Loading...
HomeMy WebLinkAboutChisana Mountain Wind Project GrantApplication7Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Application Page 1 of 24 7/2/2013 Application Forms and Instructions This instruction page and the following grant application constitutes the Grant Application Form for Round VII of the Renewable Energy Fund. A separate application form is available for projects with a primary purpose of producing heat (see RFA section 1.5). This is the standard form for all other projects, including projects that will produce heat and electricity. An electronic version of the Request for Applications (RFA) and both application forms is available online at: http://www.akenergyauthority.org/REFund7.html.  If you need technical assistance filling out this application, please contact Shawn Calfa, the Alaska Energy Authority Grant Administrator at (907) 771-3031 or at scalfa@aidea.org.  If you are applying for grants for more than one project, provide separate application forms for each project.  Multiple phases for the same project may be submitted as one application.  If you are applying for grant funding for more than one phase of a project, provide milestones and grant budget for each phase of the project.  In order to ensure that grants provide sufficient benefit to the public, AEA may limit recommendations for grants to preliminary development phases in accordance with 3 ACC 107.605(1).  If some work has already been completed on your project and you are requesting funding for an advanced phase, submit information sufficient to demonstrate that the preceding phases are completed and funding for an advanced phase is warranted.  If you have additional information or reports you would like the Authority to consider in reviewing your application, either provide an electronic version of the document with your submission or reference a web link where it can be downloaded or reviewed.  In the sections below, please enter responses in the spaces provided, often under the section heading. You may add additional rows or space to the form to provide sufficient space for the information, or attach additional sheets if needed. REMINDER:  Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials submitted to the Authority may be subject to disclosure requirements under the act if no statutory exemptions apply.  All applications received will be posted on the Authority web site after final recommendations are made to the legislature.  In accordance with 3 AAC 107.630 (b) Applicants may request trade secrets or proprietary company data be kept confidential subject to review and approval by the Authority. If you want information is to be kept confidential the applicant must: o Request the information be kept confidential. o Clearly identify the information that is the trade secret or proprietary in their application. o Receive concurrence from the Authority that the information will be kept confidential. If the Authority determines it is not confidential it will be treated as a public record in accordance with AS 40.25 or returned to the applicant upon request. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 2 of 24 7/1/2013 SECTION 1 – APPLICANT INFORMATION Name (Name of utility, IPP, or government entity submitting proposal) Alaska Power Company (APC) (subsidiary of Alaska Power & Telephone Co. [AP&T]) Type of Entity: Utility Fiscal Year End December 31 Tax ID #92-0153693 Tax Status:  For-profit Non-profit Government ( check one) Date of last financial statement audit: The audit report was issued April 9, 2013. The audit was conducted March 18 through 23. Mailing Address P.O. Box 3222 Port Townsend, WA 98368 Physical Address 193 Otto Street Port Townsend, WA 98368 Telephone 360-385-1733 Fax 360-385-7538 Email glen.m@aptalaska.com 1.1 APPLICANT POINT OF CONTACT / GRANTS MANAGER Name Point of contact for application: Glen Martin, x122 Grant Manager: Karl Wood, x128 Title Manager Permitting, Licensing, Grant Writing Grants Manager / Financial Analyst Mailing Address P.O. Box 3222 Port Townsend, WA 98368 Telephone 360-385-1733 Fax 360-385-7538 Email Glen.m@aptalaska.com Karl.w@aptalaska.com 1.2 APPLICANT MINIMUM REQUIREMENTS Please check as appropriate. If you do not to meet the minimum applicant requirements, your application will be rejected. 1.2.1 As an Applicant, we are: (put an X in the appropriate box) X An electric utility holding a certificate of public convenience and necessity under AS 42.05, or An independent power producer in accordance with 3 AAC 107.695 (a) (1), or A local government, or A governmental entity (which includes tribal councils and housing authorities); YES 1.2.2 Attached to this application is formal approval and endorsement for the project by the applicant’s board of directors, executive management, or other governing authority. If the applicant is a collaborative grouping, a formal approval from each participant’s governing authority is necessary. (Indicate Yes or No in the box ) YES 1.2.3 As an applicant, we have administrative and financial management systems and follow procurement standards that comply with the standards set forth in the grant agreement (Section 3 of the RFA). YES 1.2.4 If awarded the grant, we can comply with all terms and conditions of the award as identified in the Standard Grant Agreement template at http://www.akenergyauthority.org/veep/Grant-Template.pdf. (Any exceptions should be clearly noted and submitted with the application.) YES 1.2.5 We intend to own and operate any project that may be constructed with grant funds for the benefit of the general public. If no please describe the nature of the project and who will be the primary beneficiaries. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 3 of 24 7/1/2013 SECTION 2 – PROJECT SUMMARY This section is intended to be no more than a 2-3 page overview of your project. 2.1 Project Title – (Provide a 4 to 7 word title for your project). Type in space below. Chisana Mountain Wind Feasibility Project 2.2 Project Location – Include the physical location of your project and name(s) of the community or communities that will benefit from your project in the subsections below. 2.2.1 Location of Project – Latitude and longitude, street address, or community name. Latitude and longitude coordinates may be obtained from Google Maps by finding you project’s location on the map and then right clicking with the mouse and selecting “What is here? The coordinates will be displayed in the Google search window above the map in a format as follows: 61.195676.-149.898663. If you would like assistance obtaining this information please contact AEA at 907-771-3031. Chisana Mountain, 63.186º N, 142.553º W at elevation 3,300 feet. The location is near Tetlin and is adjacent to the buried 15kV transmission line that runs between Tok and Tetlin along an all-weather road. 2.2.2 Community benefiting – Name(s) of the community or communities that will be the beneficiaries of the project. Tok, Tetlin, Tanacross, & Dot Lake will benefit if this site proves feasible for wind power. If the Slana-Chistochina-Mentasta grid becomes connected to Tok in the future they will also benefit. Similarly, if Northway, Northway Junction, and Northway Village also become connected to Tok, they will benefit from this potential wind power. All these communities are served by APC and are currently on 100% diesel generation. 2.3 PROJECT TYPE Put X in boxes as appropriate 2.3.1 Renewable Resource Type X Wind Biomass or Biofuels (excluding heat-only) Hydro, Including Run of River Hydrokinetic Geothermal, Excluding Heat Pumps Transmission of Renewable Energy Solar Photovoltaic Storage of Renewable Other (Describe) Small Natural Gas 2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply) Pre-Construction Construction Reconnaissance Final Design and Permitting X Feasibility and Conceptual Design Construction and Commissioning Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 4 of 24 7/1/2013 2.4 PROJECT DESCRIPTION Provide a brief one paragraph description of the proposed project. The Chisana Mountain Wind Feasibility Project would consist of installing a single 50 meter meteorological tower (met tower) to record wind velocities, temperature, and humidity to determine if this site is feasible for a wind turbine installation to generate electricity for the Tok power grid. 2.5 PROJECT BENEFIT Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel costs, lower energy costs, local jobs created, etc.) If sufficient and consistent wind is found to exist at the Chisana Mountain site, the communities connected to the Tok grid (Dot Lake, Tetlin, Tanacross) would potentially have their electric rates reduced; currently paying $0.4971/kWh. The public would also benefit by the reduction of the use of diesel fuel at the Tok powerplant, which would reduce their rates, reduce air emissions from the burning of fossil fuel, and reduction of noise pollution from the operation of diesel generators. 2.6 PROJECT BUDGET OVERVIEW Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source of other contributions to the project. The total cost of the Feasibility and Conceptual Design Report is estimated to be $148,800. APC proposes to immediately go to Phase II: Feasibility and Conceptual Design. A site reconnaissance was completed in 2012; report can be found in Appendices. Part of Phase II will be to determine what permitting and environmental studies will be necessary if the site proves feasible for a wind farm. The site is accessible by road, is adjacent to a 15kV transmission line buried along the road, and most of the tower and its accoutrements’ are already owned by APC and stored in Tok. Phase II: APC requests with this application grant funding of $119,000 which is 80% of the estimated cost of Phase II ($148,800). APC will provide $29,800 in matching and in-kind funds (20% match) from its normal operating funds and an in-kind contribution of a $15,800 met tower package. APC owns two met towers, one of which is currently available; an NRG 50 meter XHD met tower. This tower and equipment that came with it is valued at $15,800; see Appendices for cost sheet from manufacturer. 2.7 COST AND BENEFIT SUMARY Include a summary of grant request and your project’s total costs and benefits below. Grant Costs (Summary of funds requested) 2.7.1 Grant Funds Requested in this application $119,000 2.7.2 Cash match to be provided $14,000 2.7.3 In-kind match to be provided $15,800 (met tower) 2.7.4 Other grant funds to be provided $ 2.7.5 Other grant applications not yet approved $ 2.7.6 Total Grant Costs (sum of 2.7.1 through 2.7.4) $148,800 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 5 of 24 7/1/2013 Project Costs & Benefits (Summary of total project costs including work to date and future cost estimates to get to a fully operational project) 2.7.7 Total Project Cost Summary from Cost Worksheet, Section 4.4.4, including estimates through construction. $148,800 (Phase II only) 2.7.8 Additional Performance Monitoring Equipment not covered by the project but required for the Grant Only applicable to construction phase projects. $ N/A 2.7.9 Estimated Direct Financial Benefit (Savings) $900,000 - $1,742,400 (fuel savings) if project goes to Phase IV 2.7.10 Other Public Benefit If you can calculate the benefit in terms of dollars please provide that number here and explain how you calculated that number in Section 5 below. $ SECTION 3 – PROJECT MANAGEMENT PLAN Describe who will be responsible for managing the project and provide a plan for successfully completing the project within the scope, schedule and budget proposed in the application. 3.1 Project Manager Tell us who will be managing the project for the Grantee and include contact information, a resume and references for the manager(s). In the electronic submittal, please submit resumes as separate PDFs if the applicant would like those excluded from the web posting of this application. If the applicant does not have a project manager indicate how you intend to solicit project management support. If the applicant expects project management assistance from AEA or another government entity, state that in this section. Overall Project Manager: Vern Neitzer – APC’s Chief Engineer, will be the Project Manager. Mr. Neitzer is located in Skagway, Alaska, and has extensive experience in managing both renewable and fossil fuel energy development. Mr. Neitzer has also been the overall project manager for the 7-Mile Ridge met tower feasibility analysis for APC over the last two years; resume can be found in the Appendices. Project Contractor: Douglas Vaught, P.E., V3 Energy, LLC., Anchorage, AK. Will be responsible for conducting the feasibility analysis using the data collected over a year. Mr. Vaught has an extensive background in renewable energy resources and in met and wind towers; resume can be found in the Appendices. 3.2 Project Schedule and Milestones Please fill out the schedule below. Be sure to identify key tasks and decision points in in your project along with estimated start and end dates for each of the milestones and tasks. Please clearly identify the beginning and ending of all phases of your proposed project. Please fill out form provided below. You may add additional rows as needed. Milestones Tasks Start Date End Date Authorization to Proceed AEA Authorizes the use of funds July 2014 Contact USF&WS & FAA Notify regarding project and whether permitting is necessary July 2014 August 2014 Land Use Authorization Finalize Tetlin Village Council Authorization July 2014 August 2014 Mobilize Equipment to Take met tower and accoutrements’ out August August Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 6 of 24 7/1/2013 Chisana Mountain W ork Site to the project site 2014 2014 Install Met Tower Create base for tower, install metering equipment on tower, raise tower, install and anchor guy-wires. August 2014 September 2014 Met tower Maintenance Inspect on as needed basis to maintain October 2014 August 2016 Analysis of Permitting & Environmental Issues for Phases III & IV To determine what will be required for field studies to permit and construct wind turbines for this site October 2014 November 2015 Geotech Study For foundation design May 2015 October 2015 Download Wind Data Remotely download data September 2015 October 2015 Renewable Energy Modeling & Design Conduct analysis of wind data, including modeling and design, financial feasibility November 2015 March 31, 2016 Draft Conceptual Design Report Conceptual design of how wind would be integrated with APC diesel operations in Tok November 2015 March 31, 2016 Final Conceptual Design Report Conduct analysis of data and write final feasibility report and conceptual design April 2016 July 31, 2016 Remove Met Tower Remove tower, accoutrements, and anything else put in place for its installation and operation August 2016 August 2016 3.3 Project Resources Describe the personnel, contractors, accounting or bookkeeping personnel or firms, equipment, and services you will use to accomplish the project. Include any partnerships or commitments with other entities you have or anticipate will be needed to complete your project. Describe any existing contracts and the selection process you may use for major equipment purchases or contracts. Include brief resumes and references for known, key personnel, contractors, and suppliers as an attachment to your application. APC: APC will manage the grant. APC has been providing power to Alaskan communities since 1957. Since then, from only a handful of employees, APC has grown to 134 employee- owners (all of AP&T) who provide power services to 25 communities. APC has experience with renewable resources after constructing 4 hydroelectric projects in S.E. Alaska and experimenting with a hydrokinetic turbine in the Yukon River. APC owns and operates 6 hydroelectric projects and has extensive experience with the integration between diesel generation and renewable energy generation. One of APC’s service centers is in Tok where diesel generation supplies power to Tok, Tetlin, Tanacross, and Dot Lake. Other small nearby grids such as the (1) Slana-Chistochina-Mentasta, and (2) Northway-Northway Village-Northway Junction are also served by APC, but are currently not connected to Tok. APC has power linemen, engineers, accounting and bookkeeping personnel in Tok as well as at the APC corporate headquarters in Port Townsend, Washington for managing the grant as well as operating and maintaining the met tower. APC has personnel certified as electrical, civil, and mechanical engineers who maintain the facilities to the highest professional standards. APC has a consistent history of excellent performance in reliability, customer service, and a long-standing reputation for being a low cost provider of electric service. Additionally, APC is committed to transitioning from fossil fuel power generation to renewable energy. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 7 of 24 7/1/2013 APC’s budgets have included several 50% grant funded projects for installation of transmission lines on Prince of Wales Island, and three RUS (Rural Utilities Service) 100% grants for the installation of transmission lines from Tok to Tetlin and Haines to Lutak, and communities along the Haines Highway. APC’s engineering staff has been involved in the design, construction and operation of hydroelectric projects since the 1980’s. APC currently maintains over 250 miles of transmission line and has seasoned staff to maintain diesel generators and hydro power plants. APC has administrators responsible for multi-million dollar budgets, including the management of 60+ employees, equipment, and all generation and distribution resources. APC has been maintaining a met tower at another ridge southwest of Tok, 7-Mile Ridge, for a couple years and has experience with its operation, maintenance, and downloading the data. APC also installed a met tower near Delta in 2010 and conducted a feasibility analysis of that site (one year of data collected). CONTRACTOR – V3 Energy, LLC: Since 2003, has extensive Alaska experience in wind resource assessment, wind site selection and permitting, rural village wind-diesel hybrid modeling and power system configuration, and meteorological test tower installation (up to 60 meters tower height). V3’s special expertise is the cold climate wind power development challenge, which includes severe cold temperatures, atmospheric icing/rime icing, permafrost, and the difficult logistics of remote area work. (V3 Energy Resume enclosed) V3 will conduct the modeling and feasibility analysis with the wind data that is collected. APC presently has the following equipment: 3421 NRG-NOW Symphonie TallTower Kit 3422 NRG-NOW Symphonie Sensor Kit 3423 NRG-NOW Symphonie Logger kit - SA 3424 InstallKit for 50mHD, 203mm TallTower 3893 Symphonie iPack for GSM, GPRS Quad Band 3368 iPack Programming for Voice Call kit APC will use this equipment for the project. APC will use their equipment and personnel to install and remove the met tower. Expenses will be related to time spent acquiring any permitting necessary, V3 Energy (Doug Vaught) will travel to/from Tok (from Anchorage) 1-2 times, and V3 will analyze the wind data and write the feasibility report. APC will develop the conceptual design in coordination with V3 and the wind data modeling and analysis. APC personnel will also be responsible for maintaining the wind tower and downloading the data, as needed, as well as other administrative duties including administering the grant funds and quarterly reports to AEA over a two year period. 3.4 Project Communications Discuss how you plan to monitor the project and keep the Authority informed of the status. Please provide an alternative contact person and their contact information. During Phase II, APC proposes to provide quarterly reports to AEA regarding the status of the work and use of the grant funds. APC has provided similar reports to AEA and other grant funding agencies over the past decade to fund various projects in Alaska and has established the necessary procedures for producing the reports expeditiously. An alternative contact would be: Vern Neitzer, Chief Engineer Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 8 of 24 7/1/2013 APC P.O. Box 459 Skagway, AK 99840-0459 907-983-2202 vern.n@aptalaska.com 3.5 Project Risk Discuss potential problems and how you would address them. Site Control – APC is working with the Tetlin Village Council to acquire authorization to access and install a met tower at the project location. If authorization is received during AEA’s application review period we will submit it as an addendum to our application. Seismic – For Phase II the seismic risk is low with just a single met tower. Underground Construction – The Project does not include a significant amount of underground construction, just the guy-wire anchors; which may be drilled and bolted into surface bedrock. Inclement Weather – Working conditions in the Tok area are very harsh during the winter. The proposed schedule assumes no work during the winter, including no equipment failures, i.e. December-March period; although this site is at least near an all-weather road, making maintenance much easier than the previously mentioned 7-Mile Ridge site. Environmental Opposition – APC is unaware of any opposition to reducing the areas electric rates ($0.4971/kWh), the main benefit if a small wind farm is proved feasible. APC believes the environmental impacts will be insignificant for this location. However, if the project moves forward into Phase III, avian studies may be required depending on what USF&WS determines is necessary to permit the project. SECTION 4 – PROJECT DESCRIPTION AND TASKS  The level of information will vary according to phase(s) of the project you propose to undertake with grant funds.  If some work has already been completed on your project and you are requesting funding for an advanced phase, submit information sufficient to demonstrate that the preceding phases are satisfied and funding for an advanced phase is warranted. 4.1 Proposed Energy Resource Describe the potential extent/amount of the energy resource that is available. Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be available for the market to be served by your project. For pre-construction applications, describe the resource to the extent known. For design and permitting or construction projects, please provide feasibility documents, design documents, and permitting documents (if applicable) as attachments to this application. This feasibility analysis will determine the potential for this location to generate electricity from wind turbines. At this time we do not know the extent or amount of energy resource that is available. The AEA state wide wind map classifies much of Interior Alaska as Class II winds. However, research has shown that this is not always the case. Based on our experience of the area we believe there is potential for this site, but only installing a met tower will give us any idea of its true potential. Other forms of renewable energy for the Tok grid have also been under analysis by APC in recent Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 9 of 24 7/1/2013 years, from hydropower to bio-mass. Finding a solution for this area will likely require a combination of resources rather than just one to get the grid off of fossil fuels. 4.2 Existing Energy System 4.2.1 Basic configuration of Existing Energy System Briefly discuss the basic configuration of the existing energy system. Include information about the number, size, age, efficiency, and type of generation. The existing electrical energy market in the Upper Tanana area consists of a local isolated power grid serving the communities of Tok, Tetlin, Dot Lake and Tanacross, as well as the other rural residents of the area. All four communities are on the same local APC grid and are therefore supplied by the existing APC diesel power plant in Tok. Peak demand has been approximately 1,800 kW, in both winter and summer. Production by the diesel power plant has averaged about 12,000 MWh/yr for the last ten years, with minor fluctuations corresponding to diesel price fluctuations. Many customers supplement their electrical use with kerosene, oil and gas for generators, as well as for heating. Several customers also use propane for cooking, clothes dryers, hot water heaters, etc. When electric rates stabilize, these other non-renewable fuel sources usage may decline, which would help clean the air and reduce toxic spills, as well as help localize the economy of the region. Solar panels are also being installed by Tok residents over the last couple years (AEA current has a grant program for Tok area residential solar panels). Energy demand is expected to grow for this area. Stable power costs are attractive to manufacturers and businesses looking to locate in this area. Healthy local economies, based on local natural and human resources can become more self-sustaining. There are 5 gensets in the Tok diesel power plant that supply electricity to all four communities, as follows: Unit #3 = CAT Model D3516, 1320 kW, Purchased / Installed 1999 Unit #4 = CAT/KATO Model 3516, 1135 kW, Purchased / Installed 1989 Unit #5 = CAT/KATO Model 3516, 1135 kW, Purchased / Installed 1995 Unit #8 = CAT/KATO Model D3508, 440 kW, Purchased / Installed 1985 Unit #9 = CAT/KATO Model 3512C, 1050 kW, Purchased / Installed 2008 If the project shows a feasible energy resource, it will potentially reduce the cost of generation by APC, and the savings would be passed on to APC’s customers in Tetlin, Tok, Tanacross and Dot Lake who currently pay $0.4971 per kWh (excluding PCE). 4.2.2 Existing Energy Resources Used Briefly discuss your understanding of the existing energy resources. Include a brief discussion of any impact the project may have on existing energy infrastructure and resources. Currently much of the power and heat generated in Alaska is from fossil fuel, including coal, diesel, natural gas or nuclear fuels. The need to move away from fossil fuel energy is painfully apparent in Alaska with high and escalating costs exacerbated by transportation challenges in rural communities that are not accessible by road. Diesel deliveries by river barge or airplane are not only expensive, but potential environmental disasters. It is anticipated that the current momentum in regulatory direction toward establishing arbitrary values in carbon markets will continue. As the carbon cycle benefits of renewable energy are inherently superior to fossil fuel energy, accounting of cost/benefit ratios for renewables will Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 10 of 24 7/1/2013 become more accurate as carbon values are quantified. The Tok area has potential for several different alternative renewable energy resource developments including hydropower, biomass, wind, and solar. None of these potential energy resources by themselves would solve the Tok areas reliance on fossil fuels, but through some form of combination thereof they could get Tok off of diesel the majority of the time; if not 100%. A hydropower site has been examined by APC west of Tok on Yerrick Creek (Yerrick Creek Hydroelectric Project). Environmental studies have been conducted along with basic engineering design and permitting to build a project. Additional funding will be needed to construct this project. Biomass has been intensely evaluated over the last 2 years by APC, but it appears the best use for this resource would primarily be to create heat for the downtown area of Tok with electricity being a secondary byproduct. APC has a met tower on 7-Mile Ridge south of Tok and has been measuring velocities there for a couple years; this site appears promising, but expensive due to its remote location. Solar has been gaining a foothold in Tok and there have been a total of 22kW in applications for Net Power of the 18kW that is allowed. We believe the Chisana Mountain site may offer another location where wind velocities are around Class 4. This grant application would fund the installation of a met tower and the analysis of the data it will collect. Access is by an existing all-weather road to the ridge and APC has a 50 meter met tower in its possession. A buried 1/0 URD Jacketed 3-phase, 15 kV cable was installed by APC from Tok to Tetlin along this road that could be eventually be used to get power from this site (if shown to be feasible) to the Tok grid. 4.2.3 Existing Energy Market Discuss existing energy use and its market. Discuss impacts your project may have on energy customers. The existing energy market is the isolated power grid serving the Upper Tanana region, including the communities of Dot Lake, Tetlin, Tanacross, Tok and surrounding areas. The communities are supplied by the Tok diesel power plant. Peak demand is about 1,800 kW in both summer and winter. It is too early to know how much electricity this location may be able to provide for the Tok grid, or how consistent the wind will be, but assuming there are at minimum Class 4 wind velocities consistently at this location the project could offset about 1,000kW of the 1,800kW peak load; currently met with diesel generation. The current limiting factor is the existing buried transmission line that will only handle 1,000kW (19.5 miles of 1/0 URD Jacketed 3-phase, 15 kV cable). Diesel would still be required, but could be reduced to less than half its current use (assuming the wind power was a consistent source at 1,000kW). Another renewable resource project may be necessary to have consistent power to eliminate diesel, except as a source of backup generation. We expect the direct impact on energy customers to be negligible in practical terms, and beneficial in economic terms; the same reliable electricity grid with a cleaner air shed and more stable energy costs. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 11 of 24 7/1/2013 4.3 Proposed System Include information necessary to describe the system you are intending to develop and address potential system design, land ownership, permits, and environmental issues. 4.3.1 System Design Provide the following information for the proposed renewable energy system:  A description of renewable energy technology specific to project location  Optimum installed capacity  Anticipated capacity factor  Anticipated annual generation  Anticipated barriers  Basic integration concept  Delivery methods The Chisana Mountain Wind Feasibility Project will determine if adequate wind is available at this site and what the conceptual design would be. If the project continues to Phase IV it will utilize commercially available, proven, wind turbine modules that would be suited for Alaska’s weather extremes and NEC compliant. Actual system design will not be available until a conceptual design is completed based on two years’ worth of wind data collected. However, this site could potentially hold 1-3 turbines depending on their power output ratings. The existing transmission line may be a limiting factor because it would only be able to transmit at a 1,000kW capacity. Therefore, current capacity would be 1,000kW. V3 Energy will evaluate the integration of wind with the Tok diesel grid along with assistance from APC engineering staff. Renewable Energy Technology: APC plans to conduct a feasibility analysis and conceptual design to assess the possibility of using wind power on the Tok grid. If the wind resource proves suitable and funding is obtained, wind turbines would be installed to serve this grid. Currently, APC anticipates that a 1,000kW capacity system could be installed; however, this study will assist in determining the best wind energy generation alternative, if feasible. Optimum installed Capacity: The purpose of this grant is to gather wind data to determine if sufficient wind exists on a consistent basis, i.e. Class 4+, in order to plan an alternative energy facility. Anticipated capacity and generation would be examined for a number of turbine types to determine the best option for this area. Anticipated Capacity Factor: The potential barriers to success of this project include weather, permitting, site control, and construction funding. Weather is a minor barrier and does not pose a threat to the completion of this project. Permitting, based on an initial investigation, does not appear to be a significant hurdle to completing this phase of the project. Construction funding would be easier to obtain with design and permits in hand. Site control is still being pursued from the Tetlin Village Council (see Appendices regarding Letters of Support). Anticipated Annual Generation: This is the purpose of the feasibility analysis. Anticipated Barriers: None Basic Integration Concept: The wind turbine(s) would need to interconnect with the existing diesel power plant. The wind power would be dispatched as necessary to allow the diesel generators to continue running at efficient levels; currently the project is not anticipated to Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 12 of 24 7/1/2013 eliminate diesel generation. Conceptual design, to be completed as a part of this project, would detail how power from a wind turbine would be integrated and delivered into the existing system in Tok. Delivery Methods: The delivery method would be examined to determine what turbine type would be best suited for the system, area, and load. 4.3.2 Land Ownership Identify potential land ownership issues, including whether site owners have agreed to the project or how you intend to approach land ownership and access issues. The land the project will be sited on is solely owned by the Tetlin Village Council. We are currently in negotiations with the Village Council to gain legitimate access to this site for the purpose of installing a met tower only. If this site proves feasible for wind power a long term agreement will be sought. 4.3.3 Permits Provide the following information as it may relate to permitting and how you intend to address outstanding permit issues.  List of applicable permits  Anticipated permitting timeline  Identify and discussion of potential barriers FAA Air Navigation Hazard Permitting. The met tower placement would be selected based on airspace availability and limitations to meet the FAA’s Notice Criteria. If the project proves feasible and the turbine location and type have been selected, APC would seek a no-hazard determination from FAA for the potential turbines. APC would do this early in the process to ensure that adequate time and resources are allocated to this effort. It is expected to take about 3 months to obtain the FAA determination for the turbines if this project goes to Phase IV. Endangered Species Act/Migratory Bird Treaty Act Consultation. Consultation with the U.S. Fish and Wildlife Service (USFWS) in compliance with the Endangered Species Act and Migratory Bird Treaty Act would be required to install the met tower. A finding letter stating that the project would not be expected to impact threatened or endangered species or birds would be drafted and submitted to the USFWS once APC is assured this project is funded. It is expected that APC would receive concurrence from the Service within one month. The authorization would be issued prior to initiating met tower work in September 2014. 4.3.4 Environmental Address whether the following environmental and land use issues apply, and if so how they will be addressed:  Threatened or endangered species  Habitat issues  Wetlands and other protected areas  Archaeological and historical resources  Land development constraints  Telecommunications interference  Aviation considerations Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 13 of 24 7/1/2013  Visual, aesthetics impacts  Identify and discuss other potential barriers TES: APC will consult with USF&WS as to what concerns they may have in regards to avian species. As long as the guy wires are marked there should be little concern about TES species for the met tower. Habitat: Other than concerns over potential impacts to avian species, there are no concerns for habitat. Wetlands: The project location does not have wetlands or other protected areas. Archaeological / Historical: Consultation with the Tetlin Village Council will determine if there is any cultural/historical significance to the project site. However, there will be no excavation for the met tower so there should be no disturbance to cultural resources if they are present. Land Development Constraints: Getting Tetlin Village Council authorization for the site. Telecommunications: The met tower will not affect telecommunications. Aviation: The single met tower will be approximately 4 air-miles from the Tetlin airport or airstrip and the FAA will be informed of its location. Visual: The mountain top is free of trees requiring no clearing; however, some brushing may be necessary. A single met tower will have little impact on visual quality in this remote area. 4.4 Proposed New System Costs and Projected Revenues (Total Estimated Costs and Projected Revenues) The level of cost information provided will vary according to the phase of funding requested and any previous work the applicant may have done on the project. Applicants must reference the source of their cost data. For example: Applicants records or analysis, industry standards, consultant or manufacturer’s estimates. 4.4.1 Project Development Cost Provide detailed project cost information based on your current knowledge and understanding of the project. Cost information should include the following:  Total anticipated project cost, and cost for this phase  Requested grant funding  Applicant matching funds – loans, capital contributions, in-kind  Identification of other funding sources  Projected capital cost of proposed renewable energy system  Projected development cost of proposed renewable energy system Until a full project feasibility analysis is completed the total anticipated project cost cannot be accurately determined. The Tok grids peak summer and winter load is approximately 1.8 MW, all of which is currently served by diesel generation. “The costs for a utility scale wind turbine in 2012 range from about $1.3 million to $2.2 million per MW of nameplate capacity installed. This cost has come down dramatically from what it was just a few years ago. Most of the commercial-scale turbines installed today are 2 MW in size and cost roughly $3-$4 million installed. Wind turbines have significant economies of scale. Smaller farm or residential scale turbines cost less overall, but are more expensive per kilowatt of energy producing capacity. Wind turbines under 100 kilowatts cost roughly $3,000 to $8,000 per kilowatt of capacity. A 10 kilowatt machine (the size needed to power a large home) might have an installed cost of $50,000-$80,000 (or more) depending on the tower type, height, and the cost of Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 14 of 24 7/1/2013 installation. Oftentimes there are tax and other incentives that can dramatically reduce the cost of a wind project.”1 Depending on what class of wind is at Chisana Mountain and how consistent it is will determine what size of wind turbine could be installed. Total Anticipated Cost. This wind power feasibility analysis will cost approximately $148,800. APC requests that AEA provide $119,000 (80%) for this project with APC providing $29,800 ($15,800 is in in-kind funds) (20%). APC in-kind funds consist of the met tower and related equipment already purchased (a $15,800 value). Total cash contribution will be $14,000. Identification of other funding sources. Once the feasibility study is completed and Class 4+ winds are found, the turbine type can be determined in the conceptual design. If the project is feasible, the next phase of this project would be final design (Phase III) and construction (Phase IV). Although it is difficult to determine without an assessment of the resource and what type, size, and number of turbines would be required, APC expects that final design and construction could cost $4,815,000. It is possible that the funding for this work could come from AEA’s Renewable Energy Fund program, USDA Rural Utility Service program, or another grant program. Projected capital cost of proposed renewable energy system/projected development cost of proposed renewable energy system. The final phases of this project would be Design/Permitting (Phase III) and Construction and Commissioning (Phase IV). APC estimates that these phases could cost $4,815,000 (until the wind data is analyzed and the number and type of turbines determined, this cost estimate cannot be considered precise). APC would provide a 20% cash match for both of these phases. Anticipated Project costs: Phase I (Reconnaissance already completed) ............................ $0 Phase II (Feasibility & Conceptual Design) ..................... $148,800 Phase III (Permitting/Environmental/Design) ................... $800,0002 Phase IV (construction) ............................................... $4,015,0003 Total ............................................................................. $4,963,800 Requested Grant Funding: $119,000 (80% of total cost for Phase II) Applicant Matching Funds: $29,800 (20% of total cost for Phase II) Other Funding Sources: Other funding sources have not been identified at this time. The Applicant will provide the matching funds for Phase II from its normal operating funds; $15,800 of which will be ‘In-Kind’ for the use of a met tower (its value) that APC owns. Projected Capital Cost of Renewable Energy System: $4,015,000 (assumed to be the cost of Phase IV Construction) Projected Development Cost of Proposed Renewable Energy System: $948,800 (assumed to be the sum of Phase I, II, and III costs). Phase II: Project Costs for Feasibility & Conceptual Design 1 http://www.windustry.org/resources/how-much-do-wind-turbines-cost 2 This number cannot be exact until more is known about the wind resource. 3 Ibid. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 15 of 24 7/1/2013 Permitting………………………………………………………………………… $2,000 Land Use Authorization………………………………………………………… $4,000 Acquire Met Tower (APC owns met tower; In-Kind Contribution)………….$15,800 Mobilize Equipment to Project Site……………………………………………..$2,000 Install Met Tower………………………………………………………………..$12,000 Met Tower Maintenance………………………………………………………… $7,000 Geotech Study for Foundation Design ……………………………………….$25,000 Analysis of Phase III Permitting & Environmental Study Needs…………… $5,000 Wind Data Analysis………………………………………............................... $4,000 Renewable Energy Modeling & Design………………………………………$30,000 Draft Conceptual Design……………………………………………………… $20,000 Final Feasibility & Conceptual Design Report……………………………… $19,000 Remove Met Tower…………………………………………………………….. $3,000 Total for Phase II: ………………………………………………………….. $148,800 Phase III: Project Costs for Final Design & Permitting Environmental Studies .......................................................................... $200,000 Permit Applications Preparation .............................................................. $35,000 Permit Applications Processing ................................................................ $65,000 Additional Met Gaging at Project Site ..................................................... $150,000 Geotechnical Investigations .................................................................... $100,000 Surveying and Mapping ........................................................................ $150,000 Final Design ......................................................................................... $100,000 Total For Phase III: .............................................................................. $800,0004 Phase IV: Project Costs for Construction Construction Management ..................................................................... $200,000 Mobilization .............................................................................................. $50,000 Acquire Wind Turbine (assume 1 at this time of 1MW) ......................... $2,000,000 Access Road Improvements .................................................................... $15,000 Switchyard .............................................................................................. $250,000 Transmission ................................................................................... $1,500,0005 Total For Phase IV: ........................................................................... $4,015,000 4.4.2 Project Operating and Maintenance Costs Include anticipated O&M costs for new facilities constructed and how these would be funded by the applicant. (Note: Operational costs are not eligible for grant funds however grantees are required to meet ongoing reporting requirements for the purpose of reporting impacts of projects on the communities they serve.) The met tower would require monthly monitoring and data management. It is expected that this would cost $7,000 for the two years the met tower is in operation, which includes 3-4 trips to inspect and perform maintenance. If wind turbines prove feasible, their maintenance would be funded by APC’s general operating funds. 4.4.3 Power Purchase/Sale 4 Is estimate but may change due to feasibility and conceptual design report. 5 May not be needed unless more than 1MW is going to be transmitted; purpose of the feasibility study. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 16 of 24 7/1/2013 The power purchase/sale information should include the following:  Identification of potential power buyer(s)/customer(s)  Potential power purchase/sales price - at a minimum indicate a price range  Proposed rate of return from grant-funded project APC is the electrical utility for the Tok area and grid. APC is providing electricity to the communities of Tok, Tanacross, Tetlin, and Dot Lake on this grid. Customers on this grid are paying $0.4971 per kWh (excluding PCE) as of September 2013. APC is the developer of this wind project and would use this resource the same as any other (currently diesel) by offsetting expenses through periodic rate case adjustments. It is expected that this project, if feasible, would lower the current electric rates for the Tok grid. At this time it is not known how much the price may be lowered or what the rate of return would be; until more is known about this potential wind resource through this feasibility study. 4.4.4 Project Cost Worksheet Complete the cost worksheet form which provides summary information that will be considered in evaluating the project. Please fill out the form provided below. Renewable Energy Source The Applicant should demonstrate that the renewable energy resource is available on a sustainable basis. Annual average resource availability. Unknown at this time; no data on wind speed yet. Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel) Existing Energy Generation and Usage a) Basic configuration (if system is part of the Railbelt6 grid, leave this section blank) i. Number of generators/boilers/other 5 ii. Rated capacity of generators/boilers/other Unit #3 = CAT Model D3516, 1320 kW, Purchased / Installed 1999 Unit #4 = CAT/KATO Model 3516, 1135 kW, Purchased / Installed 1989 Unit #5 = CAT/KATO Model 3516, 1135 kW, Purchased / Installed 1995 Unit #8 = CAT/KATO Model D3508, 440 kW, Purchased / Installed 1985 Unit #9 = CAT/KATO Model 3512C, 1050 kW, Purchased / Installed 2008 iii. Generator/boilers/other type Diesel generators iv. Age of generators/boilers/other As noted above. v. Efficiency of generators/boilers/other 14.40kWh per gallon (aggregate for all generators) 6 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 17 of 24 7/1/2013 b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank) i. Annual O&M cost for labor $119,000 (2012) ii. Annual O&M cost for non-labor $102,000 (2012) c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the Railbelt grid, leave this section blank) i. Electricity [kWh] 9,066,722kWh ii. Fuel usage Diesel [gal] 733,541 Other iii. Peak Load January – 1,745kWh; July 1,440kWh iv. Average Load v. Minimum Load vi. Efficiency 14.40kWh per gallon (aggregate for all generators) vii. Future trends d) Annual heating fuel usage (fill in as applicable) i. Diesel [gal or MMBtu] ii. Electricity [kWh] iii. Propane [gal or MMBtu] iv. Coal [tons or MMBtu] v. Wood [cords, green tons, dry tons] vi. Other Proposed System Design Capacity and Fuel Usage (Include any projections for continued use of non-renewable fuels) a) Proposed renewable capacity (Wind, Hydro, Biomass, other) [kW or MMBtu/hr] Wind = 500kW to 1,000kW (potentially); not known at this time; purpose of this feasibility analysis. Diesel = 800kW to 1,300kW (existing resource) b) Proposed annual electricity or heat production (fill in as applicable) i. Electricity [kWh] Unknown at this time (Phase II) ii. Heat [MMBtu] c) Proposed annual fuel usage (fill in as applicable) i. Propane [gal or MMBtu] ii. Coal [tons or MMBtu] iii. Wood or pellets [cords, green tons, dry tons] iv. Other Project Cost a) Total capital cost of new system $4,015,000 (precise amount unknown at this time) Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 18 of 24 7/1/2013 b) Development cost $948,800 c) Annual O&M cost of new system $7,000 - $10,000 d) Annual fuel cost Project Benefits a) Amount of fuel displaced for i. Electricity Potentially 250,000 – 484,000 gallons annually ii. Heat iii. Transportation b) Current price of displaced fuel $3.60/gal. c) Other economic benefits PCE Program will save annually once intertied with Tok; this is before the renewable energy project is connected, which will provide further savings. d) Alaska public benefits Savings to PCE Program and reduced air emissions and noise in two communities – Slana and Northway Power Purchase/Sales Price a) Price for power purchase/sale APC owns all electrical infrastructure in the three energy markets and is developing this intertie. Project Analysis a) Basic Economic Analysis Project benefit/cost ratio Unknown at this time (Phase II) Payback (years) 4.4.5 Impact on Rates Briefly explain what if any effect your project will have on electrical rates in the proposed benefit area. If the is for a PCE eligible utility please discus what the expected impact would be for both pre and post PCE. The impacts on rates is difficult to assess without knowing how much power would be available from wind turbines at Chisana Mountain. Any numbers offered here would be conjecture and not based on any data. Below we guess at what the fuel savings would be, but that is in a perfect world where there is consistent wind of Class IV or greater and handling 33-66% of the Tok grid load. The purpose of the feasibility and conceptual design will be to provide some idea of what the power output will be so that rates can be considered; it is too early to make an assessment of the rates. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 19 of 24 7/1/2013 SECTION 5– PROJECT BENEFIT Explain the economic and public benefits of your project. Include direct cost savings, and how the people of Alaska will benefit from the project. The benefits information should include the following:  Potential annual fuel displacement (gallons and dollars) over the lifetime of the evaluated renewable energy project  Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price, RCA tariff, or cost based rate)  Potential additional annual incentives (i.e. tax credits)  Potential additional annual revenue streams (i.e. green tag sales or other renewable energy subsidies or programs that might be available)  Discuss the non-economic public benefits to Alaskans over the lifetime of the project Potential Annual Fuel Savings: This project could potentially save between 250,000 – 484,000 gallons of diesel fuel; equating to $900,000 - $1,743,400 annually (based on $3.60/gal). If you figure a standard 50 years, the savings could equate to $45,000,000 – $87,120,000 (based on $3.60/gal). Anticipated Annual Revenue: Not sure at this time (feasibility phase); will also depend on how much of the wind turbines and their installation is paid for through other resources than APCs. Potential Additional Annual Incentives: N/A Potential Additional Annual Revenue Streams: N/A Non-economic Public Benefits to Alaskans: Over the lifetime of the project the residents of Tok would have reduced air emissions (5 million to 9.6 million pounds of CO2;7 based on estimate of fuel saved above) and noise pollution from the operation of the diesel plant. The transport of fuel from Fairbanks to Tok would be reduced, reducing the potential for leaks and spills along the Alaska Highway. Transferring fuel from a supply truck to the APC storage tank would be less frequent, reducing the potential for spills during fueling, keeping groundwater safer for the area. 5.1.1 Public Benefit for Projects with Private Sector Sales Projects that include sales of power to private sector businesses (sawmills, cruise ships, mines, etc.), please provide a brief description of the direct and indirect public benefits derived from the project as well as the private sector benefits and complete the table below. See section 1.6 in the Request for Applications for more information. N/A Renewable energy resource availability (kWh per month) Estimated sales (kWh) Revenue for displacing diesel generation for use at privet sector businesses ($) Estimated sales (kWh) Revenue for displacing diesel generation for use by the Alaskan public ($) 7 One gallon of diesel produces 20 lbs of CO2. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 20 of 24 7/1/2013 SECTION 6– SUSTAINABILITY Discuss your plan for operating the completed project so that it will be sustainable. Include at a minimum:  Proposed business structure(s) and concepts that may be considered.  How you propose to finance the maintenance and operations for the life of the project  Identification of operational issues that could arise.  A description of operational costs including on-going support for any back-up or existing systems that may be require to continue operation  Commitment to reporting the savings and benefits Proposed Business Structure: APC would own and operate the project. As the local utility, APC has been in operation since 1957. APC is capable of operating and maintaining this project for its design life. APC has the experience and ability to operate this project. APC has tested, operated, and maintained various renewable energy projects throughout the state of Alaska and is adept at integrating renewable resources with a diesel generation based community. O&M Financing: Financing for O&M would come from APC general operation funds. Operational Issues that may Arise: None known at this time. Commitment to Reporting the Savings and Benefits: If a wind project were constructed, APC would file annual reports for a period of five years summarizing savings and benefits; or more if requested by AEA. SECTION 7 – READINESS & COMPLIANCE WITH OTHER GRANTS Discuss what you have done to prepare for this award and how quickly you intend to proceed with work once your grant is approved. Tell us what you may have already accomplished on the project to date and identify other grants that may have been previously awarded for this project and the degree you have been able to meet the requirements of previous grants. APC has a NRG-NOW System 50m XHD met tower with anchors ready to go. No other grants have been awarded for this project. (new project in feasibility stage) APC has been able to meet the requirements of previous grants with one exception where additional time has been needed (Connelly Lake Hydro). SECTION 8 – LOCAL SUPPORT AND OPPOSITION Discuss local support and opposition, known or anticipated, for the project. Include letters of support or other documentation of local support from the community that would benefit from this project. The Documentation of support must be dated within one year of the RFA date of July 2, 2013. We are currently working to receive support from the Tetlin Village Council in the form of granting permission to access and install a met tower on Chisana Mountain. A copy of our letter is included in the Appendices. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 21 of 24 7/1/2013 SECTION 9 – GRANT BUDGET Tell us how much you are seeking in grant funds. Include any investments to date and funding sources, how much is being requested in grant funds, and additional investments you will make as an applicant. Provide a narrative summary regarding funding source and your financial commitment to the project Please provide a short narrative, and cost estimate, identifying the metering equipment, and its related use to comply with the operations reporting requirement identified in Section 3.15 of the Request for Applications. Applications MUST include a separate worksheet for each project phase that was identified in section 2.3.2 of this application, (I. Reconnaissance, II. Feasibility and Conceptual Design, III. Final Design and Permitting, and IV. Construction and Commissioning). Please use the tables provided below to detail your proposed project’s budget. Be sure to use one table for each phase of your project. If you have any question regarding how to prepare these tables or if you need assistance preparing the application please feel free to contact AEA at 907-771-3031 or by emailing the Grant Administrator, Shawn Calfa, at scalfa@aidea.org. Phase II Milestone or Task Anticipated Completion Date RE- Fund Grant Funds Grantee Matching Funds Source of Matching Funds: Cash/In- Kind/Federal Grants/Other State Grants/Other TOTALS Authorization to Proceed 07/01/14 Contact USF&WS and FAA 08/31/14 $1,600.00 $400.00 Cash $2,000.00 Land Use Authorization 08/31/14 $4,000.00 $0.00 $4,000.00 Acquire Met Tower 08/01/14 $0.00 $15,800.00 In-Kind $15,800.00 Mobilize Equipment out to Project site 08/31/14 $2,000.00 $0.00 $2,000.00 Met tower installation at Chisana Mtn site 09/30/14 $9,600.00 $2,400.00 Cash $12,000.00 Met Tower Maintenance 10/31/16 $5,600.00 $1,400.00 Cash $7,000.00 Geotech Study for Foundation Design 10/31/15 $20,000.00 $5,000.00 Cash $25,000.00 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 22 of 24 7/1/2013 Analysis of Permitting & Environmental Issues for Phases III & IV 11/30/15 $5,000.00 $0.00 $5,000.00 Download Wind Data for Analysis 10/31/15 $3,200.00 $800.00 Cash $4,000.00 Renewable Energy Modeling & Design 03/31/2016 $30,000.00 $0.00 $30,000.00 Draft Conceptual Design Report 03/31/2016 $16,000.00 $4,000.00 Cash $20,000.00 Final Feasibility & Conceptual Design Report 07/31/16 $19,000.00 $0.00 $19,000.00 Remove Met Tower 08/31/2016 $3,000.00 $0.00 $3,000.00 TOTALS $119,000.00 $28,800.00 $148,800.00 Budget Categories: Direct Labor & Benefits $44,000.00 $11,000.00 Cash $55,000.00 Travel & Per Diem Cash $0.00 Equipment $0.00 $15,800.00 In-Kind $15,800.00 Materials & Supplies Cash $0.00 Contractual Services $75,000.00 $3,000.00 Cash $78,000.00 Construction Services Cash $0.00 Other TOTALS $119,000.00 $29,800.00 $148,800.00 Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 23 of 24 7/1/2013 SECTION 10 – AUTHORIZED SIGNERS FORM Community/Grantee Name: Alaska Power Company (APC) Regular Election is held: Date: May Authorized Grant Signer(s): Printed Name Title Term Signature Glen D. Martin Mgr Permitting, Licensing, Grant Writing Permanent /s/ Glen D. Martin Karl Wood Grant Administrator Permanent /s/ Karl Wood I authorize the above person(s) to sign Grant Documents: (Highest ranking organization/community/municipal official) Printed Name Title Term Signature Robert S. Grimm CEO/President Permanent /s/ Robert S. Grimm Grantee Contact Information: Mailing Address: P.O. Box 3222 Port Townsend, WA 98368 Phone Number: 360-385-1733 x122 – Glen Martin 360-385-1733 x128 – Karl Wood Fax Number: 360-385-7538 E-mail Address: glen.m@aptalaska.com karl.w@aptalaska.com Federal Tax ID #: 92-0153693 Please submit an updated form whenever there is a change to the above information. Renewable Energy Fund Round VII Grant Application - Standard Form AEA 2014-006 Grant Application Page 24 of 24 7/1/2013 SECTION 11 – ADDITIONAL DOCUMENTATION AND CERTIFICATION SUBMIT THE FOLLOWING DOCUMENTS WITH YOUR APPLICATION: A. Contact information, resumes of Applicant’s Project Manager, key staff, partners, consultants, and suppliers per application form Section 3.1 and 3.4. Applicants are asked to provide resumes submitted with applications in separate electronic documents if the individuals do not want their resumes posted to the project web site. B. Letters or resolutions demonstrating local support per application form Section 8. C. For heat projects only: Most recent invoice demonstrating the cost of heating fuel for the building(s) impacted by the project. D. Governing Body Resolution or other formal action taken by the applicant’s governing body or management per RFA Section 1.4 that: - Commits the organization to provide the matching resources for project at the match amounts indicated in the application. - Authorizes the individual who signs the application has the authority to commit the organization to the obligations under the grant. - Provides as point of contact to represent the applicant for purposes of this application. - Certifies the applicant is in compliance with applicable federal, state, and local, laws including existing credit and federal tax obligations. E. An electronic version of the entire application on CD or other electronic media, per RFA Section 1.7. F. CERTIFICATION The undersigned certifies that this application for a renewable energy grant is truthful and correct, and that the applicant is in compliance with, and will continue to comply with, all federal and state laws including existing credit and federal tax obligations and that they can indeed commit the entity to these obligations. Print Name Glen D. Martin Signature /s/ Glen D. Martin Title Manager Permitting, Licensing, Grant Writer Date September 13, 2013