HomeMy WebLinkAboutAEA Round VII Grant Application with Attachments - SEAPA Wind Resource AssessmentRenewable Energy Fund Round VII
Grant Application -Standard Form
Application Forms and Instructions
This instruction page and the following grant application constitutes the Grant Application Form
for Round VII of the Renewable Energy Fund. A separate application form is available for
projects with a primary purpose of producing heat (see RFA section 1.5). This is the standard
form for all other projects, including projects that will produce heat and electricity . An electronic
version of the Request for Applications (RFA) and both application forms is available online at:
http://www.akenergyauthority .org/REFund7 .html .
• If you need technical assistance filling out this application, please contact Shawn Calfa,
the Alaska Energy Authority Grant Administrator at (907) 771-3031 or at
scalfa@aidea.org . ·
• If you are applying for grants for more than one project, provide separate application
forms for each project.
• Multiple phases for the same project may be submitted as one application.
• If you are applying for grant funding for more than one phase of a project, provide
milestones and grant budget for each phase of the project.
• In order to ensure that grants provide sufficient benefit to the public, AEA may limit
recommendations for grants to preliminary development phases in accordance with 3
ACC 1 07 .605(1).
• If some work has already been completed on your project and you are requesting
funding for an advanced phase, submit information sufficient to demonstrate that the
preceding phases are completed and funding for an advanced phase is warranted.
• If you have additional information or reports you would like the Authority to consider in
reviewing your application, either provide an electronic version of the document with
your submission or reference a web link where it can be downloaded or reviewed.
• In the sections below, please enter responses in the spaces provided, often under the
section heading. You may add additional rows or space to the form to provide 9ufficient
space for the information, or attach additional sheets if needed.
REMINDER:
• Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials
submitted to the Authority may be subject to disclosure requirements under the act if no
statutory exemptions apply .
• All applications received will be posted on the Authority web site after final
recommendations are made to the legislature.
• In accordance with 3 AAC 107.630 (b) Applicants may request trade secrets or
proprietary company data be kept confidential subject to review and approval by the
Authority . If you want information is to be kept confidential the applicant must:
o Request the information be kept confidential.
o Clearly identify the information that is the trade secret or proprietary in t heir
application.
o Receive concurrence from the Authority that the information will be kept
confidential. If the Authority determines it is not confidential it will be treated as a
public record in accordance with AS 40.25 or returned to the applicant upon
request.
AEA 2014-006 Application Page 1 of 22 7/2/2013
Renewable Energy Fund Round VII
Grant Application - Standard Form
SECTION 1-APPLICANT INFORMATION
Name (Name of utility, IPP, or government enti ty submitting proposal)
The Southeast Alaska Power Agency ('SEAPA')
Type of Entity: Joint Action Agency Fiscal Year End: June 30
Tax ID #92-01746698 Tax Status: __ For-profit
Date of last financial statement audit: June 30, 2012
X
Mailing Address Physical Address
Non-profit _Government (check one)
1900 First Avenue, Suite 318 Same as Mailing
Ketchikan, Alaska 99901
Telephone Fax Email
(907) 228-2281 (907) 225-2287 sthompson@.seapahydro.ora
1.1 APPLICANT POINT OF CONTACT I GRANTS MANAGER
Name Title
Trey Acteson Chief Executive Officer
Mailing Address
1900 First Avenue, Suite 318, Ketchikan, Alaska 99901
Telephone Fax Email
(907) 228-2281 (907) 225-2287 tacteson@seapahydro.org
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2 .1 As an Applicant, we are: (put an X in the appropriate box)
An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
An independent power producer in accordance with 3 AAC 107.695 (a) (1), or
A local government, or
X A governmental entity (which includes tribal councils and housing authorities);
Yes 1.2.2 Attached to this application is formal approval and endorsement for the project by
the applicant's board of directors, executive management, or other governing
authority. If the applicant is a collaborative grouping, a formal approval from each
participant's governing authority is necessary. (Indicate Yes or No in the box)
Yes 1.2.3 As an applicant, we have administrative and financial management systems and
follow procurement standards that comply with the standards set forth in the grant
agreement (Section 3 of the RFA).
Yes 1.2.4 If awarded the grant, we can comply with all terms and conditions of the award as
identified in the Standard Grant Agreement template at
httg://www. akenergyauthority. org/veeg/Grant-T emglate . gdf. (Any exceptions
should be clearly noted and submitted with the application.)
-
AEA 2014-006 Grant Application Page 2 of 22 71112013
Grant Application -Standard
Yes 1.2.5 We intend to own and operate any project that may be constructed with grant
funds for the benefit of the general public. If no please describe the nature of the
project and who will be the primary beneficiaries.
SUMMARY
This section is intended to be no more than a 2-3 page overview of your project.
2.1 Project Title -(Provide a ~ to word title your project). Type in space below.
SEAPA Wind Resource Assessment (Phases! & II)
2.2 Project location-
fnclude the physical location of your project and name(s) of the community or communities that will
benefit from your project in the subsections below.
2.2.1 location of Project-latitude and longitude, street address, or community name.
Latitude and longitude coordinates may be obtained from Google Maps by finding you project's location on the map
and then right clicking with the mouse and selecting "What is here? The coordinates will be displayed in the Google
search window above the map in a format as follows: 61.195676.-149.898663. If you would like assistance obtaining
this information please contact AEA at 907-771-3031.
Applicant accepted delivery of a 34=meter meteorological tower ('Met Tower') from the Alaska
Energy Authority in July 2013 and seeks to conduct a reconnaissance and feasibility analysis for
placement of the Met Tower along transmission line paths owned by SEAPA, which extend from
the City of Ketchikan, Alaska, located on the westem coast of Revillagegedo Island, near the
southernmost boundary of Alaska, to the Petersburg Borough, located on the north end of Mitkof
Island in Southeast Alaska.
Community benefiting-Name(s) of the community or communities that will be the
beneficiaries of the project.
The project is proposed to determine if it is feasible to use wind power to supplement the energy
needs and displace diesel generation for the communities serviced by SEAPA, which include
Ketchikan, Petersburg, and Wrangell, with the long~term objective and goal of serving the power
needs of additional communities, including Kake.
2.3 PROJECT TYPE
Put X in boxes as appropriate
2.3.1 Renewable Resource Type
X Wind Biomass or Biofuels (excluding heat-only)
Hydro, Including Run of River Hydrokinetic
Geothermal, Excluding Heat Pumps Transmission of Renewable Energy
Solar Photovoltaic Storage of Renewable
Other (Describe) Small Natural Gas
2.3.2 Proposed Grant Funded Phase(s) this Request (Check all that apply)
Pre-Construction --r Construction
X Reconnaissance Final Design and Permitting
X Feasibility and Conceptual Design Construction and Commissioning
I
AEA 2014-006 Grant Apphcatmn Page 3 of 22 7/1/2013
nd
ication -Standard
2.4 PROJECT DESCRIPTION
Provide a brief one paragraph description of the proposed project.
Applicant accepted delivery of a 34-meter meteorological tower ('Met Tower') from the Alaska
Energy Authority in July 2013 and seeks to conduct a reconnaissance and feasibility analysis to
determine if it is feasible to use wind power to supplement the energy needs and displace diesel
for the communities serviced by SEAPA. After the site assessment has determined the most
suitable site for collection of raw wind data, the MET Tower will be installed to gather two (2) years
of wind data for a thorough analysis. An analysis of the wind data and a final report will be
performed by a qualified consultant specializing in the field.
2.5 PROJECT BENEFIT
Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel
costs, lower energy costs, focal jobs created, etc.)
The proposed project phases will provide the information required to carry out the next steps of a
wind tmbine project to determine whether the wind resources are suited for integration into
SEAPA's existing transmission system to provide supplemental power and displace diesel
generation for the communities of Ketchikan, Petersburg, and Wrangell. SEAPA recognizes that
additional interties may be built to serve communities, including Kake, and additional generation
resources will be required to serve those loads. A feasibility study will be necessary to determine
if viable wind resources are present along the existing SEAPA transmission corridor. If wind
resources are determined by the study to be adequate and at locations where the construction
and maintenance of wind turbines are feasible, the following benefits may be realized:
., Displaces diesel generation
., Reduces carbon emissions
® Adds energy in winter months when it is most needed
" Provides energy source diversification
* Provides a bridge solution to meet near-term generation needs, allowing more time ti
develop the next increment of hydro
• Increased awareness for residents of the communities currently being served, and future
communities that may be served, with a greater understanding of whether wind generation
can play a role in providing renewable energy within the SEAPA region and the extent of
this role
• The State of Alaska benefits from wind resource information obtained for the Southeast
Alaska region
2.6 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source
of other contributions to the project.
Phase 1: SEAPA requests funding of $37,511 with a 5% cash match of $1,974, and in-kind
contribution of $2,456 from SEAPA for a total cost of $41,941 for Phase I of its project.
Phase II: SEAPA requests funding of $121,260 with a 5% cash match of $6,382, and in-kind
contribution of $1,000 from SEAPA for a total cost of $128,642 for Phase II of this project
AEA 2014-006 Grant
Renewable Fu Round VII
Grant ication -Standard Form
Project Phase Requested
Grant Fundin
I $37,511
II $121,260
Totals $158,771
Contribution
$2,456*
$1,000**
$3,456
*storage fees from 711112013-1010112014 for housing MET Tower@ $156/mo.
**SEAPA administrative fees
Totals
$41,941
$128,642
SEAPA's in-kind contributions to the project are estimated at $3,456, which include storage fees
to house the tower and administrative oversight of the project. To further support the SEAPA
team in project delivery, a qualified consultant will be selected. The bulk of the analysis effort and
some of the project management at the task level will be provided by the consultant Total cost of
this project, which includes SEAPA's 5% cash match and in-kind contribution is $170,583.
COST AND BENEFIT SUMARY
Include a summary of grant request and your project's total costs and benefits below.
Grant Costs
(Summary of funds requested)
2.7.1 Grant Funds Requested in this application $158,771
2.7.2 Cash match to be provided $ 8,356
2.7.3 In-kind match to be provided $ 3,456
2.7.4 Other grant funds to be provided $0
2.7.5 Other grant applications not yet approved $0
2.7.6 Total Grant Costs (sum of 2.7.1 through 2.7.4) $ 70,583
Project Costs & Benefits
{Summary of total project costs including work to date and future cost estimates to get to a fully
operational project)
2.7.7 Total Project Cost Summary from Cost Worksheet, Section $170,583
4.4.4, including estimates through construction.
2.7.8 Additional Performance Monitoring Equipment not covered $ (N/A)
by the project but required for the Grant Only applicable to
construction phase projects.
2.7.9 Estimated Direct Financial Benefit (Savings) $ (to be determined)
2.7.10 Other Public Benefit If you can calculate the benefit in terms $ (to be determined)
of dollars please provide that number here and explain how you
calculated that number in Section 5 below
Note: This grant application is for a wind resource assessment and
therefore estimations of any future wind generation is inappropriate.
AEA 2014-006 Grant
ble Fund nd
Grant Application -Standard Form
SECTION 3-PROJECT MANAGEMENT
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include contact information, a
resume and references for the manager(s). In the electronic submittal, please submit resumes
as separate PDFs if the applicant would like those excluded from the web posting of this
application. If the applicant does not have a project manager indicate how you intend to solicit
project management support If the applicant expects project management assistance from
AEA or another government entity, state that in this section.
SEAPA would provide overall project management and oversight. To further support the SEAPA
team in project delivery, a qualified consultant who specializes in the field would be selected. The
bulk of the analysis effort and some of the project management at the task level would be
provided by the consultant.
Eric Wolfe, a SEAPA employee, and current Director of Special Projects, will be the Project
Manager. Mr. Wolfe has 25 years of utility engineering and management experience. Mr. Wolfe
has advised utilities on: hydro turbine and hydroelectric plant sizing, lost revenue effects
resulting from reiicensing mitigation, forward production and cost estimates, and system
operations. Mr. Wolfe's resume is included with this application in Attachment A hereto.
3.2 Project Schedule and Milestones
Please fill out the schedule below. Be sure to identify key tasks and decision points in your
project along with estimated start and end dates for each of the milestones and tasks. Please
clearly identify the beginning and ending of all phases of your proposed _groject
Please fill out fonn provided below. You may add additional rows as needed.
Phase I
Milestones Tasks Start Date End Date
Acceptance of Delivery of MET Arrange storage for MET Tower until 07/11/2013 11/01/2014 Tower by SEAPA installation
Project Scoping and Consultant Develop and issue RFP for bids 07/2014 08/15/2014 Solicitation
Site Assessment Preparation Review GIS shapefiles, existing transmission
and Reconnaissance right-of-ways, aerial photographs,
contours/elevations, and additional wind data 09/01/2014 09/15/2014
that may be available in SEAPA's grid to
determine placement of MET Tower
Permitting After suitable location for MET Tower is
identified, determine whether SF-299 form
needed if site is on federal lands; conduct
research to determine if permit approvals
required on State lands; review SEAPA's
existing Special Use Permit & Easements if
suitable location is identified within an 09/15/2014 10/31/2014
existing transmission ROW or FERC
boundary associated with SEAPA's hydro
facilities. Determine whether NEPA process
is required for installation of the tower.
AEA 2014-006 Grant Application
nd I
Grant Application -Standard Form
MET Tower Installation
(Installation is weather
dependent depending on site
selected for instal!aUon)
Wind Data Collection
(two-year period)
Wind Resource & Assessment
Reporting
3.3 Project Resources
PHASEU
Determine whether brush clearing needed at
site for installation; raise tower into place;
calibrate and test all associated equipment.
Collection, quality-control, and archival of all
wind data from project site. Monitor quality
and status of collected data; equipment
failures to be flagged and identified through
secure web portal to reduce data loss; data
quality controlled and brief report produced to
summarize data collected on a regular basis,
subject to weather restrictions.
Complete wind resource assessment to be
performed including review of meteorological
program, analysis of wind resource
characteristics, climate adjustment,
extrapolation to hub height, estimation of
wind resource uncertainty. Provide
comprehensive wind resource report for on-
site MET Tower, to include detailed
description of the wind resource assessment
and uncertainties (detailed tables and charts
summarizing meteorological data to be
included)
11/01/2014 11/07/2014
11/07/2015 11/07/2017
11/07/2017 11/14/2017
Describe the personnel, contractors, accounting or bookkeeping personnel or firms, equipment,
and services you will use to accomplish the project. Include any partnerships or commitments
with other entities you have or anticipate will be needed to complete your project. Describe any
existing contracts and the selection process you may use for major equipment purchases or
contracts. include brief resumes and references for known, key personnel, contractors, and
suppliers as an attachment to your application.
The primary personnel for both phases of this project will be consultants with previous wind
power experience, who are familiar with SEAPA's transmission line path and the Southeast Alaska
area in general, and have the resources available to conduct a wind site assessment, analysis of
the permitting and any environmental studies that will be required, installation of the MET Tower,
collection of raw data, and analysis of the data to prepare a wind assessment report. SEAPA staff
will team up with these consultants through all phases to see the project through to completion.
SEAPA staff and their role in the project include:
J;> Trey Acteson, Chief Executive Officer, would act as Project Executive and will maintain
ultimate authority programmatically and financially.
J;> Eric Wolfe, Director of Special Projects, would lead the project management team
consisting of SEAPA staff and consultants/contractors. Together with his team, Mr. Wolfe
would provide coordination of the installation of the MET Tower and permitting
requirements.
);.> Steve Henson, Operations Manager, would provide technical assistance and information
on the existing transmission line paths, possible issues, and accessibility for the wind site
assessment
);.> Kay Key, Controller, would provide support in accounting, payables, and financial
reporting in accordance with AEA guidelines.
);.> Sharon Thompson, Executive Assistant, would prepare contract documents, an·o:mge
travel to project site, effect communications with consultant, and assist Controller in
tracking project activities for grant reporting.
The resumes of Tr cteson and Eric Wolfe are included in Attachment A to this application.
AEA 2014-006 Grant Application Page 7 of 22 7/1/2013
Renewable Energy Fund Round VII
Grant Application -Standard Form
3.4 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
Please provide an alternative contact person and their contact information.
SEAPA's project manager will communicate with consultant to effect milestones during both
phases of the project. SEAPA's Project Manager and Operations Manager will travel with
consultant to oversee installation of the MET Tower. Consultant will collect wind data for 24
months and provide regular summary reports to SEAPA, which will be available for download 15
days after the close of each month. Reports will include wind speed and shear averages at the
primary monitoring level, wind speed averages at all other monitoring levels, wind speed
extremes and standard deviations at the primary monitoring level, time and energy-weighted wind
direction rose, and plots of daily average speeds and diurnal variation. Authority will be informed
of the status via project progress reports to be submitted to the Authority in accordance with AEA ·
guidelines. Alternative contact person: Sharon Thompson, Executive Assistant, Southeast
Alaska Power Agency, 1900 First Avenue, Suite 318, Ketchikan, Alaska 99901; Ph. (907) 228-2281;
Email sthompson@seapahydro.org .
3.5 Project Risk
Discuss potential problems and how you would address them.
Remote areas in Southeast Alaska may present problems in project logistics and placement of the
MET Tower. Adverse weather could also cause project delays; however, an experienced
consultant/contractor, familiar with Alaska weather conditions, would be selected. Good team
planning and reliance on local knowledge about conditions along SEAPA's transmission line
would help mitigate any risks.
Any environmental permitting issues would be mitigated by hiring an environmental consultant
familiar with permitting wind projects in Alaska . Early consultations with agencies would occur in
order to flesh out location, avian concerns, including specific species, and mitigation issues. The
consultant would work openly with agencies and conduct studies as appropriate.
Although we believe a MET Tower is a minimal environmental risk, the consultant would
determine whether any National Environmental Policy Act (NEPA) documentation will be required.
SECTION 4-PROJECT DESCRIPTION AND TASKS
• The level of information will vary according to phase(s) of the project you propose to
undertake with grant funds.
• If some work has already been completed on your project and you are requesting funding for
an advanced phase, submit information sufficient to demonstrate that the preceding phases
are satisfied and funding for an advanced phase is warranted.
4 .1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project. For pre-construction applications, describe
the resource to the extent known. For design and permitting or construction projects, please
provide feasibility documents, design documents, and permitting documents (if applicable) as
attachments to this application.
For a wind project to be successful there is a clear need to ensure that an adequate wind resource
is available. Indicators of success include the use of reliable turbines, a high wind class, and
favorable environmental conditions. It is critical to have a full and detailed wind site assessment for
AEA 2014-006 Grant Application Page 8 of 22 7/1/2013
Renewable Energy Fund Round VII
Grant Application -Standard Form
placement of the MET Tower to determine whether a strong wind resource is available to produce a
high capacity factor to meet expectations.
The windy, rainy climate of Southeast Alaska is strongly influenced by the Pacific Ocean and
coastal mountains. It is prudent to conduct a wind assessment along SEAPA's transmission line
corridor to flesh out untapped wind resources that have not been previously studied. The quality of
the wind resource will be analyzed to ensure that it is compatible with wind generation
development.
While wind resources in Southeast Alaska conducive to generation may or may not be present, the
synergistic relationship of wind generation with existing hydro is enticing. Hydro can pick up the
load when wind falters and the wind energy contributes by allowing the hydro plants to conserve
water by not operating when wind energy is available. Kodiak Electric Association installed wind
turbines to supplement their existing hydro from Terror Lake and this project has been remarkably
successful.
While development of wind and hydro are ongoing, another plausible source of energy that could be
developed is geothermal; however, the closest source that could be tapped which is close enough
to tie into SEAPA's existing Swan-Tyee lntertie is Bell Island. Although the property is currently up
for sale, the owners had applied for three geothermal leases which were pending a consent
determination from the BLM for issuance. Actual development of geothermal would take years
pending the permitting process. No geotechnical drilling to determine whether geothermal
resources are present at that site has yet been undertaken.
As discussed in the AEA's Renewable Energy Atlas of Alaska, significant utility-scale solar
generation is unlikely in Alaska due to high capital costs and low annual solar power output.
While biomass used for heating is an exciting and welcomed technology in the SEAPA region, the
production of power from biomass is questionable due to a myriad of issues including
environmental and supply-side concerns. A careful look at the biomass energy pros and cons
reveals that it is far from the perfect energy source, but is still very promising as a replacement for
the fossil fuels currently in use for heating.
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about
the number, size, age, efficiency, and type of generation.
Swan Lake Plant
Unit 1
Unit 2
Tyee Lake Plant
Unit 1
Unit 2
Ketchikan Plant
Unit 3
Unit4
Unit 5
EXISTING GENERATION
KETCHIKAN , PETERSBURG , AND WRANGELL
Type Year Installed MW/kw
Capacity
SEAPA HYDRO
25MW
Francis 1983 12.5 MW
Francis 1983 12.5 MW
25MW
Pelton 1984 12.5 MW
Pelton 1984 12.5 MW
KETCHIKAN PUBLIC UTILITIES (KPU) HYDRO
4.2MW
Francis 1923 1.4 MW
Francis 1938 1.4 MW
Francis 1957 1.4 MW
AEA 2014-006 Grant Application Page 9 of 22
Average
Hydro Enerav (MWh)
76,000 MWh
120,000 MWh
22,500 MWh
7/1/2013
Energy Rou
Grant Application -Standard
Silvis Plant Francis 1967 2.1 MW 12,800 MWh
Beaver Falls Plant 5MW 43,400 MWh
Unit 1 Pelton 1946 (1904) 1MW
Unit 3 Pelton 1954 2MW
Unit4 Pelton 1954 2MW
KPU DIESEl
Bailey Power Plant 23MW
Unit 1 Diesel 1969 3.5MW
Unit2 Diesel 1969 3.5MW
Unit 3 Diesel 1976 5.5MW
Unit4 Diesel 1998 10.5 MW
North Point Higgins 3.2MW
CAT 1 Diesel 2005 1.6MW
CAT 1 Diesel 2005 1.6MW
PETERSBURG MUNICIPAL POWER & LIGHT (PMP&L) HYDRO
Blind Slough Hydro Pelton 1955* 1.75 MW 13,000 MWh
(*In 1982, a new stainless
steel runner was installed
on Pelton wheel)
PMP&L Diesel 11.8 MW
Unit 1 Diesel 1965 1,200 kW
Unit2 Diesel 1979 580 kW
Unit 3 Diesel 1979 680 kW
Unit4 Diesel 1972 2.1 MW
Unit 5 Diesel 1994 2.5MW
Unit6 Diesel 2000 2.5MW
Unit 7 Diesel 2012 2.25 MW
WRANGELL MUNICIPAL LIGHT & POWER (WML&P)
WML&P Diesel 8.5MW
Unit 2 Diesel 2001 2.0MW
Unit 3 Diesel 2003 2.0MW
Unit 4 Diesel 2002 2.0MW
Unit 5 Diesel 1982 2.5MW
SEAPA's existing energy resources include the Swan Lake and Tyee Lake Hydroelectric Projects.
With the completion of an intertie in late 2009, Ketchikan, Wrangell, and Petersburg are
interconnected with a SEAPA=owned transmission system. Power from the Swan and Tyee projects
are delivered to the three communities pursuant to a Long-Term Power Sales Agreement.
Ketchikan Public Utilities (KPU) owns and operates the Ketchikan Lakes, Beaver Falls, and Silvis
Lakes Hydro Projects. KPU maintains four peaking/standby diesel generators at its Bailey
Powerhouse and two other diesel generators at its North Point Higgins Substation. The diesel
generators provide power to the community in times of low reservoir levels, hydro maintenance
periods, and for emergency use during outages.
Petersburg Municipal Power & Light owns the Blind Slough Hydroelectric Project and also has
seven back-up diesel generation units; Wrangell Municipal Light & Power has four back-up diesel
units.
The anticipated effect of wind power would be less use of diesel fuel for electrical power generation
during energy and capacity shortfalls.
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of
any impact the project may have on existing energy infrastructure and resources.