HomeMy WebLinkAboutAtch 3 - financial backupWWTP ESHP Project Cost Estimate by YCE 9/18/12 - construction only cost derived from 2012 Feasibility Study; design fees, inspection services, owners project costs % applied by YCE 437,070.00$ 108,250.00$ 328,820.00$ Construction Contingency 25%82,205.00$ General Overhead and Profit 30% 123,307.50$ 534,332.50$ Mechanical and Electrical Engineering Design Fees 18% 96,179.85$ Construction Inspection Services 8% 42,746.60$ Owners Project Costs 20% 106,866.50$ Total Project Cost (2012) 780,125.45$ 849,984$ Incremental Construction Cost Difference Total Construction Costs Total Project Cost (2015) ESHP Construction Costs Base Case Construction Costs This page shows how the grant funding request was generated. Information from the 2012 feasibility study served as the basis for the application, but some of the data was modified to develop more realistic grant requests.