GRANT APPLICATION
– FOR –
JUNIPER CREEK HYDROELECTRIC PROJECT
FEASBILITY STUDY
SEPTEMBER 2012
~ SUBMITTED TO ~
ALASKA ENERGY AUTHORITY
RENEWABLE ENERGY GRANT PROGRAM – ROUND VI
RFA #AEA-13-006
~ SUBMITTED BY ~
RAM VALLEY, LLC
3527 NORTH POINT DRIVE
ANCHORAGE, AK 99502
Renewable Energy Fund Round 6
Grant Application
AEA 13-006 Application Page 1 of 21 7/3/2011
Application Forms and Instructions
This instruction page and the following grant application constitutes the Grant Application Form
for Round 6 of the Renewable Energy Fund. An electronic version of the Request for
Applications (RFA) and this form are available online at:
http://www.akenergyauthority.org/RE_Fund-6.html
If you need technical assistance filling out this application, please contact Shawn Calfa,
the Alaska Energy Authority Grant Administrator at (907) 771-3031 or at
scalfa@aidea.org.
If you are applying for grants for more than one project, provide separate application
forms for each project.
Multiple phases for the same project may be submitted as one application.
If you are applying for grant funding for more than one phase of a project, provide
milestones and grant budget for each phase of the project.
In order to ensure that grants provide sufficient benefit to the public, AEA may limit
recommendations for grants to preliminary development phases in accordance with 3
ACC 107.605(1).
If some work has already been completed on your project and you are requesting
funding for an advanced phase, submit information sufficient to demonstrate that the
preceding phases are satisfied and funding for an advanced phase is warranted.
If you have additional information or reports you would like the Authority to consider in
reviewing your application, either provide an electronic version of the document with
your submission or reference a web link where it can be downloaded or reviewed.
REMINDER:
Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials
submitted to the Authority may be subject to disclosure requirements under the act if no
statutory exemptions apply.
All applications received will be posted on the Authority web site after final
recommendations are made to the legislature.
In accordance with 3 AAC 107.630 (b) Applicants may request trade secrets or
proprietary company data be kept confidential subject to review and approval by the
Authority. If you want information is to be kept confidential the applicant must:
o Request the information be kept confidential.
o Clearly identify the information that is the trade secret or proprietary in their
application.
o Receive concurrence from the Authority that the information will be kept
confidential. If the Authority determines it is not confidential it will be treated as a
public record in accordance with AS 40.25 or returned to the applicant upon
request.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 2 of 21 7/3//2012
SECTION 1 – APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
RAM VALLEY LLC
Type of Entity: INDEPENDENT POWER PRODUCER Fiscal Year End December 31
Tax ID # none Tax Status: X For-profit or non-profit ( check one)
Mailing Address
3527 North Point Drive
Anchorage, AK 99502
Physical Address
SAME
Telephone
907-248-0058
Fax
none
Email
DBRAILEY@ALASKA.NET
1.1 APPLICANT POINT OF CONTACT / GRANTS MANAGER
Name
DAVID BRAILEY
Title
Managing Member, RAM VALLEY, LLC
Mailing Address
3527 North Point Drive
Anchorage, AK 99502
Telephone
907-248-0058
Fax
none
Email
DBRAILEY@ALASKA.NET
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
X An independent power producer in accordance with 3 AAC 107.695 (a) (1), or
A local government, or
A governmental entity (which includes tribal councils and housing authorities);
Yes
1.2.2 Attached to this application is formal approval and endorsement for its project by
its board of directors, executive management, or other governing authority. If the
applicant is a collaborative grouping, a formal approval from each participant’s
governing authority is necessary. (Indicate Yes or No in the box )
Yes
1.2.3 As an applicant, we have administrative and financial management systems and
follow procurement standards that comply with the standards set forth in the grant
agreement.
Yes
1.2.4 If awarded the grant, we can comply with all terms and conditions of the attached
grant form. (Any exceptions should be clearly noted and submitted with the
application.)
Yes
1.2.5 We intend to own and operate any project that may be constructed with grant
funds for the benefit of the general public. If no please describe the nature of the
project and who will be the primary beneficiaries.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 3 of 21 7/3//2012
SECTION 2 – PROJECT SUMMARY
This is intended to be no more than a 1-2 page overview of your project.
2.1 Project Title – (Provide a 4 to 5 word title for your project)
JUNIPER CREEK HYDROELECTRIC PROJECT FEASIBILITY STUDY
2.2 Project Location –
Include the physical location of your project and name(s) of the community or communities that will
benefit from your project in the subsections below.
2.2.1 Location of Project – Latitude and longitude, street address, or community name.
Latitude and longitude coordinates may be obtained from Google Maps by finding you project’s location on the map
and then right clicking with the mouse and selecting “What is here? The coordinates will be displayed in the Google
search window above the map in a format as follows: 61.195676.-149.898663. If you would like assistance obtaining
this information please contact AEA at 907-771-3031.
The project is located on Juniper Creek, a tributary of Eagle River near Anchorage. This
project is located at approximately 61d 26’N, 149d 27’ W.
2.2.2 Community benefiting – Name(s) of the community or communities that will be the
beneficiaries of the project.
Communities that will benefit from this project include those communities on the railbelt
energy grid.
2.3 PROJECT TYPE
Put X in boxes as appropriate
2.3.1 Renewable Resource Type
Wind Biomass or Biofuels
X Hydro, including run of river Transmission of Renewable Energy
Geothermal, including Heat Pumps Small Natural Gas
Heat Recovery from existing sources Hydrokinetic
Solar Storage of Renewable
Other (Describe)
2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply)
Pre-Construction Construction
Reconnaissance Design and Permitting
X Feasibility Construction and Commissioning
Conceptual Design
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 4 of 21 7/3//2012
2.4 PROJECT DESCRIPTION
Provide a brief one paragraph description of your proposed project.
The proposed project is a run-of-river hydroelectric project located on private property along
Juniper Creek in the Eagle River Valley, approximately 10 miles from Eagle River, Alaska. The
proposed project would include an intake / diversion structure at approximately the 1900-foot
elevation and powerhouse at the 1500-foot elevation. The design flow is estimated at 10 to 20
cfs, for an estimated installed capacity of 250 to 500 kW.
Participation of adjacent downstream property owners would increase the head available for the
project from 400 feet to either 900 feet or 1,100 feet if one or two adjacent land owners were to
participate. This would increase installed capacity to as much as 1,300 kW. Ram Valley
expects to determine the participation status of these land owners prior to the start of the
feasibility study.
2.5 PROJECT BENEFIT
Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel
costs, lower energy costs, etc.)
A feasibility study of Juniper Creek will benefit the railbelt population by determining if a viable
hydroelectric project can be constructed at Juniper Creek, and providing environmental,
technical, and economic analysis of that project. In the near term, the public benefit is the study
results. If the project is viable and constructed, the public will benefit from competitively-priced
clean renewable energy.
2.6 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source
of other contributions to the project.
The cost of the feasibility study will be $172,700. Of this cost, Ram Valley, LLC will contribute
$44,800 as cash and in-kind services and requests a $127,900 grant.
2.7 COST AND BENEFIT SUMARY
Include a summary of grant request and your project’s total costs and benefits below.
Grant Costs
(Summary of funds requested)
2.7.1 Grant Funds Requested in this application. $127,900
2.7.2 Cash match to be provided $ 2,000
2.7.3 In-kind match to be provided $ 42,800
2.7.4 Other grant applications not yet approved NA
2.7.5 Total Grant Costs (sum of 2.7.1 through 2.7.3) $172,700
Project Costs & Benefits
(Summary of total project costs including work to date and future cost estimates to get to a fully
operational project)
2.7.6 Total Project Cost (Summary from Cost Worksheet
including estimates through construction)
$4,300,000
2.7.7 Estimated Direct Financial Benefit (Savings) $5,580,000
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 5 of 21 7/3//2012
2.7.8 Other Public Benefit (If you can calculate the benefit in
terms of dollars please provide that number here and
explain how you calculated that number in your application
(Section 5.)
See narrative for other
benefits.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 6 of 21 7/3//2012
SECTION 3 – PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include contact information, a
resume and references for the manager(s). If the applicant does not have a project manager
indicate how you intend to solicit project management support. If the applicant expects project
management assistance from AEA or another government entity, state that in this section.
Mr. David Brailey will be the project manager for this project. Mr. Brailey’s resume is attached
to this application. No management assistance is expected or required by AEA.
3.2 Project Schedule and Milestones
Please fill out the schedule below. Be sure to identify key tasks and decision points in in your
project along with estimated start and end dates for each of the milestones and tasks. Please
clearly identify the beginning and ending of all phases of your proposed project.
Please fill out form provided below. You may add additional rows as needed.
Milestones Tasks Start Date End Date
Grant Agreement with AEA Sign Grant Agreement July 2013 Sept. 2013
1. Project Management, Scoping and
Contractor Solicitation Sign Contract Sept. 2013 Oct. 2013
2. Detailed Energy Resource Analysis Topo surveys, hydrology Oct. 2013 Oct. 2014
3. Identify Land and Regulatory Issues Oct. 2013 Feb. 2014
4. Permitting and Environmental Analysis Fish study Oct. 2013 July 2014
5. Market Analysis Jan. 2014 July 2014
6. Assessment of Alternatives Mar. 2014 Aug. 2014
7. Conceptual Design Analysis and Cost
Estimate Mar. 2014 Aug. 2014
8. Detailed Economic and Financial
Analysis Aug. 2014 Sep. 2014
9. Business and Operations Plans Aug. 2014 Sep. 2014
10. Draft Final Report Sep. 2014 Oct. 2014
11. Final Report Address comments Nov. 2014 Dec. 2014
Schedule is based on timely signing of grant agreement. Tasks are based on months from
grant agreement signing.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 7 of 21 7/3//2012
3.3 Project Resources
Describe the personnel, contractors, accounting or bookkeeping personnel or firms, equipment,
and services you will use to accomplish the project. Include any partnerships or commitments
with other entities you have or anticipate will be needed to complete your project. Describe any
existing contracts and the selection process you may use for major equipment purchases or
contracts. Include brief resumes and references for known, key personnel, contractors, and
suppliers as an attachment to your application.
Ram Valley, LLC intends to contract with Polarconsult Alaska, Inc. to perform engineering
consulting tasks associated with the feasibility study. Qualifications of Polarconsult and their
key personnel are attached to this proposal. Ram Valley would use the resources and expertise
of Brailey Hydrological Consultants, owned by David Brailey, to perform on-going hydrology
data collection and analysis and related professional services in support of the project and
study. Brailey Hydrological Consultants possesses the required equipment necessary to
conduct flow measurements and hydrological studies of the project area.
3.4 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
Please provide an alternative contact person and their contact information.
David Brailey will be the liaison between Ram Valley, Polarconsult, and the Alaska Energy
Authority for the duration of this project. Mr. Brailey will submit quarterly reports to the Alaska
Energy Authority throughout the project.
3.5 Project Risk
Discuss potential problems and how you would address them.
This project is still in the study phase and as such there is limited risk associated with the
project at the current level of study. In the event the studies conclude the project is not feasible,
Ram Valley LLC will not pursue the project and there is no risk.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 8 of 21 7/3//2012
SECTION 4 – PROJECT DESCRIPTION AND TASKS
The level of information will vary according to phase(s) of the project you propose to
undertake with grant funds.
If some work has already been completed on your project and you are requesting funding for an
advanced phase, submit information sufficient to demonstrate that the preceding phases are
satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project. For pre-construction applications, describe the
resource to the extent known. For design and permitting or construction projects, please provide
feasibility documents, design documents, and permitting documents (if applicable) as attachments to
this application.
Ram Valley, LLC has been monitoring the hydrology of Juniper Creek over the past three years.
Winter low flows are approximately 3 cfs, and sustained summer flows (June 15 to October 1) are 15
to 20 cfs (see hydrograph in Attachment E). Available head on Ram Valley’s property is
approximately 400 vertical feet. A design flow of 10 to 20 cfs would result in an installed capacity of
approximately 250 to 500 kW.
Participation of adjacent downstream property owners would increase the head available for the
project from 400 feet to either 900 feet or 1,100 feet if one or two adjacent land owners were to
participate. This would increase installed capacity to as much as 1,300 kW (see site map in
Attachment E).
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about the
number, size, age, efficiency, and type of generation.
Matanuska Electric Association, Inc. (MEA) serves the project area. MEA is currently building a new
generation facility in Eklutna that will meet all of its power needs starting in 2015. MEA also receives
a significant amount of electricity from the existing Eklutna Lake and Bradley Lake hydroelectric
facilities, and a minor amount of electricity from independent power producers in the region. This
project would displace fuel for the new Eklutna Power Plant.
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of any
impact the project may have on existing energy infrastructure and resources.
MEA currently relies on a combination of hydroelectricity (about 10%) and natural gas (about 90%)
for electrical generation. After 2015, this energy mixture will remain largely unchanged, although
MEA will have the option of burning fuel oil at its new Eklutna Power Plant should natural gas
supplies not be available. The new MEA plant will also be more efficient than Chugach Electric
Association’s Beluga Power Plant which currently supplies substantially all of MEA’s non-hydro
electricity.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 9 of 21 7/3//2012
4.2.3 Existing Energy Market
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
The railbelt energy grid is the largest utility grid in Alaska and can readily absorb all of the electrical
output of this project. This project by itself will not have a significant impact on energy customers,
however the cumulative impact of this and other small hydro projects being studied or built on the
railbelt will tend to lower and stabilize rates over time by reducing dependence on natural gas for
electrical generation. In total, approximately 20 MW of mostly run-of-river small hydros are currently
in various stages of study or development throughout the railbelt. During the summer months, this
equates to more than 1/5th of MEA’s total system demand.
4.3 Proposed System
Include information necessary to describe the system you are intending to develop and address
potential system design, land ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
A description of renewable energy technology specific to project location
Optimum installed capacity
Anticipated capacity factor
Anticipated annual generation
Anticipated barriers
Basic integration concept
Delivery methods
The specific project design would depend on the preferred project configuration that would be
determined by the proposed feasibility study. Generally, the project would consist of the
following major components:
1. A diversion structure to collect water from the south fork of Juniper Creek near the upper property
line at 1900 foot elevation. This would likely consist of a concrete structure in the creek. A
second diversion structure would be located on the north fork, with an approximately 1,200-foot
long pipeline to convey this water to the south fork intake.
2. An intake structure to filter debris out of the water and direct water into the project penstock.
3. An approximately 1,500 foot long penstock down to the lower property line at 1,400-foot
elevation. The penstock would be buried for frost protection where possible.
4. A powerhouse fitted with a single turgo or pelton turbine. Single or dual jets may be used
depending on the selected design flow.
5. An induction generator.
6. A power line extension to the existing MEA distribution system in the area.
The project’s installed capacity is estimated at approximately 250 kW to 500 kW. The capacity factor
is estimated to be between 0.50 and 0.70, with higher capacity factors for lower design flows. Annual
energy generation is estimated at 1,530 to 2,190 MWh. All of these parameters depend on which
project configuration is identified by the feasibility study as the best development at Juniper Creek.
Extension of the project onto downstream property(ies) would increase annual energy generation to
as much as approximately 6,000 MWh.
No barriers to implementation are known.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 10 of 21 7/3//2012
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the project or
how you intend to approach land ownership and access issues.
Land where the project would be located is owned by Ram Valley, LLC. Extension of the project
onto adjacent private property(ies) downstream would require participation agreements setting forth
the terms of access and shared ownership issues.
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
List of applicable permits
Anticipated permitting timeline
Identify and discussion of potential barriers
The project is expected to require the following major permits for construction.
1. The project is believed to not be under FERC jurisdiction. A declaration of intention would be filed
with FERC to confirm this regulatory determination.
2. Authorizations from the Municipality of Anchorage as needed to conform with land use and zoning
regulations.
3. Fish Habitat Permit. The project reach on Juniper Creek is above listed anadromous fish habitat,
and possibly above resident fish habitat as well. Fish trapping would be performed to help confirm
the presence or absence of resident fish (such as Dolly Varden) in the project reach.
4. U.S. Department of Army permits for work in waters of the U.S. including wetlands.
5. Alaska Department of Natural Resources Water Rights.
6. RCA authorization. A Utility Certificate from the Regulatory Commission of Alaska may be
required depending on how Ram Valley proceeds with the project.
Once a decision to develop the project is made (at the conclusion of the Feasibility Study), permits
are estimated to take 1.5 to 3 years to obtain. This estimate will be refined once the project
configuration is determined. The longer timeframe would apply if significant resource issues are
identified in the course of the feasibility study.
No permitting barriers are known at this time.
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will be
addressed:
Threatened or Endangered species
Habitat issues
Wetlands and other protected areas
Archaeological and historical resources
Land development constraints
Telecommunications interference
Aviation considerations
Visual, aesthetics impacts
Identify and discuss other potential barriers
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 11 of 21 7/3//2012
The following assessment is based on currently available information. More detailed responses
would depend on the specific project configuration that is selected.
Threatened or endangered species: None known.
Habitat issues: None known.
Wetlands and other protected areas: Most of the project footprint is uplands, some wetlands areas
would likely be affected by the project.
Archeological resources: None known.
Land development constraints: The project would need to conform with MOA land use and zoning
regulations.
Telecommunications Interference: None known.
Aviation considerations: None known.
Visual, aesthetics impacts: None known.
Other potential barriers: None known.
4.4 Proposed New System Costs and Projected Revenues
(Total Estimated Costs and Projected Revenues)
The level of cost information provided will vary according to the phase of funding requested and any
previous work the applicant may have done on the project. Applicants must reference the source of
their cost data. For example: Applicants records or analysis, industry standards, consultant or
manufacturer’s estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of the
project. Cost information should include the following:
Total anticipated project cost, and cost for this phase
Requested grant funding
Applicant matching funds – loans, capital contributions, in-kind
Identification of other funding sources
Projected capital cost of proposed renewable energy system
Projected development cost of proposed renewable energy system
Total project costs will depend on the project configuration which has not been determined. Based
on known site conditions, a cost of $2000 to $4000 per kW of installed capacity is considered
appropriate at this level of study. This equates to a capital cost of $500,000 to $2,000,000
depending on the project capacity.
The cost of the feasibility study is $172,700. Ram Valley, LLC requests $127,900 in grant funds and
is providing $42,800 as an in-kind match and $2,000 as a cash match from its own resources for the
study.
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by the
applicant.
(Note: Operational costs are not eligible for grant funds however grantees are required to meet
ongoing reporting requirements for the purpose of reporting impacts of projects on the communities
they serve.)
The project concept is not sufficiently developed at this point in time to provide meaningful O&M cost
estimates. No factors are currently known that would result in abnormally high or low O&M costs
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 12 of 21 7/3//2012
compared to typical costs for small to medium-sized run-of-river hydroelectric projects in Alaska.
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
Identification of potential power buyer(s)/customer(s)
Potential power purchase/sales price - at a minimum indicate a price range
Proposed rate of return from grant-funded project
Sale of power from the Juniper Creek project could take a number of forms. The most
straightforward power sales contract to put in place would be to sell electricity to MEA on a wholesale
basis. MEA’s power purchase rate for non-firm power (the avoided cost of fuel, purchased power
and O&M) is currently approximately $0.05 to 0.07 per kWh.
Sale to other railbelt utilities is also an option, although this can be contractually challenging due to
the need to negotiate wheeling rates over the MEA and potentially other systems. Sale to non-
utilities is also a possibility in certain instances, but it can be more difficult to set up these contractual
relationships.
Detailed cost-based rates are not yet available for the project at the current level of study. Economic
and financial analysis is one of the tasks that will be completed as part of the feasibility study. Cost
analysis completed to date indicate that the cost-based rate for the project is likely in the same range
as MEA’s future avoided cost of energy (fuel + O&M), indicating the project is economically viable.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 13 of 21 7/3//2012
4.4.4 Project Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered in
evaluating the project.
Renewable Energy Source Juniper Creek Hydroelectric Project
The Applicant should demonstrate that the renewable energy resource is available on a
sustainable basis.
Annual average resource availability. Capacity factor of 0.50 at 20 cfs, 0.70 at 10 cfs.
(a 20 cfs project is used for this worksheet)
Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel)
Existing Energy Generation and Usage
a) Basic configuration (if system is part of the Railbelt1 grid, leave this section blank)
i. Number of generators/boilers/other Railbelt
ii. Rated capacity of generators/boilers/other Railbelt
iii. Generator/boilers/other type Railbelt
iv. Age of generators/boilers/other Railbelt
v. Efficiency of generators/boilers/other Railbelt
b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank)
i. Annual O&M cost for labor Railbelt
ii. Annual O&M cost for non-labor Railbelt
c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the
Railbelt grid, leave this section blank)
i. Electricity [kWh] Railbelt
ii. Fuel usage
Diesel [gal] Railbelt
Other Railbelt
iii. Peak Load Railbelt
iv. Average Load Railbelt
v. Minimum Load Railbelt
vi. Efficiency Railbelt
vii. Future trends Railbelt
d) Annual heating fuel usage (fill in as applicable)
i. Diesel [gal or MMBtu] --
ii. Electricity [kWh] --
iii. Propane [gal or MMBtu] --
iv. Coal [tons or MMBtu] --
1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric
Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 14 of 21 7/3//2012
v. Wood [cords, green tons, dry tons] --
vi. Other --
Proposed System Design Capacity and Fuel Usage
(Include any projections for continued use of non-renewable fuels)
a) Proposed renewable capacity
(Wind, Hydro, Biomass, other)
[kW or MMBtu/hr]
500 kW
b) Proposed annual electricity or heat production (fill in as applicable)
i. Electricity [kWh] 2,190,000 kWh
ii. Heat [MMBtu] --
c) Proposed annual fuel usage (fill in as applicable)
i. Propane [gal or MMBtu] --
ii. Coal [tons or MMBtu] --
iii. Wood [cords, green tons, dry tons] --
iv. Other Up to 20 cfs of water from Juniper Creek on a continuous
basis.
Project Cost
a) Total capital cost of new system $2,000,000
b) Development cost $350,000
c) Annual O&M cost of new system $ 32,850 (based on $0.015 per kWh O&M cost)
d) Annual fuel cost $0
Project Benefits
a) Amount of fuel displaced for
i. Electricity Approximately 32,000 mmBtu per year (32,000 MCF of natural gas)
ii. Heat --
iii. Transportation --
b) Current price of displaced fuel Price of natural gas to railbelt utilities is approximately
$6 to 7 per MCF.
c) Other economic benefits --
d) Alaska public benefits $ 208,000 per year in avoided fuel costs (at $6.50 per MCF),
plus $21,900 in MEA avoided O&M costs (valued at $0.01
per kWh). Totaling $229,900 in public benefits.
Power Purchase/Sales Price
a) Price for power purchase/sale MEA’s avoided cost of electricity is anticipated to be
equivalent to the cost based rate for the project.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 15 of 21 7/3//2012
Project Analysis
a) Basic Economic Analysis
Project benefit/cost ratio $ 5.58 million in benefits / $3.67 million in costs = 1.52
(calculated using Round 6 AEA/ISER economic model)
Payback (years) $ 4,350,000 total development cost / 229,900 avoided costs =
18.9 years
4.4.5 Proposed Biomass System Information
Please address the following items, if know. (For Biomass Projects Only)
Not Applicable.
SECTION 5– PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings,
and how the people of Alaska will benefit from the project.
The benefits information should include the following:
Potential annual fuel displacement (gallons and dollars) over the lifetime of the evaluated
renewable energy project
Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or cost based rate)
Potential additional annual incentives (i.e. tax credits)
Potential additional annual revenue streams (i.e. green tag sales or other renewable
energy subsidies or programs that might be available)
Discuss the non-economic public benefits to Alaskans over the lifetime of the project
The project would displace approximately 32,000 MCF of natural gas annually, or 1.6 million
MCF (assuming that MEA can use natural gas for the full 50-year life of the Juniper Creek
project). At a value of $6.50 per MCF, this is worth $208,000 annually, or $10.4 million over the
50-year life of Juniper Creek.
This project will also reduce MEA’s O&M costs at its new Eklutna Power Plant. This plant will
use reciprocating engines. By reducing the run-time on these engines, the Juniper Creek
project will reduce the amount MEA spends on engine overhauls, oil, filters, and similar costs,
as well as on the purchase of ammonia for scrubbing the plant exhaust to meet ADEC air quality
criteria. The incremental value of these avoided O&M costs is estimated at $0.01 per kWh, or
$21,900 annually.
The combined direct financial benefits of the project are $229,900.
This project would increase the efficiency of MEA’s distribution grid by providing more
distributed generation. This would benefit MEA members by increasing the electrical efficiency
of MEA’s grid and slightly lowering the amount of energy generation required at the Eklutna
Power Plant. With an assumed increase in grid efficiency of 2%, this project would eliminate an
additional 2% x 2,190,000 kWh x $0.11/kWh = $4,818 in generation costs annually.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 16 of 21 7/3//2012
A wholesale power purchase contract with MEA would likely be at their system average avoided
cost (fuel plus O&M). The AEA/ISER model assumes this to be $0.11 per kWh when Juniper
Creek is commissioned in 2018. This is estimated to be similar to the cost-based rate for
Juniper Creek. Gross annual revenue at this power purchase rate would be $240,900.
Sale of the ‘green tags’ from this project would potentially increase project revenues. Green
Tags on the voluntary market have stabilized at a price of approximately $0.001 per kWh, which
would result in incremental revenue of $2,190 per year assuming that all Green Tags from the
project were sold.
All communities connected to the railbelt grid would benefit from this project. This project would
increase the amount of renewable energy available to the railbelt, decreasing dependence on
fossil fuels, which in the case of natural gas in Cook Inlet is a diminishing resource. This project
would also not be subject to any future carbon taxes that may be imposed on the burning of
fossil fuels. Carbon taxes would increase the incremental value and public benefit of this project
as compared with burning natural gas or fuel oil.
SECTION 6– SUSTAINABILITY
Discuss your plan for operating the completed project so that it will be sustainable.
Include at a minimum:
Proposed business structure(s) and concepts that may be considered.
How you propose to finance the maintenance and operations for the life of the project
Identification of operational issues that could arise.
A description of operational costs including on-going support for any back-up or existing
systems that may be require to continue operation
Commitment to reporting the savings and benefits
Ram Valley anticipates that it would become an Independent Power Producer and sell power on
a wholesale basis to the local utility, MEA.
O&M costs for the project would be funded by revenues from sale of electricity. The market value
of the electricity easily exceeds expected O&M costs. No unusual operational issues are known
at this time.
Operational costs would include periodic scheduled overhauls of the turbines, generators, and
ancillary equipment, maintenance of the project intake and related hydro project operations.
Back up electric service would be provided by MEA.
Ram Valley, LLC commits to reporting the savings and benefits associated with the Juniper Creek
hydroelectric project should it be found feasible and move forward to construction.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 17 of 21 7/3//2012
SECTION 7 – READINESS & COMPLIANCE WITH OTHER GRANTS
Discuss what you have done to prepare for this award and how quickly you intend to proceed
with work once your grant is approved.
Tell us what you may have already accomplished on the project to date and identify other grants
that may have been previously awarded for this project and the degree you have been able to
meet the requirements of previous grants.
Ram Valley, LLC has been monitoring stream flow on Juniper Creek, reviewing site topography,
and related technical matters over the past three years to determine if the resource is likely to
support a hydroelectric development. Our preliminary analysis indicates that the site has good
flows through the winter and warrants detailed technical and engineering analysis to determine
development costs and economic feasibility.
Ram Valley has not received any prior grants for this project.
SECTION 8– LOCAL SUPORT
Discuss what local support or possible opposition there may be regarding your project. Include
letters of support from the community that would benefit from this project.
Attached to this application are letters of support from South Fork Hydro, LLC and Matanuska
Electric Association, Inc.
Ram Valley, LLC is not aware of any opposition to this project.
SECTION 9 – GRANT BUDGET
Tell us how much you want in grant funds Include any investments to date and funding sources,
how much is being requested in grant funds, and additional investments you will make as an
applicant.
Provide a narrative summary regarding funding sources and your financial commitment to the
project.
Ram Valley, LLC will provide in-kind services and labor in the form of equipment usage and
professional labor, primarily provided by David Brailey, member of Ram Valley and principal of
Brailey Hydrological Consultants. Ram Valley will also provide a cash match by purchasing
stream gauging equipment for installation at the proposed intake site on Juniper Creek. Ram
Valley, LLC already owns the property where the project would be located.
Applications should include a separate worksheet for each project phase that was identified in
section 2.3.2 of this application, (Reconnaissance, Feasibility, Conceptual Design, Design and
Permitting, and Construction). Please use the tables provided below to detail your proposed
project’s budget. Be sure to use one table for each phase of your project.
If you have any question regarding how to prepare these tables or if you need assistance preparing the
application please feel free to contact AEA at 907-771-3031 or by emailing the Grant Administrator,
Shawn Calfa, at scalfa@aidea.org.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 18 of 21 7/3//2012
Milestone or Task
Anticipated
Completion
Date
RE- Fund
Grant Funds
Grantee
Matching
Funds
Source of
Matching
Funds:
Cash/In-
kind/Federal
Grants/Other
State
Grants/Other
TOTALS
Grant Agreement with AEA
Notice to
Proceed = 0
months
1. Project Management,
Scoping and Contractor
Solicitation
End of 2rd
month $0 $0 $0
2. Detailed Energy Resource
Analysis
End of 14th
month $7,500 $32,800 Cash and
In-Kind $40,300
3. Identify land and Regulatory
Issues
End of 7th
month $8,300 $3,600 Cash and
In-Kind $11,900
4. Permitting and
Environmental Analysis
End of 12th
month $11,800 $1,200 Cash and
In-Kind $13,000
5. Market Analysis End of 12th
month $9,300 $800 Cash and
In-Kind $10,100
6. Assessment of Alternatives End of 13th
month $14,500 $0 $14,500
7. Conceptual Design Analysis
and Cost Estimate
End of 13th
month $30,400 $0 $30,400
8. Detailed Economic and
Financial Analysis
End of 14th
month $11,400 $0 $11,400
9. Business and Operations
Plans
End of 14th
month $6,200 $1,600 Cash and
In-Kind $7,800
10. Draft Final Report End of 15th
month $24,900 $2,400 Cash and
In-Kind $27,300
11. Final Report End of 17th
month $3,600 $2,400 Cash and
In-Kind $6,000
TOTALS $127,900 $44,800 $172,700
Budget Categories:
Direct Labor & Benefits $0 $42,500 In-kind $42,500
Travel & Per Diem $0 $300 In-kind $300
Equipment $0 $2,000 Cash $2,000
Materials & Supplies $0 $0 $0
Contractual Services $127,900 $0 $127,900
Construction Services $0 $0 $
Other $0 $0 $
TOTALS $127,900 $44,800 $172,700
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 19 of 21 7/3//2012
Project Milestones that should be addressed in Budget Proposal
Reconnaissance Feasibility Design and
Permitting Construction
1. Project scoping and
contractor solicitation.
2. Resource
identification and
analysis
3. Land use, permitting,
and environmental
analysis
4. Preliminary design
analysis and cost
5. Cost of energy and
market analysis
6. Simple economic
analysis
7. Final report and
recommendations
1. Project scoping
and contractor
solicitation.
2. Detailed energy
resource analysis
3. Identification of
land and regulatory
issues,
4. Permitting and
environmental
analysis
5. Detailed analysis of
existing and future
energy costs and
markets
6. Assessment of
alternatives
7. Conceptual design
analysis and cost
estimate
8. Detailed economic
and financial
analysis
9, Conceptual
business and
operations plans
10. Final report and
recommendations
1. Project scoping
and contractor
solicitation for
planning and
design
2. Permit
applications (as
needed)
3. Final
environmental
assessment and
mitigation plans
(as needed)
4. Resolution of
land use, right of
way issues
5. Permit approvals
6. Final system
design
7. Engineers cost
estimate
8. Updated
economic and
financial analysis
9. Negotiated
power sales
agreements with
approved rates
10. Final business
and operational
plan
1. Confirmation that all
design and feasibility
requirements are
complete.
2. Completion of bid
documents
3. Contractor/vendor
selection and award
4. Construction Phases
–
Each project will have
unique construction
phases, limitations,
and schedule
constraints which
should be identified
by the grantee
5. Integration and
testing
6. Decommissioning old
systems
7. Final Acceptance,
Commissioning and
Start-up
8. Operations Reporting
ATTACHMENT A
PROJECT TEAM QUALIFICATIONS
ATTACHMENT B
LETTERS OF SUPPORT
ATTACHMENT C
ELECTRONIC VERSION OF ENTIRE APPLICATION
ATTACHMENT D
GOVERNING BODY RESOLUTION
ATTACHMENT E
ADDITIONAL MAPS AND PROJECT INFORMATION
JUNIPER CREEK FLOW01020304050600 30 60 90 120 150 180 210 240 270 300 330 360DAY OF CALENDAR YEARFLOW (CFS)Average Daily Flow Data, 2008 - 2012(Basin area above gauging station: 8.1 sq. mi.)