Re: Pelican — Renewable Energy Fund Grant Application — Project Schedule
Dear Mr. White:
Thank you for your correspondence of September 24, 2010 regarding the City of
Pelican Renewable Energy Fund Application. Per your request, please find enclosed
the project schedule that was inadvertently omitted from Appendix F of our application.
The project schedule was prepared by CE2, the project Construction Manager, and was
based on construction funding being available in September 2010. The estimated
timeframe to complete the project is roughly 6 to 7-months. Should funding become
available next summer, the construction is expected to proceed following the same
timeline as presented in this schedule, just delayed by one calendar year.
The Grant Budget anticipated construction completion date should be May 19t" 2012,
subject to funding availability by September 2011.
We welcome your review and evaluation of our proposal, and look forward to working
with you on this project. Please contact me with any questions at (907)`735-2202.
Sincerely,
City of Pelican `
Patricia Phillips
Mayor
OFFICE OF THE MAYOR - PUBLIC WORKS DEPARTMENT - PELICAN HEALTH CLINIC - PELICAN VOLUNTEER FIRE DEPARTMENT
2010 Pelican Hydra Completion AEA Pelican Hydro Completion
P.A.
Preliminary Construction Schedule
ID Task Name
Duration
Start
Finish ! p10 Oct'10 Nov'10 Dec'10 : Jan'll Feb'11 Marl l Apr'll May'11
9/5 9/12911992610130/1 0/1 -0/2 013 i1117111 1/2 11211215. 211 2/1 '22 1/2 1/9 1 It6'..1/23. 1130 2/6 2/132/20'2127 316 31133/203/27. 4/3 4/104117424. 5/1' 518 5/15522
1 Pelican Hydro Completion
204 days
Mon 9/20/10
Thu 6/19/11
z Mobilization
6 days
Mon 9/20/10
Mon 9/27/10
3 Complete dam structure and install log boom
30 days
Mon 9/27110
Mon 11/1/10'
4 ! Clear & grub
18 days
Mon 11/l/10
Mon l l/22/10
5 Drill/blast STA 7+00 to STA 8+00 and construct
18 days
Mon 11/22/10
Tue 12/14110'
penstock alignment
5 Drill/blast STA 9+32 to 12+40 and construct penstock
24 days
Tue 12/14/10
Thu 1/13/11.
alignment
7 Construct lower penstock alignment from surge tank
18 days
Thu 1/13/11
Thu 2/3/11'
to powerhouse
e Construct pipeline trestle
36 days
Thu 2/3/11
Thu 3/17111 i
s Install powerhouse and controls upgrades
48 days
Tue 3/1/11
Tue 4/26/11
10 Install surge tank
6 days
Thu 3/17/11
Thu 3/24/11
11 Install 48" pipeline surge tank to dam
18 days
Thu 3/24/11
Thu 4/14/11
12 ' Install 42" pipeline surge tank to powerhouse
12 days
Thu 4114/11
Thu 4/28111
Install electrical service to trash rack
6 days
Thu 4/28/11
Thu 5/5/11
14 j Testing and cleanup
6 days
Thu 5/5/11
Thu 5112/11
15 Demobilization
6 days
Thu 5/12/11
Thu 5119/11
Prepared for: Alaska Energy AuthoritylRural Energy Group
Task
]
Progress Summary ^ External Tasks Deadline
Project: Pelican Hydro Completion Sched
Date: Fri 9/3110
Split
Milestone ♦ Project Summary External Milestone
Page 1