HomeMy WebLinkAboutGunnuk Creek Appendix AHydropower Reconnaissance Report for Kake, Alaska — 2013
Introduction
Existing electrical load in Kake is approximately 350 kVVwithout Cold Storage operations, approximately
800 kW while the Cold Storage is running. The local utility is owned by IPEECand they run diesel
generators to produce electricity. Approximately 216,000 gallons of diesel was burned for electricity in
2012 at a total cost of $860,000. The cost of electricity in Kake during 2012 was 63 cents per M. Sate
PCEsubsidiesfor Kake residential energy totaled $480,000 in 2012 (see attached PCEstats page).
CLrrently, the Ftl only applies to residential use that does not exceed 500 M.
Hydropower development options near the community of Kake are limited because of relatively gentle
topography and regionally low precipitation, however, both Gunnuk and Cathedral Falls systems have
been evaluated to some degree in the past. In recent years the State of Alaska and IP[Ehave been
focusing on developing the Kake-Petersburg Intertie for delivering hydroelectricity to Kake.
The Kake-Petersburg Intertie (M) has been studied by consultants and agencies for over 10 years and
has been discussed as an infrastructure need for at least 40 years. Recent studies have concluded that
the 1,R cannot provide a guaranteed supply of hydroelectricity to meet Kake's total load forecast
because of contractual obligations to the communities of Wrangell, Petersburg and Ketchikan (see Kake-
Petersburg Transmission Intertie Study Update, 2012). The 2009 estimated cost of the PI is expected to
be 3040 million dollars resulting in an estimated consumer side cost of approximately 34 oents per
kWh. In light of this information we believe it is worth taking another look at local hydropower options
to complement a possible PR.
Basic Etats for Hydro -feasibility in the G.Annuk Creek Watershed
• The Gannuk Creek watershed isapproximately 10,000 acres.
• There are approximately 38 miles of stream in the watershed.
• The land is owned by 9ALASM and Kake Tribal Corporations and there is a ,'T--ALIRJSr
conservation easement within the watershed (see attached map).
• There is an existing dam at —125 feet elevation that was designed to provide reliable drinking
water and run of the river power (up to 11 kW) for the Gunnuk Creek Hatchery.
• The Hatchery currently has aooessto 22 cis of flow for overall operations
• A small lake (Alpine Lake) exists in the upper reaches of a secondary tributary to Clannuk Creek
and currently provides drinking water to the community. Approximately .5 cfs is currently
required to meet local water consumption. Community water was historically provided by
Gunnuk Creek at the 125' dam site but is now being pulled from Alpine Lake because of
economic considerations There is concern in the community that the Alpine Lake site provides a
less healthy water supply because the lake is relatively stagnant. Development of a hydro -facility
could allow for returning the water tap to the Kake Dam and improving drinking water quality.
Based on US3Sflow data for 2005-2008, annual mean flow at the hatchery site rangesfrom 77
ds to 111 cfs, monthly mean flows range from 36 cfs to 167 cfs, daily mean below 40 cts occ ur
approximately 45 %of the total USGSrecord and for up to 5 weeks at a time, daily mean below
60 cfs occur approximately 58 %of the total U83Srecord and for up to 5 weeks at a time.
Hydroelectrical Development Options
A study was conducted in 1977 that looked at developing hydroelectrical power in Qannuk (reek by
impounding the primary tributaries into a 586 acre lake (see attached). The study estimated that this
reservoir could provide a continuous flow of 75 cfs to a 1,000 kW powerhouse.
Alternatively, we have been studying the possibility of creating smaller reservoirs (136 & 141 Acres
acres) in two different tributaries of the Gunnuk Watershed (see attached).
In the Al pine Lake Scenario, the reservoir would be used to augment total Creek flows during low flow
periods in a run of the river scenario that would include an intake at 330 feet of elevation and a 2.5-2.75
mile penstock (depending on powerhouse location). Rows into Alpine Lake basin are unknown but are
estimated to bean annual mean of 7.5 cfs. There is an out of basin opportunity for augmenting flows to
Alpine Lake from the Turn Mountain watershed that is estimated to have an annual mean of 7.5 cfs.
In the Qannuk Lake Scenario, the reservoir would provide the sole source of flow to the powerhouse.
Annual mean flowsto this reservoir are estimated at 13.5 cfs. There is an out of basin stream nearby
that would provide an additional annual mean of 9 ds and derivesfrom elevations and slopesthat may
be favorable for capturing late spring snow melt . This scenario would require less fill, would capture
more flow at the reservoir and provide considerably more head than the Alpine Lake Scenario but it
would require a longer penstock (4.4 miles vs 3 miles).
Some questionsthat need to be answered to better understand the feasibility of these designs are:
1. Can these reservoir designs be maintained by existing+out of barn flows under adequate
power generation scenarios?
2. Which, if any, of the designs are economically feasible?
The table below summarizes a rough estimate of power availability for the two designs described above.
Alpine Lake Scenario
K/ at 20 cfs
KW at 40 cfs
KW at 60 cfs
Power Available at Dam Ste (200' Head)
268
531
999
Power Available at Hatchery Ste (300' Head)
370
734
1105
136 Acre Feservoir Capacity (in days)
397
200
133
Gunnuk lake Scenario
KW at 20 cfs
KW at 40 cfs
KW at 60 cfs
Power Available at Dam Ste (400' Head)
536
1062
1597
Power Avallable at Hatchery Ste (475' Head)
634
1256
1890
141 Acre Reservoir Capacity (in days)
198
100
67
Initial reconnaissance of the Alpine Lake option suggests that it would be worth conducting some stream
gaging and rough design work for cost -benefit analysis. The attached map indicates the location of three
gaging locations that would provide information on out of basin water supply, existing lake recharge
rates and total combined flow at a possible intake site. Our hope is that IPEC, the city of Kake, Kake
Tribal Corp and the Organized Village of Kake would consider using this report as a bas sfor submitting a
joint proposal to AEA to develop a more robust feasibility study Gunnuk Creek Hydroelectrical potential.
Kake Fa
Utility: I N8 DE PASS4GE 9 EcTHC
R4"tin9PLrioc!- 07/01111..0&/30112
Community Population
557
Last Peported Month
June
No. of Monthly Payments Made
12
ilsidential Customers
235
Community Facility Customers
16 R
Other Customers (Non-PCF)
56
Fiscal Year PCEPayments
x
$479,138 - -- -b•"
PCE Statistical Data
PCE9igiblekM- Residential Customers
893,785
AverageAnnual PCEPaymentper Eligible
$1,909
Customer
I�EligiblekWh-CbmmunityFacility
238,531
Average PCEPaymentper 9igiblekM
$0.42
Customers
Total FC Bigible kWh
1,132,316
Last Reported ibadential Rye Charged
$0.63
(based on 500 kWh)
Average Monthly PCE9igiblekWh per
317
Last imported PC=Level (per kWh)
$0.42
Residential Customer
Average Monthly PCE9igible kWh per
1,242
Effective Residential Rate (per kWh)
$021
Cbmmunit Facility Customer
Average Monthly PCEBigible Clommunity
36
PCE9igiblekMvsTotalk 'bid
43.4%
Facility kWh per person
Additional Statistical Data
Reported by Co nrnunity`
Generated and Purchased kM26,541
Generation Costs
Diesel kWh Generated
Fuel Used (Gallons)
216,348
Non -Diesel kWh Generated
Fuel Cost
$862,275
Purchased kWh
Average Rice of Fuel
$3.99
Total Ftirc based & Generated
Annual Non -Fuel E ¢penses
$580,032
Non -Fuel 6¢�ense per kWh sold
$0.22
Omwmed and Sold kWh
E fiaency and Une Loss
Fesidentid kWh SbId*kM51,800
8,439
Consumed vs Generated (kWh SbId vs
90.4%
Generated-Purdhased
Community Facility kWh S>Id7,737
Line Loss (%)
Other kWh Sold Pon-PCB3,806
Fuel Efficiency (kWh per gallon of diesel)
7 $%
13.34
Total kWh SbId9
982
rbwerhouse (PI-() Consumption
Total kWh Wid & Ffi Cbnsump,1,
782
comments
7hedata contained inthisreportisprimarilybased oninformation submittedbytheutilitywiththeirmonthlyFCEreports Changesto
the reported data andror significant anomalies have been noted in the comments
Fbge 74 of 179