HomeMy WebLinkAboutCVEA RE6 Application - Allison Creek ProjectCopper Valley Electric Association, Inc.
Allison Creek Project
AEA 13 - 006
Renewable Energy Fund Round 6 Grant Application
September 21, 2012
Copper Valley Electric Association, Inc.
PO Box 45
Glennallen, Alaska 99588
(907-)822-3211 * Fax (907) 822-5586
Renewable Energy Fund Round 6
Grant Application
AEA 13-006 Application Page 1 of 25 7/3/2011
Allison Creek Project
Grant Application
SEPTEMBER 2012
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 2 of 25 7/3//2012
Application Forms and Instructions
This instruction page and the following grant application constitutes the Grant Application Form
for Round 6 of the Renewable Energy Fund. An electronic version of the Request for
Applications (RFA) and this form are available online at:
http://www.akenergyauthority.org/RE_Fund-6.html
If you need technical assistance filling out this application, please contact Shawn Calfa,
the Alaska Energy Authority Grant Administrator at (907) 771-3031 or at
scalfa@aidea.org.
If you are applying for grants for more than one project, provide separate application
forms for each project.
Multiple phases for the same project may be submitted as one application.
If you are applying for grant funding for more than one phase of a project, provide
milestones and grant budget for each phase of the project.
In order to ensure that grants provide sufficient benefit to the public, AEA may limit
recommendations for grants to preliminary development phases in accordance with 3
ACC 107.605(1).
If some work has already been completed on your project and you are requesting
funding for an advanced phase, submit information sufficient to demonstrate that the
preceding phases are satisfied and funding for an advanced phase is warranted.
If you have additional information or reports you would like the Authority to consider in
reviewing your application, either provide an electronic version of the document with
your submission or reference a web link where it can be downloaded or reviewed.
REMINDER:
Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials
submitted to the Authority may be subject to disclosure requirements under the act if no
statutory exemptions apply.
All applications received will be posted on the Authority web site after final
recommendations are made to the legislature.
In accordance with 3 AAC 107.630 (b) Applicants may request trade secrets or
proprietary company data be kept confidential subject to review and approval by the
Authority. If you want information is to be kept confidential the applicant must:
o Request the information be kept confidential.
o Clearly identify the information that is the trade secret or proprietary in their
application.
o Receive concurrence from the Authority that the information will be kept
confidential. If the Authority determines it is not confidential it will be treated as a
public record in accordance with AS 40.25 or returned to the applicant upon
request.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 3 of 25 7/3//2012
SECTION 1 – APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
Copper Valley Electric Association, Inc. (CVEA)
Type of Entity: Electric Utility Fiscal Year End: December
Tax ID # 92-0023631 Tax Status: For-profit or x non-profit ( check one)
Mailing Address
PO Box 45
Glennallen, AK 99588
Physical Address
Mile 187 Glenn Highway
Glennallen, AK 99588
Telephone
907-822-3211
Fax
907-822-5586
Email
Matthews@cvea.org
1.1 APPLICANT POINT OF CONTACT / GRANTS MANAGER
Name
Jaime L. Matthews
Title
Manager of Administration & Finance
Mailing Address
PO Box 45
Glennallen, AK 99588
Telephone
907-822-8311
Fax
907-822-5586
Email
Matthews@cvea.org
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
x An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
An independent power producer in accordance with 3 AAC 107.695 (a) (1), or
A local government, or
A governmental entity (which includes tribal councils and housing authorities);
Yes
or
No
1.2.2 Attached to this application is formal approval and endorsement for its project by
its board of directors, executive management, or other governing authority. If the
applicant is a collaborative grouping, a formal approval from each participant’s
governing authority is necessary. (Indicate Yes or No in the box )
Yes
or
No
1.2.3 As an applicant, we have administrative and financial management systems and
follow procurement standards that comply with the standards set forth in the grant
agreement.
Yes
or
No
1.2.4 If awarded the grant, we can comply with all terms and conditions of the attached
grant form. (Any exceptions should be clearly noted and submitted with the
application.)
Yes
or
No
1.2.5 We intend to own and operate any project that may be constructed with grant
funds for the benefit of the general public. If no please describe the nature of the
project and who will be the primary beneficiaries.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 4 of 25 7/3//2012
SECTION 2 – PROJECT SUMMARY
This is intended to be no more than a 1-2 page overview of your project.
2.1 Project Title – (Provide a 4 to 5 word title for your project)
Allison Creek Project – FERC Project Number 13124
2.2 Project Location –
Include the physical location of your project and name(s) of the community or communities that will
benefit from your project in the subsections below.
The Allison Creek Hydroelectric Project is located adjacent to the Prince William Sound,
immediately south of Port Valdez, Alaska.
CVEA is a member-owned electric cooperative providing central station electric service to a
relatively large geographic area of Eastern Interior and Prince William Sound. CVEA is a
stand-alone (not interconnected to another power system) electric utility.
The service territory is divided into two districts, the Valdez District and the Copper River Basin
District. The Valdez District is comprised of the organized area of the City of Valdez. The
Copper River Basin District incorporates many outstretched communities.
2.2.1 Location of Project – Latitude and longitude, street address, or community name.
Latitude and longitude coordinates may be obtained from Google Maps by finding you project’s location on the map
and then right clicking with the mouse and selecting “What is here? The coordinates will be displayed in the Google
search window above the map in a format as follows: 61.195676.-149.898663. If you would like assistance obtaining
this information please contact AEA at 907-771-3031.
61.055388,-146.348126
2.2.2 Community benefiting – Name(s) of the community or communities that will be the
beneficiaries of the project.
All electric consumers located in the Copper River Basin and Valdez Districts. These
communities include: Valdez, Glennallen, Gakona, Gulkana, Tazlina, Copper Center, Kluti-
Kaah, Copperville, Kenny Lake, Tolsona, Mendeltna, Nelchina, Eureka, and Sheep Mountain.
2.3 PROJECT TYPE
Put X in boxes as appropriate
2.3.1 Renewable Resource Type
Wind Biomass or Biofuels
x Hydro, including run of river Transmission of Renewable Energy
Geothermal, including Heat Pumps Small Natural Gas
Heat Recovery from existing sources Hydrokinetic
Solar Storage of Renewable
Other (Describe)
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 5 of 25 7/3//2012
2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply)
Pre-Construction Construction
Reconnaissance Design and Permitting
Feasibility x Construction and Commissioning
Conceptual Design
2.4 PROJECT DESCRIPTION
Provide a brief one paragraph description of your proposed project.
The Allison Creek Project is a run of the river (ROR) alternative involving construction of a
diversion structure on Allison Creek at elevation 1,300 feet. Water will be diverted from the
creek into a 42 inch surface / buried penstock to a 6.5 megawatt powerhouse near tidewater.
Attachment A is the Final Feasibility Study which provides details on this project as presented
and approved by the CVEA Board of Directors.
2.5 PROJECT BENEFIT
Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel
costs, lower energy costs, etc.)
CVEA’s vision is to reduce or eliminate our dependence on fossil fuel and stabilize the
Cooperative’s cost of generation with regional, sustainable resources.
Allison Creek is a fuel savings project which leads to lower cost and stable energy for CVEA’s
members. The original cost of Allison Creek power was estimated to be 21¢ per kWh which was
equivalent to $80/bbl oil.
With grants already received, the cost of power is estimated to be 15.93¢ per kWh. Diesel costs
are currently 27¢ per kWh. This is a large reduction in power costs.
2.6 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source
of other contributions to the project.
The total project is estimated to cost $38,804,000 (in 2010$). Cost details are provided on page
16 of Attachment A.
CVEA has been awarded $13,288,000 through various grants. Page 1 of Attachment D details
the source of funds, grants received so far, and a plan of finance for the future. Details are
discussed later in the application.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 6 of 25 7/3//2012
2.7 COST AND BENEFIT SUMARY
Include a summary of grant request and your project’s total costs and benefits below.
Grant Costs
(Summary of funds requested)
2.7.1 Grant Funds Requested in this application. $ 6,114,000
2.7.2 Cash match to be provided $ 6,114,000
2.7.3 In-kind match to be provided $ 0
2.7.4 Other grant applications not yet approved $ 0
2.7.5 Total Grant Costs (sum of 2.7.1 through 2.7.3) $ 12,228,000
Project Costs & Benefits
(Summary of total project costs including work to date and future cost estimates to get to a fully
operational project)
2.7.6 Total Project Cost (Summary from Cost Worksheet
including estimates through construction)
$ 38,804,000
2.7.7 Estimated Direct Financial Benefit (Savings) $4,148,571 annually at
current fuel costs.
2.7.8 Other Public Benefit (If you can calculate the benefit in
terms of dollars please provide that number here and
explain how you calculated that number in your application
(Section 5.)
$ Unknown, see section 5
for other benefits.
SECTION 3 – PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include contact information, a
resume and references for the manager(s). If the applicant does not have a project manager
indicate how you intend to solicit project management support. If the applicant expects project
management assistance from AEA or another government entity, state that in this section.
Please see Attachment B for all resumes. CVEA will be accepting bids in winter 2012/2013 for a
Construction Manager at Risk.
- CVEA’s Executive Engineer / Project Manager is John Duhamel. John is the Project
Manager for CVEA and has been involved with the project for two years. John has led
the role for CVEA in filing the license application which was submitted to FERC on
August 30, 2011.
- CVEA’s Chief Executive Officer (CEO) Robert A. Wilkinson has been in the utility
industry for 26 years. Robert provides support to CVEA Management and communicates
results and decisions to CVEA’s Board of Directors.
- CVEA’s Manager of Administration & Finance is Jaime Matthews who has worked in the
utility industry for 12 years. Jaime will be the grant manager for CVEA.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 7 of 25 7/3//2012
3.2 Project Schedule and Milestones
Please fill out the schedule below. Be sure to identify key tasks and decision points in in your
project along with estimated start and end dates for each of the milestones and tasks. Please
clearly identify the beginning and ending of all phases of your proposed project.
Please fill out form provided below. You may add additional rows as needed.
Milestones Tasks
Start
Date
End
Date
Equipment & Materials Purchase Key Equipment 1 Q
2013
4 Q
2014
Award Construction Contract Solicit, receive proposals and award 4 Q
2012
1Q
2013
Complete 30% Design Produce 30% Design for use in construction
proposal development
3 Q
2012
1 Q
2013
Complete 100% Design Produce 100% Design for construction 3 Q
2012
2 Q
2013
Project Construction Break ground and build the project 3 Q
2013
3 Q
2015
Project Start-up Start-up and Commissioning 3 Q
2015
4 Q
2015
Dollars specific to this grant request are for purchasing equipment and materials. Please see
attachment D for further breakdown in financial information.
3.3 Project Resources
Describe the personnel, contractors, accounting or bookkeeping personnel or firms, equipment,
and services you will use to accomplish the project. Include any partnerships or commitments
with other entities you have or anticipate will be needed to complete your project. Describe any
existing contracts and the selection process you may use for major equipment purchases or
contracts. Include brief resumes and references for known, key personnel, contractors, and
suppliers as an attachment to your application.
See Attachment B for All Resumes.
Michael Purdy with Michael E. Purdy Associates is assisting CVEA with all procurement
activities associated with the project.
McMillen LLC was chosen to complete the final design on the project and act as the Owner’s
Representative throughout construction.
In Winter 2012/2013 CVEA will accept bids for a Construction Manager at Risk.
At this stage of the project CVEA has not purchased any major equipment but there are several
power plant parts that have long lead times and will require purchasing soon.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 8 of 25 7/3//2012
3.4 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
Please provide an alternative contact person and their contact information.
Monthly written and financial reports are prepared for updating the Board of Directors at
CVEA’s monthly board meetings which occur on the third Thursday of each month.
Under CVEA’s current grants, monthly written and financial reports are prepared quarterly
which include progress-to-date, accomplished milestones, and any changes or updates to the
scope of the project.
CVEA has been meeting with AEA personnel at least annually to provide in-person reports and
to answer any questions on the project.
3.5 Project Risk
Discuss potential problems and how you would address them.
Since 2007, CVEA has been studying the hydroelectric potential of the Allison Lake Basin. In
2010 CVEA completed review of five project alternatives including construction of an earth
filled dam at elevation 1,345 feet and a 9,000 foot penstock to a powerhouse near tidewater.
The project, which was deemed technically feasible, had significant geotechnical, access and
avalanche challenges that drove project economics to an unacceptable level.
The current project reduces construction risk associated with the site, lessens avalanche and
access risks, and has fewer environmental impacts.
In comparison to other hydroelectric projects, the risks and problems for this project are quite
small. There is always the risk of cost over-runs due to the discovery of unknown conditions
(such as archeological finds or unstable ground) but our current research finds this remote.
Cost over-runs could also occur because of harsh weather during construction.
Because the terrain is steep, the working conditions of the project are difficult and safety cabling
of people and materials will be common. Much of the construction will be accomplished with
helicopters and/or a tram system. This adds the risks associated with helicopter operations and
weather will have an impact on the progress of helicopter work. The use of a tram system will
help to keep construction progressing despite weather unworthy to fly in.
Other risks will be spelled out in very detailed plans such as the erosion control plan, spill
control and prevention plan, quality control plan, and other site plans. In all, the risks and
problems can be controlled by planning and proper oversight.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 9 of 25 7/3//2012
SECTION 4 – PROJECT DESCRIPTION AND TASKS
The level of information will vary according to phase(s) of the project you propose to
undertake with grant funds.
If some work has already been completed on your project and you are requesting funding for
an advanced phase, submit information sufficient to demonstrate that the preceding phases
are satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project. For pre-construction applications, describe
the resource to the extent known. For design and permitting or construction projects, please
provide feasibility documents, design documents, and permitting documents (if applicable) as
attachments to this application.
Attachment A, Pages 6-12 discuss details on system loads, resources, hydrology, etc.
The fully subscribed energy potential is 23,300,000 kWhs per year. With existing system loads,
and nature of seasonal generation, CVEA has the ability to utilize 16,000,000 of these kWhs. All
the information presented in this grant application is based on 16,000,000 kWhs.
In early 2011, CVEA distributed a Strategic Issues Paper to all CVEA members. This paper
discusses projects and technologies being researched. A copy of this report is located at the
following location: http://www.cvea.org/resources/pdfs/strategicIssuesPaper2011.pdf
CVEA continues to evaluate other alternatives to reduce the cost of power for CVEA’s members.
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about
the number, size, age, efficiency, and type of generation.
CVEA generates electrical power at its two diesel plants, one in Valdez and one in Glennallen, a
Cogeneration project in Valdez, and a 12 megawatt hydro facility in Valdez. Power is
transferred between the two districts on a 106-mile transmission line through Thompson Pass
and the Chugach Mountains.
The CVEA Cogeneration Plant is a state-of-the-art facility located at the Petro Star Valdez
Refinery. It is a 5.2 megawatt Solar turbine and heat recovery unit that utilizes "light straight
run" as its fuel source and provides exhaust heat to the attached crude heater for Petro Star’s use
in the refining process. The plant was completed in the spring of 2000 and is remotely controlled
from the Solomon Gulch hydroelectric facility. Efficiency for this unit is 9.3 kWhs per gallon for
production of electricity but the project sells heat at a combined efficiency of 75-80%. Annual
O&M costs for 2012 are budgeted at $47,700 which does not include labor.
The Glennallen Diesel Plant (GDP) is the oldest of CVEA’s three thermal plants. It has
expanded over the years to meet the needs of CVEA customers. The available generation
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 10 of 25 7/3//2012
capacity of the plant is 11 megawatts. The GDP houses a total of seven diesel engines; three
Fairbanks Morse 38D8 1/8 opposed piston units, two Enterprise DSR 46 units, one Caterpillar
3516B unit, and one EMD unit with a capacity of 2.8 megawatts. The five largest units are
remotely controlled from the Solomon Gulch hydroelectric facility. The current average
efficiency is 14 kWhs per gallon. Annual O&M costs for 2012 are budgeted at $274,000 which
does not include labor.
The Valdez Diesel Plant (VDP) was constructed after the 1964 Good Friday Earthquake that
caused the city of Valdez to relocate to its present location. The plant houses one Fairbanks
Morse 38D8 1/8 opposed piston unit, three Enterprise DSR 46 units, and a trailer-mounted Solar
Centaur turbine unit. The available generation capacity of this plant is 8.9 megawatts. The three
largest units are remotely controlled from the Solomon Gulch hydroelectric facility. The average
efficiency is 13.7 kWhs per gallon. Annual O&M costs for 2012 are budgeted at $88,200 which
does not include labor.
Previously owned by the Four Dam Pool Power Agency, CVEA acquired ownership of the
Solomon Gulch hydroelectric facility in February 2009. The 12-megawatt Solomon Gulch
hydroelectric facility is located on Dayville Road in Valdez. Power is generated by two Fuji
Francis water turbines. The facility began providing power to CVEA customers in 1982. CVEA
operates its dispatch center from this facility. The plant is manned 24 hours a day, seven days a
week. Plant operators are responsible for the operation of up to four generation plants at one
time via remote control operations. From the hydro plant, operators can start and stop units in
any or all of CVEA's three generation facilities: Glennallen diesel, Valdez diesel, or the
cogeneration plant, as well as the hydro project. Annual O&M costs for 2012 are budgeted at
$282,500 which does not include labor.
CVEA's service areas are tied together with a 106-mile, 138-kilovolt transmission line that is
owned and operated by CVEA. The transmission line provides a link to all four generating
plants. Power can flow from any of the generating facilities to end consumers. Historically,
power flows from the Solomon Gulch hydro plant to the Copper River Basin District during the
summer months. The transmission line traverses severe terrain between the two districts and
parts of it, in the Thompson Pass area, has severe avalanche risk. The transmission line was last
damaged by an avalanche in December 2009.
CVEA’s Rates
CVEA had not had a base rate change since 1998. In June 2012 the overall rate structure was
changed. In general the Cost of Power was replaced by the Fuel Charge and G&T Charge. This
allows CVEA to explain the costs related to our rates. In addition a heat credit will be applied in
the months the Cogen is producing heat. Additional information can be found on CVEA’s website
at www.cvea.org
The graph on the following page illustrates CVEA’s average revenue per kWh collected for 2009,
2010 and 2011. The average revenue includes the cost of power charge which is included in a
separate line below.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 11 of 25 7/3//2012
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of
any impact the project may have on existing energy infrastructure and resources.
Currently CVEA generates approximately 51% of our kWhs with hydro. This will increase to
66% after Allison Creek. The graph below illustrates before Allison Creek and after.
2009 2010 2011
Residential 0.1999$ 0.2212$ 0.2773$
Small Commercial 0.2161$ 0.2483$ 0.2813$
Large Commercial <200 KW 0.1980$ 0.2316$ 0.2620$
Large Commercial >200 KW 0.2044$ 0.2345$ 0.2687$
Residential 0.1730$ 0.1941$ 0.2514$
Small Commercial 0.1854$ 0.2162$ 0.2527$
Large Commercial 0.1867$ 0.2136$ 0.2530$
Cost of Power per kWh (all)0.1159$ 0.1492$ 0.1824$
VALDEZ
COPPER BASIN
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 12 of 25 7/3//2012
4.2.3 Existing Energy Market
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
The Allison Creek project would have a positive impact on CVEA’s members by lowering the
Cost of Power and would allow CVEA to not be as dependent on fossil fuels as we are today. In
addition, the project will provide long term energy at a stable price.
4.3 Proposed System
Include information necessary to describe the system you are intending to develop and address
potential system design, land ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
A description of renewable energy technology specific to project location
Optimum installed capacity
Anticipated capacity factor
Anticipated annual generation
Anticipated barriers
Basic integration concept
Delivery methods
The primary features of the run of river project include the following:
- A low diversion structure on Allison Creek at elevation 1,300
- A 42” diameter surface / buried penstock
- A 6.5 MW powerhouse along Allison Creek at elevation 130 with a 3.8 mile transmission
line leading to the Petro Star substation
- A permanent 550 foot access road to the powerhouse and a temporary 4,500 foot trail for
penstock construction access
- Additional details can be found in the final feasibility report in Attachment A
The general arrangement is identified on the map on the following page.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 13 of 25 7/3//2012
The fully subscribed energy potential is 23,300,000 kWhs per year; however, with existing system
loads, and nature of seasonal generation, CVEA has the ability to utilize 16,000,000 of these
kWhs.
Page 6 of Attachment A discusses the run of the river operation. Without a reservoir to regulate
available flows at the intake, the project can only be operated when instantaneous flows are
within the range of physical capability of the generating equipment. All flows greater than the
maximum capability will flow past the intake as spill.
On the basis included in the final feasibility report, the plant could operate approximately 62% of
the time and the total amount of the water available for generation is represented in the chart on
the following page.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 14 of 25 7/3//2012
The chart below identifies the energy potential on a monthly basis.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 15 of 25 7/3//2012
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the
project or how you intend to approach land ownership and access issues.
The land surrounding Allison Lake is owned by the State of Alaska. CVEA has acquired an
access permit from Alyeska for field studies as the work requires a physical crossing of Alyeska
property. This permit is renewed annually.
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
List of applicable permits
Anticipated permitting timeline
Identify and discussion of potential barriers
CVEA was awarded the FERC preliminary permit on September 4, 2008. The purpose of the
preliminary permit is to secure and maintain priority to allow CVEA to study the power potential
of Allison Lake and develop information necessary to support a license application. The license
application was filed on August 30, 2011.
Other permits required are standard among hydroelectric projects. Land use permits from the
land owners and water rights permits are typical requirements and are obtained before
construction begins on the project.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 16 of 25 7/3//2012
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will
be addressed:
Threatened or Endangered species
Habitat issues
Wetlands and other protected areas
Archaeological and historical resources
Land development constraints
Telecommunications interference
Aviation considerations
Visual, aesthetics impacts
Identify and discuss other potential barriers
CVEA has completed the necessary studies required to submit a license application. CVEA has
worked closely with all agencies to study the necessary aspects of the project prior to the license
application being filed. Additional study may occur as required by FERC prior to a license being
issued. Environmental studies will continue through construction and for 5 years after the
project is complete.
4.4 Proposed New System Costs and Projected Revenues
(Total Estimated Costs and Projected Revenues)
The level of cost information provided will vary according to the phase of funding requested and
any previous work the applicant may have done on the project. Applicants must reference the
source of their cost data. For example: Applicants records or analysis, industry standards,
consultant or manufacturer’s estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of
the project. Cost information should include the following:
Total anticipated project cost, and cost for this phase
Requested grant funding
Applicant matching funds – loans, capital contributions, in-kind
Identification of other funding sources
Projected capital cost of proposed renewable energy system
Projected development cost of proposed renewable energy system
The total construction cost is estimated at $32,106,000 (in 2010 $). The total project cost is
estimated at $38,804,000.
CVEA is requesting $6,114,000 in this round of grant applications. Attachment D on Pages 1
gives the details on CVEA’s plan of finance.
CVEA plans to apply for any federal funding that may come available. The remaining amount
will be funded with loans. CVEA will continue to explore all possibilities to secure the lowest
cost financing available.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 17 of 25 7/3//2012
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by
the applicant.
(Note: Operational costs are not eligible for grant funds however grantees are required to meet
ongoing reporting requirements for the purpose of reporting impacts of projects on the
communities they serve.)
Project O&M costs are estimated at $280,000 as identified in Page 16 on Attachment A. CVEA is
not pursuing grant funding for O&M as these costs would be funded through electric rates.
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
Identification of potential power buyer(s)/customer(s)
Potential power purchase/sales price - at a minimum indicate a price range
Proposed rate of return from grant-funded project
CVEA estimates the first year cost of power to be approximately 15.93¢. This estimate includes
financing the remaining $25,516,000 at 7%. For every 100 basis point reduction (1%), the
project cost is reduced by approximately .6¢ per kWh. For every $1 million in grant funds
received, the project cost is reduced .5¢ per kWh.
CVEA will use 16,000,000 out of the 23,300,000 kWhs on start up. Subscription of the excess
power will occur as the member base grows.
4.4.4 Project Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered
in evaluating the project.
Renewable Energy Source
The Applicant should demonstrate that the renewable energy resource is available on a
sustainable basis.
Annual average resource availability. 23,300,000 kWh
Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel)
Existing Energy Generation and Usage
a) Basic configuration (if system is part of the Railbelt1 grid, leave this section blank)
i. Number of generators/boilers/other 14 (see page 9 of grant application for breakdown)
ii. Rated capacity of generators/boilers/other 37.1 MW (see page 9 of grant application)
1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric
Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 18 of 25 7/3//2012
iii. Generator/boilers/other type Fairbanks Morse, Enterprise, Caterpillar, Solar
iv. Age of generators/boilers/other Ranges from 1952-2009
v. Efficiency of generators/boilers/other Ranges from 9.3 kWh / gallon to 15.2 kWh / gallon,
average diesel efficiency 14.0 kWh / gallon
b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank)
i. Annual O&M cost for labor $1,336,179
ii. Annual O&M cost for non-labor $692,400
c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the
Railbelt grid, leave this section blank)
i. Electricity [kWh] 80,421,185 kWh’s – 2011 gross generation
ii. Fuel usage
Diesel [gal] 1,758,616 gallons – 2011 actual
Other LSR: 1,883,401 gallons – 2011 actual
iii. Peak Load 13.50 MW – 2011 actual
iv. Average Load 12.30 MW – 2011 actual
v. Minimum Load 11.40 MW – 2011 actual
vi. Efficiency Ranges from 9.3 kWh / gallon to 15.2 kWh / gallon
vii. Future trends Minimal growth
d) Annual heating fuel usage (fill in as applicable)
i. Diesel [gal or MMBtu] N/A
ii. Electricity [kWh]
iii. Propane [gal or MMBtu]
iv. Coal [tons or MMBtu]
v. Wood [cords, green tons, dry tons]
vi. Other
Proposed System Design Capacity and Fuel Usage
(Include any projections for continued use of non-renewable fuels)
a) Proposed renewable capacity
(Wind, Hydro, Biomass, other)
[kW or MMBtu/hr]
Hydro
b) Proposed annual electricity or heat production (fill in as applicable)
i. Electricity [kWh] 16,000,000 kWh first year (assumption used in all
analysis)
23,300,000 kWh fully subscribed
ii. Heat [MMBtu] N/A
c) Proposed annual fuel usage (fill in as applicable)
i. Propane [gal or MMBtu]
ii. Coal [tons or MMBtu]
iii. Wood [cords, green tons, dry tons]
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 19 of 25 7/3//2012
iv. Other
Project Cost
a) Total capital cost of new system $38,804,000
b) Development cost $32,106,000
c) Annual O&M cost of new system $280,000
d) Annual fuel cost N/A
Project Benefits
a) Amount of fuel displaced for
i. Electricity 1,142,857 gallons x $3.63 = $4,148,571
ii. Heat
iii. Transportation
b) Current price of displaced fuel $3.63 per gallon
c) Other economic benefits
d) Alaska public benefits
Power Purchase/Sales Price
a) Price for power purchase/sale N/A
Project Analysis
a) Basic Economic Analysis
Project benefit/cost ratio $102,136,856 / $38,804,000 = 2.63
Payback (years) 16 years (see attachment D: financial backup for details)
4.4.5 Proposed Biomass System Information
Please address the following items, if know. (For Biomass Projects Only) - N/A
What woody biomass technology will be installed (cord wood, pellets, chips, briquettes,
pucks).
Efficiency of the biomass technology.
Thermal or electric application.
Boiler efficiency.
Displaced fuel type and amount.
Estimated tons of wood pellets or chips (specify) to be used per year, and average moisture
percentage.
Estimated cords of wood to be used per year, specify whether dry or green and the moisture
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 20 of 25 7/3//2012
percentage.
Ownership/Accessibility. Who owns the land and are their limitations and restrictions to
accessing the biomass resource?
Inventory data. How much biomass is available on an annual basis and what types (species)
are there, if known?
SECTION 5– PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings,
and how the people of Alaska will benefit from the project.
The benefits information should include the following:
Potential annual fuel displacement (gallons and dollars) over the lifetime of the evaluated
renewable energy project
Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or cost based rate)
Potential additional annual incentives (i.e. tax credits)
Potential additional annual revenue streams (i.e. green tag sales or other renewable
energy subsidies or programs that might be available)
Discuss the non-economic public benefits to Alaskans over the lifetime of the project
This project allows CVEA to displace approximately 1,664,000 gallons of fossil fuel when fully
subscribed. At current load levels, utilizing 16,000,000 kWhs per year, CVEA will displace
1,142,857 gallons per year. At current fuel prices this equates to approximately $4,148,571
annually. With a 2% increase in fuel annually over 30 years, this equates to a fuel savings of
$178,600,856 as identified on Page 5 of Attachment D.
With the addition of Allison Creek and the project costs, CVEA members will save approximately
$1,853,698 in the first year. This savings increases as fuel costs increase.
CVEA is excited at the prospect of adding Allison Creek to our power production capabilities.
Allison Creek will move our hydro production from 51% to 66% and it eliminates the use of 1.66
million gallons of diesel fuel per year. This in turn eliminates 19,000 tons of CO2 emissions, and
10,000 tons of other hazardous emissions. As an additional benefit, it reduces the chance of
acidification of the oceans at our current rate and it reduces the chances of an oil spill since we
would need fewer refueling operations.
The positive effects of eliminating the use of fossil fuel cannot be ignored when calculating the
merit of this project. We understand that Allison Creek has a footprint (albeit small) in the
environment. We understand that some impacts will be felt by birds, fish, mammals and view-
shed. We have been working very closely with state and federal agencies to minimize these
impacts and we believe we have achieved a project that has an overwhelmingly net positive
impact on the environment and community.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 21 of 25 7/3//2012
SECTION 6– SUSTAINABILITY
Discuss your plan for operating the completed project so that it will be sustainable.
Include at a minimum:
Proposed business structure(s) and concepts that may be considered.
How you propose to finance the maintenance and operations for the life of the project
Identification of operational issues that could arise.
A description of operational costs including on-going support for any back-up or existing
systems that may be require to continue operation
Commitment to reporting the savings and benefits
CVEA is a locally regulated IRC 501 (c)(12) cooperative electric utility organized and doing
business under AS 10.25 Alaska Electric and Telephone Cooperative Act. CVEA was
incorporated in 1955 and has been doing business under Certificate of Public Convenience and
Necessity No. 10 since 1959. CVEA proposes to own and operate the Allison Creek hydroelectric
facility. CVEA demonstrates sustainability in its every day successful operation of the
cooperative.
The maintenance and operations would be funded through electric rates.
CVEA owns redundant generation assets to adequately back up the Allison Creek project in the
event the project cannot deliver energy to the CVEA system.
CVEA has identified the benefits in Section 5 and has a commitment to report any other savings
and benefits as the project progresses.
SECTION 7 – READINESS & COMPLIANCE WITH OTHER GRANTS
Discuss what you have done to prepare for this award and how quickly you intend to proceed
with work once your grant is approved.
Tell us what you may have already accomplished on the project to date and identify other grants
that may have been previously awarded for this project and the degree you have been able to
meet the requirements of previous grants.
CVEA is moving forward with the project as identified with the project schedule included in
Attachment B. CVEA currently has 18,000,000 available for commercial financing through
National Rural Utilities Cooperative Finance Corporate (NRUCFC). Once numbers are
finalized a full plan of finance will be developed.
CVEA has been in compliance with the three grants issued on this project:
- State of Alaska 2008 capital budget appropriation (grant #2195314) $ 1,000,000
- Renewable Energy Fund Round I (grant 2195390) $ 2,288,000
- State of Alaska 2010 capital budget appropriation (grant #7910012) $10,000,000
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 22 of 25 7/3//2012
SECTION 8– LOCAL SUPORT
Discuss what local support or possible opposition there may be regarding your project. Include
letters of support from the community that would benefit from this project.
In June 2011, CVEA solicited support from CVEA members for the Allison Creek Project. This
was a very successful effort and the final product comprised of two volumes of letters and signed
petitions given to the State of Alaska in support of a capital budget appropriate request. In
summary CVEA received 326 letters of support and 700 petition signatures. Included with this
application are 14 letters, more are available upon request. There is no known opposition of the
Project.
SECTION 9 – GRANT BUDGET
Tell us how much you want in grant funds Include any investments to date and funding sources,
how much is being requested in grant funds, and additional investments you will make as an
applicant.
Provide a narrative summary regarding funding sources and your financial commitment to the
project.
Please see the attached estimate of budget costs. CVEA is requesting funds for equipment
purchases as there is a long lead time for these types of items. A typical long lead time purchase
at CVEA is separated into payment phases: award of contract, fabrication of equipment,
completion and delivery.
Attachment D, financial backup breaks out the project funding by the phases identified in the
budget form.
Applications should include a separate worksheet for each project phase that was identified in
section 2.3.2 of this application, (Reconnaissance, Feasibility, Conceptual Design, Design and
Permitting, and Construction). Please use the tables provided below to detail your proposed
project’s budget. Be sure to use one table f or each phase of your project.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 23 of 25 7/3//2012
If you have any question regarding how to prepare these tables or if you need assistance preparing the
application please feel free to contact AEA at 907-771-3031 or by emailing the Grant Administrator,
Shawn Calfa, at scalfa@aidea.org.
Tables created for milestones within the funding period. Please see Attachment D for breakdown by
month for entire project.
Milestone or Task
Anticipated
Completion
Date
RE- Fund
Grant Funds
Grantee
Matching
Funds
Source of
Matching
Funds:
Cash/In-
kind/Federal
Grants/Other
State
Grants/Other
TOTALS
(List milestones based on
phase and type of project.
See Milestone list below. )
Owner’s Representative 4 Q 2015 $ 100,000 $ 100,000 Cash $ 200,000
Construction Services 3 Q 2015 $ 425,000 $ 425,000 Cash $ 850,000
Project Mgmt, Insurance, etc. 2 Q 2014 $ 625,000 $ 625,000 Cash $1,250,000
Equipment & Materials 1 Q 2015 $4,964,000 $4,964,000 Cash $9,928,000
$ $ $
$ $ $
$ $ $
TOTALS $6,114,000 $6,114,000 $12,228,000
Budget Categories:
Direct Labor & Benefits $ $ $
Travel & Per Diem $ $ $
Equipment $4,964,000 $4,964,000 Cash $ 9,928,000
Materials & Supplies $ $ $
Contractual Services $ 725,000 $ 725,000 Cash $ 1,450,000
Construction Services $ 425,000 $ 425,000 Cash $ 850,000
Other $ $ $
TOTALS $6,114,000 $6,114,000 $12,228,000
Equipment and Materials will be detailed out in winter 2012/2013. There are many long lead
time items that have to be purchased.
Renewable Energy Fund Round 6
Grant Application
AEA13-006 Grant Application Page 24 of 25 7/3//2012
SECTION 10 – AUTHORIZED SIGNERS FORM
Community/Grantee Name: Copper Valley Electric Association, Inc.
Regular Election is held:
Date: 9-21-12
Authorized Grant Signer(s):
Printed Name Title Term Signature
John Duhamel Executive Engineer See attached signed
board resolution
Temporary in CEO’s
absence
Robert A. Wilkinson Chief Executive Officer See board resolution
I authorize the above person(s) to sign Grant Documents:
(Highest ranking organization/community/municipal official)
Printed Name Title Term Signature
Robert A. Wilkinson Chief Executive Officer See board resolution
Grantee Contact Information:
Mailing Address: Jaime L. Matthews
Phone Number: 907-822-8311
Fax Number: 907-822-5586
E-mail Address:
Matthews@cvea.org
Federal Tax ID #: 92-0023631
Please submit an updated form whenever there is a change to the above information.
Allison Lake Hydropower DevelopmentFINAL FEASIBILITY STUDYADDENDUM
January 2011
The Energy Company
Robert A. Wilkinson, CEO December 20, 2010
Copper Valley Electric Association H-327730
P.O. Box 45
Glennallen, AK 99588-2832
Dear Robert Subject: Allison Creek Hydroelectric Project
Final feasibility Study – Addendum
We are pleased to submit herewith our Addendum to the Final Feasibility Study for the Allison Lake
Hydroelectric Project. This addendum presents our analysis of two additional options for the project as follows:
• Alternative 4a (Alt 4a): A run-of-river development on Allison Creek commencing approximately 2,000
downstream of the outlet of Allison Lake consisting of a diversion structure and a penstock leading to a
6.5 MW powerhouse at the same location as considered for Alt 3c.
• Alternative 4b (Alt 4b): The addition of an inflatable gate on the Solomon Gulch Spillway that would
raise the normal maximum water surface of Solomon Lake by five feet.
Our principal conclusions for these two alternatives as stated within the report include:
• Alternative 4a
- A run-of-river Alt 4a development of the Allison Creek basin is not cost effective with operation
within the existing CVEA system load.
- With the addition of 2 MW to the CVEA system load, the project would be competitive with the
cost of diesel generation.
- The reduced scale of the hydropower development of the Allison Creek basin as offered by Alt 4a
would reduce the risk of construction cost overruns, seepage and dam safety concerns and
environmental impacts as compared to Alt 3c.
- Alt 4a is superior to Alt 3c in all respects.
• Alternative 4b
- The addition of inflatable gates to the Solomon Gulch Spillway as proposed for Alt 4b would add
approximately 2 GWh of energy to the CVEA system.
- The addition of inflatable gates to the Solomon Gulch Spillway as proposed for Alt 4b would
require amendment to existing FERC License for the Solomon Gulch Project.
- On the basis of the energy potential and cost estimates prepared for this evaluation, Alt 4b currently
would not be an economically viable project.
Based on these conclusions we recommend that the CVEA adopt Alt 4a as the preferred alternative for the
development of the hydroelectric potential of the Allison Creek basin and that further consideration of Alt 3c and
Alt 4b be terminated.
We greatly appreciate the opportunity to work with you on this interesting project. If you have any questions
regarding the subject report, be sure to give us a call.
Yours very truly,
A. Richard Griffith, P.E.
Project Manager
Hatch Acres Corporation
6 Nickerson Street, Suite 101, Seattle, WA 98109 USA
Tel: 206-352-5730 • Fax: 206-352-5734 • www..hatchacres.com
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 i
Table of Contents
1. Introduction............................................................................................................................................1
1.1 General..........................................................................................................................................1
1.2 Alternative 4 – General Arrangement.............................................................................................2
1.3 Alternative 4a – Diversion Structure on Allison Creek with Penstock leading to
Powerhouse (Alt 4a).......................................................................................................................3
1.4 Alternative 4b – Raising Solomon Gulch Reservoir Maximum Water Surface 5 feet with
Inflatable Gates on Spillway (Alt 4b) ..............................................................................................4
2. Power Studies..........................................................................................................................................6
2.1 Unconstrained Run-of-River Operation ..........................................................................................6
2.2 System Loads and Resources..........................................................................................................7
2.2.1 System Loads........................................................................................................................7
2.2.2 System Resources.................................................................................................................7
2.3 AUTO Vista Model: Allison Creek Run-of-River Hydropower Development...................................8
2.4 Hydrology......................................................................................................................................8
2.5 Hydro Equipment Characteristics ...................................................................................................9
2.6 AUTO Vista Results........................................................................................................................9
3. Project Construction Cost and Construction Schedule..........................................................................13
3.1 Construction Cost Estimates .........................................................................................................13
3.1.1 Alternative 4a.....................................................................................................................13
3.1.2 Alternative 4b.....................................................................................................................14
3.2 Construction Schedule.................................................................................................................15
3.3 Economic Analysis.......................................................................................................................16
3.3.1 Cost of Power – Alternative 4a...........................................................................................16
3.3.2 Cost of Power – Alternative 4b...........................................................................................17
4. Regulatory and Environmental Considerations......................................................................................19
4.1 Alternative 4a...............................................................................................................................19
4.1.1 Regulatory Considerations..................................................................................................19
4.1.2 Environmental Field Investigations .....................................................................................19
4.1.3 Environmental Considerations............................................................................................20
4.2 Alternative 4b ..............................................................................................................................21
4.2.1 Regulatory Considerations..................................................................................................21
4.2.2 Environmental Field Studies ...............................................................................................21
4.2.3 Environmental Considerations............................................................................................21
5. Conclusions and Recommendations......................................................................................................22
5.1 Conclusions.................................................................................................................................22
5.1.1 Alternative 4a.....................................................................................................................22
5.1.2 Alternative 4b.....................................................................................................................22
5.2 Recommendations .......................................................................................................................23
6. References.............................................................................................................................................24
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 ii
Tables
Table 1.1 FFS – Design and Economic Conditions..................................................................................1
Table 2.1 AUTO Vista Hydrologic Years ................................................................................................9
Table 2.2 Annual Generation – Existing Condition, Loads and Resources............................................10
Table 2.3 Annual Generation – Alt 4a w/ Existing Load........................................................................10
Table 2.4 Annual Generation – Alt 4b w/ Existing Load .......................................................................10
Table 2.5 Annual Generation – Existing Resources w/ 2 MW Additional Load.....................................11
Table 2.6 Annual Generation – Alt 4a w/ 2 MW Additional Load ........................................................11
Table 2.7 Annual Generation – Alt 4b w/ 2 MW Additional Load........................................................11
Table 2.8 Annual Benefits – Alt 4a & 4b...............................................................................................12
Table 3.1 Alternative 4a – Total Construction Cost (Bid 1/2010)..........................................................14
Table 3.2 Alternative 4b – Total Construction Cost (Bid 1/2010) .........................................................15
Table 3.3 Basic Assumptions for Economic Analysis.............................................................................1 6
Table 3.4 Alternative 4a – First Year Annual Cost (2010 Dollars).........................................................16
Table 3.5 Alternative 4a – Cost of Power.............................................................................................17
Table 3.6 Alternative 4b – Cost of Power.............................................................................................18
Table 4.1 Summary of Major Environmental Field Studies ...................................................................20
Figures
Figure 1.1 Alternative 4 General Arrangement........................................................................................2
Figure 1.2 Alternative 4a – Plan and Profile............................................................................................3
Figure 1.3 Diversion Structure – Plan and Cross Section.........................................................................4
Figure 1.4 Typical Obermeyer Gate Installation......................................................................................5
Figure 1.5 Solomon Gulch Obermeyer Spillway Gate Cross Section.......................................................5
Figure 2.1 Allison Creek Annual Flow-Duration Curve............................................................................6
Figure 2.2 Allison Average Monthly Distribution of Energy Production ..................................................7
Figure 2.3 AUTO Vista Model Elements: Alts 4a and 4b..........................................................................8
Figure 2.4 Allison Powerhouse Unit Characteristics – 2 x 3.25 MW Units..............................................9
Figure 3.3 Alternative 4a – Construction Schedule................................................................................15
Appendices
Appendix A – Alternative 4a, System Dispatch
Appendix B – Obermeyer Gate Cost Estimate
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 1
1. Introduction
1.1 General
A fundamental premise of the studies leading to the Final Feasibility Study (FFS) for the Allison Lake
Hydroelectric Project (Project) of May 2010 was that an additional hydropower project is needed to
support the Solomon Gulch Project during winter months. Currently the Copper Valley Electric
Association, Inc. (CVEA) must rely on diesel generation to meet system load to make up for the
inability of the Solomon Gulch Project to generate during the winter period. The Allison Creek basin
exhibits the same basic annual pattern of inflow as the Solomon Gulch basin. The 7 months of May
through November are estimated to account for 98% of the annual inflow leaving only a 2%
contribution for the 5 months of December through April. Accordingly, the focus of project studies
has been to determine the most cost-effective manner to develop storage within Allison Lake to allow
for generation during the low flow winter time period. In all, six different schemes, Alt 1, Alt 2 and
Alt 3a through Alt 3d, were reviewed and reported on as part of the previous studies for the Project.
The manner in the proposed design for each alternative to provide the necessary storage is described
in Section 1.3 through Section 1.5 of the FFS.
The Project studies have shown that each of the six arrangements are technically and
environmentally feasible. However, the studies also reveal that each arrangement includes
significant challenges potentially affecting their long term economics and/or operational reliability as
listed in Table 1.1.
Table 1.1
Final Feasibility Report
Design and Economic Considerations
Alternative Design and Economic Considerations
Alt 1 Tunnel cost
Alt 2 Tunnel cost
Alt 3a Reliable operation of siphon and maintenance thereof during winter period
Alt 3b Drilling of micro-tunnel in glacial moraine
Alt 3c Embankment cost, foundation conditions for embankment, seepage, liquifaction & avalanches
Alt 3d Embankment cost, foundation conditions for embankment, seepage, liquifaction & avalanches
Subsequent to the completion of the FFS, the range of challenges as summarized above led to a
concern regarding the viability of a storage project within the Allison Creek drainage. However, the
high elevation of the first 2000’ below the outlet of Allison Lake suggests that there would be a
significant amount of energy available from Allison Creek as a run-of-river project. To date the system
load characteristics of CVEA has been such that much of the this additional energy would be
stranded; i.e. there would be no load available for the project to serve.
Recently, however, a 2 MW industrial facility has been brought into the CVEA system. This
additional load will provide an opportunity to CVEA to more fully operate a run-of-river project to
accommodate what would otherwise be served by diesel generation. This scheme is referred to as
Alt 4.
The purpose of this Addendum to the FFS dated May 2010, is to present the evaluation of the
economic viability of alternative run-of-river arrangements for capturing the hydropower potential of
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 2
Allison Creek as a project to serve an expanded CVEA system load. Accordingly, the scope of work
leading to this Addendum to the FFS has included the following activities:
1. Development of alternative project arrangements consistent with the purposes of this
Addendum
2. Review of Allison Lake hydrology as related to the run-of-river hydropower potential of the
identified alternatives
3. Preliminary layout and cost estimate of hydroelectric project features for each of the
identified project arrangements
4. Economic evaluation of the identified alternatives
5. Environmental review of the of the identified alternatives
6. Preparation of this addendum to the Final Feasibility Report including the resulting
conclusions and recommendations
1.2 Alternative 4 – General Arrangement
The primary features of the run-of-river project selected for this review include the following:
• A low diversion structure on Allison Creek at El. 1300,
• A 42” diameter surface / buried penstock,
• A 6.5 MW powerhouse along Allison Creek at El. 130 with a 1.75 mile transmission line
leading to the Solomon Gulch switchyard, and
• A permanent 1,000 foot access road to the powerhouse and a temporary 4,500 foot trail for
penstock construction access.
The general arrangement for Alt 4 of these features is shown in Figure 1.1. Two versions of Alt 4 are
reviewed herein as described in the following paragraphs.
Figure 1.1
Alternative 4 General Arrangement
ALTERNATIVE 4
Diversion Structure
Powerhouse
Penstock
Allison Lake
ALTERNATIVE 4
Diversion Structure
Powerhouse
Penstock
Allison Lake
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 3
1.3 Alternative 4a – Diversion Structure on Allison Creek with Penstock leading to
Powerhouse (Alt 4a)
Alt 4a includes the primary features as described above. Plan and profile views of Alt 4a are shown
in Figure 1.2. The general details of the penstock and powerhouse are shown on Figures B.6 and
B.7 respectively within Appendix B of the FFS. The actual dimensions of the penstock and
powerhouse will be in proportion to the 42” penstock and 6.5 MW powerhouse as referenced above
for Alt 4 in lieu of the 36” penstock and 4 MW powerhouse for Alt 3c as shown in the FFS.
The access road to the powerhouse as shown in Figure 1.2 will be designed in accordance with the
criteria set forth in Appendix C.3. The design of the access trail from the loop road off the Trans
Alaska Pipeline System corridor to the point where the penstock crosses over a ridge will follow the
same alignment to that point as was studied for the construction access for Alt 3c. However, the
width of the corridor will be reduced consistent with the use helicopters as the primary access for
construction of the penstock and diversion structure.
Figure 1.2
Alternative 4a – Plan and Profile
PLAN
PROFILE
The diversion structure will located along Allison Creek at approximately El. 1300. The specific
location and type of diversion scheme to be used for the run-of-river option will be determined at the
next level of the design process. A conceptual drawing of the type of diversion structure used for the
present purpose is shown in Figure 1.3.
Surface / Buried Penstock
0+005+0010+0015+0020+0025+0030+0035+0040+0045+0050+0055+0060+0065+00100
500
1000
Elevation (ft)Station(ft )
Powerhouse
70+00Surface / Buried Penstock
0+005+0010+0015+0020+0025+0030+0035+0040+0045+0050+0055+0060+0065+00100
500
1000
Elevation (ft)Station(ft )
Powerhouse
70+00Diversion Structure
Powerhouse
S u rf a ce / B u ri ed Pe n st o c k
AccessTrail
AccessRoad
Allison Lake
Diversion Structure
Powerhouse
S u rf a ce / B u ri ed Pe n st o c k
AccessTrail
AccessRoadAccessRoad
Allison Lake
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 4
Figure 1.3
Diversion Structure – Plan and Cross Section
PLAN
CROSS SECTION
1.4 Alternative 4b – Raising Solomon Gulch Reservoir Maximum Water Surface 5 feet
with Inflatable Gates on Spillway (Alt 4b)
Alt 4b adds additional storage to Solomon Gulch reservoir by modifying the spillway with 5 foot
high inflatable gates extending the full length of the 450 foot long spillway. The proprietary
Obermeyer Gate System consist of steel panels that are raised up by inflating a rubber bladder. This
is necessary because the alternative rubber bladder gates without steel panels are not sufficiently
controllable. They must be either in the fully inflated or fully deflated mode and can release too
much water into the tailrace during the transition. The Obermeyer gates can operate at any stage
between up or down thereby controlling water release. The profile view of Alt 4b is shown in Figure
1.5. 130013101300131001020 5030 40
SCALE IN FEET42”FPenstockAllison Creek130013101300131001020 5030 40
SCALE IN FEET
01020 5030 4001020 5030 40
SCALE IN FEET42”FPenstockAllison CreekAllison CreekEL. 1300
EL. 1306
WS EL. 1301 @ 80 cfs
WS EL. 1305 @ 800 cfs
15 201005
SCALE IN FEET
EL. 1300
EL. 1306
WS EL. 1301 @ 80 cfs
WS EL. 1305 @ 800 cfsWS EL. 1305 @ 800 cfs
15 201005
SCALE IN FEET
15 20100515 20100 5 15 201005
SCALE IN FEET
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 5
Figure 1.4
Typical Obermeyer Gate Installation
Figure 1.5
Solomon Gulch Obermeyer Spillway Gate Cross Section
COLLAPSIBLE REINFORCED RUBBER
RESTRAINING STRAP TYP (3) PLACES
EACH 19.56’ GATE SECTION
TOP OF GATE EL. 690.0
STEEL GATE PANEL SUPPLIED IN NOMINAL
19.56’ LENGTHS. (23) GATE PANELS SPAN
450’ GATE LENGTH
DUCTILE IRON
CLAMP CASTING
EL. 684.5 INFLATABLE DUAL CHAMBER AIR BLADDER
SUPPLIED IN NOMINAL 19.56’ LENGTHS
RESTRAINING STRAP ANCHOR BOLT TYP
(6) PLACES EACH 19.56’ GATE SECTION
STAINLESS STEEL MAIN ANCHOR
BOLT TYP 12’ ON CENTER
COLLAPSIBLE REINFORCED RUBBER
RESTRAINING STRAP TYP (3) PLACES
EACH 19.56’ GATE SECTION
TOP OF GATE EL. 690.0
STEEL GATE PANEL SUPPLIED IN NOMINAL
19.56’ LENGTHS. (23) GATE PANELS SPAN
450’ GATE LENGTH
DUCTILE IRON
CLAMP CASTING
EL. 684.5 INFLATABLE DUAL CHAMBER AIR BLADDER
SUPPLIED IN NOMINAL 19.56’ LENGTHS
RESTRAINING STRAP ANCHOR BOLT TYP
(6) PLACES EACH 19.56’ GATE SECTION
STAINLESS STEEL MAIN ANCHOR
BOLT TYP 12’ ON CENTER
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 6
2. Power Studies
2.1 Unconstrained Run-of-River Operation
By definition, without a reservoir to regulate available flows at the intake, a hydropower project can
only be operated when instantaneous flows are within the range of physical capability of the
generating equipment. All flows greater than the maximum capability will flow past the intake as
spill. In addition, all flows required for other instream uses as well as all flows less than that required
to operate the smallest hydropower unit must be passed by the intake.
This condition is illustrated in Figure 2.1 in the form of an annual flow duration curve for the run-of-
river hydropower arrangement described in Section 1. The curve, which is based on the hydrology
defined in the FFS, shows that a run-of-river facility installed on Allison Creek could operate
whenever the flows in the creek are between 9 cfs and 85 cfs for the condition:
• The minimum instream flow release is 5 cfs
• The minimum turbine flow is 4 cfs, and
• The maximum turbine flow is 80 cfs.
Figure 2.1
Allison Creek Flow Annual Flow-Duration Curve
On this basis, the plant could operate approximately 62% of the time and the total amount of water
available for generation, Qgen, is represented by the blue cross-hatched area within Figure 2.1. The
difference in elevation between the diversion structure and the powerhouse times Qgen times 8,760
hours in a year provides an estimated 23.3 GWh as the average total amount of energy potentially
available from a run-of-river project on Allison Creek.
The same basic approach as applied to monthly flow duration curves results in the monthly
distribution of the 23.3 GWh as shown in Figure 2.2.
0.0
50.0
100.0
150.0
200.0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
ExcedenceFlow (cfs)Instream Flow
Qmin=5 cfs
Unit Qmin=4 cfs
Generation 23.3 GWh
(Unit Qmax=80 cfs)
Spill
ExcedenceFlow (cfs)0.0
50.0
100.0
150.0
200.0
0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
ExcedenceFlow (cfs)Instream Flow
Qmin=5 cfs
Unit Qmin=4 cfs
Generation 23.3 GWh
(Unit Qmax=80 cfs)
Spill
ExcedenceFlow (cfs)
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 7
Figure 2.2
Allison Average Monthly Distribution of Energy Production
The above analysis is valid for the case that the energy from the project is not constrained by the
system load conditions. Specifically, the monthly distribution of energy as shown in Figure 2.2 is
important from the perspective the ability of CVEA to assimilate a run-of-river project on Allison
Creek into their system. For example, the Solomon Gulch Project can substantially accommodate
the total system under current load conditions for the month of July. Accordingly, the 4.8 GWh
available generation from Allison Lake could theoretically be stranded and the Allison Creek flows
would spill past the intake.
However, the complete loss of the 4.8 GWh will be offset to some degree by the storage capability
within Solomon Gulch by allowing Solomon Gulch to remain full longer into the fall season. The
analysis of this opportunity is with the AUTO Vista model as presented in the FFS is presented below
for Alt 4a and Alt 4b.
2.2 System Loads and Resources
2.2.1 System Loads
The AUTO Vista model operates on an hourly time step to meet system loads in the most cost
effective manner using available system resources as a function of their respective cost of production.
For the present study, two cases for the system load were considered as follows:
• The system load as recorded by CVEA data for 2006, as was the basis for all previous
studies.
• The above case with the addition of a new 2 MW load to continuously serve Petro Star
for 50 weeks of the year.
2.2.2 System Resources
The system resources considered for the existing case included the combined diesel plant facilities in
Valdez and Glennallen, the combined cycle unit as operated under the contract with Petro Star, and
the existing hydropower facilities at the Solomon Gulch Project. The proposed development
included the additions as discussed in Section 1 above as well as retirement of the existing thermal
generation resources to the extent possible in each respective case under consideration.
0.1 0.0 0.0 0.1
2.2
4.3
4.8
4.3
3.6
2.7
1.0
0.4
0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Total Annual Energy
= 23.3 GWh
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 8
2.3 AUTO Vista Model: Allison Creek Run-of-River Hydropower Development
AUTO Vista was used to evaluate the generation benefits of various upgrade configurations under
consideration for the Project during the studies leading to the FFS Report. As stated at the close of
Section 1, the focus of this Addendum includes Alt 4a and Alt 4b as discussed below. The following
is a description of the program and a discussion of the how AUTO Vista was applied for the
condition that the run-of-river operation of the Project is required to operate within the CVEA system.
The AUTO Vista model for the Project includes the drainage basins for both the existing Solomon
Gulch Project and Allison Lake. It is comprised of a series of arcs and nodes with each element
having its set of characteristics as defined in the FFS. The graphical model for the existing system, Alt
4a and Alt 4b as expressed in these terms is shown in Figure 2.3. Major features of the AUTO Vista
model are briefly described below.
Figure 2.3
AUTO Vista Model Elements: Alt 4a and Alt 4b
2.4 Hydrology
The hydrology used for the AUTO Vista model is based on the work done by the U.S. Army Corps of
Engineers (COE) in 1982 as part of their evaluation of the potential project configurations for
maximizing the Allison Lake resource. The correlations developed from that study results in a 39-
year period of average daily flows from 1950 through 1989. A statistical analysis of this period of
record was performed to establish a representative smaller group of 7 years for use within the present
AUTO Vista. The set of 7 years was chosen on the basis of balancing the wet to dry conditions of
annual inflow to the two basins. The specific years chosen and the associated representative inflow
conditions are summarized in Table 2.1.
ALSQ
(Allison Lake
Inflow)
ALSS
(Allison Lake Spill)
ALSP
(Allison Lake
Power)
ALST
(Allison Lake TWL)
SLGR
(Solomon Gulch Reservoir)
SLGQ
(Solomon Gulch Inflow)
SLGP
(Solomon Gulch Power)
SLGT
(Solomon Gulch TWL)
S_SINK
(Source_Sink)
SINS
(Solomon
Instream Flow)
SLGS
(Solomon Gulch Spill)
SLGINS_RJ
(Solomon Gulch INS Junc)
ALSSPWY_RJ
(Allison SPWY TWL)
ALSR
(Allison Lake)
A_SINK
(Source_Sink)
ALSQ
(Allison Lake
Inflow)
ALSS
(Allison Lake Spill)
ALSP
(Allison Lake
Power)
ALST
(Allison Lake TWL)
SLGR
(Solomon Gulch Reservoir)
SLGQ
(Solomon Gulch Inflow)
SLGP
(Solomon Gulch Power)
SLGT
(Solomon Gulch TWL)
S_SINK
(Source_Sink)
SINS
(Solomon
Instream Flow)
SLGS
(Solomon Gulch Spill)
SLGINS_RJ
(Solomon Gulch INS Junc)
ALSSPWY_RJ
(Allison SPWY TWL)
ALSR
(Allison Lake)
A_SINK
(Source_Sink)
ALSR
(Allison Lake)
A_SINK
(Source_Sink)
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 9
Table 2.1
AUTO Vista Hydrologic Years
2.5 Hydro Equipment Characteristics
The performance curves for the Solomon Gulch powerhouse have been included as provided by the
CVEA. The new units at the proposed Allison Lake powerhouse for Alt 4a is based on Hatch Acres
in-house generic data for Pelton units. Both alternatives include a 6.5 MW generating station
comprised of two 3.25 MW generating units. A plot of the characteristics used in this analysis for
each of the 3.25 MW units is shown in Figure 2.4.
All elements of the conduit system components for each alternative have been assumed to perform in
accordance with published engineering data.
Figure 2.4
Allison Powerhouse Unit Characteristics – 2 x 3.25 MW Units
2.6 AUTO Vista Results
Stacked bar charts indicating the most efficient dispatch of system resources as required to meet the
system load are included in Appendix A for the existing condition, Alt 4a and Alt 4b. The first
charts compare the existing condition to the development alternatives for the 1961 water year, which
is the 50% year as indicated in Table 2.1.
Total Inflow
Year Percentile Acre-Feet
1969 10% 28,900
1984 25% 30,800
1954 25% 30,900
1961 50% 33,200
1957 75% 36,100
1977 75% 37,900
1989 90% 42,800
Average 34,400
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
0 5 10 15 20 25 30 35 40 45Discharge (cfs)Efficiency (%)0.0
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
Power (MW)Calculated Efficiency
Caculated Power
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 10
The annual generation for the base case of the existing load and resource condition for each of the 7
years included in the analysis is shown in Table 2.2 and the annual generation for Alt 4a and Alt 4b
for the existing load condition is shown in Tables 2.3 and 2.4 below.
Table 2.2
Annual Generation – Existing Condition, Loads and Resources
Table 2.3
Annual Generation – Alt 4a w/ Existing Load
Table 2.4
Annual Generation – Alt 4b w/ Existing Load
Generation (MWh)
Year Solomon Allison Total Hydro Diesel Cogen Total
196 9 51,900 0 51,90 0 11,300 23,100 86,400
1984 55,200 0 55,200 8,100 23,000 86,400
1954 55,700 0 55,700 7,600 23,000 86,400
1961 59,700 0 59,70 0 6,100 20,600 86,400
1957 58,500 0 58,500 7,200 20,700 86,400
1977 61,800 0 61,80 0 3,100 21,500 86,400
1989 62,100 0 62,100 4,400 19,900 86,400
Average 57,800 0 57,800 6,800 21,700 86,400
Generation (MWh)
Year Solomon Allison Total Hydro Diesel Cogen Total
196 9 54,60 0 13,700 68,400 50 0 17,50 0 86,400
1984 54,000 15,100 69,200 300 16,900 86,400
1954 49,500 13,800 63,400 500 22,500 86,400
1961 53,20 0 14,100 67,300 50 0 18,50 0 86,400
1957 55,100 11,800 67,000 500 18,900 86,400
1977 57,80 0 12,400 70,200 30 0 15,90 0 86,400
1989 57,900 10,300 68,200 400 17,800 86,400
Average 54,600 13,000 67,700 400 18,300 86,400
Generation (MWh)
Year Solomon Allison Total Hydro Diesel Cogen Total
1969 55,100 15,30 0 70,400 500 15,50 0 86,400
1984 55,000 16,200 71,200 400 14,800 86,400
1954 51,900 13,600 65,500 500 20,300 86,400
1961 55,300 14,40 0 69,800 400 16,20 0 86,400
1957 56,100 12,900 69,000 500 16,800 86,400
1977 59,300 12,90 0 72,200 500 13,70 0 86,400
1989 59,300 10,900 70,100 500 15,800 86,400
Average 56,000 13,700 69,700 500 16,200 86,400
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 11
The annual generation for the base case of the additional 2MW load and resource condition for each
of the 7 years included in the analysis is shown in Table 2.5 and the annual generation for Alt 4a and
Alt 4b for the additional 2MW load condition is shown in Tables 2.6 and 2.7 below.
Table 2.5
Annual Generation – Existing Resources w/ 2 MW Additional Load
Table 2.6
Annual Generation – Alt 4a w/ 2 MW Additional Load
Generation (MWh)
Year Solomon Allison Total Hydro Diesel Cogen Total
1969 57,000 18,100 75,100 3,000 25,500 103,500
1984 57,700 19,000 76,700 3,000 23,900 103,500
1954 53,500 17,800 71,300 8,200 24,100 103,500
1961 58,900 16,600 75,500 4,200 23,800 103,500
1957 59,600 15,200 74,800 4,600 24,200 103,500
1977 61,900 15,700 77,700 2,000 23,900 103,500
1989 62,600 14,000 76,600 4,600 22,400 103,500
Average 58,700 16,600 75,400 4,200 24,000 103,500
Table 2.7
Annual Generation – Alt 4b w/ 2 MW Additional Load
The annual general benefits from the AUTO Vista Analyses for Alt 4a and Alt 4b can then be
summarized for each load case as shown in Table 2.8 in terms of the incremental hydropower
generation and associated reduction on thermal power as required to satisfy the system load for each
of the alternatives under consideration. Please note that the minor differences between the hydro
and thermal generation values for each alternative are due to rounding within the AUTO Vista
modeling.
Generation (MWh)
Year Solomon Allison Total Hydro Diesel Cogen Total
1969 51,700 0 51,700 28,700 23,100 103,500
1984 54,800 0 54,800 25,600 23,100 103,500
1954 55,500 0 55,500 24,900 23,100 103,500
1961 59,100 0 59,100 21,400 23,000 103,500
1957 62,100 0 62,100 19,800 21,700 103,500
1977 66,000 0 66,000 15,200 22,400 103,500
1989 66,500 0 66,500 15,500 21,600 103,500
Average 59,400 0 59,400 21,600 22,600 103,500
Generation (MWh)
Year Solomon Allison Total Hydro Diesel Cogen Total
196 9 58,200 19,000 77,200 900 25,400 103,500
1984 58,500 20,200 78,700 1,000 23,900 103,500
1954 55,600 17,800 73,400 5,900 24,200 103,500
1961 60,400 17,100 77,500 2,300 23,700 103,500
1957 61,300 15,600 76,900 2,600 24,100 103,500
1977 63,800 15,700 79,500 300 23,700 103,500
1989 63,800 14,900 78,600 2,500 22,400 103,500
Average 60,200 17,200 77,400 2,200 23,900 103,500
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 12
Table 2.8
Annual Benefits – Alt 4a & 4b
Resource Existing Alt 4a Alt 4b Existing Alt 4a Alt 4b
Hydro 57,800 67,700 69,700 59,400 75,400 77,400
Fossil 28,500 18,700 16,700 44,200 28,200 26,100
Total 86,300 86,400 86,400 103,600 103,600 103,500
Benefit 9,900 11,900 16,000 18,000
Existing Load - Generation (MWh) 2 MW Addition - Generation (MWh)
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 13
3. Project Construction Cost and Construction Schedule
Construction costs and schedules were prepared and reported for the various upgrade configurations
under consideration for the Project during the Pre-Feasibility Study, Interim Feasibility Review and
Final Feasibility Study. As stated at the close of Section 1, the focus of this Addendum to the Final
Feasibility Study Report includes Alt 4a and Alt 4b as discussed below.
3.1 Construction Cost Estimates
All cost estimates are based on January 2010 bid price levels. The Direct Construction cost for each
alternative is the total of all costs directly chargeable to the construction of the project and in essence
represents a contractor’s bid. Indirect costs include an allowance for contingencies, engineering and
owner administration and are added to the Direct Construction Cost to result in the Total
Construction Cost. The contingency used for all alternatives was 25%. Engineering and Owner
Administration assumed for all alternatives was 15% of construction cost, inclusive of contingencies.
The period of time required to complete the FERC licensing process can be expected to be
approximately 3 years. Adding another 2+ years to construct the project over three construction
seasons suggests that a realistic on-line date of the project to be in the range of 2015. Accordingly, it
is appropriate to include escalation to the above costs to determine a realistic on-line cost for the
project. However, for the purposes of the present economic analyses, 2010 dollars are used herein
to avoid the need to hypothesize what the cost of thermal generation may be that far into the future.
3.1.1 Alternative 4a
The basis for the construction cost of the various elements of Alt 4a are listed below as follows:
• Mobilization. The mobilization cost is taken directly from the estimates for Alt 3c on
the basis that the construction activities for the initial year of construction are nearly
identical.
• Construction Access Trail. The cost of the 4,500 foot access trail to the high point of the
penstock above the powerhouse is estimated as 60% of the estimate for the access road
for Alt 3c. The overall length of the trail is approximately 30% of that of the route for
Alt 3c and the width of the road bench for the trail will be two-thirds for that required
for Alt 3c. However, the alignment for the trail will be the same as that for the Alt 3c
road, which is by far the most difficult portion for construction.
• Diversion Structure. The cost for the diversion structure is based on the unit costs for
similar features of the nearby diversion structure for the Humpback Creek project that is
currently under construction for Cordova Electric Cooperative.
• Surface Pipeline / Penstock. The cost of the surface pipeline / penstock is based on the
detailed estimates developed for the comparable penstock segments of Alt 3c as
included in Appendix E of the FFS.
• Powerhouse. The costs for the major equipment within the 6.5 MW powerhouse are
based on preliminary quotations from equipment suppliers while the cost for other
lower cost items were obtained from in-house cost data and from recently obtained bid
prices on similar construction.
• Switchyard. The switchyard cost is taken directly from the estimate for Alt 3c.
• Transmission. The transmission cost is taken directly from the estimate for Alt 3c.
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 14
The resulting construction cost estimate for Alt 4a is summarized in Table 3.1.
Table 3.1
Alternative 4a
Total Construction Cost (Bid 1/2010)
Item
1. Mobilization $1,573,000
2. Construction Access Trail $2,916,000
3. Dam, Intake & Spillway
a. Diversion Structure $2,230,000
b. Spillway $0
$2,230,000
4. Surface Penstock / Pipeline
a. HDPE Pipeline $0
b. Steel Pipeline $5,176,000
Subtotal $5,176,000
5. Powerhouse
a. Civil Works $2,594,000
b. Turbine & Generator $4,710,000
c. Misc. Mech. Equip.$683,000
d. Misc. Elec. Equip.$1,015,000
e. Bridge Crane $187,000
Subtotal $9,189,000
6. Switchyard $525,000
7. Transm. & Interconnection $310,000
Direct Construction Cost (Bid 1/09)$21,919,000
Escalation -$590,000
Direct Construction Cost (Bid 1/10)$21,329,000
Contingencies $6,076,000
Engineering & Owner Admin.$4,111,000
Total Construction Cost (Bid 1/10)$32,106,000
3.1.2 Alternative 4b
The cost for the addition of a Obermeyer Gate on the top of the Solomon Gulch Spillway 5 feet in
height was considered on its own as an incremental feature for the CVEA system. The cost of this
addition is based on a preliminary quotation for the gate materials and a configuration as suggested
by the Obermeyer company. The costs for modifications to the existing spillway and installation of
the gate are based on estimated quantities of construction and in-house unit costs. The resulting cost
for Alt 4b is summarized in Table 3.2.
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 15
Table 3.2
Alternative 4b
Total Construction Cost (Bid 1/2010)
Item
Labor $2,106,000
Equipment $235,000
Materials $1,951,000
Direct Construction Cost (Bid 1/10)$4,292,000
Contingencies $858,000
Engineering & Owner Admin.$773,000
Total Construction Cost (Bid 1/10)$5,923,000
3.2 Construction Schedule
The construction schedule for Alt 4a and Alt 4b is primarily controlled by the following major
factors:
• Delivery time for major powerhouse equipment
• Access to Allison Lake for construction activity
• Four month window for construction activity at Allison Lake
A similar approach has been used to develop a schedule for each alterative relative to the purposes
of the cost estimates presented above and the annual costs presented below for each alternative. The
schedule for Alt 4a is presented in Figure 3.3 as an example thereof.
Figure 3.3
Alternative 4a
Construction Schedule
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 16
3.3 Economic Analysis
Annual costs of the Project can be apportioned into fixed and variable costs. For this analysis, the
fixed amount, amortization of the Total Capital Requirements less earnings on Reserves, is based on
7% interest rate financing over a 30-year term. Variable annual costs escalate each year and include
operation and maintenance (O&M) costs, administrative and general expenses, interim replacements
and insurance. The basic assumptions for determining the annual fixed and variable costs of the
Project are shown in Table 3.3.
Table 3.3
Basic Assumptions for Economic Analyses
Item Value
Construction Period (Alt 4a) 25 months
Financing Term 30 years
Financing Interest Rate 7%
Reinvestment Rate Same as financing
Escalation of Project Costs 3% annually
Financing Reserve 1 year of debt service
Financing Expenses 3% of Total Investment Cost
Variable Annual Costs $500,000
3.3.1 Cost of Power – Alternative 4a
The Total Investment cost includes interest during construction (IDC) over an assumed 25-month
construction period. As outlined above, we have assumed that construction at the project site would
come to a stop during the winter months, with the exception of equipment installation within the
powerhouse structure. The development of the annual cost for Alt 4a is shown in 2010 dollars on
Table 3.4.
Table 3.4
Alternative 4a – First Year Annual Cost (2010 dollars)
Item Cost
Total Construction Cost (Bid 1/10)$32,106,000
Interest During Construction 2,435,000
Total Investment Cost $34,541,000
Reserve Fund 3,127,000
Financing & Legal 1,036,000
Working Capital 100,000
Total Capital Requirements (1/10)$38,804,000
Annual Cost
Debt Service $3,127,000
O&M Cost 280,000
Administrative & General 112,000
Insurance 50,000
Interim Replacements 50,000
Earnings on Reserve Fund (219,000)
Total First-Year Annual Cost $3,400,000
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 17
As discussed in Section 2 above, the unit cost of power becomes a function of the extent to which
the power available from the Project can actually contribute to the CVEA system load on a day-to-
day, hour-to-hour basis. In this regard, three scenarios are presented including:
1. The AUTO Vista studies performed indicate that a total of 9,900,000 kWh from the
Project can be used within the existing CVEA system load.
2. With an additional 2 MW of load within the CVEA system, the AUTO Vista studies
performed also indicate that a total of 16,000,000 kWh from the Project can be
effectively utilized.
3. The review of the available flow data for Allison Creek indicate that a 6.5 MW run-of-
river project at the site would have the capability to produce a total of 23,300,000 kWh
at such time that the CVEA system load that would not constrain its operation.
The cost of power resulting from these three scenarios is presented in Table 3.5.
Table 3.5
Alternative 4a – Cost of Power
3.3.2 Cost of Power – Alternative 4b
As indicated by the results included in Table 2.8, the addition of the Obermeyer gate to the Solomon
Gulch spillway adds 2,000,000 kWh to the energy for the Alt 4a development with and without the
anticipated additional 2 MW of load to the CVEA system. Further, the Alt 4b contribution to the
CVEA system load is essentially the same without a run-of-river development of Allison Creek. The
resulting cost of power during the first year of operation is shown in Table 3.6.
Item Value
Alt 4a with Existing System Load (kWh)9,900,000
First-Year Cost of Power (1/2010) ($/kWh)$0.343
Alt 4a with 2 MW Additional Load (kWh)16,000,000
First-Year Cost of Power (1/2010) ($/kWh)$0.213
Alt 4a with Expanded CVEA System (kWh)23,300,000
First-Year Cost of Power (1/2010) ($/kWh)$0.146
Total First-Year Annual Cost $3,400,000
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 18
Table 3.6
Alternative 4b – Cost of Power
Item Cost
Total Construction Cost (Bid 1/10)$5,469,000
Interest During Construction 255,000
Total Investment Cost $5,724,000
Reserve Fund 526,000
Financing & Legal 172,000
Working Capital 100,000
Total Capital Requirements (1/10)$6,522,000
Annual Cost
Debt Service $526,000
O&M Cost 280,000
Administrative & General 112,000
Insurance 50,000
Interim Replacements 50,000
Earnings on Reserve Fund (37,000)
Total First-Year Annual Cost $981,000
Added Hydro Generation, Existing System (kWh)2,000,000
First-Year Cost of Power (1/2010) ($/kWh)$0.491
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 19
4. Regulatory and Environmental Considerations
4.1 Alternative 4a
4.1.1 Regulatory Considerations
CVEA provided the Preliminary Application Document (PAD), including the Draft Application for
License and Preliminary Draft Environmental Assessment (PDEA) (Draft Application) for the Allison
Lake Project to entities listed on the Project Contact List on April 13, 2010. The PAD, including the
Draft Application for License, described the proposed 4.5 MW storage project and was prepared
under the regulation for Major Unconstructed Project Less Than 5 MW pursuant to 18 CFR 4.61.
The proposed run-of-river modification to the Project would have an installed capacity of 6.5 MW
and therefore would be greater than 5 MW and the Application for License would be prepared
pursuant to 18 CFR 4.41, Major Unconstructed Project Greater Than 5 MW. This change in the
applicable FERC regulation would not significantly affect the environmental work to date and the
PDEA, however, the Engineering Exhibit A as provided on April 13, 2010, would need to be
modified and expanded to address engineering Exhibits A through D as required by 18 CFR 4.41.
The change from the 4.5 MW storage project to the proposed 6.5 MW run-of-river project will
require:
• Revision of the PDEA to present the run-of-river project description and related operation.
• Preparation of the revised engineering exhibits. The Draft Application as provided on April
13, 2010, included the engineering Exhibit A for the proposed 4.5 MW storage project
pursuant to 18 CFR 4.61. The change to the proposed 6.5 MW run-of-river project changes
the applicable FERC regulation to 18 CFR 4.41 and the engineering exhibits expand to
Exhibits A through D.
• Preparation and issuance of Revised Scoping Document 1 (SD1). The process for issuing the
revised SD1 was discussed with FERC Staff. CVEA will not be required to hold new scoping
meetings, nor conduct an additional site visit. FERC Staff recommended that CVEA (1)
provide a revised SD1 along with a revised PAD to entities on the Project Contact List; and,
(2) following provision of these revised documents, schedule a teleconference with the
resource agencies and other interested participants to discuss the revised proposed Project.
In light of the above, the level of effort going forward for document preparation for the 6.5 MW run-
of-river option would be greater than that required for the 4.5 MW storage option due to the
redundancies involved with the 18 CFR 4.41 process. However, the downstream benefits in the
activities for development of the run-of-river project would be greatly increased as discussed below,
greatly overweighing the additional effort required for document preparation and the licensing
process itself.
4.1.2 Environmental Field Investigations
In support of the preliminary permit, environmental field investigations began in 2008 for the
Project. The status of these field investigations and desk-top reviews as of May 2010 is summarized
in Section 5 of the FFS and the complete reports can be found in Appendix F to the FFS. The major
studies conducted are listed in Table 4.1.
All of the studies to date are equally applicable to the run-of-river project as discussed herein and
those arrangements considered in the FFS. Further, the selection of a run-of-river arrangement for the
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 20
project is not expected to require any new major areas of study in the support the FERC licensing
process. However, as indicated by Table 4.1, on-going work will be required in several areas as
follows:
• Water Use & Quality. The on-going work in this area will primarily be continued
monitoring of the two stream gages in order to develop and maintain a continuous record for
the flow regime for Allison Creek.
• Biological Resources. The baseline work for fish populations and habitat, vegetation, birds
and mammals, and wildlife habitats is complete. Areas that will require further work
include:
- Aquatic Resources: Further work will be necessary to provide a basis for final
negotiation of the amount of flow required to maintain an in-stream flow between
the diversion structure and the powerhouse.
- Wetlands: Further work will be required to evaluate the extent of any wetlands
located along the selected transmission line alignment.
• Archaeological / Historical Resources. The field work for the archaeological and historical
resources of the project area has been completed.
Table 4.1
Summary of Major Environmental Field Studies
Type of Field Investigation Conducted By Timeline
Geological Resources
(As described in Section 2) R&M Consultants Began: 2008
Completed: 2009
Water Use and Quality R&M Consultants Began: 2008
Completed: on-going
Biological Resources
- Fish and Aquatic Resources
- Vegetation
- Wetlands
- Birds and Mammals
- Wildlife Habitats
ABR, Inc. Began: 2008
Completed: on-going
Archaeological/Historical NLUR, Inc. Began: 2009
Completed: 2010
4.1.3 Environmental Considerations
While the regulatory framework for Alt 4a is more detailed than that associated for Alt 3c, the
associated scope of environmental issues is greatly reduced. The more significant elements of this
comparison are:
• Allison Lake would be left in its natural state in the case of Alt 4a, which has not been the
case for all arrangements previously considered. In the lake-tap alternatives the lake would
have been drawn down by as much as 100 feet during the winter season; and in the case of
Alt 3c the lake would have been raised 43 feet thereby inundating the existing east and west
shorelines and the delta at the south end of the lake.
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 21
• The construction activity of the dam near the outlet of the lake would disturb a significant
area with attendant concerns for water quality within Allison Creek to a much greater extent
that would be associated with the construction of the diversion structure for Alt 4a.
• The construction of the diversion structure for Alt 4a would not require that a road be
constructed to the outlet of Allison Lake nor the extensive amount of traffic thereon
associated with the construction of the major dam structure included with Alt 3c.
• In the case of Alt 3c, there would be a potential for seepage beneath and around the dam
resulting in a loss of water available for hydropower generation as well as changed ground
water conditions in the glacial moraine downstream of Allison Lake. While not likely, any
seepage that may occur at the location of the diversion structure associated with Alt 4a
would be very minor.
• In the case of Alt 4a, the flow regime within Allison Creek would remain unchanged
between Allison Lake and the diversion structure as well as the within the reach downstream
of the powerhouse, the latter being the area of primary concern for the habitat for both
resident and anadromous fish species.
All of these factors would greatly reduce the level of effort of that required for Alt 4a as compared to
Alt 3c for agency consultation throughout the remaining licensing activities as well as for
environmental monitoring during construction and operation of the project.
4.2 Alternative 4b
4.2.1 Regulatory Considerations
An amendment to the existing Solomon Gulch Project FERC License (No. P-2742) would be required
for the proposed five foot raise in the normal maximum water surface of Solomon Lake as proposed
for Alt 4b. The amendment would require that agency consultation take place in a manner
comparable to that currently anticipated for the Allison Lake development. As part of the
consultation process, issues that were not resolved according to current practice during the original
licensing process would likely be revisited by existing agency staff.
4.2.2 Environmental Field Studies
Ostensibly, the environmental field studies would focus on habitat values within the additional area
to be submerged surrounding Solomon Lake as the result of the proposed five foot raise in the
normal maximum water surface of Solomon Lake. It can be expected, however, that agency
consultation would result in requests for further studies with regard to other aspects of the project
that were not studied in accordance with current practice as part of the original licensing process.
4.2.3 Environmental Considerations
No specific concerns of a fatal flaw nature have been identified with regard to the environmental
effects of the proposed five foot raise in the normal maximum water surface of Solomon Lake as
proposed for Alt 4b.
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 22
5. Conclusions and Recommendations
5.1 Conclusions
5.1.1 Alternative 4a
In addition to the general conclusions relating to the development of a hydropower project in the
Allison Creek basin as provided in the FFS, conclusions specific to the run-of-river Alt 4a gained as
the result of the present evaluation include the following:
• The scope of the project as propose for the run-of-river Alt 4a is significantly reduced from
that associated with Alt 3c.
• A run-of-river Alt 4a development of the Allison Creek basin can produce 22.3 GWh of
energy on an average annual basis within the environment of an unconstricted system load.
• A run-of-river Alt 4a development of the Allison Creek basin would produce 9.8 GWh of
energy on an average annual basis within the existing CVEA system load. The project is not
cost effective under this load condition.
• With the addition of 2 MW to the CVEA system load, the Alt 4a average annual contribution
to the CVEA system load would increase to 16.0 GWh. On this basis, the project would be
competitive with the cost of diesel generation.
• Further increases in the CVEA system load would in turn result in a further reduction in the
cost of power from Alt 4a.
• The reduced scale of the hydropower development of the Allison Creek basin as offered by
Alt 4a would in turn minimize the risk of construction cost overruns relative to that
potentially associated with Alt 3c.
• The diversion structure proposed for Alt 4a would entail a minimal, if any, risk of seepage or
other dam safety related issues in contrast to that potentially associated with the large dam at
the outlet of Allison Lake as proposed for Alt 3c.
• On the basis that the installed capacity of the run-of-river Alt 4a is expected to be greater
than 5 MW, FERC 18 CFR 4.41 would be the required regulation for the preparation of a
FERC License Application for the project.
• The reduced scale of the hydropower development of the Allison Creek basin as offered by
Alt 4a will result in an overall reduction in environmental effects relative to that associated
with Alt 3c.
• In contrast to any of the storage project arrangements as previously considered for
development of the Allison Creek basin, the run-of-river configuration as proposed for Alt 4a
would maintain the existing flow and temperature regimes downstream of powerhouse. This
would be a major advantage for Alt 4a owing to the critical importance of this reach of
Allison Creek to resident and anadromous fish populations.
• Alt 4a is superior to Alt 3c in all respects.
5.1.2 Alternative 4b
Conclusions specific to Alt 4b gained as the result of the present evaluation include the following:
• The addition of inflatable gates to the Solomon Gulch Spillway as proposed for Alt 4b would
add approximately 2 GWh of average annual energy to the CVEA system for service to all
system load and resource conditions considered for the project, existing and future.
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 23
• The addition of inflatable gates to the Solomon Gulch Spillway as proposed for Alt 4b would
require an amendment to existing FERC License for the Solomon Gulch Project.
• On the basis of the energy potential and cost estimates prepared for this evaluation, the
addition of inflatable gates to the Solomon Gulch Spillway as proposed for Alt 4b would not
currently be an economically viable project relative to the other resources available to the
CVEA.
5.2 Recommendations
Based on the conclusions referenced and outlined above, we provide the following
recommendations:
• Adopt Alt 4a as the preferred alternative for the development of the hydroelectric potential
of the Allison Creek basin.
• Terminate further consideration of Alt 3c and Alt 4b.
• Complete the analysis of the environmental effects of a hydropower development within the
Allison Creek basin on the basis of Alt 4a.
• Optimize the capacity of the powerhouse for the run-of-river Alt 4a.
• Prepare a FERC License Application for Alt 4a pursuant to the provisions of 18 CFR 4.41.
Copper Valley Electric Association, Inc. - Allison Lake Hydroelectric Project
Addendum – Final Feasibility Report
December 2010 24
6. References
1. Hatch Acres Corporation, Allison Lake Hydropower Development – FINAL FEASIBILITY STUDY,
prepared for Copper Valley Electric Association, May 2010 .
2. HDR Engineering, Inc., SOLOMONGULCH HYDROELECTRIC PROJECT – RESERVOIR
CAPACITY – FEASIBILITY STUDY, prepared for Copper Valley Electric Association, November
1991.
Appendix A
Alt 4a System Dispatch
Nov DecApr MayJanJunMarFebSep Oct NovAugJulAlt 4aGeneration (MW)AUTOVista ANALYSIS AUTOVista ANALYSIS ––ALT 4aALT 4aAnnual Dispatch w/ Existing Load Annual Dispatch w/ Existing Load ––19611961SG 2Allison 1DieselAllison 2CogenSG 1ExistingAppendix A -1
Nov DecApr MayJanJunMarFebSep Oct NovAugJulAlt 4aGeneration (MW)AUTOVista ANALYSIS AUTOVista ANALYSIS ––ALT 4aALT 4aAnnual Dispatch w/ 2 MW Added Load Load Annual Dispatch w/ 2 MW Added Load Load ––19611961SG 2Allison 1DieselAllison 2CogenSG 1Existing + 2 MWAppendix A -2
McMillen Team Page 59
Attachment D: Financial backup page 1
Allison Creek Plan of Finance
The final feasibility report indicates the total cost of the Allison Creek project in 2010 dollars is
$38,804,000.
Copper Valley Electric received $10,000,000 from the State of Alaska FY12 capital budget. The
following language is included in Senate Bill 46; “It is the intent of the legislature that the state's
capital investment into energy generation projects not exceed 50% of the total investment
required to fully complete those projects”.
Total Project Cost $38,804,000
Maximum 50% State of Alaska investment $19,402,000
State of Alaska Summary for Allison Creek
2008 Capital Budget Appropriation (Grant 2195314) $ 1,000,000
2009 Round I REF (Grant 2195390) $ 2,288,000
2011 Capital Budget Appropriation (Grant 7910012) $10,000,000
2012 Round V REF (Applications due 8/26/11) $ 6,114,000 note 1
Total State of Alaska $19,402,000 = 50% State
Note 1:
Section 1.15 of the Renewable Energy Fund Round V applications state construction is limited to
$8 million per project however the 50% language from SB 46 limits CVEA from applying for all
amounts eligible under the grant application.
Other Round V limitations require final design and permitting to be $500,000 or no more than
20% of anticipated construction cost. CVEA’s estimate for construction only is $32 million.
20% equates to $6.4 million. Final design and permitting is estimated at $2.27 million which
does not exceed the threshold in round 5. CVEA is not applying for final design and permitting
costs.
Round V Application
CVEA is applying for $12,228,000 with 50% match: $6,114,000 State and $6,114,000 CVEA.
Remaining Funding/Matching
CVEA intends to apply for any Federal funding that may become available. If no grants are
available, CVEA will secure funding through the lowest cost financing available.
Currently CVEA is a 100% borrower through our banker National Rural Utilities Cooperative
Financing Corporation (CFC). CVEA has been in contact with CFC throughout the project and
verbally been given the okay to borrow the amount needed. CVEA will continue to explore all
possibilities to secure the lowest cost financing available.
Allison Creek Cash Flow by Year
Format of Grant Budget Form for all funding
Total
Estimated
Amount
Through
12-31-12 1 Q 2013 2 Q 2013 3 Q 2013 4 Q 2013
Pre - Design and Construction (Filing License Appilcation)3,575,383 3,575,383
Design and Permitting 2,670,000 960,000 1,260,000 50,000 50,000 50,000
Project Scoping / contractor solicitation 50,000 50,000
Final enviornmental assessment and mitigation plans 20,000 20,000
Resolution of land use, right of way issues 20,000 20,000
Permit approvals 20,000 20,000
Final system design 1,900,000 750,000 1,150,000
Owner's Representative 600,000 100,000 50,000 50,000 50,000 50,000
Updated economic and financial analysis -
Negotiated power sales agreements with approved rates -
Final business and operational plan 60,000 60,000
Construction 32,558,617 - 5,000,000 3,700,000 3,625,000 3,375,000
Confirmation that all design/feasibility requirements complete 50,000 50,000
Completion of bid documents 50,000 50,000
Contractor/vendor selection and award 100,000 100,000
Construction phases (each project will have unique phases)850,000 125,000 125,000
Integration and testing 200,000
Decommissioning old systems (N/A)- -
Equipment & Materials 27,995,000 5,000,000 3,000,000 3,000,000 3,000,000
Other: Project Mgmt, Insurance, Etc.3,163,617 500,000 500,000 250,000
Final acceptance, commissioning and start up 100,000
Operations Reporting 50,000
TOTAL 38,804,000 4,535,383 6,260,000 3,750,000 3,675,000 3,425,000
Cash Spending By Quarter
Prior Funding (CVEA, RE1) pre-2012 3,860,000
10 Million Capital Budget Appropriation 675,383 6,260,000 3,064,617
Renewable Energy Fund Round 6 - CVEA 50%1,837,500 1,712,500
Renewable Energy Fund Round 6 - Grant 50%1,837,500 1,712,500
CVEA Financing 685,383
4,535,383 6,260,000 3,750,000 3,675,000 3,425,000
2013
P:\Finance\Grants\State Grant Applicatons\RE Round 6\Allison Creek Cash Flow Page 1 of 3 9/19/2012
Allison Creek Cash Flow by Year
Format of Grant Budget Form for all funding
Total
Estimated
Amount
Pre - Design and Construction (Filing License Appilcation)3,575,383
Design and Permitting 2,670,000
Project Scoping / contractor solicitation 50,000
Final enviornmental assessment and mitigation plans 20,000
Resolution of land use, right of way issues 20,000
Permit approvals 20,000
Final system design 1,900,000
Owner's Representative 600,000
Updated economic and financial analysis -
Negotiated power sales agreements with approved rates -
Final business and operational plan 60,000
Construction 32,558,617
Confirmation that all design/feasibility requirements complete 50,000
Completion of bid documents 50,000
Contractor/vendor selection and award 100,000
Construction phases (each project will have unique phases)850,000
Integration and testing 200,000
Decommissioning old systems (N/A)-
Equipment & Materials 27,995,000
Other: Project Mgmt, Insurance, Etc.3,163,617
Final acceptance, commissioning and start up 100,000
Operations Reporting 50,000
TOTAL 38,804,000
Cash Spending By Quarter
Prior Funding (CVEA, RE1) pre-2012
10 Million Capital Budget Appropriation
Renewable Energy Fund Round 6 - CVEA 50%
Renewable Energy Fund Round 6 - Grant 50%
CVEA Financing
1 Q 2014 2 Q 2014 3 Q 2014 4 Q 2014
50,000 50,000 50,000 50,000
50,000 50,000 50,000 50,000
3,500,000 3,375,000 3,475,000 3,250,000
250,000 125,000 225,000
3,000,000 3,000,000 3,000,000 3,000,000
250,000 250,000 250,000 250,000
3,550,000 3,425,000 3,525,000 3,300,000
1,775,000 789,000
1,775,000 789,000
1,847,000 3,525,000 3,300,000
3,550,000 3,425,000 3,525,000 3,300,000
2014
P:\Finance\Grants\State Grant Applicatons\RE Round 6\Allison Creek Cash Flow Page 2 of 3 9/19/2012
Allison Creek Cash Flow by Year
Format of Grant Budget Form for all funding
Total
Estimated
Amount
Pre - Design and Construction (Filing License Appilcation)3,575,383
Design and Permitting 2,670,000
Project Scoping / contractor solicitation 50,000
Final enviornmental assessment and mitigation plans 20,000
Resolution of land use, right of way issues 20,000
Permit approvals 20,000
Final system design 1,900,000
Owner's Representative 600,000
Updated economic and financial analysis -
Negotiated power sales agreements with approved rates -
Final business and operational plan 60,000
Construction 32,558,617
Confirmation that all design/feasibility requirements complete 50,000
Completion of bid documents 50,000
Contractor/vendor selection and award 100,000
Construction phases (each project will have unique phases)850,000
Integration and testing 200,000
Decommissioning old systems (N/A)-
Equipment & Materials 27,995,000
Other: Project Mgmt, Insurance, Etc.3,163,617
Final acceptance, commissioning and start up 100,000
Operations Reporting 50,000
TOTAL 38,804,000
Cash Spending By Quarter
Prior Funding (CVEA, RE1) pre-2012
10 Million Capital Budget Appropriation
Renewable Energy Fund Round 6 - CVEA 50%
Renewable Energy Fund Round 6 - Grant 50%
CVEA Financing
1 Q 2015 2 Q 2015 3 Q 2015 4 Q 2015
25,000 25,000 25,000 25,000
25,000 25,000 25,000 25,000
2,245,000 250,000 450,000 313,617
200,000
1,995,000
250,000 250,000 250,000 163,617
100,000
50,000
2,270,000 275,000 475,000 338,617
TOTAL
3,860,000
10,000,000
6,114,000
6,114,000
2,270,000 275,000 475,000 338,617 12,716,000
2,270,000 275,000 475,000 338,617 38,804,000
2015
P:\Finance\Grants\State Grant Applicatons\RE Round 6\Allison Creek Cash Flow Page 3 of 3 9/19/2012