Renewable Energy Fund Round 4
Project Cost/Benefit Worksheet
RFA AEA11-005 Application Cost Worksheet Page 1 7-21-10
Please note that some fields might not be applicable for all technologies or all project
phases. The level of information detail varies according to phase requirements.
1. Renewable Energy Source
The Applicant should demonstrate that the renewable energy resource is available on a
sustainable basis.
Annual average resource availability. 716,000 kWh
Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel)
2. Existing Energy Generation and Usage
a) Basic configuration (if system is part of the Railbelt1 grid, leave this section blank)
i. Number of generators/boilers/other 3
ii. Rated capacity of generators/boilers/other 67 kW, 101 kW, 179 kW
iii. Generator/boilers/other type Diesel generators
iv. Age of generators/boilers/other 3 years old (new power plant, 2007)
v. Efficiency of generators/boilers/other Net powerplant efficiency 12.5 kWh/gallon
(per PCE data, 2008-2010)
b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank)
i. Annual O&M cost for labor FY 09 $21,650
ii. Annual O&M cost for non-labor FY 09 $165,221 (90% of this amount is fuel)
c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the
Railbelt grid, leave this section blank)
i. Electricity [kWh] 340,000 kWh
ii. Fuel usage
Diesel [gal] 31,500 gal
Other none
iii. Peak Load 240 kW
iv. Average Load 50 kW
v. Minimum Load 20 kW
vi. Efficiency Net utility efficiency approx 11 kWh per gallon (per PCE data, 2008-2010)
vii. Future trends Likely flat with diesels, increasing with hydro.
d) Annual heating fuel usage (fill in as applicable)
i. Diesel [gal or MMBtu] Unknown
ii. Electricity [kWh] Included in utility numbers
iii. Propane [gal or MMBtu] Unknown
iv. Coal [tons or MMBtu] Zero
v. Wood [cords, green tons, dry tons] Unknown
vi. Other Unknown
1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric
Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power.
Renewable Energy Fund Round 4
Project Cost/Benefit Worksheet
RFA AEA11-005 Application Cost Worksheet Page 2 7-21-10
3. Proposed System Design Capacity and Fuel Usage
(Include any projections for continued use of non-renewable fuels)
a) Proposed renewable capacity
(Wind, Hydro, Biomass, other)
[kW or MMBtu/hr]
200 kW total hydro capacity
50 kW run-of-river project and 150 kW storage project.
b) Proposed annual electricity or heat production (fill in as applicable)
i. Electricity [kWh] 716,000 kWh
ii. Heat [MMBtu] -
c) Proposed annual fuel usage (fill in as applicable)
i. Propane [gal or MMBtu] -
ii. Coal [tons or MMBtu] -
iii. Wood [cords, green tons, dry tons] -
iv. Other -
4. Project Cost
a) Total capital cost of new system $2,561,000
b) Development cost $395,000
c) Annual O&M cost of new system $17,300
d) Annual fuel cost zero
5. Project Benefits
a) Amount of fuel displaced for
i. Electricity 27,400 gal
ii. Heat 8,300 gal
iii. Transportation -
b) Current price of displaced fuel $4.00 per gal (actual price, 2010)
$3.99 per gal (2010 AEA model price for heating fuel – used
for benefits calculations)
c) Other economic benefits Value of other economic benefits, such as carbon taxes, are
included in AEA’s fuel cost projections.
d) Alaska public benefits No quantifiable benefits. Numerous indirect and intangible
benefits.
6. Power Purchase/Sales Price
a) Price for power purchase/sale Est. retail utility rate with the project is $0.12 to 0.64 per kWh
7. Project Analysis
a) Basic Economic Analysis
Project benefit/cost ratio $4.02M / $3.10M = 1.30
Payback (years) $3.10M / $162,435 = 19.1 years