HomeMy WebLinkAboutREF VI Appendix F P14066_GartinaFalls_Exhibit ALICENSE APPLICATION
Gartina Falls Hydroelectric Project
FERC PROJECT NO. 14066-000
EXHIBIT A
Inside Passage Electric Cooperative
P.O. Box 210149
Juneau, Alaska 99821
May 2012
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-i May 2012
EXHIBIT A
PROJECT DESCRIPTION
TABLE OF CONTENTS
1.0 INTRODUCTION......................................................................................................... A-1
1.1 General Project Setting and Location ......................................................................... A-1
1.2 Drainage Area ............................................................................................................. A-1
2.0 PROJECT FEATURES................................................................................................ A-3
2.1 Diversion/Intake .......................................................................................................... A-3
2.2 Penstock ...................................................................................................................... A-3
2.3 Powerhouse ................................................................................................................. A-3
2.4 Tailrace ....................................................................................................................... A-4
2.5 Access Roads .............................................................................................................. A-4
2.6 Transmission Line/Switchyard ................................................................................... A-4
3.0 MODE OF OPERATION ............................................................................................ A-9
4.0 ESTIMATED PROJECT COSTS ............................................................................. A-11
5.0 PURPOSE OF PROJECT .......................................................................................... A-13
LIST OF TABLES
Table A-1. Summary of Project features. ................................................................................... A-5
LIST OF FIGURES
Figure A-1. Gartina Falls Annual Flow Duration Curve. .......................................................... A-2
Figure A-2. Gartina Falls Average Monthly Flow. .................................................................... A-2
Figure A-3. Electrical One Line Diagram for the Gartina Falls Hydroelectric Project. ............ A-7
Figure A-4. Gartina Falls Average Monthly Generation. .......................................................... A-9
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-ii May 2012
This page intentionally left blank.
Section 1 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-1 May 2012
1.0 INTRODUCTION
1.1 General Project Setting and Location
The proposed Gartina Falls Hydroelectric Project site is located on the northeast side of
Chichagof Island in southeast Alaska approximately 5 air miles southeast of Hoonah.
Specifically, the Project is located in Alaska, Copper River Meridian, T43S and T44S, R61E, in
Sections 35 and 2, 11 respectively. Gartina Creek is a low-gradient stream that originates in the
mountains to the south of Hoonah Harbor.
The Gartina Falls Project would consist of a small diversion dam and intake just above Gartina
Falls, a steel penstock, a powerhouse located at the base of Gartina Falls, access roads, and an
overhead transmission line. The proposed project will have an installed capacity of 455 kW.
1.2 Drainage Area
The Gartina Creek drainage area at the project site, consisting of 10.3 square miles, is primarily
located in T43S 34-36 and T44S, R61E, Sections 11-15, 22-27. The elevation in the basin varies
from elevation 218 at the diversion site to a high of approximately 2,900 feet and is generally
oriented in a southwesterly direction. The mean basin elevation is approximately 1,240 feet.
The drainage basin surrounding Gartina Creek is primarily steep with slopes averaging about
25%. The basin is generally forested with areas of muskeg near the creek and tributary streams
and exposed bedrock outcroppings in the higher elevations. The estimated average annual flow
at the point of diversion is 64 cfs. A flow duration curve and annual hydrograph are shown in
Figures A-1 and A-2, respectively. Additional detailed hydrology is presented Appendix D of
Exhibit E of this license application.
Section 1 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-2 May 2012
Figure A-1. Gartina Falls Annual Flow Duration Curve.
Figure A-2. Gartina Falls Average Monthly Flow.
0
100
200
300
400
500
600
700
800
900
1000
0 102030405060708090100Discharge (cfs)Probability of Exceedance (%)
Gartina Falls
Annual Flow Duration Curve
0
20
40
60
80
100
120
Discharge (cfs)
Section 2 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-3 May 2012
2.0 PROJECT FEATURES
Project features are summarized in Table A-1 and described below.
2.1 Diversion/Intake
A diversion will be constructed approximately 125 upstream of the top of Gartina Falls. The
crest of the diversion will be at elevation 228 fmsl. The diversion will consist of a center section
with a moveable gate and a fixed crest overflow section. The fixed crest overflow section will be
constructed with rock fill with a concrete core wall. The rock fill will be grouted on the
downstream side to provide stability and durability. The crest length of the overflow section will
be approximately 42 feet long and the section will act as a spillway with uncontrolled overflow
when inflows exceed the powerhouse flow. The center gate section will consist of a 14-foot wide
radial gate that will be raised during high flow events to add flood capacity and to pass
accumulated sediment. Stoplog slots will be located at the upstream end of the radial gate section
to provide a means to dewater the gate during periods of maintenance.
The intake structure will consist of a small concrete box-type of structure located on the left side
of the diversion. The front of the intake will be protected by a sluiceway and trash rack. Stoplog
slots will be located at the upstream end of the sluiceway to provide a means to dewater the
intake during periods of maintenance. A steel transition piece will connect the intake to the
penstock. A small valve house will be located immediately downstream of the intake. The valve
house will house the penstock shutoff valve and operator as well as batteries needed to ensure
fail-safe operation and level control and flow sensors.
Access to the diversion/intake site will be provided by the primary Project access road.
2.2 Penstock
An approximate 225-ft-long welded steel penstock will convey water from the intake to the
powerhouse. The penstock will have a diameter of 54 inches corresponding to a maximum flow
rate of 110 cfs. The initial 125 feet of the pipeline will be buried and will be located on an
existing bench parallel to the stream. The final 100 feet will be above ground and will drop
steeply down the hillside to the powerhouse. The above-ground penstock will be supported by a
simple saddle support at approximately mid-span. The penstock will have a polyurethane lining
and coating to provide corrosion protection. Thrust blocks will be provided at changes in
alignment and grade as well as at the powerhouse. The penstock will have a leak detection
system installed on it that will automatically close the intake pipeline shutoff valve in the highly
unlikely event that a leak occurs.
2.3 Powerhouse
The powerhouse will be located approximately 80-ft downstream of the falls which are the
location of the anadromous barrier of Gartina Creek. The powerhouse will sit on an excavated
bench at or about elevation 170 which is above the ordinary high water mark of Gartina Creek.
The powerhouse will be a concrete building 22-ft wide by 32-ft long and 12-ft high. The
powerhouse will contain one 455 kW horizontal cross-flow turbine/generator set, inlet piping,
guard valve, switchgear, and controls. Centerline of the turbine will be at approximately
elevation 172.5.
Section 2 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-4 May 2012
2.4 Tailrace
Powerhouse flows will discharge into a chamber below the powerhouse and then through an
opening in the powerhouse foundation directly to Gartina Creek approximately 80 feet
downstream of the base of the falls. The opening in the powerhouse foundation will be protected
by a movable picket fence. The picket fence can be lowered when migrating fish are present to
protect against inadvertent entry into the discharge chamber.
A 12-inch diameter pipeline will be routed from the discharge chamber below the powerhouse to
the pool at the base of Gartina Falls. This pipeline will convey 8-10 cfs of the powerhouse flow
to the pool whenever the project is in operation. When the project is not in operation, natural
flows will pass by the diversion/intake structure and flow over the falls to the pool. This
combination will ensure that a constant flow of water is introduced to the pool at the base of the
falls at all times.
2.5 Access Roads
A limited amount of new access road will be needed to construct and operate the project. Large
portions of the drainage basin have already been logged and an extensive logging road system
exists in the area. Approximately 0.5 miles of new road will be required to access both the
powerhouse site and the diversion site from the existing road system.
The primary project access road will originate at FR 8503 and will run approximately 0.4 miles
ESE to the diversion/intake site. The primary access road will have a road width of 18-feet and
with gravel surfacing similar to the existing logging roads in the area. A short, approximately
0.1 mile long spur road will provide access to the powerhouse site. The powerhouse spur road
will have a road width of 14 feet and gravel surfacing.
Access to the project site will be restricted by a gate located at the beginning of the project
access road. This gate will be closed and locked as a normal operating procedure.
2.6 Transmission Line/Switchyard
The switchyard at the powerhouse will consist of a pad-mounted disconnect switch and a pad-
mounted step-up transformer located on the roof of the powerhouse. A buried 12.5 kV
transmission line would follow the powerhouse access road from the powerhouse to the junction
with the main project access road. The transmission line will then transfer to a 12.5kV overhead
line that will follow the project access road and then the existing logging roads to a point of
interconnection near the Hoonah airport. Total length of the transmission line will be
approximately 3.8 miles.
Poles would be designed as tangent line structures on about 300 foot centers. Design of the line
using tangent construction will provide raptor protection. Collision avoidance devices will be
installed on the line at appropriate locations to protect migratory birds.
A communications cable will be installed parallel to the transmission line to allow operators in
the diesel plant to monitor and control the hydroelectric project.
An electrical one-line depicting the generation and interconnection is shown in Figure A-3.
Section 2 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-5 May 2012
Table A-1. Summary of Project Features.
Location Alaska, Copper River Meridian, T43S and T44S, R61E, in Sections 35 and 2, 11
respectively, Chichagof Island, Alaska, near the community of Hoonah. Approximate
latitude 58 o 03’ and longitude 135o 23’.
Intake Concrete box type located on left side of diversion.
Diversion 56-ft. long, crest elevation = 228 msl.
Reservoir None. Limited pool behind diversion structure.
Usable storage: 0 AF
Surface area: 1.7 acre
Penstock Total Length: 225 ft.
Diameter: 54 inches
Material: Steel
Components: Polyurethane exterior coating, Polyurethane interior lining
Powerhouse
Size: 22 ft. by 32 ft.
Number of Units: One
Type of Turbine: Cross-flow
Design Flow: 110 cfs
Range of Flow: 11-110 cfs
Gross Head: 62 ft.
Net Head: 58 ft.
Turbine Power: 600 HP
Generator: 455 kW
Auxiliary Units N/A
Future Units N/A
Operation Run of river, Automatic
Transmission Line Voltage: 12.5 kV
Length: 3.8 miles
Type: 0.1 miles buried in conduit, 3.7 miles overhead on timber
poles, tangent line construction
Access Roads Length: 0.5 mile new road
Average Annual Energy 1,810 MWh
Estimated Project Cost $6,694,000. (2012 dollars)
Section 2 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-6 May 2012
This page intentionally left blank.
Section 2 Exhibit A Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative FERC No. 14066 A-7 May 2012 Figure A-3. Electrical One Line Diagram for the Gartina Falls Hydroelectric Project.
Section 2 Exhibit A Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative FERC No. 14066 A-8 May 2012 This page intentionally left blank.
Section 3 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-9 May 2012
3.0 MODE OF OPERATION
The Gartina Falls Hydroelectric Project will operate entirely in a run-of-the-river mode,
generating electrical energy from available streamflow. Water up to the desired turbine flow will
be diverted through the powerhouse and returned to Gartina Creek near the base of the falls.
Turbine flow will range from a minimum of about 11 cfs to a maximum of 110 cfs depending on
the electrical load of the system and the available water. This mode of operation is expected to
result in 1,810 MWh of average annual generation. The average monthly generation is shown on
Figure A-4 and represents a dependable capacity of 110 kW.
Figure A-4. Gartina Falls Average Monthly Generation.
The plant will be operated automatically and controlled remotely from the diesel power plant
located in Hoonah. Operators will make periodic inspections to the Project at least weekly to
inspect the facilities. Additionally, the Project’s Supervisory Control and Data Acquisition
(SCADA) system will include level, pressure and temperature sensing, gate and valve position
monitoring and generation monitoring. In the event of an alarm, an operator will be immediately
notified.
In the event of a shut-down for any reason, water will begin to immediately spill over the
spillway and flow the short distance to falls. As such, flow will be maintained continuously
downstream of the project.
Inflows in excess of 110 cfs will initially flow over the uncontrolled spillway and into Gartina
Creek. When inflows reach 500 cfs, the radial gate will be opened and inflows will flow past the
Project along the natural creek bed simulating a natural flushing flow.
This combined mode of operation will result in flows upstream of the diversion and downstream
of the Project tailrace being exactly the same as flows would be if the Project was not
constructed.
0
50
100
150
200
250
300
Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug SepEnergy, MWhGartina Falls
Average Monthly Generation
Section 3 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-10 May 2012
This page intentionally left blank.
Section 4 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-11 May 2012
4.0 ESTIMATED PROJECT COSTS
The total cost of the Project is estimated to be approximately $6.7 million as shown below:
Direct Construction Costs $4,200,000
Contingency $1,050,000
Engineering $420,000
Licensing $370,000
Owners General Administration $210,000
Construction Management $210,000
Interest During Construction $234,000
Total $6,694,000
Annual operation and maintenance costs are estimated as shown below:
Financing $123,000*
Operations & Maintenance $50,000
Insurance $67,000
Total $240,000
* Assumes 50% grant funding and 50% renewable energy fund loan from the State of Alaska.
Section 4 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-12 May 2012
This page intentionally left blank.
Section 5 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-13 May 2012
5.0 PURPOSE OF PROJECT
The purpose of the Gartina Falls Hydroelectric Project is to generate renewable power and
energy to serve the community of Hoonah, Alaska. The development of this renewable energy
project will replace existing diesel generation in Hoonah. The replacement of this generation
will reduce diesel consumption by approximately 135,000 gallons per year and carbon dioxide
(CO2) emissions by approximately 1,500 tons annually.
Section 5 Exhibit A
Gartina Falls Hydroelectric Project Inside Passage Electric Cooperative
FERC No. 14066 A-14 May 2012
This page intentionally left blank.