK 99546-2011 Physical Address 100 Mechanics Way Adak, AK 99546 Telephone 907-592-4500 Fax (907) 592-4262 Email llockett@adak-ak.gov 1.1 APPLICANT POINT OF CONTACT / GRANTS MANAGER Name Mr. Layton J. Lockett Title City Manager Mailing Address PO Box 2011 Adak, AK 99546-2011 Telephone (907) 592-4500 Fax (907) 592-4262 Email llockett@adak-ak.gov 1.2 APPLICANT MINIMUM REQUIREMENTS Please check as appropriate. If you do not to meet the minimum applicant requirements, your application will be rejected. 1.2.1 As an Applicant, we are: (put an X in the appropriate box) An electric utility holding a certificate of public convenience and necessity under AS 42.05, or An independent power producer in accordance with 3 AAC 107.695 (a) (1), or X A local government, or A governmental entity (which includes tribal councils and housing authorities); Yes 1.2.2 Attached to this application is formal approval and endorsement for the project by the applicant’s board of directors, executive management, or other governing authority. If the applicant is a collaborative grouping, a formal approval from each participant’s governing authority is necessary. (Indicate Yes or No in the box ) Yes 1.2.3 As an applicant, we have administrative and financial management systems and follow procurement standards that comply with the standards set forth in the grant agreement (Section 3 of the RFA). Yes 1.2.4 If awarded the grant, we can comply with all terms and conditions of the award as identified in the Standard Grant Agreement template at http://www.akenergyauthority.org/veep/Grant-Template.pdf. (Any exceptions should be clearly noted and submitted with the application.) Yes 1.2.5 We intend to own and operate any project that may be constructed with grant funds for the benefit of the general public. If no please describe the nature of the project and who will be the primary beneficiaries. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 2 of 22 7/1/2013 SECTION 2 – PROJECT SUMMARY This section is intended to be no more than a 2-3 page overview of your project. 2.1 Project Title – (Provide a 4 to 7 word title for your project). Type in space below. Adak Wind Data Collection, Analysis, and Preliminary Design 2.2 Project Location – Include the physical location of your project and name(s) of the community or communities that will benefit from your project in the subsections below. Adak Island, City of Adak, Alaska 2.2.1 Location of Project – Latitude and longitude, street address, or community name. Latitude and longitude coordinates may be obtained from Google Maps by finding you project’s location on the map and then right clicking with the mouse and selecting “What is here? The coordinates will be displayed in the Google search window above the map in a format as follows: 61.195676.-149.898663. If you would like assistance obtaining this information please contact AEA at 907-771-3031. Project wind field study location coordinates 51.843900 degrees and latitude 176.677548 longitude. 2.2.2 Community benefiting – Name(s) of the community or communities that will be the beneficiaries of the project. City of Adak 2.3 PROJECT TYPE Put X in boxes as appropriate 2.3.1 Renewable Resource Type X Wind Biomass or Biofuels (excluding heat-only) Hydro, Including Run of River Hydrokinetic Geothermal, Excluding Heat Pumps Transmission of Renewable Energy Solar Photovoltaic Storage of Renewable Other (Describe) Small Natural Gas 2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply) Pre-Construction Construction Reconnaissance Final Design and Permitting X Feasibility and Conceptual Design Construction and Commissioning Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 3 of 22 7/1/2013 2.4 PROJECT DESCRIPTION Provide a brief one paragraph description of the proposed project. The proposed project is for wind field data collection, analysis and preliminary engineering design. Wind field data collection will require a one year collection period as recommended by AEA for location of wind generators. The wind data will be analyzed and used for the design of the wind generators and related facilities. The City of Adak has completed a hydroelectric power feasibility analysis and preliminary engineering prepared by McMillen LLC. The report recommends hydro – wind generation with pump storage development project that includes hydroelectric power generation, raising the Lake Bonnie Rose and Lake DeMarie dams, construction of the penstock, powerhouse (2 MW hydro), transmission lines, wind generation (4.5 MW), wind pump from L. DeMarie to L. Bonnie Rose storage, and associated facilities. Both lakes are in the same watershed. The hydro - wind generation with pump storage project will supply hydro and wind generated power to the community as well as pump water to the higher elevation Lake Bonnie Rose to store potential energy for conversion into hydropower generation to the community to meet demand (a buffering effect). The next step in the development process is wind field data collection and analysis to design the wind generation system. The hydropower feasibility component and preliminary engineering design is complete in the McMillen report. 2.5 PROJECT BENEFIT Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel costs, lower energy costs, local jobs created, etc.)  The existing residential and commercial cost of electric power averages $1.24 / kWh. The existing diesel generating equipment is not properly sized for base loads, inefficient with high operating cost, and near the end of its useful life. The total existing generation capacity is less than 800 kWh and unable to meet existing residential and commercial demand. The Icicle Seafood plant recently closed due to the cost of power and lack of capacity to meet plant demand. The implementation of the hydro / wind pump storage project will reduce the cost of electric power to the $0.17 to $0.21 range at 2MW power utilization. Under the existing system, the cost of power will greatly diminish the economic ability of the community to survive. Low cost power in combination with the major infrastructure assets (over $4.5 billion in past federal investments) of Adak offers major economic development opportunities for Adak to become a major economic growth center for the region and the State. The Aleut Corporation and the City have recently completed negotiations with a major seafood processing firm (Adak Cod Cooperative) to operate the existing seafood plant. The prospect of low cost power is a major factor in the seafood firm’s interest in operating a plant at Adak. The development of the proposed project will eliminate the power cost equalization payments by the State resulting in annual savings of $290,795 (PCE FY12) to the State or a future value of $7,059,000 (8% compounded monthly for 40 years). Without implementation of the proposed project, the annual PCE costs will continue to escalate as diesel fuel costs increase and as the existing generator continues to fail. Using FY 2012 AEA data of 2,682,173 kWh sold at the average rate of $1.24 per kWh equals $3,325,895 in total power cost to the community. Many of the industrial and commercial power users self-generated and that energy is not included in the FY 2012 data. Furthermore with rates at and above $1.24/kWh, residents are highly considering and planning for self-generation. With implementation of the proposed project using the FY 2012 kWh power sold data and the projected rate of $0.21 per kWh, the annual power cost to the community is estimated at $563,256. The annual total power cost savings to the community with the hydro wind pump storage project is estimated at $2,762,638 based on FY 2012 data. The estimated future value of the cost savings over the 40 year expected life of the project is estimated at over $67.0 million. This estimate is conservative because at lower cost per kWh, residents will use considerably more power and switch from self-generation to the community grid, and major commercial users such as the seafood plant will switch from self-generation to the grid. Further, value added seafood Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 4 of 22 7/1/2013 processing under the current cost per kWh is not economically feasible. With lower cost power, expansion of the seafood processing industry is economically viable. The future value of cost savings by replacing the current power system with the proposed project is approximately 2 to 3 times greater than the above conservatively estimated future value of savings. With low cost energy, other potentially industries identified in the federally funded Adak Economic Adjustment Strategy can be attracted to Adak. Seafood processing expansion and other potential industries will create new jobs and income in the region and the State. 2.6 PROJECT BUDGET OVERVIEW Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source of other contributions to the project. The cost of the proposed project, wind field data collection, analysis, and preliminary engineering design, is estimated at $160,000. The City has not established a capital project budget for the FY 2015 (award date) and is unable to provide matching funds at this time. Prior to the August 1, 2014 AEA award date, the City will provide a cash match as well as in-kind services including grant administration and equipment for the installation of the wind data collection. Implementation of the total hydro wind pump storage project is estimated at $72.4 million including replacement of the diesel generators (backup to hydro / wind generation), update of the community grid, and the hydro / wind generation / pump storage system. The total development project will be financed by federal grants and loans, potential state investment, city bonds, etc. The hydropower feasibility study with preliminary engineering design was financed in part by a federal grant with City cash match funds. 2.7 COST AND BENEFIT SUMARY Include a summary of grant request and your project’s total costs and benefits below. Grant Costs (Summary of funds requested) 2.7.1 Grant Funds Requested in this application $160,000.00 2.7.2 Cash match to be provided $0 2.7.3 In-kind match to be provided $ 2.7.4 Other grant funds to be provided $ 2.7.5 Other grant applications not yet approved $ 2.7.6 Total Grant Costs (sum of 2.7.1 through 2.7.4) $160,000.00 Project Costs & Benefits (Summary of total project costs including work to date and future cost estimates to get to a fully operational project) 2.7.7 Total Project Cost Summary from Cost Worksheet, Section 4.4.4, including estimates through construction. $72,400,000.00 2.7.8 Additional Performance Monitoring Equipment not covered by the project but required for the Grant Only applicable to construction phase projects. $ NA 2.7.9 Estimated Direct Financial Benefit (Savings) $ $167.5 million (Future Value) 2.7.10 Other Public Benefit If you can calculate the benefit in terms of dollars please provide that number here and explain how you calculated that number in Section 5 below. $ See Section 5 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 5 of 22 7/1/2013   SECTION 3 – PROJECT MANAGEMENT PLAN Describe who will be responsible for managing the project and provide a plan for successfully completing the project within the scope, schedule and budget proposed in the application. 3.1 Project Manager Tell us who will be managing the project for the Grantee and include contact information, a resume and references for the manager(s). In the electronic submittal, please submit resumes as separate PDFs if the applicant would like those excluded from the web posting of this application. If the applicant does not have a project manager indicate how you intend to solicit project management support. If the applicant expects project management assistance from AEA or another government entity, state that in this section. The Project Manager is Layton J. Lockett, Adak City Manager (PO Box 2011, Adak, AK 99546; 907-592-4500; and llockett@adak-ak.gov). Mr. Lockett has Bachelor and Master Degrees in Business Management (University of Alaska, Anchorage and LaSalle University, Philadelphia, Pennsylvania). He currently holds the positions of: Adak City Manager since 2010; Vice-President & Board Member of the Adak Community Development Corporation; Treasurer & Board Member of the Southwest Alaska Municipal Conference; and Managing Member of the 100 Knot Stop, LLC (Adak, Alaska). In these positions, Mr. Lockett has implemented a new Adak city accounting system, managed numerous federal, state, and local grants, managed the municipal budget, resolved requirements outlined by the State of Alaska to ensure grant and financial compliance, supervised 19 City employees, played a key role in retaining the closed seafood plant’s equipment in the community, engaged on the negotiation team in attracting Adak Cod Cooperative to operate the seafood plant, and engaged in numerous other municipal and economic development activities on behalf of the City. 3.2 Project Schedule and Milestones Please fill out the schedule below. Be sure to identify key tasks and decision points in in your project along with estimated start and end dates for each of the milestones and tasks. Please clearly identify the beginning and ending of all phases of your proposed project. This project schedule is limited to the Wind Feasibility and Conceptual Design Component. Please fill out form provided below. You may add additional rows as needed. Milestones Tasks Start Date End Date Grant Award 08/14 08/14 Develop Engineering Services scope & RFQ for proposed project Prepare RFQ and advertise competitive procurement 08/02/14 08/15/14 Award Engineering Services Contract for the proposed project Evaluation and selection of most qualified engineering firm 09/10/14 09/15/14 Erect wind data collection equipment Contractor procures equipment, ships, and installs equipment at wind field site 10/15/14 11/15/14 Progress reporting Monthly written and teleconference reports 09/15/14 02/29/16 Monitor wind data collection Data collection, monitor equipment performance, repairs as necessary, and initial analyses 11/15/14 11/15/15 Data Analyses - Permitting and environmental analysis Wind data analyses including wind speeds, operating duration, energy generation potential, permitting & environmental issues, and other design criteria to initiate preliminary engineering 11/15/15 12/31/15 Preliminary engineering design- cost estimates, regulatory issues & Identify wind generators & capacity, engineering placement, associated equipment, 01/01/16 02/15/16 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 6 of 22 7/1/2013 feasibility analysis access infrastructure, identify issues and problems to be resolved, regulatory issues, integration with hydropower component, and capital and operating costs. Final Report Prepare draft final report for review, incorporate comments, and prepare final reports 02/16/16 02/29/16 3.3 Project Resources Describe the personnel, contractors, accounting or bookkeeping personnel or firms, equipment, and services you will use to accomplish the project. Include any partnerships or commitments with other entities you have or anticipate will be needed to complete your project. Describe any existing contracts and the selection process you may use for major equipment purchases or contracts. Include brief resumes and references for known, key personnel, contractors, and suppliers as an attachment to your application. The City of Adak has implemented a modern financial accounting system that includes trained accounting personnel, financial oversight, accounting software, and routine Council certified financial statements that meet the requirements of the State of Alaska. The City Manager provides day to day oversight of the system with internal controls. Competitive procurement of contract services must meet the requirements of the City procurement policies and procedures (Chapter 4.05 Purchasing) which meet State and federal regulations. The Aleut Corporation is the land owner of the wind field study site. The corporation strongly endorses this proposed project and agrees to provide the land for the wind field project facilities under a no cost lease agreement. The resume of the City Manager is attached. The City of Adak under a federal Economic Development Administration grant has completed a hydropower feasibility study and preliminary engineering analysis. The wind field data collection component was not a component of these analyses. The wind field data collection, analysis and wind generation system preliminary engineering design is the critical next step required to proceed to total project final design. The proposed project will bring the wind component to the pre-final design stage of the hydroelectric component completed by McMillen LLC. 3.4 Project Communications Discuss how you plan to monitor the project and keep the Authority informed of the status. Please provide an alternative contact person and their contact information. The City of Adak has established procedures for monitoring and project communication with the Authority. These procedures includes detailed written monthly progress reports that include reporting on scope of work task completion, problems encountered, interim findings and data results, and other pertinent information. These reports are supplemented with teleconference calls with the selected engineering firm. Personnel of the Authority will receive copies of the monthly reports as well as all required project financial reports. Authority personnel will be invited to participate in the regular project teleconferences and site visits. City internal project communication includes distributing and discussing project reports in the weekly City department staff meetings and routine reporting to the City Council. The City Manager will inform the public on the proposed project in regularly scheduled public meetings. In addition, the project progress reports will be shared with the Adak Community Development Corporation (ACDC). ACDC holds regularly scheduled public meetings that are generally attended by public and private entities with interests at Adak Island. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 7 of 22 7/1/2013 3.5 Project Risk Discuss potential problems and how you would address them. This is a feasibility and conceptual design project with low risks. Potential low risks include the following: The proposed wind field site is on a ridge at 600 feet above sea level. There is rock outcropping on the site. The wind data collection equipment including the equipment towers will be secured with guy wires, attached to the rock. We expect periods of extremely high winds at times at this location. These wind conditions may damage anemometers, data loggers or other monitoring equipment. We propose to minimize this risk by having a regular (weekly and after every storm event) protocol site visits by City staff during the data collection period to insure the system is collecting data properly. SECTION 4 – PROJECT DESCRIPTION AND TASKS  The level of information will vary according to phase(s) of the project you propose to undertake with grant funds.  If some work has already been completed on your project and you are requesting funding for an advanced phase, submit information sufficient to demonstrate that the preceding phases are satisfied and funding for an advanced phase is warranted. 4.1 Proposed Energy Resource Describe the potential extent/amount of the energy resource that is available. Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be available for the market to be served by your project. For pre-construction applications, describe the resource to the extent known. For design and permitting or construction projects, please provide feasibility documents, design documents, and permitting documents (if applicable) as attachments to this application. The proposed renewable energy resources are the use of wind power coupled with hydropower supplemented with wind energy pump storage to store energy (water) at the higher elevation L. Bonnie Rose and using the stored water energy for use at times when the wind resource cannot be used. The amount of wind energy that can be produced is large (4.5MW McMillen Report estimate). The site of the wind field is the ridge just east of Lake DeMarie (about 1.0 miles Southwest of Adak). The McMillen report estimates that three turbines located at the wind field site will produce 1.5 MW of power each. The potential wind resources at the site according to the Renewable Energy Atlas of Alaska for Google Earth generated via modeling is considered “outstanding” at the proposed site. The energy density according to the same atlas is 600-800 W/m2. According to the McMillen hydropower feasibility report, the cost to produce power using hydro / wind with a wind pump storage, diesel backup, and upgraded grid system is $0.21 per kWh at a 2 MW demand (this includes principal and interest loan costs as well as O&M costs including minor use of diesel as a backup source). The hydro component of the project has a generation capacity of 2 MW. The average generating capacity of the total system is 2.5 MW and 8.5 MW peak capacity (hydro, wind, & diesel). An alternative generation system considered is replacement of the existing system by a new efficient diesel based system. The estimated cost for a new diesel generation system to provide this level of power is approximately $0.40 per kWh (2013) under the same cost assumptions. With a diesel system, costs will continue to escalate as fuel prices increase. The hydropower feasibility and preliminary design component of the proposed development is complete. In order to complete the analysis of the proposed total system, the proposed project is required to collect wind data, its analysis, and preliminary design of the wind generation component. With completion of the proposed project, the total project will be able to go to final design and construction. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 8 of 22 7/1/2013 4.2 Existing Energy System 4.2.1 Basic configuration of Existing Energy System Briefly discuss the basic configuration of the existing energy system. Include information about the number, size, age, efficiency, and type of generation. A detailed description of the existing power generation system is provided in the McMillen hydropower feasibility technical report and in an earlier feasibility analysis by TDX Power (2013). The McMillen description includes line diagrams and a detailed description of key components of the system. The system is now limited to a single 800 kW (output) diesel generator. A second 800 kW diesel generator has failed, thereby limiting the total existing capacity to 800 kW. The remaining generator has been in service since 1982 and is near the end of its serviceable life. The power delivery system is old and is showing signs of wear. There have been numerous outages. A reconnaissance evaluation conducted by an electrical engineer for the McMillen feasibility study concluded that the system was near the end of its service life. There are numerous examples of deferred maintenance of the generator and power delivery system. 4.2.2 Existing Energy Resources Used Briefly discuss your understanding of the existing energy resources. Include a brief discussion of any impact the project may have on existing energy infrastructure and resources. According to AEA statistical compilations, a little over 3 million kWh’s were generated in fiscal year 2012. The average load is 344 kWh. According to a TDX feasibility study, there are seasonal peak demands by the fish processing plant of over one (1) MWh. Due to outages and insufficient existing generation capacity, the fish processing plant load is being met offline. This wind energy feasibility and preliminary engineering design project will have no impact on the existing energy infrastructure but the overall project’s goals are to modernize the Adak energy infrastructure with available renewable resources and to lower the cost of energy to all consumers. 4.2.3 Existing Energy Market Discuss existing energy use and its market. Discuss impacts your project may have on energy customers. The existing market is residential, light commercial, industrial, and government use. The fish processing plant that has in the past produced energy offline will become a major customer. . The City has implemented energy austerity measures as energy prices increase. With lower cost energy, the fish processing plant will be able to expand to value added processing. The City will also be able to reduce the austerity measures, thereby ensuring public facilities are in better condition as well as enable readiness for emergency response. Existing residential and commercial customers currently generate off line or implement more extreme conservation methods, detrimental to some, due to the high energy costs. These customers use oil for heat due to current high electric energy costs. A shift in use is expected as energy costs decrease with implementation of the proposed total project. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 9 of 22 7/1/2013 4.3 Proposed System Include information necessary to describe the system you are intending to develop and address potential system design, land ownership, permits, and environmental issues. 4.3.1 System Design Provide the following information for the proposed renewable energy system:  A description of renewable energy technology specific to project location  Optimum installed capacity  Anticipated capacity factor  Anticipated annual generation  Anticipated barriers  Basic integration concept  Delivery methods The total renewable energy system is a hydro / wind generation system with pump storage on a new updated energy grid with new diesel generators as backup. The estimated cost for the entire project is 72.4 million dollars. The estimated base capacity is 2 MW with an average capacity of 2.5 MW based on the pattern of hydro and wind generation and the pattern of demand. Peak capacity is estimated at 8.5 MW. The anticipated average annual generation is 17,520,000 kWh. The McMillen technical report identifies two additional future hydroelectric power development projects with approximately 1 MW of additional capacity. A more detailed analysis of the recommended system and its capital and operating cost is provided in the McMillen Technical Report. The McMillen report executive summary is attached. 4.3.2 Land Ownership Identify potential land ownership issues, including whether site owners have agreed to the project or how you intend to approach land ownership and access issues. The wind field area is owned by The Aleut Corporation. The corporation will lease the land to the City at no cost. No problems are anticipated. The land ownership of the other components of the total project is the City. 4.3.3 Permits Provide the following information as it may relate to permitting and how you intend to address outstanding permit issues.  List of applicable permits  Anticipated permitting timeline  Identify and discussion of potential barriers For the proposed wind study component, we will apply for a FAA permit and if required, we will engage in a USF&WS Section 7 Consultation. There are numerous permits required for the total renewable energy project that are described in detail in the McMillen Technical Report (executive summary attached). Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 10 of 22 7/1/2013 4.3.4 Environmental Address whether the following environmental and land use issues apply, and if so how they will be addressed:  Threatened or endangered species  Habitat issues  Wetlands and other protected areas  Archaeological and historical resources  Land development constraints  Telecommunications interference  Aviation considerations  Visual, aesthetics impacts  Identify and discuss other potential barriers For the proposed AEA wind study project, there are no known threatened, endangered species, or species of concern in the wind field area. Wetlands and other protected areas are not within the wind field location. The University of Alaska Anchorage is conducting ongoing archaeological and historic resource field work and investigations. No known archaeological or historic resource sites are within the wind field study area. The proposed AEA wind field study area is in an undeveloped area with no development constraints. The telecommunications firm at Adak strongly endorses the subject project (see attached letter). We intend to secure a FAA permit for the proposed wind study project. Similarly and if required, a USF&WS Section 7 Consultation will be conducted prior to the start of the proposed AEA wind study project. No visual or aesthetics impact is anticipated for the proposed AEA project. The implementation of the total hydro / wind energy project will address numerous environmental issues including fish habitat. The full sized wind turbines will need to address avian issues. Due to its location away from the airport and the city, other interference issues are not expected or will be minor. The McMillen Technical Report provides details on potential environmental issues and permitting. The cost of permitting is included in the total capital development cost presented herein. 4.4 Proposed New System Costs and Projected Revenues (Total Estimated Costs and Projected Revenues) The level of cost information provided will vary according to the phase of funding requested and any previous work the applicant may have done on the project. Applicants must reference the source of their cost data. For example: Applicants records or analysis, industry standards, consultant or manufacturer’s estimates. 4.4.1 Project Development Cost Provide detailed project cost information based on your current knowledge and understanding of the project. Cost information should include the following:  Total anticipated project cost, and cost for this phase  Requested grant funding  Applicant matching funds – loans, capital contributions, in-kind  Identification of other funding sources  Projected capital cost of proposed renewable energy system  Projected development cost of proposed renewable energy system This grant application is for $160,000 for a wind data collection, analysis, and preliminary engineering design under AEA category Feasibility and Conceptual Design (McMillen cost estimate). The project will provide the wind generation engineering to compliment the hydroelectric engineering completed by McMillen. The combined reports will allow the City to proceed with financing, final design, and Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 11 of 22 7/1/2013 construction. The McMillen report was funded in part by the Economic Development Administration and the City. The total new energy system capital cost is estimated at $72.4 million. It includes replacement of the current energy grid along with new back up diesel generators, the raising of two dam (Lake Bonnie Rose and Lake DeMarie), and the construction of a penstock, hydro turbines, wind turbines, and transmission lines. The McMillen Technical Report provides detailed hydroelectric engineering information about the recommended total energy development (executive summary is attached). 4.4.2 Project Operating and Maintenance Costs Include anticipated O&M costs for new facilities constructed and how these would be funded by the applicant. (Note: Operational costs are not eligible for grant funds however grantees are required to meet ongoing reporting requirements for the purpose of reporting impacts of projects on the communities they serve.) The operation and maintenance costs for the proposed wind study equipment are negligible and are included in the grant application budget. The O&M costs of the total energy development project are estimated at $568,000 (McMillen). The costs will be covered by energy system revenues. 4.4.3 Power Purchase/Sale The power purchase/sale information should include the following:  Identification of potential power buyer(s)/customer(s)  Potential power purchase/sales price - at a minimum indicate a price range  Proposed rate of return from grant-funded project Under the proposed AEA project, there will be no purchase or sale of power (Feasibility and Conceptual Design). Upon implementation of the total renewable energy project, residential, commercial, industrial, and government are the target customers with an average demand of 2 MW in the initial years of operation. The fish processing plant (Adak Cod Cooperative) demand is estimated at 1 MW. Future demand will increase as the fish processing plant expands operations and new economic development projects are completed. 4.4.4 Project Cost Worksheet Complete the cost worksheet form which provides summary information that will be considered in evaluating the project. Please fill out the form provided below. Renewable Energy Source The Applicant should demonstrate that the renewable energy resource is available on a sustainable basis. Annual average resource availability. Estimated 4.5 MW (wind) Estimated 3 MW+ (hydro) Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel) Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 12 of 22 7/1/2013 Existing Energy Generation and Usage a) Basic configuration (if system is part of the Railbelt1 grid, leave this section blank) i. Number of generators/boilers/other 1 ii. Rated capacity of generators/boilers/other 800 kWh iii. Generator/boilers/other type Diesel iv. Age of generators/boilers/other 31 plus years v. Efficiency of generators/boilers/other 10.8 kWh per gallon of diesel (AEA FY12) b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank) i. Annual O&M cost for labor $2.5 million total (AEA FY12) ii. Annual O&M cost for non-labor c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the Railbelt grid, leave this section blank) i. Electricity [kWh] 3,012,311 (generated) 2,682,173 (sold) (AEA FY12) ii. Fuel usage Diesel [gal] 278,867 (AEA FY12) Other iii. Peak Load 700 kW (McMillen) iv. Average Load 344 kW (AEA) v. Minimum Load Estimated 150 kW (McMillen) vi. Efficiency 10.8 kWh per gallon (AEA FY12) vii. Future trends Less efficiency, increased outages, & higher cost d) Annual heating fuel usage (fill in as applicable) i. Diesel [gal or MMBtu] Not Available ii. Electricity [kWh] Not Available iii. Propane [gal or MMBtu] Not Available iv. Coal [tons or MMBtu] none v. Wood [cords, green tons, dry tons] none vi. Other none Proposed System Design Capacity and Fuel Usage (Include any projections for continued use of non-renewable fuels) a) Proposed renewable capacity (Wind, Hydro, Biomass, other) [kW or MMBtu/hr] 2 MW base (Wind/Hydro pump-storage) with a 2.5 MW average depending on demand patterns and wind patterns. Maximum capacity 8.5 MW with wind, hydro, and backup diesel in full operation. 1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric  Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power.    Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 13 of 22 7/1/2013 b) Proposed annual electricity or heat production (fill in as applicable) i. Electricity [kWh] 17,520,000 kWh (McMillen) ii. Heat [MMBtu] Not Available c) Proposed annual fuel usage (fill in as applicable) i. Propane [gal or MMBtu] 0 ii. Coal [tons or MMBtu] 0 iii. Wood or pellets [cords, green tons, dry tons] 0 iv. Other 0 Project Cost a) Total capital cost of new system $72.4 million (final design and construction) [McMillen] b) Development cost c) Annual O&M cost of new system $568,000 (McMillen) d) Annual fuel cost Project Benefits a) Amount of fuel displaced for i. Electricity 1,358,139 FY12 (AEA FY12) ii. Heat Not Available iii. Transportation Not Available b) Current price of displaced fuel $4.42 (AEA FY12) c) Other economic benefits $2,762,638 (annual savings FY12 data), $67.0 million (future value based on FY12), & $167.5 million (projected future value) d) Alaska public benefits $290,795 (PCE FY 12) & $7.1 million (future value based on FY12 data) Power Purchase/Sales Price a) Price for power purchase/sale Power Purchase - Not Applicable (Adak renewable energy) Adak local power sale $0.21 per kWh Project Analysis a) Basic Economic Analysis Project benefit/cost ratio 2.35 to 1 Payback (years) 40 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 14 of 22 7/1/2013 4.4.5 Impact on Rates Briefly explain what if any effect your project will have on electrical rates in the proposed benefit area. If the is for a PCE eligible utility please discus what the expected impact would be for both pre and post PCE. The estimated direct benefit is the reduction of electric rates for all consumers with the new renewable energy system plus the economic benefit of new jobs and income to Alaska residents. The current energy rates average $1.24 per kWh. The current system does not have the generation capacity to meet total residential, commercial, government, and industrial demand. Many residents, commercial firms, and the seafood processing plant use standalone diesel to generate power to meet their need because of the lack of capacity of the utility or because of the high cost of utility supplied power. With implementation of the hydro / wind with pump storage renewable power project, the cost of power is estimated at $0.21 per kWh. The Adak utility is PCE eligible. The FY 2012 AEA PCE reports an annual disbursement of $290,795 or a future value of $7,059,000 (average 8% compounded monthly for 40 years). Using FY 2012 AEA data of annual kWh sold of 2,682,173 kWh at the average rate per KWh of $1.24 equals $3,325,895 in total power cost to the community on the grid. Many of the residential, industrial, and commercial power users self-generated. With implementation of the proposed project using the FY 2012 kWh power sold data and the projected rate of $0.21 per kWh, the annual power cost to the community is estimated at $563,256. The annual FY 2012 total power cost savings to the community with the proposed hydro wind pump storage system is estimated at $2,762,638. The estimated future value of the cost savings over the 40 year estimated life of the project is estimated at over $67.0 million. A more realistic estimated future value of these cost savings is $167.5 million when self-generation, energy demand, and other factors are taken into consideration. This estimate is more realistic because at a lower cost per kWh, all consumers will use considerably more power and switch from self-generation to the community grid, and major industrial users such as the seafood plant will switch from self-generation to the grid. SECTION 5– PROJECT BENEFIT Explain the economic and public benefits of your project. Include direct cost savings, and how the people of Alaska will benefit from the project. The benefits information should include the following:  Potential annual fuel displacement (gallons and dollars) over the lifetime of the evaluated renewable energy project  Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price, RCA tariff, or cost based rate)  Potential additional annual incentives (i.e. tax credits)  Potential additional annual revenue streams (i.e. green tag sales or other renewable energy subsidies or programs that might be available)  Discuss the non-economic public benefits to Alaskans over the lifetime of the project Based on the AEA FY12 report, the annual fuel displacement is 278,867 gallons of fuel at $4.42 per gallon or $1,232,600 in FY12. Under the existing generation system, the annual fuel displacement is estimated at over 1.6 million gallons annually assuming 2 MW of usage. With implementation of the total renewable energy project, the annual fuel displacement is estimated at over 1.3 million gallons annually assuming 2 MW of usage over a conventional diesel system. The net savings in costs include buyback Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 15 of 22 7/1/2013 costs as well as all O&M costs including diesel backup are $3,333,000 per year over a conventional diesel system. These figures are based on cost assumptions generated by the McMillen Hydroelectric Feasibility Study Technical Report (Executive Summary is attached). Because this energy is developed on and for Adak Island there is no proposed power purchase agreements. Other additional incentives and revenues are unknown at this time. Non-economic public benefits include the quality of living in which there is a reliable power system with redundancy in generation sources. There is a savings of over $5.7 million in fossil fuels based on 1.3 million gallons per year with a conventional diesel system. 5.1.1 Public Benefit for Projects with Private Sector Sales Projects that include sales of power to private sector businesses (sawmills, cruise ships, mines, etc.), please provide a brief description of the direct and indirect public benefits derived from the project as well as the private sector benefits and complete the table below. See section 1.6 in the Request for Applications for more information. Renewable energy resource availability (kWh per month) 1,460,000 Estimated sales (kWh) $17,520,000 (annual) Revenue for displacing diesel generation for use at privet sector businesses ($) $1,839,600 / year (assuming fish processing plant and other offline users use 1 MW average) Estimated sales (kWh) 8,760 kWh Revenue for displacing diesel generation for use by the Alaskan public ($) $1,839,600 / year (assuming public/residential use 1 MW average) SECTION 6– SUSTAINABILITY Discuss your plan for operating the completed project so that it will be sustainable. Include at a minimum:  Proposed business structure(s) and concepts that may be considered.  How you propose to finance the maintenance and operations for the life of the project  Identification of operational issues that could arise.  A description of operational costs including on-going support for any back-up or existing systems that may be require to continue operation  Commitment to reporting the savings and benefits The proposed business structure is a local utility. M&O will be financed out of cash flow from utility revenues. The McMillen report does not identify any unusual operational issues of a hydro wind renewable energy system. The system will employ proven technology. The existing diesel generation system will be replaced. The new 2MW diesel system is solely design as a backup system. In a remote area such as Adak, a backup system is required for community safety. The Adak utility will follow normal AEA reporting. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 16 of 22 7/1/2013 SECTION 7 – READINESS & COMPLIANCE WITH OTHER GRANTS Discuss what you have done to prepare for this award and how quickly you intend to proceed with work once your grant is approved. Tell us what you may have already accomplished on the project to date and identify other grants that may have been previously awarded for this project and the degree you have been able to meet the requirements of previous grants. The City of Adak has received financial assistance from the Economic Development Administration (EDA) to conduct a hydroelectric feasibility analysis and preliminary engineering. These analyses have been completed and the McMillen summary report is attached to this application. The scope of the completed project included 1) site analyses; 2) geographical investigations; 3) geotechnical analyses; 4) hydrologic analyses; 5) design criteria development and environmental considerations; 6) preliminary engineering design of three (3) alternatives; 7) preliminary cost estimates; 8) technical report describing the three alternatives and the recommended alternative for development; and 9) project coordination and meetings. The above analyses were completed on September 18, 2013 at a cost of $139,446 by McMillen LLC, a renewable energy engineering firm. A copy of the summary report by McMillen LLC is attached to this application. The EDA funded study originally focused on hydropower sources and integration with the City electrical and water systems. Key findings from the Report (Executive Summary is attached) include the following: 1. There are two pure hydropower alternatives analyzed. Both hydropower alternatives are feasible from a construction and integration standpoint. However, these alternatives are not large enough to generate sufficient power to address the existing industrial demand and the City’s potential economic development demand. 2. Before any future renewable energy implementation is undertaken, a necessary first step is to update the existing electrical grid and replace the diesel power generation system. 3. Due to the limited running water supply in the watershed, ample storage at the two reservoirs in close proximity, considerable vertical difference between reservoirs, ample wind resources nearby, and the relatively low cost to create considerable usable storage in both reservoirs, a hydro / wind generation system with pump storage alternative was analyzed and recommended as the best alternative. Because this feasibility study was focused on hydropower at its inception, it has considerable detail on costs, benefits and methods to achieve raising the dams, penstock, powerhouse, transmission, and other related tasks. Use of wind power as a viable option was considered in the middle of the project. Sufficient wind data has not been completed to sufficiently understand the wind resource and to develop a wind generation system preliminary engineering design. Hence, the proposed AEA application is required to complete the total project design. The McMillen report recommends that a wind field data collection, analysis, and preliminary design project be completed prior to the final design and construction of the total project. The EDA grant is in final stages of the grant closeout process. The final technical report will be edited and printed. The final financial reporting is the last step required to complete the EDA grant. The City of Adak, upon Authority award of financial assistance for the proposed project, will immediately initiate the competitive procurement of an engineering firm with the qualifications to provide the wind field data collection services, analyses, and preliminary engineering design of the wind energy component of the total project. The duration of the proposed project is eighteen months. The total duration of the proposed project includes procurement, wind data collection, analyses, design, and final reporting is eighteen months. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 17 of 22 7/1/2013 With completion of the proposed project and the work completed by McMillen LLC, the total project will be ready for final design and construction. SECTION 8 – LOCAL SUPPORT AND OPPOSITION Discuss local support and opposition, known or anticipated, for the project. Include letters of support or other documentation of local support from the community that would benefit from this project. The Documentation of support must be dated within one year of the RFA date of July 2, 2013. The proposed project is strongly supported by the residents, commercial firms, the Adak Community Development Corporation (represents local business), the seafood processing plant and The Aleut Corporation. There is no opposition to the project. SECTION 9 – GRANT BUDGET Tell us how much you are seeking in grant funds. Include any investments to date and funding sources, how much is being requested in grant funds, and additional investments you will make as an applicant. Provide a narrative summary regarding funding source and your financial commitment to the project The proposed AEA project will be solely funded by a Round 7 AEA grant. The City has not established a capital project budget for the FY 2015 (award date) and is unable to provide matching funds at this time. Prior to the August 1, 2014 AEA award date, the City will provide a cash match as well as in-kind services including grant administration and equipment for the installation of the wind data collection. The City was able to attract Adak Cod Cooperative to operate the former Icicle Seafood plant. To prevent the bank sale of the equipment assets of Icicle Seafood, the City and the community development corporation successfully purchased these assets at a cost of over $2.0 million. If the assets were sold to a non-Adak entity, the sole major industrial plant was non-operable. The City of Adak is committed to implementing the total renewable energy project to assure economic survival and to create an economic growth center to the benefit of the region and the State. The City commissioned the original hydroelectric feasibility study and is committed to moving this project forward. The City has invested considerable time and expense as a match to the EDA grant. The City will invest the time and expense to the AEA grant. Implementation of the total renewable energy project will require a major investment of City resources. Please provide a short narrative, and cost estimate, identifying the metering equipment, and its related use to comply with the operations reporting requirement identified in Section 3.15 of the Request for Applications. The cost estimate is based on similar projects, the scope of the project, and adjusted to reflect costs related to the Adak location. The proposed project consists of a data collection phase, an analysis of the data, and preliminary engineering design of the wind generation components including capital and operating cost estimates, environmental issues, and permitting. The first step in the data collection phase is installation of the met towers and anemometers as well as data loggers. The preferred wind field site is located on a ridge at elevation 600 feet. A recommended configuration of the 30 meter tall tower includes anemometers located at 10, 20, and 30 meters on the tower. Two additional 10 meter met towers with anemometers at Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 18 of 22 7/1/2013 the top will be erected. In addition to wind data, we will also measure pressure and temperature. The data logger(s) will receive data from the 5 anemometers along with pressure and temperature measurements taken at short intervals (on the order of every 5-10 minutes). Wind direction will be measured as well as part of the anemometer measurement and it will be collected on a separate band of the data logger. Based on comparative evaluation of similar projects, the cost for the three towers, 5 anemometers and pressure and temperature sensors along with a data logger(s) is approximately $65,000. The cost of shipping and installation by a trained crew on a remote site (about ¼ mile and 200 feet above a road) on a remote island is estimated at $15,000. City employees will check the system on a weekly schedule and after storms to ensure all the equipment is working properly. A specific system is not priced at this time because the City will issue a competitive procurement immediately following the grant award. The competitive procurement will include equipment configuration specifications. The data from this phase will be compiled and made available to AEA. The data collected will to be checked and verified. Correlations and relationships between the different sensors will be developed. Graphs and analysis of the wind directions and speeds will be determined. The data will be analyzed in spreadsheets and specialized computer programs to determine the average wind energy output for different turbine configurations in order to create preliminary design recommendations. The pattern of wind energy availability will be determined to evaluate the integration of a wind energy system with the hydropower configuration and the pump storage system. The estimated cost is $80,000 for data analysis, preliminary engineering design of the wind generation components, capital and operating cost estimates, environmental analyses, permitting, and other associated analyses. The total estimated cost of the project is $160,000. Applications MUST include a separate worksheet for each project phase that was identified in section 2.3.2 of this application, (I. Reconnaissance, II. Feasibility and Conceptual Design, III. Final Design and Permitting, and IV. Construction and Commissioning). Please use the tables provided below to detail your proposed project’s budget. Be sure to use one table for each phase of your project. If you have any question regarding how to prepare these tables or if you need assistance preparing the application please feel free to contact AEA at 907-771-3031 or by emailing the Grant Administrator, Shawn Calfa, at scalfa@aidea.org. Milestone or Task Anticipated Completion Date RE- Fund Grant Funds Grantee Matching Funds Source of Matching Funds: Cash/In- kind/Federal Grants/Other State Grants/Other TOTALS (List milestones based on phase and type of project. See Milestone list below. ) $ $ $ Feasibility & Preliminary Design $ $ $ Grant Award 08/01/14 $0.00 $ $0.00 Develop Engineering Services scope & RFQ for proposed project 08/15/14 $0.00 $ in-kind $0.00 Award Engineering Services Contract for the proposed project 09/15/14 $0.00 $ in-kind $0.00 Erect wind data collection equipment 11/15/14 $80,000 $ $80,000 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 19 of 22 7/1/2013 Progress reporting continuous $0.00 $ $ Monitor wind data collection 11/15/15 $2,000 $ $2,000 Data Analyses - Permitting and environmental analysis 12/31/15 $35,000 $ $35,000 Preliminary engineering design- cost estimates, regulatory issues & feasibility analysis 02/15/16 $43,000 $ $43,000 Final report & recommendations 02/29/16 $0.00 $ $0.00 TOTALS $160,000 $ $160,000 Budget Categories: Direct Labor & Benefits $ $ $ Travel & Per Diem $ $ $ Equipment $ $ $ Materials & Supplies $ $ $ Contractual Services $160,000 $ $160,000 Construction Services $ $ $ Other $ $ $ TOTALS $160,000 $ $160,000 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 20 of 22 7/1/2013 Project Milestones that should be addressed in Budget Proposal Reconnaissance Feasibility Design and Permitting Construction 1. Project scoping and contractor solicitation. 2. Resource identification and analysis 3. Land use, permitting, and environmental analysis 4. Preliminary design analysis and cost 5. Cost of energy and market analysis 6. Simple economic analysis 7. Final report and recommendations 1. Project scoping and contractor solicitation. 2. Detailed energy resource analysis 3. Identification of land and regulatory issues, 4. Permitting and environmental analysis 5. Detailed analysis of existing and future energy costs and markets 6. Assessment of alternatives 7. Conceptual design analysis and cost estimate 8. Detailed economic and financial analysis 9, Conceptual business and operations plans 10. Final report and recommendations 1. Project scoping and contractor solicitation for planning and design 2. Permit applications (as needed) 3. Final environmental assessment and mitigation plans (as needed) 4. Resolution of land use, right of way issues 5. Permit approvals 6. Final system design 7. Engineers cost estimate 8. Updated economic and financial analysis 9. Negotiated power sales agreements with approved rates 10. Final business and operational plan 1. Confirmation that all design and feasibility requirements are complete. 2. Completion of bid documents 3. Contractor/vendor selection and award 4. Construction Phases – Each project will have unique construction phases, limitations, and schedule constraints which should be identified by the grantee 5. Integration and testing 6. Decommissioning old systems 7. Final Acceptance, Commissioning and Start-up 8. Operations Reporting ATTACHMENTS City of Adak 1. City of Adak – Authorizing Resolution 2. Executive Summary of Adak Hydroelectric Feasibility and Preliminary Engineering – McMillen LLC 3. Resume of the Adak City Manager – Layton J. Lockett 4. The Aleut Corporation Letter of Support 5. Adak Cod Cooperative Letter of Support 6. Adak Community Development Corporation Letter of Support 7. Adak Eagle Enterprises LLC CITY OF ADAK Hydroelectric Feasibility Study Technical Report Prepared For: City of Adak Prepared By: McMillen, LLC Funded in part by the Economic Development Administration Grant#: EDA 07-79-06843 September 18, 2013 City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 2 Draft Technical Report September 18, 2013 Executive Summary The purpose of this report is to evaluate alternatives, prepare a preliminary engineering analysis, and examine the feasibility of producing hydroelectric power from streams and reservoirs near Adak, Alaska for the City of Adak. Special emphasis is given to projects that y involve Lake Bonnie Rose or Lake De Marie because of their close proximity to and integration with other city interests. The Project includes alternatives development as well as site analyses, geographical investigations, geotechnical analyses, hydrologic analyses, and design criteria development. As part of design criteria development, integration with the city's water supply and electrical grid as well as construction feasibility, and environmental and permitting issues are given strong consideration. This report and its appendices include preliminary engineering design for three alternatives, including preliminary cost estimates and the recommended alternative for development. Adak Island was originally developed by the U.S. Navy during World War II. In order to provide the base and its personnel with power, a sizeable diesel generation system and electric distribution network was developed on the island. The Navy continued operations on the island until 1997, when the base was closed and the land and associated infrastructure were turned over to the Aleut Corporation and the City of Adak. This changed the electrical demand from a military base with some 6,000 or more personnel to a small Alaskan city of approximately 300-400 residents. Electrical costs on the island are high due to the oversized generation system and a complete reliance on diesel fuel which has been increasing in cost in recent years. In addition, much of the work on the electrical grid dates back to the Cold War and World War II with components that are, in many cases, decades old, inefficient, and nearing the end of their useful life. Due to the high electrical costs and unreliability of the system, the Aleut Corporation, the City of Adak, and Adak Community Development Corporation are not able to pursue the strategies outlined in the Economic Adjustment Reuse Plan. The City’s over-riding need for this Project is to examine hydroelectric development from Lake Bonnie Rose and Lake De Marie, as well as surrounding areas to evaluate whether the associated cost savings provide a feasible project. From the feasible alternatives, a preliminary design for three preferred alternatives are developed that can readily be integrated into design-build activities. One of the most important considerations is how each alternative integrates with the City’s existing electrical system. A field reconnaissance of the electrical system was conducted in April 2013 with results discussed in this report and in Appendix D. The key finding is that the system is at or near the end of its useful design life. There are numerous examples of switching stations and transformers showing signs of wear with indications that they are about to fail. One transformer provides the sole route for power from the generators to the electrical grid. Failure of this transformer will render the city without power until a replacement transformer can be installed or standby generators will need to be used. Because of the remoteness of the island, this may result in days or weeks without power. Based on recent communication with the City, the power system recently has been exhibiting serious issues that confirm the April findings. In a recent discussion with a City official, 30 outages have occurred in the first half of the month of September (2013). The last remaining generator is not sized properly for a city of the size of Adak and is inefficient, especially during low load periods. The combination of the above issues makes energy costs higher than most surrounding cities and villages. Given Adak’s strong economic development potential with excellent port and infrastructure, lower cost energy will create an economic growth center with major benefits to the region and the State. Because of the poor condition of the existing generators and electrical grid system, a reconnaissance level cost estimate to replace the electrical grid and generators was completed and is presented in the report. The City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 3 Draft Technical Report September 18, 2013 cost for full replacement is estimated at just under 17.5 million dollars. This includes replacement of the diesel generating system as well as all main feeder power lines, switches and transformers. Even without hydropower installed, the replacement of this system saves at least 20% in diesel generating costs due to greater efficiencies as a result of properly sizing the generating system and less line losses in the distribution system. Having the electrical grid and generators replaced would also allow for maximum benefit from the hydroelectric and wind power resources. The current diesel system consisting of one generator and largely manual controls would make fully utilizing variable hydro inputs and working with partial demand loads difficult and inefficient. After field reconnaissance and geological and hydrological evaluation, three alternatives have been selected as possible power generating systems for the city. Detail on how these three alternatives were selected is given in Appendix D. The three alternatives are summarized briefly in the Table below: Alternative/ Issue Alt. 1 Wind- Pump Storage Alt. 2 Lake Bonnie Rose Dam to PRV1 Alt. 3 Moffett Creek Potential Powerhouse Size 2 MW (Hydro)* 4.5 MW (Wind) 246 kW 513 kW Potential Total Project Cost $54.9 Mil $21.3 Mil $18.5 Mil Basic Description  Installation of wind turbines near Lake DeMarie.  Raise/fix Lake DeMarie and Lake Bonnie Rose Dams to provide 2,000 acre- feet of useable storage for each dam.  Install 2 Francis turbines to pump water to upper reservoir during windy periods to buffer system and generate power when wind is down.  Raise/fix Bonnie Rose Dam to create 2,000 acre-feet of useable storage.  Replace city water main from Dam to Pressure Reducing Valve house one (PRV-1) and use turbine to convert excess pressure to electrical power.  Use excess water to create more power at 2nd turbine near Mitt Lake.  Build two diversion dams on the North and South Forks of Moffett Creek.  Combine water on North Fork and deliver down penstock to powerhouse at head of valley.  Generate power with new Turbine.  Requires 5 miles of transmission line. * This is the capacity of water turbines. Wind turbines will have a capacity of 4.5 MW and the average capacity of this system depending on wind patterns will be close to 2.5 MW. Alternative 1: Wind- Pump Storage Alternative 1 takes advantage of two natural features that are available in the mountains southwest of Adak. First, there are ridgelines with strong, reliable winds passing through the area. Second, there are two lakes, Lake Bonnie Rose and Lake De Marie, in close proximity to one another with an elevation difference between the lakes of approximately 500 feet. In order to utilize wind as an energy source, a buffer is required in order to provide consistent power during low wind periods and utilize the excess energy generated during peak wind periods. To provide this buffer, a pump storage system will be installed under this alternative between Lake Bonnie Rose and Lake De Marie. Each dam will be raised so that each reservoir will have a useable storage up to 2,000 acre-feet. Bonnie Rose needs to be raised 6 feet at the spillway while the De Marie dam requires a 14.1 foot raise in height. Both dam raises are designed to encapsulate the existing dams and needed repairs to both dams will occur as part of the Dam raise. The design includes a new 42-inch diameter steel penstock that will be located City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 4 Draft Technical Report September 18, 2013 from the Lake Bonnie Rose dam and extend approximately 4,860 feet down the valley to the upstream end of Lake De Marie and the new powerhouse. The 42-inch penstock will accommodate up to 60 cubic feet per second (“cfs”) of water. Under normal operating conditions, the system flow is designed to be between 20 cfs and 60 cfs. Depending on configuration, power output from the turbines is estimated to be up to 2 megawatts (“MW”). Power output from the three wind turbines installed as part of this alternative can be up to 4.5 MW. If all power sources are cumulated (i.e. the new diesel generators, the wind and the water turbines when the reservoir is full) there is a potential peak power output of 8.5 MW but this generation output can only be sustained for short time periods. At Lake De Marie, a new powerhouse will be constructed to house the two Francis style turbine/pump units as well as all of the necessary electrical and controls systems. The Francis style turbine generator units are capable of being operated as a pump or turbine, allowing for the dual-use pump/storage as designed, without the need for additional piping and equipment. This allows the units to pump water from Lake De Marie to Lake Bonnie Rose when excess wind power is available and generate power by flowing water from Lake Bonnie Rose to Lake De Marie when wind power is not adequate to meet the City’s electrical demands. The ridge selected for the wind turbine farm is located east of Lake De Marie, directly north of Lake Bonnie Rose. This ridge was selected due to its proximity to the proposed Lake De Marie powerhouse as well as the generally exposed wind conditions. Three, 1.5 MW wind turbines were preliminarily selected for the feasibility analysis of Alterative 1. This ensures that during optimal wind events, with turbines operating at peak capacity, there is still power available for pumping flow from Lake De Marie to Lake Bonnie Rose as well as meeting city power demands. For wind turbine integration into the pump storage system, an approximately 0.35 mile long transmission line will be required between the wind turbine farm and the Lake De Marie powerhouse. To transport the power back to the city, a new transmission line will be required from the powerhouse to the south side of town, adjacent to the small boat harbor. This transmission line is designed to be approximately 1.6 miles long. A preliminary analysis was performed in order to determine the approximate amount of power that may be generated by Alternative 1 on an annual basis. Based on wind analysis summarized in report, there is a strong likelihood that the wind turbines will operate over 85% of the time. During times when there is adequate wind, a pump or pumps will buffer spikes in available wind energy and push water from Lake De Marie to Lake Bonnie Rose. Wind power will provide power both for the pump(s) and to the power needs of the city. During times of inadequate wind, water will flow from Lake Bonnie Rose to Lake De Marie and the turbine units will provide electrical power in place of wind. Because the time period of adequate wind is 85% of the time, the capacity of the pumping system may be smaller than the turbine system. The exact configuration of turbine power vs. pump capacity is beyond the scope of the reconnaissance-level evaluation. However, a well-configured combination of wind and water turbine power can be designed to minimize the diesel fuel generation as a back-up to the system. Based on the preliminary analysis and assumptions of the available wind for generation, it is estimated that the system will be capable of generating a base rate of 2 MW of power. This will result in a potential annual generation of approximately 17,500 mega-watt hour (MWh). Because wind is producing near peak capacity for 40% of the time, the average output of this system is approximately 2.5 MW. However, in order to use this level of power, there needs to be demand during times when the wind power is available. In order to verify the wind resource available, a year-long, site-specific wind study will be required prior to final design. The reason for a site-specific wind study is to understand the local turbulence and the predominant direction of the wind in order to create the best wind turbine design. City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 5 Draft Technical Report September 18, 2013 Alternative 2: Bonnie Rose Dam to PRV-1 and Mitt Lake Lake Bonnie Rose combines high elevation (738.6 feet) with storage and a watershed of nearly 2 square miles to provide water to the reservoir and lake. This creates a high head water source to be used for generating power. Alternative 2 utilizes this water source to develop powerhouses at PRV-1 and Mitt Lake. Starting at Lake Bonnie Rose, a dam repair and raise will be completed to provide more reservoir storage. The current dam has deficiencies in the main embankment as well as in spillway capacity. The raise of the dam is similar to Alternative 1 except instead of a 42 inch penstock there will be a new 15-inch steel penstock, approximately 7,600 feet long, that will be installed from Lake Bonnie Rose to the new powerhouse located at the existing PRV-1 station. Currently, there is a steel pipeline that follows this exact routing as the city’s water supply pipeline. This water supply pipeline is estimated to have been installed during World War II, with minimal upgrades since, and is reaching the end of its useful life. One of the key benefits of Alternative 2 is the replacement of this pipeline with a new, reliable penstock serving both the city water supply and power production. The new, larger penstock will allow the full flow of up to 6 cfs to be transported to the new powerhouse, at the existing PRV-1 site, with minimal head loss. The new powerhouse will be located adjacent to the existing PRV-1 station. The remainder of the flow not required by the City, approximately 5 cfs, will be diverted into a new 15-inch steel penstock to convey the excess water from PRV-1 to the Mitt Lake powerhouse. This exposed penstock will be approximately 2,200 feet long running alongside the existing road. Both generators will be Pelton style with the one at PRV-1 producing 167 kW and the one at Mitt Lake producing 79 kW. In order to integrate the two powerhouses and the City electrical network, a new transmission line will need to be installed from the PRV-1 powerhouse, along the road, to the south side of town near the small boat harbor. If it is assumed the powerhouses will have an operation time of 80%, the system will be capable of generating approximately 1,725 MWh annually. Alternative 3: Moffett Creek Moffett Creek's watershed drains from a nearly 4,000-foot peak. This is the highest point on Adak Island and nearly double the elevation of the mountains that drain to form Bonnie Rose or other creeks near Adak. For this reason, Moffett Creek receives considerably more snow and stream flow peaks later in the summer than the creeks supplying water to Bonnie Rose. Moffett Creek also has a greater unit discharge per basin area than streams near Bonnie Rose. Because of the combination of high elevation and a good water supply, Moffett Creek has potential for hydropower. This alternative includes two diversion structures (small dams), a pipeline between diversions (15 inch; 1,050 feet long), and a penstock to a powerhouse located at the head of the valley. It also requires a transmission line that is 4.1 miles long. The diversion structures will be small, approximately 10-15 feet in height and 200-230 feet long. The diversions will be constructed with twin sheet pile walls with an earthen fill between them. The intake portion of the diversion will be located at the approximate creek bottom location and be controlled with a pair of slide gates. In high flow events, these gates will be capable of allowing water to bypass the diversion structure and travel down the existing stream channel. The gate arrangement will also allow the intake structure to function with the presence of surface ice as the intake will draw off of the bottom of the water column instead of the surface. The main, 28 inch, penstock delivering flow to the Moffett Creek powerhouse will extend from the main division approximately 4,550 feet down the valley to the powerhouse. The Moffett Creek powerhouse will be located just upstream of a natural stream gradient break point at an approximate elevation of 240 feet. Because the stream upstream of the powerhouse consists of poor habitat that may not contain fish, the full City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 6 Draft Technical Report September 18, 2013 stream flow of the creek can probably be used for hydropower. Within the powerhouse, a Pelton style turbine generator assembly will be located along with all the necessary electrical and controls equipment. Based on the preliminary analysis of Alternative 3, it is estimated that the system can produce an average of 300 kW. This estimate includes the variation in stream flows as well as down time for maintenance related items. Maintenance related downtime is expected to be performed during low power demand periods to minimize effects on generation. Based on these assumptions it is estimated that the Moffett Creek powerhouse will generate approximately 2,628 MWh annually. However, since this configuration is run of the river, considerable adjustments will be needed with this system as there is considerable stream flow variability and very little storage. Comparison of Alternatives All three alternatives are feasible from a constructability standpoint. All three have key obstacle(s) that need to be overcome before construction occurs. The major difference among the alternatives are each systems overall capacity, pattern of power production, and cost both in terms of absolute cost and cost per kilowatt hour. The table below summarizes some of these comparisons and contrasts. Alternative/ Issue Alt. 1 Wind- Pump Storage Alt. 2 Lake Bonnie Rose Dam to PRV-1 Alt. 3 Moffett Creek Potential Powerhouse Size 2 MW (Hydro) 4.5 MW (Wind) 246 kW 513 kW Potential Total Project Construction Cost $54.9 Mil $21.3 Mil $18.5 Mil Potential Annual O&M Cost* $568,000 $1,863,940 $1,554,540 Cost per kilowatt hour (expected use; 688 KW)** $0.61 $0.72 $0.52 Cost per kilowatt hour (base pump storage capacity; 2 MW)** $0.21 $0.48 $0.45 Biggest Obstacle(s)  In stream flow reservation will need to be adjusted.  Requires wind study.  High cost on absolute basis  In stream flow reservation will need to be adjusted.  High cost on kWh basis  Land ownership has not been determined. Ordinance cleanup has not been completed.  Stream flows extremely variable making generation to full potential difficult. Biggest selling point  Provides power for both city and future development.  Uses natural features (wind and large lake areas) to highest advantage.)  Fixes Bonnie Rose dam  Provides relatively constant power to grid which will reduce generation costs if tied into system correctly.  Will improve city water supply reliability and fix Bonnie Rose Dam.  Provides 1/2 MW of Hydro power at relatively low cost City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 7 Draft Technical Report September 18, 2013 *This potential O&M cost includes the estimated cost of diesel generation under each of the alternatives at the expected use level (688 kW average use) which is double that of the current AEA estimate given (AEA, 2013a). ** The cost per (kilo-watt-hour (kWh) for expected (688 kW average use) and full use (2 MW average use) includes cost for upgrading the electrical grid (~$17.5 million) and all financing charges assuming 3% interest and 40 year buyback period along with estimated diesel costs and other operation and maintenance costs.. In order to better evaluate the alternatives, the alternatives need to be compared with leaving the system “as is” versus replacing the power grid and generators as the first step towards hydropower. The Table below starts with the existing system, adds replacement of the distribution grid diesel generation system and then adds the incremental benefit, as well as costs, of adding each of the hydropower alternatives. Description of Improvements Cost of Improvements Total Cost per kWh including construction and O&M Costs including diesel generation costs Existing System – No Action No improvements $0 $1.24/kWh for Current Load (344 kW)** $0.88/kWh for Expected Load (688 kW)** NA* for Higher Loads ( 2, 2.5 MW) New Diesel generation and power Grid (no hydro Alternatives Replace existing generators with 3 new Diesel generators. Replace electrical grid with new wiring, switches, transformers etc. $17.5 million design and construction cost $0.66/kWh for Current Load (344 kW) $0.50/kWh for Expected Load (688 kW) $0.40/kwh for P/S Base Load (2 MW) NA* for P/S Average Load (2.5 MW) Alternative 1: Pump Storage between Bonnie Rose and DeMarie with Wind Replace diesel generators and distribution grid. Raise Dams, install Penstock, water and wind turbines as well as power house and lines. $17.5 million for new power grid and diesel generation $54.9 million for Design and Construction of Alternative Total Cost: $72.4 million $1.23/kWh for Current Load (344 kW) $0.61/kWh for Expected Load (688 kW) $0.21/kwh for P/S Base Load (2 MW) $0.17/kwh for P/S Average Load (2.5 MW) Alternative 2: Lake Bonnie Rose to PRV-1 to Mitt Lake Replacement of electrical grid and diesel generation system. Raise Bonnie Rose Dam. Construct 2 penstocks, 2 power houses and transmission lines. $17.5 million for new power grid and diesel generation $21.3 million for Design and Construction of Alternative Total Cost: $38.8 million $0.83/kWh for Current Load (344 kW) $0.72/kWh for Expected Load (688 kW) $0.48/kwh for P/S Base Load (2 MW) NA* for P/S Average Load (2.5 MW) Alternative 3 : Moffett Creek Replacement of electrical grid and diesel generation system. Design and construction of two diversion dams, a diversion pipeline, penstock and powerhouse, as well as transmission line for Moffett Creek to main distribution grid. $17.5 million for new power grid and diesel generation $18.5 million for Design and Construction of Alternative Total Cost: $36.0 million $0.70/kWh for Current Load (344 kW) $0.52/kWh for Expected Load (688 kW) $0.40/kwh for P/S Base Load (2 MW) NA* for P/S Average Load (2.5 MW) *NA – Not applicable because system cannot meet these load demands. ** The $1.24 per kWh is based on recent pricing from TDX for Adak. The $0.88/kWh is based on adding non fuel costs to a $0.41/kWh fuel cost from AEA report and then adding a $0.11/kWh cost to reflect a recent cost increase. City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 8 Draft Technical Report September 18, 2013 Each of the actions has a cost for construction of the improvements as well as the total cost that factors in Operation and Maintenance and the cost of providing diesel fuel. For comparison, according to AEA statistics, the cost per kWh in 2012 was $1.13/kWh for residential users. Based on a recent personal communication, this rate is to be raised to $1.24 per kWh. Also according to city sources, rates vary from $1.09 per kWh to $1.78 per kWh based on type and amount of use. According to the AEA report, the fuel related generation cost is $0.41 per kWh. Operation and maintenance and other non-fuel related costs for the current usage of 344 kW are $2,170,496 based on data from the 2013 AEA report. This non-fuel cost is used as a base figure for the expected load (688 kW) as well. When the grid and diesel generators are replaced, the maintenance and operation costs, besides diesel costs, are reduced to 200,000 dollars due to the fact that new equipment is installed that is properly sized to the system. This greatly reduces maintenance costs. In evaluating the costs per kWh, there is value to replacing the electrical grid and diesel generators no matter what the expected load may be. Compared with no action, there are consistent savings at all loads. For hydropower, the results show that Alternative 1 is a cost saving alternative if there are loads approaching 2 MW. Alternative 1 has a high fixed capital cost but its operating expenses are largely the same up to 2 MW because power can be generated from wind or hydropower without using diesel. Even at the average load of 2.5 MW, diesel will not need to be used because power will come from optimum use of wind and water turbine power. If Adak is expecting to attract economic growth, having the pump storage system (Alternative 1) will nearly halve the cost to generate power on a per kWh basis as compared to a replaced diesel system. Beyond potential new businesses, current base businesses such as the fish processing plant, which is currently closed, are likely to come on line and use power under these costs. The fish processing plant in the past, under a prior owner, used over a MW of power during peak periods seasonally but generated off line. Both Alternative 2 and Alternative 3 show no cost savings as compared with just replacing the diesel generator and grid alone, however it will move the City away from fossil fuels to more renewable sources. Conclusions and Recommendations Based on the cost estimates, full replacement of the diesel generation and electrical grid system is warranted. Over a 40 year buy back period, the cost to generate per kWh is lower ($1.24 vs. $0.66 per kWh at the estimated current load and $0.88 vs. $0.50 per kWh at the expected load. Furthermore, the current system is limited to less than 800 kW generation capacity unless new generators and other electrical equipment are added. The current energy grid and generation system is outdated and there is considerable deferred maintenance. Since the savings are immediate, as well as the advantages of having a more reliable power grid, this power and generation system is recommended to be replaced as soon as possible. Even with loan payback, the reduced costs in diesel generation and maintenance show a favorable economic gain over a 40 year payback period. After reviewing the cost per kWh for each alternative, only Alternative 1 (wind pump storage), is recommended for lower energy costs that may lead to economic development potential. This alternative gives low cost power especially at full 2 MW demand, allowing for economic growth and stability in power costs. Even at expected load (688 kW) the cost of pump storage per kWh is comparable with grid and diesel generator replacement only. As the electrical demand grows toward full capacity, the pump storage becomes more economical. City of Adak Hydroelectric Feasibility Study McMillen, LLC Page 9 Draft Technical Report September 18, 2013 With any major wind energy project, a site specific study is strongly recommended. The study normally will collect at least one year of data (REAP, 2011). It is recommended that funds be acquired to start this study as soon as possible. The study will determine which type of turbine system and configuration will best capture wind energy and work under the unique wind conditions that will be found on the ridges near Lake DeMarie. Alternative 1 can be broken down into sub steps with some parts being completed while the wind study is ongoing. The dam raises, penstock, and powerhouse installations will be designed and constructed immediately with the wind turbines being constructed the following year. The following plan of action is recommended: Description of Action Cost Schedule (with assumed November 1st, start date Step 1: Replace Power Grid and Diesel Generators Replace existing generators with 3 new Diesel generators. Replace electrical grid with new wiring, switches, transformers etc. $17.5 million design and construction cost Design: November 1, 2013 – April 31, 2014 Construction: June 1, 2014 – November 15, 2014 Step 2: Complete Alternative 1 – Wind / Pump Storage 2.a Wind Study $200,000 November 1, 2013 – December 15, 2014 2.b Raise Bonnie Rose Dam, DeMarie Dam, build power house and Penstock along with road building and trail improvements. $26.7 million design and construction cost Design/Permitting: November 1, 2013 – April 31, 2014 Construction: May 15, 2014 – November 15, 2014 2.c Design/Install Wind Turbines $28.2 million design and construction cost. Design: December 15, 2014 – April 31, 2015 Construction: June 1, 2015 – November 15, 2015 Please note this is an aggressive schedule that assumes funds can be procured quickly. The schedule may need to be adjusted based on funding sources’ timeframes or unforeseen permitting issues.