Loading...
HomeMy WebLinkAboutouzinkie_line_extension_feasibility_final_report May 2011.01d FEASIBILITY STUDY REPORT OUZINKIE LINE EXTENSION OF MONASHKA FEEDER (HIGH SUBSTATION) Prepared for: KODIAK ELECTRIC ASSOCIATION, INC 1711 Chichenoff Street Kodiak, Alaska 99615 Prepared by: DRYDEN & LaRUE, INC. 3305 Arctic Blvd. Anchorage, Alaska 99503 April 2011 Ouzinkie Line Extension Feasibility Study Page 2 I. Introduction  Kodiak Electric Association (KEA) has tasked Dryden & LaRue with performing a feasibility study of an intertie between the existing KEA’s distribution system and the town of Ouzinkie on Spruce Island. The majority of the route would be an overhead extension of the Monashka distribution feeder supplied from High Substation, with a short submarine crossing between Kodiak Island and Spruce Island, and an overhead tie into Ouzinkie’s existing distribution system. II. Power Supply  The existing Monashka Feeder extends from High Substation to the bailer facility at Monashka creek approximately 5 miles, of which about 3 miles is underground. The majority of the overhead section is closest to the substation and consists of 1/0 ACSR overhead conductor on standard pole top assemblies with 8’ arms. The underground section follows the road out to Monashka Bay and is 4/0 AL 15 kV conductor. The existing line has a capacity of approximately 5 MW without voltage drop considerations. KEA information indicates that the current feeder peak loading is about 800 kW with a fairly low power factor. A new line to Ouzinkie would extend the Monashka Feeder and connect with the existing Ouzinkie distribution system. The current peak electrical load in Ouzinkie is approximately 150 kW (from KEA); for this report we will be using a peak future load of 300 kW. This new load can be added to the existing Monashka Feeder without exceeding its capacity. For feasibility level, the line extension is designed for a total feeder load of approximately 5 MW, with a maximum load at Ouzinkie of 300 kW as noted above. The biggest issue with the new line extension is voltage drop considerations. A preliminary look at the Monashka Feeder voltage profile considered various options, including different conductor sizes and different operating voltages. It appears the most economical option for installation is to extend the overhead line using 1/0 ACSR, operated at 12 kV, with possible installation of a pole mounted capacitor bank to assist with voltage regulation. Installation and location of this regulatory capacitor bank should be examined further as the project moves forward; our best voltage profile was obtained with the capacitor bank installed at Ouzinkie, but this was modeling the line with the Ouzinkie system as a load bus with no generation running on the Ouzinkie system. In addition, as future loading is added to the existing portion of the Monashka feeder, it is assumed that appropriate voltage regulation measures will be installed as required for those future loads. Ouzinkie Line Extension Feasibility Study Page 3 III. Line Routing  The terrain on the north end of Kodiak Island is undulating with small hills and wide valleys. The location of new electrical lines is subject to several considerations including  Land ownership  Soil/Rock conditions  Icing conditions  Construction and maintenance access  Termination sites Two possible overland routes have been tentatively identified and are shown on the following map. Final routing will depend on assessment of the specific conditions. Route #1 begins at the end of the existing Monashka Feeder and follows the eastern side of Monashka Mountain, at approximately the 500’ elevation contour. Note that there is an existing trail lower down the side of the hill, but following a higher elevation maintains the route on Borough and Ouzinkie Native Corporation land. From Monashka Mountain the route follows the coast north, again following the 500’ approximate elevation contour, and connects to the coast about half way between Otmeloi Point and Course Point. The overhead portion of Route #1 is approximately 6 miles in length. A segment of submarine cable, just under a mile in length, crosses the Narrow Strait and lands just east of Black Point on Spruce Island. From there, a short segment of overhead line ties into the Ouzinkie distribution system near the landfill. Route #2 starts out using the same alignment as Route #1, following the east side of Monashka Mountain. On the north side of Monashka Mountain, instead of following the coast, this alternate route heads inland and follows the first small valley and creek that flows north and ends up at the head of Neva Cove opposite Ouzinkie Point. The overhead portion of Route #2 is approximately 7 miles in length. A submarine crossing of about a mile and a half would then terminate on the North Side of Ouzinkie Point, from which a short section of overhead would connect into the Ouzinkie distribution system. In reviewing both routes, a helicopter flyover was performed in order to look at the routes as well as potential submarine cable landing sites. The terrain of Route #2 is slightly gentler than that over which Route #1 traverses. However, both routes appear to be feasible construction options utilizing helicopter for access and transportation. Route #2 is approximately one mile longer than Route 1 and appears it may require more clearing than Route #1; we anticipate it will be slightly more expensive. Since neither overhead route offers a significant advantage over the other, and because ultimately the route selection will depend on the submarine crossing, the higher cost of Route #2 was used as the budgetary estimate for this study. A route map indicating both routes is attached to this report in Appendix A. Ouzinkie Line Extension Feasibility Study Page 4 IV. Permitting  Based upon the potential routes, the following is a listing of permits along with the permitting agencies that may be required for completion of this project. This does not include easements from any corporate or private land owners.  Right-of-Way/Driveway Permits – Kodiak Island Borough, etc  Nationwide Permit 12 (Utility Activities) or 404 Individual Permit – Corps of Engineers  Section 10 Navigable Water Permit – Corps of Engineers  Coastal Project Questionnaire and Certification Statement – DNRDCOM  DNLR Right-of-Way Grant (Lands and Navigable Waters) – DNR  Title 16 Anadramous Fish Stream Permit – ADF&G  Notice of Intent for Storm Water Discharge Associated with Construction Activities – EPA  Notice of Proposed Construction or Alteration – FAA V. Overhead Construction  As was noted above, this feasibility report will be using 12 kV construction for the overhead portion of the line extension. A typical distribution assembly is anticipated, with crossarm construction 3-phase assemblies using raptor protection spacing and a neutral conductor attached to the pole beneath the crossarm. An estimated ruling span of 250’ and typical 45’ class 3 wood poles are assumed. For this high level feasibility estimate, a 3/8” EHS or similar strength guy strand for guying deadends and angles is anticipated and plate anchors will be used wherever possible. Design will be to NESC Heavy Loading District and Grade “B” construction using standard NESC overload and strength factors. VI. Submarine Cable Construction  Because the feasibility of this connection depends greatly on the feasibility of the submarine crossing, Cabletricity Connections Ltd. was retained to examine the feasibility of two potential submarine crossings. They have recommended an installation of four single conductor submarine cables for this crossing over two multi-conductor submarine cables. We have included their report in Appendix C. From the report, based on existing readily available information, both routes appear to be technically feasible. However, more detailed information is required at these crossing locations in order to both select a preferred option and to verify the feasibility of the project. Therefore as this project moves forward, the recommendation is to Ouzinkie Line Extension Feasibility Study Page 5 perform bathymetric surveys and marine geophysical studies to refine and verify the submarine feasibility. VII. Cost Estimates  A feasibility level cost estimate has been prepared to determine if the project fits within reasonable funding; this estimate should be considered rough order of magnitude as it is based on a conceptual level of design. The overhead portion of this line consists of typical construction methods with many similar examples throughout Alaska. The submarine cable portion is completely different and requires very sophisticated equipment and expertise that is not available in state. Submarine power cables are presently being installed around the world by a very few companies. Since many of these are large multimillion dollar endeavors with huge electrical capacity, small distribution level projects do not necessarily fit with the norm. There are many water crossings in Alaska that use standard URD (underground residential) cables that are typically buried in the ground. When this type of cable is used in a submarine application, these installations have a fairly short life because the environment is too harsh. This feasibility study is based on a submarine cable installation that is more typical of large projects with an armored cable specifically constructed for submarine use and installed with equipment and methods that will better assure a long cable life. The feasibility level estimate for this project is included in Appendix B. VIII. Possible Timeline  Depending on funding availability, the following rough timeline could be considered for design, permitting and construction of this project. Assuming project design starts in Summer/Fall of 2011, the longest lead permit item would be the DNR Right-of-Way grant across navigable waters (for the submarine crossing), which has an expected duration of 12 months. Design and bathymetric survey should be completed to the point where that permit can be submitted in Fall of 2011. (The permit for the crossing would be approved by Fall 2012). Design of the overhead line would be completed for material ordering, staking and potential bidding by end of 2011. In spring to early summer of 2012, the line could be cleared, staked and design finalized for construction in Summer and Fall of 2012. The submarine cable would be bid in 2012 and anticipated installation would be Fall of 2012 or Late Spring of 2013, with the line extension expected to be operational in 2013. Ouzinkie Line Extension Feasibility Study Page 6 IX. Conclusion  The overhead portion of the line is typical and no fatal flaws are expected or anticipated. However, the feasibility of constructing this particular line extension is highly dependent on the successful installation of the submarine cable which is dependent on locating satisfactory sea bottom conditions. As noted in the submarine cable section, the next phase of feasibility will be to perform some underwater survey to determine the sea bottom conditions. Until this is completed, the feasibility of the project is in question.     Ouzinkie Line Extension Feasibility Study Appendix A APPENDIX A – ROUTE MAP  Ouzinkie Line Extension Feasibility Study Appendix B APPENDIX B – COST ESTIMATE  Item Cost Overhead Wood Pole Line (15 kV) Wood Poles 440,000$ Pole Top Assemblies 200,000$ Guys and Anchors 120,000$ Conductor 430,000$ Miscellaneous 60,000$ Mob/Demob 100,000$ Clearing 150,000$ Helicopter/Access Costs 750,000$ Capacitor Bank/Voltage Regulation 40,000$ Recloser/Line Sectionalizing (Monashka Creek area) 45,000$ Interconnection/Communications* 540,000$ Subtotal 2,875,000$ Submarine Cable Crossing Materials/Supply 602,000$ Installation 1,780,000$ Engineering/Pre-lay Surveys and Mapping 297,000$ Subtotal 2,679,000$ Total Overhead Line + Submarine Cable 5,554,000$ Indirect Costs, not including Submarine Cable Portion (Permitting, Engineering, etc) (20%) 575,000$ Contingency (15%) 833,100$ Total Cost Range 6,129,000$ to 6,962,100$ *This does not include any synchronization controls for operating Ouzinkie generation sources simultaneously with the KEA feed Ouzinkie Line Extension - Monashka Feeder Feasibility Level Estimate Costs Ouzinkie Line Extension Feasibility Study Appendix C APPENDIX C – SUBMARINE CABLE CONNECTION STUDY  Cabletricity Spruce Island 25 kV ac Submarine Cable Connection Study - Submitted to: Dryden & LaRue. Inc. by: Cabletricity Connections Ltd. April 8, 2011 Cabletricity Report 2011-2 Spruce Island 25 kVac Submarine Cable Connection Study 2 Disclaimer This report was prepared by Cabletricity Connections Ltd. (Cabletricity) solely for Dryden & LaRue, Inc. Dryden & LaRue has the right to reproduce, use and rely upon this report for purposes related to providing an electricity connections between Spruce Island and Kodiak Island, Alaska, including without limitation, the right to deliver this report to regulatory authorities in support of, or in response to, regulatory inquiries and proceedings. For the purposes of this Disclaimer, all parties other than Cabletricity, Dryden & LaRue and their customer for this project, are “Third parties”. Neither Cabletricity or Dryden & LaRue represent, guarantee or warrant to any Third Party, expressly or by implication, the accuracy, suitability, reliability, completeness, relevance, usefulness, timeliness, fitness or availability of this report for any purpose or the intellectual or other property rights of any person or party in this report. Third Parties shall not use any information, product or process disclosed, described or recommended in this report and shall not rely upon any information, statement or recommendation contained in this report. Should any Third Party use or rely upon any information, statement, recommendation, product or process disclosed, contained, described or recommended in this report, they do so entirely at their own risk. To the maximum extent permitted by applicable law, in no event shall Cabletricity or Dryden & LaRue accept any liability of any kind arising in any way out of the use or reliance by any Third Party upon any information, statement, recommendation, product or process disclosed, contained, described or recommended in this report. Copyright Notice This report is copyright protected by Cabletricity and may not be reproduced in whole or part without the prior written consent of Cabletricity. Acknowledgement This report was prepared by: G. Allen MacPhail, P.Eng. Principal Engineer Cabletricity Connections Ltd. Revision No. Description Date Spruce Island 25 kVac Submarine Cable Connection Study 3 Contents 1. Introduction.................................................................................................................. 4 2. Route Descriptions...................................................................................................... 4 2.1 Route A – East Option ........................................................................................ 5 2.2 Route B – West Option ................................................................................ 6 2.3 Comparison of Route Options ........................................................................... 7 3. Submarine Cable System Description and Parameters ............................................ 8 4. Installation Methodology ........................................................................................... 10 5. Environmental Impact of Options .............................................................................. 10 5.1 Environmental Impact During Construction ..................................................... 10 5.2 Environmental Impact during Operation .......................................................... 11 6. Hazards and Mitigation Measures ............................................................................. 11 6.1 Natural Hazards ................................................................................................ 11 6.2 Anthropogenic Hazards, Avoidance and Mitigation ......................................... 15 6.3 Hazards and Risks Summary ........................................................................... 15 7. Costs .......................................................................................................................... 16 8. Conclusions and Key Findings .................................................................................. 17 9. References ................................................................................................................ 19 10. Appendices ............................................................................................................. 19 Appendix A – Cost Estimates ........................................................................................ 20 Appendix B – Budgetary Cost Quotation – Submarine Cables.................................... 21 Appendix C – Budgetary Cost Quotation – Submarine Cable Transportation and Laying 22 Spruce Island 25 kVac Submarine Cable Connection Study 4 SPRUCE ISLAND 25 KVAC SUBMARINE CABLE CONNECTION STUDY 1. Introduction Spruce Island lies across Narrow Strait from near the northeast tip of Kodiak Island, Alaska. The main settlement, Ouzinkie, independently generates electricity for residential and commercial users on the island. There is a desire to increase reliability and flexibility of electricity supply on Spruce Island, by installing a 25 kV submarine power cable connection between the two islands. It would initially be energized at 15 kV, but a higher voltage rating would provide opportunities for future up-rating. The present electrical load on Spruce Island is less than 1 MW. This report examines two separate preliminary options for routing a new submarine cable supply system between the two islands. One route option is across the northwest entrance to Narrow Strait west of Ouzinkie and the other is a more central crossing east of Ouzinkie. Attributes of each route are identified, costs estimated and preliminary recommendations made. They are considered to be preliminary because the investigation was done only using readily available information in the public domain, without benefit of hydrographic and marine geophysical surveys. Should cost estimates be within the range of affordability, it is recommended that these surveys be done and used as a basis for refining final routes and costs, including considerations for overhead line interfaces. 2. Route Descriptions The two routes selected for consideration and comparison are shown in Figures 1 as an aerial view and Figure 2 from a bathymetric chart. Both are technically feasible, subject to verification with supplemental surveys and final designs. Cable performance and costs will vary for the two routes. Figure 1: Cable routing options – aerial view (source: Google Earth) Spruce Island 25 kVac Submarine Cable Connection Study 5 Figure 2: Cable routing options – bathymetry view (source: NOAA Chart 16594 – depths in fathoms) A central route running due north-south into Ouzinkie Harbor was considered, but rejected because of heavy vessel traffic in the area and possible threats from anchor damage. Both route options are crossed by the Alaska Marine Highway Ferry System between Port Lions and Kodiak. 2.1 Route A – East Option The south terminal for the east route option would cross Narrow Strait starting at a small gravel bar almost due south of Ouzinkie Harbor and east of Neva Cove. Cable route length would be approximately 1.0 miles (1.6 km) and as shown in Figure 2, maximum water depth would be about 53 fathoms (318 feet; 97 m). The marine chart does not indicate water current velocity through this area, but the U.S. National Oceanic and Atmospheric Administration (NOAA) „Tides and Currents‟1 tables show the maximum tidal current in Narrow Strait to be 2.2 knots (1.1 m/s). These relatively high water currents could subject the cables to abrasion from current-driven sands and gravels, vortex shedding vibration at free spans and possible accelerated corrosion. Vortex shedding vibration can result in fatigue failure of metallic cable components, such as armor wires, metallic shield and conductor, as well as abrasion at cable touchdown points. 1 http://tidesandcurrents.noaa.gov/currents (accessed February 2011) Spruce Island 25 kVac Submarine Cable Connection Study 6 Ultimate routes would be refined to choose as gentle and even a slope as possible to the bottom of Narrow Strait. On the north side of the Strait, the cables would terminate in a wide bay east of Black Point. Figure 3 does not show any kelp beds in the area. Shores on both sides are subject to erosion and possible sediment mobility due to high water currents. The existence of sand waves and mega-ripples on the bottom of Narrow Strait is a possibility. Hydrographic and geophysical surveys of the sea bottom would be needed to carefully determine an optimum route through a relatively challenging environment for submarine cables. The area experienced significant tsunami damage during the 1964 seismic event, so cable terminals should be located as high as practical above the tidal zone to avoid damage should a similar event reoccur. F inal route selection activities should aim to avoid possible underwater and above-ground landslides due to earth shaking. Figure 3: Route A – East route option (source: Google Earth) 2.2 Route B – West Option The south terminal for the West route option would begin near the entrance to Neva Cove and terminate on the west shore of Spruce Island near a small lake, as shown in Figure 4. Cable route length would be approximately 1.4 miles (2.3 km). As shown in Figure 2, maximum water depth would be about 11 fathoms (66 feet; 20 m). The final route would be selected to avoid shallows and ensure at least 30 feet (9 m) water depth. NOAA Tide and Current tables do not indicate water currents in this area, but they could be higher than in the main part of Narrow Strait due to the constriction caused by Ouzinkie Point, and the shallower water. NOAA Chart 16594 indicates „rip tides‟ west of Ouzinkie Point, which could be a hazard to submarine cables if they pass through the same area. The cable descent to sea bottom would be more gradual than for the east Route A, at both cable landings. High water currents could subject the cables to abrasion from current-driven sands and gravels, vortex shedding vibration at free spans, and possible accelerated corrosion. Shores on both sides are subject to erosion and possible sediment mobility due to high water currents. Hydrographic Spruce Island 25 kVac Submarine Cable Connection Study 7 and geophysical surveys of the sea bottom would be needed to carefully determine an optimum cable route. The marine chart shown in Figure 2 indicates kelp beds near the north landing. They are habitat for marine life and could complicate cable laying activities so should be avoided. Figure 4: Route B - West route option – aerial view (source: Google Earth) 2.3 Comparison of Route Options Following is a preliminary comparison of the characteristics of each route option, expressed mainly in terms of the geographical setting, economic impact and natural/man-made hazards. Attribute Route A - East Route B - West Length (mi/km) 1.0/1.6 1.4/2.3 Max. depth (feet/m) 318/97 66/20 Max. water current (knots) 2.2 2.2 inferred Shore approach incline steep gentle Sea bottom profile irregular irregular ROW acquisition uncertain uncertain Anchor hazards medium medium Fishing hazards medium medium Tugboat tow line hazards medium medium Vortex shedding vibration hazards medium medium Bottom abrasion hazards high high Shoreline erosion hazards high high Armor wire corrosion hazards high high Table 1: Attributes of route options Spruce Island 25 kVac Submarine Cable Connection Study 8 3. Submarine Cable System Description and Parameters The cable system proposed for this project is a single-core design with either cross-linked polyethylene (XLPE) or ethylene propylene rubber (EPR) insulation. Cables would be supplied to meet the following general specifications and recommendations. IEC 60840 „Power cables with extruded insulation and their accessories for rated voltages above 30 kV (Um = 36 kV) up to 150 kV (Um = 170 kV) - Test methods and requirements‟ ICEA S-93-639, „5-46 kV Shielded Power Cable for Use in the Transmission and Distribution of Electric Energy‟ ICEA S-94-649, „Standard for Concentric Neutral Cables Rated 5 through 46 kV‟ AEIC CS8 „Specification for Extruded Dielectric, Shielded Power Cables Rated 5 through 46 kV‟ Electra No. 171 article: „Recommendations for mechanical tests on submarine cables‟ The cable conductor would be #1/0 AWG stranded copper with strand-fill water blocking compound. Insulation thickness would be about 8.0 mm for the 25 kV level. Cable weight in air would be approximately 5.2 kg/m. Outside diameter would be approximately 50.5 mm. Because of the relatively remote location and low availability of cable laying vessels for installation and repair, it was assumed that installing four single-core cables would be the most economical, with one serving as a spare in case of a cable failure. They could be laid, and repaired if necessary, with a landing barge transporter vessel, as shown in Figure 5, which is available in the Pacific Northwest. Figure 5: Cable laying vessel suitable for laying single-core cables to Spruce Island A general description of the proposed single-core cables id given in Figure 6. Cabletricity A Copper conductor B Conductor screen C Insulation D Insulation screen + Water swelling tape E Concentric neutral + Water swelling tape F Inner cable jacket G Polypropylene Bedding H Galvanized steel wire Armor I Polypropylene Serving Figure 6: General description of proposed single-core cable (source: Prysmian) It was anticipated that the customer might consider two three-core cables, so for completeness, information is provided in Figure 7. Figure 7: General description of alternate three-core submarine cable (source: www.nexans.de, accessed January 2011) The three-core cable conductor would also be #1/0 AWG stranded copper with strand-fill water blocking compound and 8 mm insulation thickness for the 25 kV level. Cable weight in air would be approximately 13 kg/m. Outside diameter would be approximately 90 mm. Comparative budgetary costs of single-core versus three-core cables are provided in Appendix B. They confirm that supplying four single core cables would be less costly than two three-core Spruce Island 25 kVac Submarine Cable Connection Study 10 cables, for this application. Repairs would also be easier to carry out, since cable repair equipment could be lighter duty and splices could be made faster. 4. Installation Methodology Regardless of route option finally selected, the relatively high water currents and steep underwater slopes for at least some of the landings, suggests using a cable laying barge with superior positioning capabilities. If needed an outboard thruster could be used to assist lateral stability of the cable laying barge. It is anticipated that PE or PVC conduits would be pre-installed at each landing site, so cables could be pulled ashore quickly, without concerns about tidal cycles interfering with maintaining trenches open during the critical landing operation. Lay-barge, tug and diver standby time would also be minimized. Figure 8 shows an example of a typical installation of conduits and trench backfilling for a 25 kV submarine cable project. Figure 8: Typical pre-installation and backfilling of conduits through inter-tidal zone (source: BC Hydro) Once the first end was safely ashore and anchored, the cable laying barge would carefully lay the cable down the incline of the sea bottom. Laying cables on the relatively flat sea bottom for most of the route between terminals would be relatively straight-forward and fast, provided weather was good. Laying the cable up the critical incline to the remote terminals would be done in a similar manner. 5. Environmental Impact of Options 5.1 Environmental Impact During Construction Impact to the sea bottom is expected to be minimal, since the cable would not be buried, except from terminal poles to about 3.5 feet (1.0 m) vertically below Mean Low Water (MLW). Burial Spruce Island 25 kVac Submarine Cable Connection Study 11 depth would be about 3.5 feet (1.0 m), to protect against hazards such as vessel groundings, high wave energy, sediment transport and abrasion. Final selection of landing sites would strive to locate areas where excavation was as easy as possible and environmental impact was minimal. Emissions from internal combustion engines would be released by the cable laying barge, tugboat, excavators, generators and miscellaneous equipment during cable laying and construction of the cable landings. Care would be taken to avoid harm to kelp beds and other habitat for marine life, such as eel grass. Eel grass is not expected at any of the route options due to high water currents and the probable absence of fine sands, but this will need to be confirmed. 5.2 Environmental Impact during Operation The cables would not contain any insulating fluids that could possibly leak out into the ocean environment. A small amount of heat would be emitted when the cables were energized and loaded. Effects on the land or aquatic habitat are expected to be negligible. 6. Hazards and Mitigation Measures The three route options pose several natural and man-made (anthropogenic) hazards. 6.1 Natural Hazards 6.1.1 High water current velocity As noted above, predicted water current velocities for all route options reach a maximum of 2.0 knots (1.0 m/s). These velocities are typically predicted at about 5 to 10 m above the sea bottom and will be reduced with height above bottom in accordance with bottom texture, as described in the formula below [1]. Zspan and Zmeas are the heights above the bottom for cable and measurements, respectively. Assuming Vmeas = 1.0 m/s, Zspan = 0.5 m, Zmeas = 10.0 m then Vspan = 0.8 m/sec Spruce Island 25 kVac Submarine Cable Connection Study 12 Implications of high water velocities are increased tendency for vortex shedding vibration at cable free spans [1], abrasion at free span touchdown points and rapid replenishment of oxygen at armor wire corrosion sites. 6.1.2 Armor wire abrasion Abrasion of armor wires can occur due to sand blasting from current-driven granular material on the sea bottom and from movement at free span touchdown points due to vortex shedding vibration. Modern power cables use at least one layer of polypropylene twine over the bitumen coated armor wires. Polypropylene is more resistant to abrasion than jute twine used up until several decades ago. Nevertheless, it is expected that eventually the serving layer will wear through. Possible mitigation methods are to: - Install cables where water currents are low. - Install cables where bottom conditions are relatively smooth. - Lay cables very carefully to avoid long free spans. - Bury cables (often uneconomical and triggers additional environmental approvals). - Manufacture cables with an extra layer of tough armor serving, delaying abrasion and exposure of armor wires to open sea water [2]. 6.1.3 Armor wire corrosion Armor corrosion is affected by the following main in-situ seawater parameters. - dissolved oxygen content - sea currents - temperature - salinity - marine growth and decaying organic matter Site water currents are relatively high, leading to high oxygen concentrations due to mixing of water as it passes through Narrow Strait between Kodiak and Spruce Island. Wave action will also lead to high oxygen concentration in the shallow waters of the west Route B. Submarine cable armor wires are susceptible to four main corrosion mechanisms. General chemical corrosion Chemical corrosion occurs where cables are directly exposed to salty, oxygen-rich sea water. Primary protection is by coating the steel armor wires with zinc. Secondary protection is provided by the hot bitumen coating and polypropylene serving applied during manufacturing. The bitumen and serving layer can be degraded during installation, by external impacts and due to sand- blasting abrasion from high water currents. References describe the corrosion rate of hot dipped galvanized zinc coatings immersed in seawater to be about 9 µm/year on average [4]. For bare carbon steel, references show the corrosion rate to be about 10 µm/year if buried beneath the sea bottom in anaerobic conditions [4] and about 50 µm/year if immersed in seawater [5]. Typical cables would have an armor wire diameter of 4.19 mm. ICEA S-66-524 requires a minimum zinc weight of 275 g/m2 to be incorporated into the wire diameter. Zinc coating thickness and steel wire radius are calculated to be about 3 µm and 2090 µm respectively. Applying the above corrosion rates for unburied cables indicates that the zinc would be lost in less than a year Spruce Island 25 kVac Submarine Cable Connection Study 13 and the steel in about 40 years. It is noteworthy that the 50 µm/year corrosion rate for steel in seawater is very dependent on oxygen concentration and water current velocity. Mitigation efforts could increase the zinc coating thickness and improve the quality of bitumen coating over the wires. Some users have specified individual armor wires with polymer jackets. A cathodic protection system is required in order to prevent consumption of steel under the jacket, in the event of damage. AC corrosion AC cables are subject to corrosion in areas of mutual impedance change, notably where the inter- phase spacing of single-core cables converges/diverges near the landings. Here induced „transverse‟ AC currents in the armor can pass into the sea or sea bottom [6]. If AC current densities are sufficiently high, AC corrosion can occur. Mitigation and avoidance possibilities are to specify cables with a low resistance metallic shield (or return conductor), which causes most of the return current to flow in it rather than the armor wires. It is recommended to specify distribution submarine cables with a 100 % metallic shield (concentric neutral same size as central conductor), in order to minimize return current flowing in the armor, seawater and deep earth. Nevertheless, some zero sequence AC current will flow transversely through natural paths from cable armor into the sea and earth. In order to reduce such transverse currents, some utilities install sea electrodes near the cable terminals, connected to the distribution neutral. Otherwise the rate of change in cable separation needs to be carefully controlled, with a suggested value of 15 feet separation change per 300 feet of cable [6]. It should be noted that this value is strongly dependent on cable design specifics. Differential aeration corrosion This occurs where cables transition from buried, where oxygen levels are low, to unburied, where concentrations are higher. As described in [7], the equilibrium potential of the iron corrosion cathodic reaction at constant pH depends on dissolved oxygen concentrations as follows: E0 = constant + 0.0148*log(p(O2)) Volts Where p(O2) is the partial pressure of oxygen in equilibrium with the quantity of the same gas dissolved in water. As a consequence, if a part of an iron wire is prevented from being reached by dissolved oxygen due to burial, while another part is not because it is unburied, a longitudinal potential difference will develop in the armor wires. The exposed part will behave cathodically with respect to the buried part, which will corrode. The corrosion rate is determined by the ratio between buried and unburied lengths, and the relative amount of dissolved oxygen in water. This phenomena has been observed when recovering old submarine cables. Mitigation efforts could apply cathodic protection to the armor wires. Geo-magnetically induced leakage current corrosion Spruce Island 25 kVac Submarine Cable Connection Study 14 Another explanation for advanced corrosion at the transitions between buried and unburied sections is due to geo-magnetically induced DC currents in the armor wires [2], [8]. The potential difference between two locations, which is generated by tidal flow of electrically conductive seawater in the presence of the earth‟s magnetic field, can be calculated as follows. E = B*V*L Where E = induced electromotive force B = vertical component of earth‟s magnetic field L = width of water crossing V = velocity of water flow, assumed perpendicular to cables DC leakage current from the armor is dependent on leakage resistance. Where buried, the resistance is higher and the leakage current lower. Where current leaves the armor wires, they become anodic, resulting in corrosion. The maximum corrosion rates occur at discontinuities between buried and unburied sections, at locations where the water dept h changes rapidly and near the terminals. Mitigation efforts could be to completely bury the cables or to apply cathodic protection to armor wires. Microbiologically influenced corrosion (MIC) Sea bottoms comprised of decomposing organic matter can result in sulphide reducing bacteria creating acids that corrode cable armor [9], [10]. Fortunately these conditions do not appear to be present for submarine cables installed in most Alaskan waters. Corrosion protection measures Most of the above corrosion hazards can be mitigated by applying an impressed current cathodic protection system. Typically they place a potential of about -0.8 to -1.1 Volts (relative to a Ag/AgCl half cell) onto the armor wires. Detailed application descriptions are provided in [11]. It is recommended that an impressed current cathodic protection system be applied to any new Kodiak to Spruce Island cables as an insurance measure. 6.1.4 Free spans and vortex shedding vibration Susceptibility to cable vortex shedding vibration at free spans can be calculated using methods described in [1]. Calculations require knowledge of water currents and the cable‟s dynamic bending stiffness, as well as other knowledge about geometry of the free span, cable tension, etc. As described previously, vortex shedding vibration can cause fatigue failure of cable metallic components, as well as abrasion at touchdown points. Some free spans are inevitable, so mitigation efforts need to be directed at carefully controlling cable bottom tensions during laying and final resting place on the sea bottom. This suggests using divers to monitor and control cable touchdown in shallow water. Spruce Island 25 kVac Submarine Cable Connection Study 15 6.2 Anthropogenic Hazards, Avoidance and Mitigation 6.2.1 Fishing The Kodiak and Spruce Island areas are popular for commercial and recreational fishing. Bottom trawlers can pose threats to submarine cables but there is presently no information on whether they are used in the Narrow Straits area or not. Avoidance and mitigation is typically to bury cables, however it is considered to be uneconomical for this size of project. 6.2.2 Vessel anchors These usually pose the largest threat to submarine cables. Due to high water currents in the area it is unlikely that vessels would set an anchor for mooring purposes, however, they can be dropped accidentally or deployed purposely to prevent a vessel from running aground. Typical avoidance/mitigation measures are to bury cables below anchor penetration depth, however that is considered uneconomical for this size of project. 6.2.3 Vessels running aground Probability is considered to be low. Mitigation/avoidance is to bury cables to about 3.5 feet (1.0 m) vertically below MLW. 6.2.4 Tugboat tow lines Forestry is an important industry and tugboats sometimes tow log booms through the area. Tow lines can sag to the sea bottom and abrade power cables. This hazard could be particularly high for the shallow waters of the westerly Route B. Mitigation would suggest cable burial, which is considered to be uneconomical, given low probability of occurrence. 6.3 Hazards and Risks Summary This sub-section provides a subjective quantitative summary of hazards and risks, with and without mitigation. They are very preliminary because site surveys studies have not yet been done, however, they provide a format for further consideration and evaluations. „Risk‟ is defined mathematically as the product of probability times consequence. For these purposes the following weighting system was used: Probability (or Likelihood) Low 1 Medium Low 2 Medium 3 Medium High 4 High 5 Consequences (or Impact) Low 1 Medium Low 2 Medium 3 Medium High 4 High 5 Spruce Island 25 kVac Submarine Cable Connection Study 16 Hazard ID Probabil- ity without mitigation Conse- quence without mitigation Risk without mitigation Risk reducing measure Probability with mitigation Conse- quence with mitigation Risk with mitigation Comments Abrasion 4 5 20 Serving ++ 3 5 15 burial impractical Corrosion 5 5 25 CP 2 5 10 burial impractical Vibration 4 5 20 ROV 2 5 10 ROV planned Fishing 3 5 15 bury 3 5 15 burial impractical Anchors 3 5 15 bury 3 5 15 burial impractical Towlines 2 5 10 bury 4 5 20 burial impractical Grounding 2 5 10 bury 1 5 5 burial planned Environment 3 3 9 EMP 1 1 1 EMP planned Ranking 124 91 Table 2: Hazards and Risks summary for Route A - East Hazard ID Probabil- ity without mitigation Conse- quence without mitigation Risk without mitigation Risk reducing measure Probability with mitigation Conse- quence with mitigation Risk with mitigation Comments Abrasion 5 5 25 Serving ++ 4 5 20 burial impractical Corrosion 5 5 25 CP 2 5 10 burial impractical Vibration 4 5 20 ROV 2 5 10 ROV planned Fishing 3 5 15 bury 3 5 15 burial impractical Anchors 3 5 15 bury 3 5 15 burial impractical Towlines 4 5 20 bury 4 5 20 burial impractical Grounding 2 5 10 bury 1 5 5 burial planned Environment 3 3 9 EMP 1 1 1 EMP planned Ranking 139 86 Table 3: Hazards and Risks summary for Route B - West The rankings are relatively close, and as noted above, risks were estimated without benefit of marine surveys. The risk of abrasion for Route B - West is higher due to uncertainties about the „Rip Tides‟ shown on marine charts, and therefore suggest a preference for Route A – East until further investigations are carried out. Rankings also do not consider implications of overhead line location on cable route selection. Rankings are therefore subject to change once the other investigations are complete. 7. Costs Detailed cost estimates were done for the two route options two. Budgetary cable supply costs were obtained from a leading U.S. manufacturer of 25 kV submarine cables (Appendix B). Budgetary cable transportation and laying costs were obtained from a company with much experience installing telecommunication and power submarine cables on the west coast of North Spruce Island 25 kVac Submarine Cable Connection Study 17 America (Appendix C). Estimate results are detailed in Appendix A and summarized in Tables 4 and 5 below. Assumptions for the estimates were as follows: 1. Costs are in 2011 Dollars. 2. Cables are as described in Appendix A. 3. Proposed cable routes are approximately 1.6 and 2.3 km long. 4. Maximum water depth is 97 m. 5. Cable is supplied by competitive tendering. 6. Cable laying will be done in summer months. 7. Owner's Engineering, Project management and Permitting costs are included at 10%. 8. Interest During Construction is not included. 9. Cost of obtaining rights-of-way is not included. 10. Estimate accuracy is -15%/+25%. 11. No contingency has been applied (15% is recommended at this stage). Four 1/c cables #1/0 Cu conductor Supply ($) 434,000 Installation ($) 1,780,000 Engineering, project management & permitting ($) 280,000 Total 2,494,000 Table 4: Cost estimate summary for Route A – East Option Four 1/c cables #1/0 Cu conductor Supply ($) 602,000 Installation ($) 1,780,000 Engineering, project management & permitting ($) 297,000 Total 2,679,000 Table 5: Cost estimate summary for Route B – West Option 8. Conclusions and Key Findings A preliminary desk top investigation has been carried out into the feasibility of installing a 25 kV submarine cable link between Kodiak and Spruce Islands. The following conclusions were reached. Detailed bathymetric surveys, marine geotechnical and marine geophysical studies will be needed to refine cable routes before a final option is selected. Both route options appear to be technically feasible, subject to verification with completion of the above surveys and studies. The Route A - East option appears slightly more desirable from a long term cable performance perspective. The Route A – East option also has lowest initial costs due to less cable. Much of the cost is for mobilizing to and demobilizing from a relatively remote site, which tends to reduce the overall cost differential due to route length variations. Spruce Island 25 kVac Submarine Cable Connection Study 18 None of the routes appear to have high environmental impacts, but further investigations are required to confirm possible conflicting locations of kelp, eel grass and other critical marine life habitat. Cable abrasion, corrosion and vortex shedding vibration hazards have the highest risk rankings, mainly due to high water currents and oxygen concentrations. Cathodic protection systems are recommended to mitigate cable armor corrosion for the new cables. Cable laying methods will need to assure accuracy in placing cables on the sea bottom to avoid long free spans and possible vortex shedding vibration problems, especially for the relatively steep approaches to cable terminals for Route A - East. Spruce Island 25 kVac Submarine Cable Connection Study 19 9. References 1. G.E. Balog, K. Bjørløw-Larsen, A. Ericsson, B. Dellby, „Vortex Induced Vibration on Submarine Cables‟, Paper B1-208, CIGRE 2006, Paris. 2. M. Furugen, et al, „Completion of Submarine Cable Lines Combining Low Environmental Impact with Low Cost‟, Furukawa Review No. 21, 2002. 3. Porter, F. C. „Corrosion Resistance of Zinc and Zinc Alloys‟, Dekker, New York, 523pp. 1994. 4. E. Bascom, et al, „Construction Features and Environmental Factors Influencing Corrosion on a Self-Contained Fluid-Filled Submarine Cable Circuit in Long Island Sound‟, IEEE Trans. On Power Delivery, Vol. 13, No. 3, July 1998. 5. P. Anelli, „Some Considerations on the Chemical Corrosion of a Submarine Cable in Sea Water‟. Submitted with Pirelli‟s bid for BC Hydro MSA-DMR 525 kV AC submarine cables, February 1979. 6. G. Luoni, P. Anelli, „Armour Corrosion in Single Core Submarine Cables‟, Paper A 76 190-9, IEEE PES Winter Meeting, New York, NY, January 25-30, 1976. 7. P. Anelli, „Some Considerations on the Chemical Corrosion of a Submarine Cable in Sea Water‟. Submitted with Pirelli‟s bid for BC Hydro MSA-DMR 525 kV AC submarine cables, February 1979. 8. M. Fujii, T. Uematsu, et al, „Steel Armour Corrosion of Submarine Cable‟, IEEE PES Summer Meeting, Los Angeles, CA, July 16-21, 1978. 9. H. A. Flores, „Submarine Cables to 34.5 kV of the Carmen Beach to Cozumel Island in Mexico. Corrosion Specification and Operational Experience‟, Paper B1-115, CIGRE 2010, Paris. 10. M. Eashwar et al, „Microbiologically Influenced Corrosion of Steel During Putrefaction of Seawater: Evidence for a New Mechanism‟, NACE, Corrosion 49, 108, 1993. 11. Det Norske Veritas, „Recommended Practice RP-401, Cathodic Protection Design‟, Det Norske Veritas www.dnv.com, January 2005. 10. Appendices Spruce Island 25 kVac Submarine Cable Connection Study 20 Appendix A – Cost Estimates Item Description Route A - East Route B - West Supply Quantity Unit Price Extended Price Quantity Unit Price Extended Price S-1 Supply 1/c 35 kV, # 1/0 copper conductor, EPR or XLPE insulation, 100% concentric neutral, single wire armored submarine cable (meters)6,400 60 384,000 9,200 60 552,000 S-2 Supply terminal poles, hardwaure, disconnects, arrestors and cable terminations for each side 2 25,000 50,000 2 25,000 50,000 S-T Subtotal - Supply 434,000 602,000 Installation by Cable Laying Contractor + Local Crews Quantity Unit Price Extended Price Quantity Unit Price Extended Price I-1 Mobilize cable laying barge, tug and crew from Seattle-Vancouver area to Spruce Island area 14 33,929 475,000 14 33,929 475,000 I-2 Mob/demob local cable crews from Anchorage area or equal (2 + 2 days)4 15,000 60,000 4 15,000 60,000 I-3 Local crews install conduits from 1 m below MLW to terminal poles 2 100,000 200,000 2 100,000 200,000 I-4 Cable laying contractor Installs 4 submarine cables from barge (1 day prep + 1 day per cable + 3 days bad weather standby)7 50,000 350,000 7 50,000 350,000 I-5 Local crews pull-in 4 submarine cables on land including terminations (1 day per cable + 2 days bad weather standby)6 15,000 90,000 6 15,000 90,000 I-6 Local crews install cathodic protection system, including sea anodes - one side only (lump sum)1 100,000 100,000 1 100,000 100,000 Demobilize cable laying barge, tug and crew from Spruce Island back to Seattle-Vancouver area 14 33,929 475,000 14 33,929 475,000 I-7 Miscellaneous (per day)6 5,000 30,000 6 5,000 30,000 I-T Subtotal - Installation 1,780,000 1,780,000 Engineering E-1 Engineering, project management, permitting, properties (10% of Supply + Installation)221,400 238,200 E-2 Marine surveys, navigation and mapping (days)10 5,000 50,000 10 5,000 50,000 E-3 Commissioning tests (4 days)3 3,000 9,000 3 3,000 9,000 E-T Subtotal - Engineering 280,400 297,200 TOTAL Supply, Installation and Engineering 2,494,400 2,679,200 Spruce Island 25 kVac Submarine Cable Connection Study 21 Appendix B – Budgetary Cost Quotation – Submarine Cables 1 Allen MacPhail From:Kirk Lauritsen [lauritsen@okonite.com] Sent:April 6, 2011 4:01 PM To:a.macphail@ieee.org Subject:FW: Budgetary cost quotations for single-core and three-core 25 kV submarine cables         Allen,  Budgetary as follows.                                          Alternative 1: $15/ft                                      Alternative 2: $35/ft                                      Alternative 3: $22/ft                                      Alternative 4: $60/ft      We could only do the single conductors in continuous lengths.    We could also do the 3 conductors but it would need to be spliced..    Submarine Cable ESTIMATING ONLY.    Thanks again Allen.    Kirk Lauritsen  Okonite Portland  Office (503) 598‐0598  Cell  (503) 807‐5102  lauritsen@okonite.com          For Allen MacPhail, Consulting.    One of our customers is planning a 25 kV submarine cable link to Spruce Island from Kodiak Island in Alaska. We are preparing a feasibility study for them with another consultancy in Anchorage. The question has arisen whether to use four single-core cables or two-three core cables. We would appreciate it if you could provide us with budgetary costs to supply both types, in two different conductor sizes. Assume delivery on reels FOB trucks in the Port of Seattle, where they would be transferred to an installation contractor’s barge. Cable requirements would be as follows: Alternative 1: Single core cable: Conductor size: 1C # 1/0 Compact copper, 354 mil wall Okoguard Armour: galvanized. steel wire – single layer Length: 1.5 miles x four single-core cables = 6.0 miles on four reels Alternative 2: 2 Three-core cable: Conductor size: 3C # 1/0 Compact copper, 345 mil Okoguard Armour: Overall galvanized steel wire – single layer Length: 1.5 miles x two three-core cables = 3.0 miles on one or two reels Alternative 3: Single core cable: Conductor size: 1C# 250 kcmil copper, 345 mil Okoguard Armour: steel wire – single layer Length: 1.5 miles x four single-core cables = 6.0 miles on four reels Alternative 4: Three-core cable: Conductor size: 3C # 250 kcmil copper, 345 mil Okoguard Armour: steel wire – single layer Length: 1.5 miles x two three-core cable = 3.0 miles on one or two reels Cables should be supplied in general accordance with ICEA S-94-639, ICEA S-93-649 and AEIC CS8. Maximum water depth is about 300 feet. Thanks very much for your help with this Kirk. A reply by April 8, 2011 would be appreciated. Best regards, Allen. Allen MacPhail, P. Eng. Cabletricity Connections Ltd. 1221 Devonshire Crescent  Vancouver, BC  Canada V6H 2G2  Tel/Fax: 604-738-5289  Mobile: 778-840-3210 E-mail: a.macphail@ieee.org   Spruce Island 25 kVac Submarine Cable Connection Study 22 Appendix C – Budgetary Cost Quotation – Submarine Cable Transportation and Laying Page | 1 April 5th, 2011 G. Allen MacPhail, P.Eng. Principal Engineer Cabletricity Connections Ltd. Via E-Mail: a.macphail@ieee.org RE: Budgetary Price Proposal for Submarine Cable Installation Spruce Island, AK Dear Allen, Island Tug has reviewed the Spruce Island 35 kV Submarine Cable Connection Study and is pleased to submit a budgetary price proposal for the intended submarine cable installation between Kodiak Island and Spruce Island in Alaska, USA. For the submarine cable installation ITB recommends to use the ITB503 in combination with a support tug and a thruster. The ITB 503 is a 168’ - 48’ deck barge equipped with submarine cable installation equipment which is suitable to be towed from Vancouver, BC to Kodiak Island, AK. The support tug shall be the Island Tugger with sufficient accommodation for the number of crew needed for the deck operations on board the ITB503. ITB has estimated the cost for mobilization, standard cable installation, divers and demobilization including fuel cost. # Days Budgetary Price Mobilization Vancouver-Spruce Island 14 $ 475,000.00 Submarine Cable Installation 7 $ 350,000.00 Demobilization Spruce Island-Vancouver 14 $ 475,000.00 $ 1,300,000.00 The above prices and assumptions reflect the current market for budgetary purposes. A detailed scope of work will have to be developed closer to the project date. When a detailed scope of work is approved , ITB looks forward to the opportunity to be a part of the cable installation project between Spruce Island and Kodiak Island, AK. Yours sincerely, Island Tug and Barge Ltd. John Lindsay Vice President & General Manager 55 Rogers Street Vancouver, BC Canada V6A 3X8 Office: 604-873-4312 Facsimile: 604-873-4318 Cable Lay and Repair Job History Date Approx Type of  Started Customer Location Length (ft) Work Feb‐65 B.C. Tel Deep Bay‐Brown Isl Repair cable ends Feb‐65 B.C. Tel Marpole ‐ Fraser River 2,000                       Pick‐up and re‐lay Feb‐65 B.C. Tel Gibson Landing 1,800                       Pick‐up and salvage Feb‐65 B.C. Tel Fraser River Pick‐up, Splice, cut back and re‐lay Apr‐65 B.C. Tel Jap Bay ‐ Beaver Pt 6,500                       Lay and repair Apr‐65 B.C. Tel Savory Isl ‐ Lund 16,000                     Lay Apr‐65 B.C. Tel Vancouver‐Nanaimo Apr‐65 B.C. Tel Chemainus‐Thetis May‐65 B.C. Tel Pt Grey‐Shoal Hbr‐Sylvia Bay Jul‐65 B.C. Tel Ucluelet & Tofino‐Sooke Hbr‐Shiringham  Light‐Port Renfrew 7,319                         Lay Jul‐65 B.C. Tel Half Moon Bay‐Point Roberts Jul‐65 B.C. Tel Point Roberts Jul‐65 B.C. Hydro Grief Pt‐Vananda Jul‐65 B.C. Tel Chemainus‐Bucaneer Bay‐Gunga Pt‐Billings  Bay‐Cockburn Pt Jul‐65 B.C. Tel Gunga Pt‐Pender Hbr 180,000                  Pickup gulf cable and re‐lay in several locations to length 180,000 ft. Aug‐65 B.C. Hydro Texada Isl ‐ Grief Pt 18,000                     Lay Sep‐65 B.C. Hydro Vananda‐West Grief Pt 18,000                     Lay Oct‐65 R.E. Dueck Dolphin Rd‐Knapp Isl 3,000                       Lay Oct‐65 B.C. Hydro Westview‐Vananda 18,000                     Lay Dec‐65 B.C. Tel Cambie Bridge 1,800                       Lay Dec‐65 B.C. Tel Gossip Isl 3,000                       Lay Feb‐66 B.C. Hydro Piers Isl from Vancouver Isl 8,000                       Lay Mar‐66 B.C. Tel Piers Isl 4,000                       Lay Apr‐66 B.C. Hydro Grief Pt‐Vananda 20,000                     Lay Apr‐66 B.C. Tel Britannia Beach‐Woodfibre 18,000                     Lay Jun‐66 B.C. Tel Brentwood Bay‐Willis Pt 2,500                       Lay Jun‐66 B.C. Tel Thetis Isl & Chemainus 20,000                     Lay Jul‐66 B.C. Tel Denman Isl Fanny Bay & Deep Bay 6,000                       Lay Jul‐66 B.C. Hydro Hastings Pt‐Knapp Isl 3,000                       Lay Jul‐66 B.C. Tel Thetis Isl Repair  Aug‐66 B.C. Tel Nanaimo‐Kanaka Bay Repair Sep‐66 B.C. Tel Grief Pt‐Vananda 18,000                     Lay Nov‐66 B.C. Hydro Acitve Pass 5,000                       Lay and repair May‐67 B.C. Tel Morray Channel 1,500                       Lay May‐67 B.C. Tel West Vancouver Repair Jul‐67 B.C. Tel Quadra & Galiano Isl 9,665                       Lay Oct‐67 B.C. Tel Johnston St Bridge 3,000                       Pickup and salvage Apr‐68 B.C. Hydro Vananda‐Grief Pt 18,000                     Pickup, repair and re‐lay Apr‐68 B.C. Hydro Denman Isl‐Hornby & Gabriola‐Harmack 10,000                     Lay Apr‐68 B.C Hydro Texada‐Grief Pt Repair Jun‐68 B.C. Hydro Saltspring to Kuper Isl Repair Jun‐68 B.C. Tel St John Pt Mayne‐Saturna Isl Repair shore ends Aug‐68 B.C. Hydro Vananda‐Grief Pt 18,000                     Lay Oct‐68 B.C. Tel Lantzville‐Winchelsea Isl 20,000                     Lay Nov‐68 B.C. Hydro Grief Pt 18,000                     Pickup, repair and lay Dec‐68 B.C. Tel Canoe Pass 2,000                       Lay Dec‐68 B.C. Tel Babine Lake 15,000                     Lay Jan‐69 B.C. Tel Babine Lake 15,000                     Lay Jan‐69 B.C. Hydro Crofton‐Saltspring 8,000                       Lay Jan‐69 B.C. Hydro Saltspring‐Kuper Isl Repair Jan‐69 B.C. Hydro Vananda‐Grief Pt 18,000                     Repair and re‐lay Jan‐69 B.C. Hydro Crofton‐Saltspring 8,000                       Pickup, repair & re‐lay Feb‐69 B.C. Tel Mayne Isl‐Saturna Isl Repair Feb‐69 B.C. Tel Mayne Isl‐Saturna 1,200                       Repair & re‐lay Mar‐69 B.C. Hydro Crofton Repair Mar‐69 B.C. Hydro Piers Isl Repair Mar‐69 B.C. Tel Pitt River 1,500                       Lay Mar‐69 B.C. Tel Pitt River 1,500                       Lay May‐69 B.C. Tel Howe Sound‐Savoury Repair shore ends May‐69 B.C. Tel Bowen Isl‐Whytecliff Repair May‐69 B.C. Hydro Crofton 3,000                       Repair & re‐lay Jun‐69 Orcas Power Ropez & San Juan 5,000                       Pickup, repair & re‐lay Jun‐69 B.C. Hydro Kuper‐Crofton 1,500                       Repair & re‐lay Jun‐69 B.C. Tel Cordova Spit‐Piers Isl Swartz Bay Repair shore ends Jul‐69 B.C. Tel Mayne & Saturna Isl 1,600                       Lay Jul‐69 Canadian Dept of Transport San Juan Pt‐Port Renfrew 10,000                     Lay Sep‐69 B.C. Hydro Westview‐Grief Pt 18,000                     Pickup, repair & re‐lay Nov‐69 B.C. Hydro Saltspring & Crofton 8,000                       Lay Nov‐69 B.C. Hydro Langdale & Gambier Repair Jan‐70 B.C. Hydro Beaver Pt to Otter Bay 45,000                     Lay three cables Feb‐70 B.C. Hydro Bella Bella 9,000                       Lay three cables Feb‐70 B.C. Hydro Active Pass 5,000                       Pickup & re‐lay Feb‐70 B.C. Tel Quadra Isl & Campbell River 11,000                     Pickup, repair & re‐lay Apr‐70 B.C. Hydro Grief Pt‐Vananda 18,000                     Lay Jun‐70 B.C. Hydro Sarah Point‐Carter Isl 16,000                     Lay two cables Jun‐70 B.C. Tel Irvins Landing & Quarry Bay Repair Jul‐70 B.C. Tel Fraser St Repair Aug‐70 B.C. Tel Fraser St Repair Sep‐70 Canadian Dept of Transport Whiffin Spit 4,000                       Lay Sep‐70 B.C. Tel Cadboro Pt‐Strongtide Isl Repair Oct‐70 B.C. Hydro North Pender‐Saturna Isl 21,000                     Lay three cables Oct‐70 B.C. Tel Gibsons‐Keats Isl‐Madiera Park 6,000                       Lay Oct‐70 B.C. Tel Campbell River‐Quatiaske 11,000                     Lay Nov‐70 B.C. Tel Beaver Pt‐Jap Bay, North Pender, Beaver Pt &15,000                     Pickup, repair & re‐lay in new location Nov‐70 B.C. Hydro Coffin Pt‐Thetis Isl 8,000                       Lay Nov‐70 B.C. Hydro Kuper Isl & Saltspring Repair Jan‐71 B.C. Hydro Booth Bay‐Crofton Repair Jan‐71 B.C. Hydro Grief Pt‐Vananda 18,000                     Pickup, repair & re‐lay Jan‐71 B.C. Hydro Sandspit‐Skidegate 2,500                       Repair & lay Mar‐71 B.C. Hydro Mayne Isl‐Galiano Repair Mar‐71 B.C. Hydro Crofton Repair May‐71 B.C. Hydro Bowen Island Repair May‐71 B.C. Tel North Pender & Mayne Repair 1of 4 Cable Lay and Repair Job History Date Approx Type of  Started Customer Location Length (ft) Work Jul‐71 B.C. Tel Winchelsea Isl Repair Jul‐71 B.C. Hydro Vananda Repair Aug‐71 Canadian Dept of Transport Bamfield Hbr, Lennard Isl, Lookout Isl 30,000                     Lay Aug‐71 B.C. Tel Murray Rd, Sooke‐Elisa Pt 3,000                       Lay Sep‐71 B.C. Hydro Comorant Isl‐Malcolm Isl 33,000                     Lay three cables Sep‐71 B.C. Hydro Sandspit‐Skidegate 14,000                     Pickup old & re‐lay new cable Nov‐71 B.C. Tel Gunga Pt‐Pender Hbr Repair Jan‐72 B.C. Hydro Texada Isl‐Phase A 18,000                     Pickup Jan‐72 Orcas Power Lopez‐San Juan Repair Feb‐72 B.C. Hydro Twawwassen Repair Mar‐72 B.C. Hydro Vananda‐Grief Pt 18,000                     Lay Apr‐72 Seaspan Vancouver Hbr‐Overseas Telecom Repair Apr‐72 B.C. Hydro Tsawwassen Repair May‐72 B.C. Hydro Chattham Isl Repair May‐72 B.C. Telephone Nanaimo Hbr‐Protection Isl 4,000                       Lay May‐72 Orcas Power 26,000                     Lay two cables & pickup & re‐lay BP cable Jun‐72 B.C. Tel Buckley Bay‐Denman Isl 5,000                       Lay Jun‐72 B.C. Tel Mayne Isl‐Saturna Repair Jun‐72 B.C. Hydro Chatham Isl 12,000                     Lay three cables Sep‐72 Orcas Power San Juan Channel 13,400                     Pickup & re‐lay Sep‐72 B.C. Tel Mayne Isl‐Active Pass 6,000                       Lay Sep‐72 Department of Transportation Lookout Isl‐Spring Isl 8,000                       Lay Oct‐72 B.C. Hydro Trial island Repair Nov‐72 B.C. Hydro Off Roberts Bank Repair ‐ 138  KV gas fill Nov‐72 Orcas Power Pear Pt 1,000                       Pickup & reposition Dec‐72 B.C. Tel Active Pass 5,000                       Pickup & salvage Jan‐73 B.C. Tel Nanimo‐Newcastle Isl‐Pender Hbr 8,000                       Pickup & re‐lay Jan‐73 Department of Transportation Orlebor Pt‐Entrance Isl 3,000                       Lay Mar‐73 B.C. Tel Sooke Repair Apr‐73 B.C. Hydro Quatsino Sound 3,200                       Lay Apr‐73 B.C. Hydro Vananda‐Grief Pt Repair May‐73 Orcas Power San Juan‐Lopez Isl Repair May‐73 B.C. Tel Savory Isl 11,000                       Repair Jun‐73 B.C. Hydro Vananda‐Grief Pt Jul‐73 B.C. Tel Active Pass 6,000                       Lay Aug‐73 B.C. Tel Pickup Georgia St. relay Lasquiti 125,000                  Pickup & re‐lay Aug‐73 Department of Transportation Port Renfrew‐San Juan Repair Sep‐73 Orcas Power San Juan‐Lopez Repair Sep‐73 B.C. Tel Swartz Bay‐Piers Isl & Pender Hbr 3,000                       Lay Oct‐73 Orcas Power Lopez‐Lan Juan 6,000                       Lay Oct‐73 Department of Transportation Sandheads‐Roberts Bank 13,400                     Lay Nov‐73 B.C. Hydro Hornby & Denman Repair Nov‐73 B.C. Hydro Trial Isl Repair Feb‐74 B.C. Hydro Grief Pt Repair Apr‐74 Department of Transportation Entrance Isl Repair Apr‐74 B.C. Hydro Prince Rupert Repair Apr‐74 B.C. Tel Barnston Isl 3,000                       Lay May‐74 B.C. Tel Nelson Isl Repair Jul‐74 B.C. Hydro Jones Isl Repair Jul‐74 B.C. Tel Langdale‐Avanlon Bay 3,500                       Lay Aug‐74 B.C. Hydro Grief Pt. Repair Aug‐74 Department of Transportation Sandheads Repair Oct‐74 B.C. Tel Active Pass Repair Mar‐75 B.C. Tel Pitt River Bridge 1,500                       Lay Apr‐75 B.C. Hydro Prince Rupert 1,700                       Lay Apr‐75 B.C. Hydro Saturna Isl‐Pender Hbr 1,300                       Repair May‐75 B.C. Tel Bedwell Hbr 3,600                       Lay May‐75 B.C. Hydro Alert Bay‐Vancouver Isl 8,500                       Lay Jul‐75 B.C. Hydro Denman Isl 7,500                       Lay Jul‐75 B.C. Hydro Grief Pt‐Texada Isl 2,200                       Repair Jul‐75 B.C. Tel Bella Bella 8,600                       Lay Aug‐75 B.C. Tel Pitt River Bridge 1,500                       Lay Oct‐75 B.C. Hydro New Brighton, Gambier Isl Repair Dec‐75 B.C. Hydro Knapp Isl Repair Feb‐76 B.C. Hydro Grief Pt‐Vananda 2,500                       Repair two cables Apr‐76 B.C. Hydro Trial Isl Repair Apr‐76 B.C. Tel Winchelsea Isl 170                          Repair May‐76 B.C. Hydro Active Pass Repair Jun‐76 B.C. Hydro Vananda‐Grief Pt 5,000                       Repair Aug‐76 B.C. Hydro Trial Isl Repair Oct‐76 B.C. Tel Thetis Isl Repair Oct‐76 B.C. Hydro Vananda‐Grief Pt 22,000                     Pickup & re‐lay cable Nov‐76 B.C. Tel Thetis Isl Repair Dec‐76 B.C. Hydro Pitt river 1,000                       Lay Jun‐77 Jul‐77 B.C. Hydro Trial Isl 4,400                       Pickup & re‐lay new cable Jul‐77 B.C. Tel Esquimalt Hbr 4,200                       Lay Sep‐77 B.C. Hydro Denman Isl 7,500                       Lay Oct‐77 B.C. Tel Active Pass Pickup cable Nov‐77 B.C. Tel Esquimalt Hbr 3,600                       Pickup & lay new cable Dec‐77 B.C. Hydro Tofino 12,000                     Lay Dec‐77 B.C. Hydro Bella Bella 8,000                       Repair & lay new cable Jan‐78 B.C. Hydro Bella Bella 8,000                       Repair & lay new cable Feb‐78 B.C. Tel Esquimalt Repair Apr‐78 B.C. Tel Campbell River Repair Jun‐78 B.C. Tel Strongtide Isl Repair Sep‐78 B.C. Hydro Active Pass Repair Oct‐78 B.C. Tel Bella Bella 8,600                       Pickup & lay new cable Dec‐78 B.C. Tel Ewquimalt & Sooke 4,200                       Lay Feb‐79 B.C. Hydro Sandspit, Queen charlotte Isls Repair Apr‐79 Transport Canada Merry Isl 9,000                       Lay Apr‐79 B.C. Tel Sooke Repair cable ends May‐79 B.C. Hydro Skidegate 21,000                     Lay May‐79 B.C. Tel Hornby Isl 6,000                       Lay May‐79 B.C. Tel Gabriola Isl Repair 2of 4 Cable Lay and Repair Job History Date Approx Type of  Started Customer Location Length (ft) Work Jun‐79 B.C. Hydro Tsawwassen Repair Aug‐79 B.C. Tel Beaver Pt, Village Bay Repair Oct‐79 B.C. Hydro Bowen Isl 18,000                     Lay Nov‐79 Orcas Power Spieden Isl 3,000                       Lay Nov‐79 B.C. Hydro Bowen Isl Repair May‐80 B.C. Tel Pender Hbr Repair Jun‐80 C.H.E. Williams Second Narrows 4,800                       Lay Jul‐80 B.C. Hydro Sandspit, Bowen Isl 10,000                     Pickup & re‐lay Aug‐80 B.C. Tel Lasquiti Isl Pickup Aug‐80 B.C. Tel Bidwell Pickup Jan‐81 B.C. Hydro Active Pass Repair Feb‐81 B.C. Hydro Prince Rupert 6,000                       Repair & lay Apr‐81 B.C. Tel Thetis Isl Repair Apr‐81 B.C. Tel Keats Isl, Bowen Isl Repair May‐81 B.C. Tel Nelson Isl, Billings Bay Repair May‐81 B.C. Tel Nelson, BC 18,000                     Lay Jun‐81 B.C. Tel Esquimalt 4,000                       Pickup & re‐lay Jun‐81 B.C. Tel Active Pass 5,000                       Pickup Jun‐81 B.C. Tel Nelson Isl Repair Jul‐81 B.C. Hydro Cortez Isl 6,000                       Lay Aug‐81 B.C. Tel Point Roberts, Mayne Isl 72,000                     Pickup Oct‐81 Mr. C. Andre Daymen Isl 3,000                       Lay Oct‐81 Mr. E. Cawyer Hudson Isl 3,000                       Lay Nov‐81 Can‐Dive Serv. Nov‐81 Teleglobe Can Vancouver Hbr 11,000                     Repair & lay Dec‐81 B.C. Hydro Active Pass 6,000                       Repair & lay Jan‐82 B.C. Tel Lund Repair Feb‐82 B.C. Hydro Keats Isl Temporary repair Mar‐82 Ace Electrical Fox Isl, Washington 4,200                       Lay Mar‐82 B.C. Hydro Keats Isl Repair Mar‐82 Orcas Power Bell Isl, Pole Pass, Destruction Isl 6,800                       Lay Mar‐82 Mr. C. Andre Daymen Isl, Thetis Isl 3,000                       Lay Mar‐82 Western Power Gossip Isl 1,800                       Lay Mar‐82 B.C. Tel Cap Cockburn 9,000                       Repair & lay Mar‐82 B.C. Hydro Keats Isl 3,500                       Re‐lay Apr‐82 B.C. Tel Savory Isl   6,000                       Repair & lay May‐82 B.C. Tel Banfield 1,680                       Lay Jul‐82 B.C. Tel Pender Hbr 1,800                       Repair & lay Jul‐82 Transport Canada Entrance Isl 3,500                       Lay Aug‐82 B.C. Hydro Tofino Area 64,450                     4 ‐ lays Aug‐82 B.C. Tel Stubbs Island Inspection Sep‐82 Telephone Utilities of Washington Lopez Island Repair Sep‐82 Chesham Investments Goudge Island 1,000                       Pickup & lay  Sep‐82 B.C. Hydro Bowen Island Repair Oct‐82 B.C. Tel Mayne Island Repair Nov‐82 B.C. Hydro Egmont 16,000                     3 ‐ lays Nov‐82 B.C. Tel Egmont 2,800                       Lay Jan‐83 B.C. Hydro Bowen Island Repair May‐83 Alaska Power Auth. & Mitsui (USA Wrangell 264,000                  Lay 16 cables 138 kv Jul‐83 B.C. Tel Saturn to Main Island Repair Sep‐83 B.C. Hydro Active Pass Repair Dec‐83 B.C. Tel Madera Park 4,000                       New lay Mar‐84 Orcas Power & Light Decatur to Blakley Isl Repair Apr‐84 B.C. Hydro Parker Isl to Saltspring Isl 16,000                     Lay Jun‐84 B.C. Hydro Parker Isl to Saltspring Isl 16,000                     Lay Jun‐84 Dawson Construction Ketchikan, Alaska 4,000                       Lay Jul‐84 B.C. Tel Buccanear Bay Repair Aug‐84 Dept. of National Defence Parry Bay 12,000                     Lay Oct‐84 Orcas Power & Light Blakely Isl to Decatur Lay Nov‐84 B.C. Tel Gunga Pt to Cape Cockburn 6,000                       Repair Nov‐84 B.C. Tel False Creek 10,000                     Pickup May‐85 B.C. Hydro Mayne to Saturna Repair May‐85 Estate of R.M. Andrews Jr. Kuper Isl to Norway 10,000                     Supply & lay cable Jun‐85 B.C. Hydro Bowen Isl Repair Aug‐85 Western Power & Light Johnson Isl 3,000                       Lay Aug‐85 B.C. Hydro Port McNeill 17,000                     Pickup and lay Sep‐85 B.C. Tel West Vancouver & Sechelt Remove into storage Oct‐85 B.C. Tel Mayne Isl 12,000                     Lay Nov‐85 Pacific Telecom Services Orcas to Blakely Isl Lay Apr‐86 B.C. Hydro Active Pass 5,000                       Repair and lay May‐86 B.C. Hydro Bowen Isl Repair Jul‐86 B.C. Hydro Tofino Repair Sep‐86 B.C. Tel Protection Isl 4,500                       Lay Oct‐86 B.C. Hydro Active Pass 5,000                       Lay ‐ 3 Nov‐86 B.C. Tel Coal Island Transfer stored cable Jan‐87 Bill Garden Johnson Isl 3,000                       Lay cable Jan‐87 B.C. Tel Cape Cockburn Repair May‐87 Central Coast Power Gunboat Pass 6,000                       Lay ‐ 3 Jul‐87 B.C. Tel Lund & Savary 20,000                     Lay Jul‐87 Orcas Power Orcas Island 5,750                       Retrieve and Lay Sep‐87 B.C. Hydro Bowen Island 30,000                     Lay ‐ 3 Jan‐88 (West Coast Trans Cont.) Northern Gulf of Georgia Pipeline survey Jan‐88 B.C. Tel Ucluelet 1,968                       Lay Jan‐88 B.C. Tel Tofino 6,900                       Lay Jan‐88 B.C. Tel Kyuhuot 15,400                     3 ‐ Lays Jan‐88 B.C. Tel Quatsino 14,100                     Lay Jan‐88 B.C. Tel Fulford Hbr 6,000                       Splice & lay ‐ 4 Jan‐88 B.C. Tel Trincomali Channel Lay Jan‐88 B.C. Tel Johnson Channel 22,000                     Lay ‐ 4 Jan‐88 B.C. Tel Keats Island 40,000                     Lay 1 Jan‐88 B.C. Tel Thetis Island‐Vancouver Isl 11,000                     Lay Feb‐88 Public Utility District 1Lake Crescent 13,000                     Lay Jan‐89 BC Hydro Port McNeill ‐ Alert bay 7,000                       Lay Feb‐89 Inter Island Telephone Blakely Isl to Decatur 4,000                       Lay Mar‐89 Arctic Services Saanich Inlet Set Monitors 3of 4 Cable Lay and Repair Job History Date Approx Type of  Started Customer Location Length (ft) Work Mar‐89 BC Telephone Pitt River 3,000                       lay May‐89 Dawson Construction Back Island 14,000                     lay Jun‐89 BC Hydro Alert Bay  7,000                       Lay Jun‐89 Orcas Power & Light San Juan Island Repair Jun‐89 BC Hydro Kitkatla 100,200                  Lay Jun‐89 Inter Island Telephone Decatur to Blakley Isl 4,000                       lay Jul‐89 BC Hydro Bowen Island 1,000                       Lay Sep‐89 BC Hydro Pender Hbr 3,000                       Lay Oct‐89 HN Engineering Porcher Island ‐ Stephens Island 60,000                     lay Oct‐89 Transport Canada Ballenas Island lay Mar‐90 Orcas Power Lopez island ‐ San Juan Island 14,000                     Lay Jun‐90 Mitsui & Co Lopez island ‐ San Juan Island Lay ‐ 4 Apr‐91 John Vincent Forrest Island 12,000                     Lay May‐91 Telephone Utilities of Washington Gig Harbor ‐ Vashon Island 14,000                     lay Jun‐91 Transport Canada Breakwater island Lay Aug‐92 PTI Communications Pear Pt. Cable re‐positioning Sep‐93 Westmar Consultants Subtle Island Lay Jan‐94 BC Hydro Feb‐94 BC Hydro Saturna to Pender Island 8,000                       Repair and Relay Apr‐94 B.C. Tel Saturna to Samual 2,300                        Jun‐94 BC Hydro Tofino 6,500                       Lay Sep‐94 B.C. Tel Sandspit to Queen Charlotte City 19,685                     Lay fibre optic submarine cable Nov‐94 BC Hydro Denman to Hornby Island 4,000                       Repair and Lay Jan‐95 Orcas Power & Light San Juan Island to Spiedel Island 8,000                       Repair and Relay Jan‐96 Sigma Engineering Brown Bay 12,000                     Lay ‐ 3 Mar‐96 Vancouver Island Power Coulter island 15,000                      Apr‐96 BC Hydro Pearson Island 7,500                       Lay Apr‐96 Transport Canada Merry Isl Lay Aug‐96 BC Hydro Gohiano Island 12,000                     Inspection and Recovery Apr‐97 BC Telephone Lions Bay ‐ Furry Creek Lay ‐ 2 Apr‐97 Raven Bay Holdings May Island 1,600                       8 submarine cables Oct‐97 R&R Excavating Ltd. Stewart island 18,000                     3x25kV Jun‐98 Ledcor Industries Shuswap Lake 87,000                     Lay Oct‐98 Century Tel Shaw island ‐ Crane Island 2,060                       Lay Oct‐98 ICF Ltd. Sutton Island 2,500                       Lay Feb‐99 Transport Canada Nanaimo Retrieve and Lay May‐99 B.C. Tel Saturna ‐ Mayne Island pick up and lay Jul‐99 Horizon Power Installations James Island 1,700                       Lay Jul‐99 B.C. Tel Denman Island 17,000                     48 Fibre submarine cables VCR Island and Denman Island Aug‐99 Century Tel San Juan Islands 9,980                       3 cable laying projects Oct‐99 B.C. Hydro Knapp Isl repair Feb‐00 B.C. Tel Sook harbour 4,020                       Lay Feb‐00 Alaska Electric Light&Power Stephens Passage 69,131                     Lay, 20 cables Mar‐00 Synex Energy Fair Harbour ‐ Chamiss Bay 20,000                     Lay May‐00 B.C. Hydro lawyer Island ‐ Smith Island Repair and Relay Jun‐00 B.C. Tel Sandspit 21,155                     11 cables Jul‐00 B.C. Hydro Campbell River 7,500                       Repair and Lay Jul‐00 Horizon Power Installations Knapp Isl Lay Nov‐00 B.C. Tel Lund Island ‐ Savary island 12,000                     Lay May‐01 B.C. Tel Chemainus Isl ‐ Thetis Isl. 7,000                       lay Jun‐01 UMA Engineering Ltd. Entrance Isl Lay Feb‐02 B.C. Hydro Campbell River pick up and lay Feb‐02 B.C. Tel Gossip Isl 3,000                       Repair and relay Apr‐02 International Telecom Repair May‐02 B.C. Hydro Dolphin Rd ‐ Knapp Island 8,500                       Retrieve and lay May‐02 B.C. Tel Alert Bay ‐ Beaver Cove 10,000                     lay Sep‐02 B.C. Hydro Sechelt 16,000                     lay 3 cables Nov‐02 Seapower North Trail island 3,000                       Lay Jan‐03 University of Victoria Alcatel 247,500                  Retrieve and storage Feb‐03 Horizon Power Installations Pym Island 4,950                       Lay power and water  Mar‐03 B.C. Hydro Alert bay 8,580                       Retrieve and lay Jun‐03 Komex International Forrest Island 7,000                       lay of waterline Jun‐03 Canadian Coastguard Pym Island 5,250                       lay Aug‐03 Komex International Forrest Island Repari submarine waterline Oct‐03 B.C. Hydro Pender to Salt Spring 19,800                     lay of 4 cables May‐04 B.C. Hydro Saturna Island lay Sep‐05 B.C. Hydro Grief Pt ‐ Texada Island Retrieve and lay of 4 cables Nov‐05 Synex Energy Walters Cove 25,000                     Lay Jan‐06 B.C. Tel Passage Island 8,530                       Lay Sep‐06 Clean Current Power Systems Race Rocks 1,650                       Lay Nov‐06 B.C. Hydro Denman Island ‐ Buckley Bay 16,830                     Retrieve and lay of 3 cables Nov‐06 B.C. Tel Mayne Island ‐ Saturna Island Replacement of three cables Jan‐07 B.C. Hydro Saturna Isl ‐ North Pender Isl 36,730                     Replacement of three cables Jan‐07 B.C. Hydro Saturna Island ‐ Mayne Island Repair Apr‐07 University of Victoria Venus Strait of Georgia Array 27,650                     lay Aug‐07 BCTC Trincomali Channel 77,000                     Retrieve and lay Sep‐07 Canpac Divers Roberts Bank ROV  inspection Sep‐07 B.C. Hydro Alert Bay 25,245                     Replacement of three cables Dec‐07 Canpac Divers Sandheads ROV  inspection Jul‐08 Raytheon Company Winchelsea Isl 5,200                       lay Jul‐08 B.C. Hydro Pender to Salt Spring 16,500                     lay spare cable Aug‐08 BCTC Texada Island ROV  inspection Sep‐08 B.C. Hydro Saturna Island 100,000                  Retrieve 3 cables + lay 2 cables Aug‐09 B.C. Hydro Texada Island ROV  inspection Aug‐10 B.C. Hydro Okanogan Lake 49,200                     Retrieve 3 cables + Lay 4  new 25 kV cables Sep‐10 WestCoast Diving Contractors Thetis Island 3,600                       Install power cable to private island Sep‐10 TELUS Burrard Inlet 12,000                     Retrieval of 2 telecom cables Aug‐10 Orcas Power & Light Spieden Island ROV Inspection Oct‐10 VISCAS Corporation Trincomali Channel 48,000                     Retrieve 2 cables  + lay 2 252 kV power cables 374 Total Jobs Total Feet Handled 3,614,448        4of 4 Safety Management Structure Tier 1 Tier 2 Tier 3 Policy Health, Safety, Quality and Environmental Safety, Quality and Pollution Prevention Manual Company Procedure Manual Operations Manuals Tug  Barge  Shop Tier 4 Supporting Instructional Letters WHMIS Manual ECOPRO Plan HS&E Manual CDN & US SOPEP Passage Plan Emergency Plans and Drill Book Bulk Oil Products Quality Assurance man al Deck Cargo Product Handling Manual Barge Maintenance Log Certificates and License Book Charts and Publications Checklist Manual ISPS Plan Etc. Our Mission Island Tug creates the highest value solutions for our customers in bulk liquids, submarine cable and support services on the West Coast of North America and the Arctic. We seek long-term relationships with our customers, priding ourselves on delivering innovative solutions tailored to their needs. Through our talented people living our values, continuous process improvement and leading-edge equipment, we lead the industry in safety, performance, professionalism, and environmental stewardship, while generating sustainable stakeholder value. Our standards are high. We define excellence—and we deliver. Our Values Everyone Returns Home Safely! At Island Tug we… • Value our People and invest in their future • Deliver on our promises and thrive on a good reputation • Create value for our Customers at every level • Respect one another • Communicate openly, honestly and with integrity • Are positive and passionate in everything we do • Value competence, experience, knowledge, and innovation • Are committed to social responsibility and environmental stewardship • Celebrate our Successes Island Update Last month, we put our new dynamically positioned (DP2) cable barge to work for the first time, laying the biggest cable we’ve ever handled – 242-kV cable made by Viscas – in Trincomali Channel. The project was an enormous group effort, and the end user, BC Hydro, was delighted with the results. “Island Tug has been doing cable since 1968, but now we’ve taken a huge step,” says Ferdi van de Kuijlen. “Now we can handle any size of cable, so it’s a great opportunity for the business.” It’s also an opportunity to contribute to the economy, as any big cable lay job involves other businesses such as dive companies, shore contractors, environmental compa- nies, and safety experts. “We received positive feedback from the client,” adds Ferdi. “They were very happy that they have now a company that can do this here in BC. Now they can look in their back yard instead of going south of the border.” Andy Farmer served as technical advisor and helped with project implementation, working closely with the cable experts to make sure the equipment operated properly. “We had to get to know the equipment, and the procedure we were using was also new to this company,” he says. “As well, we did a lot of recording of data – measuring the angle and tension of the cable, for example.” Andy says that the preparation took much longer than the I s l a n d T u g a n d B a r g e L t d.November 2010 Everyone returns home safely! job itself. “We had to acquire, build, and assemble equipment. “But now we have our DP barge, so the next project will be a lot quicker.” Mate and relief Master Alex Edwards has done a lot of cable work in his 12 years with ITB, but says this project was definitely different. “It was a bigger job than anything we’ve done,” he says. “There were 32 people on the barge, and it was so impressive to see everyone in their roles, and every- thing going so smoothly.” Those people were each focused on their piece of the project, and dedicated to one thing: getting the cable out of the pan, over the stern and onto the bottom without damag- ing it. “It’s surprisingly delicate and you had to be careful with it,” says Alex. Geoff Porter, director and general manager of our project partner Seabridge Marine, calls the barge a “fantastic” piece of machinery. “This was one of the premier cable lay jobs in the world at the moment,” he says. “There are only a few companies in the world that can manufacture it, and laying it is a big deal.” That big deal was made a little easier by the fact that ITB and Seabridge have a well- established working relationship. “The best thing about work- ing with ITB is that everyone always wants to do things right,” he says. “You don’t have to argue that point ever – and that’s a nice way to work.” Our commitment to doing things right resulted in a successful first project for our DP2 barge. And we expect that this is only the beginning. ITB 45 completes major cable projectITB 45 completes major cable project “Thank you for your cooperation during the entire cable install, I am sure BCH and guests height- ened your stress level … they were amazed at ITB’s profession- alism to ensure a first-class per- formance. The BC Hydro team were impressed with ITB’s efforts to successfully complete the cable installation; we are pleased to have a viable local contractor to be available to assist.” — Harvey Manchuk, Construction Officer, BC Hydro To help people get in touch with where they are, where they are going, and how to improve their performance, ITB has been conducting employee evaluations. “The evaluations provide one-on-one feedback with our seagoing crew,” says John Lindsay. “It’s a way of identify- ing what you do well, what you can improve, and what direction you want to move in. Not everyone wants to become a mate, for example. But if you want to keep on as a deckhand, maybe we can identify ways to help you be a better deckhand.” Port Captains Bill Ford, Jed Brown, and Gary Duncan have been doing the evaluations, uncovering strengths and opportunities for improvement. “It’s a way to measure how our employees are doing – and that’s good information for the company as well as for the employees themselves,” says Jed. He adds that the evaluations help reveal whether or not a person is ready to advance. For the role of master, for example, there’s a long checklist that covers everything from handling boats to handling people and paperwork. “For those who want to move up, if they have the potential and the ability, we put them through more training,” says Gary. “It can be an overwhelming job though, so they don’t move up until we see fit, and until they’re comfortable. It’s important that they be the best they can be at their own jobs before they step into the next role.” There are also a few who simply aren’t suited to stepping up to the next level yet. “A couple of guys told us it hurt to hear that, but they really appreciated hearing the truth,” says Jed. “Now they can really work on the areas they need to work on, instead of wondering why they’re getting passed by.” Good training is priceless In conjunction with the evaluations, the trio is heading up an intensive training program for mates ready to move up to a master position. “In my time, the training was pretty slim,” says Bill. “The industry tended to hire people who have the savvy and pick things up on the job. But honestly, the seat of the pants method is not the ideal way to learn.” A more formal training program helps reduce damage and injury. Bill notes that even with a few green masters, our damage has been down since the training has been imple- Nov 2010 Everyone returns home safely! Page 2 of 3 mented. Spending the money on training rather than on fixing damage, makes good business sense. One employee who successfully stepped into the role of master last February was Neil Parris. “The formal training was very beneficial,” he says. “It took a lot of guesswork out of it. The theory is the same when you come into any landing or approach; it’s a matter of current and wind. But having someone with the kind of experience Gary has showing me how it’s done gave me experience that would have taken years to get on my own.” Neil adds that he’s glad the company has moved toward a more formal training program. “It’s a very steep learning curve,” he says. “Without the training, I don’t think I would have had the nerve to jump in and do it.” For the trainers, helping people achieve their best is very satisfying. Says Gary, “It’s really rewarding to me because I’ve seen many of them as green, inexperienced deckhands, and now they’re doing a heck of a good job.” Evaluations and training help us be the best we can be Gary Duncan gives Neil Parris the benefit of his experience and wisdom during a training session. Safety corner by Stephen Shimek A near miss is an event that did not result in injury or damage, but that had the potential to do so. Near miss reporting allows us to deal with those events before they become problems. A recent near miss at ITB provides a good example of how the process should work. In this case, the Master did all the paperwork right away, documenting ex- actly what happened and making recommendations for procedures that would help prevent a similar incident in the future. The meticulous way he wrote it allowed us to present the issue very clearly in a meeting with the customer and contractor, and get them involved. It allowed them to understand what the issues were, and it set the ground for us to move forward. A few weeks later, we were able to use that document again in a conference call so that everyone still had a clear picture of what happened and no details were lost with the passage of time. Once you take the step to document an issue, you know that it’s preserved – frozen in time. The information can then be used as we develop measures that will prevent the incident from occurring again. The Master did a fantastic job of reporting, and his attention to detail will result in important safety improvements. So while paperwork may not be anyone’s favourite task, near-miss reporting is a necessary and valuable way for us to ensure that we are continually improving. ITB has won a North American Occupational Safety and Health (NAOSH) Week safety award in the “Marine” category. A secondary “Special Award” was given for “Most Innovative.” Our seagoing division took the prize for the two activities it submitted. One was the abandon ship and survival at sea training that was arranged at the BCIT marine campus. The other was the publication of a summary of all our incidents that have occurred during the first quarter of 2010. As well, our maintenance facility received an honourable mention for its two NAOSH Week activities. Five groups did a “what’s wrong with this photo” hazard identification activity. One group each day presented their scenario to the rest of the maintenance facility. The rest of the groups had to identify the issues or hazards in each photo. For its second submission, the facility conducted a spill drill. Although our third entry didn’t win official recognition, it did result in producing an excellent tool that we will use. Our office created a visitor site safety information pamphlet to hand out to visitors and contractors who come to the office. The pamphlet provides key emergency information and safety procedures that they should know while visiting or working for ITB. Nov 2010 Everyone returns home safely! Page 3 of 3 From left: Don Lynum, Jed Brown, John Lindsay, Stephen Shimek, Roger Wright and Vincent Russell, Director, Industry & Labour Services, WorkSafeBC The awards were presented last month at the NAOSH awards luncheon. But the benefits go well beyond the award ceremony – all our projects supported our core value that “everyone returns home safely,” and participating in these and other safety projects contributes to our continual safety improvement. ITB receives safety award NATIONAL SAFETY AWARD ISLAND TUG AND BARGE LTD.