HomeMy WebLinkAboutESP Generator Project_Round4.mppIDTask NameDurationStartFinish1Issue Notice to Proceed1 day?Mon 4/4/11Mon 4/4/112FERC Permit30 daysTue 1/10/12Mon 2/20/123Environmental Studies100 days?Tue 2/21/12Mon 7/9/124Winter Flow Study (2) sites109 days?Tue 2/21/12Fri 7/20/125Summer Flow Study (4) sites90 daysMon 7/23/12Fri 11/23/12678Prototype Design30 days?Tue 4/5/11Mon 5/16/119Order Turbine Components60 daysTue 5/17/11Mon 8/8/1110Turbine testing30 daysTue 8/9/11Mon 9/19/1111Order Gear Box Components45 daysTue 5/17/11Mon 7/18/1112Gear Box testing30 daysTue 7/19/11Mon 8/29/111314Dummy Shroud Manufacture60 days?Mon 6/11/12Mon 9/3/1215Dummy Shroud Install30 days?Mon 9/3/12Fri 10/12/121617ESP Generator Prototype Fabrication & FAT1 dayTue 9/20/11Tue 9/20/1118Seal: IS PB F Single SB CL-7 EHL X (SE27672SA)45 days?Wed 9/21/11Tue 11/22/1119Gear Box: 30:1 Increaser (as required)15 daysWed 9/21/11Tue 10/11/1120Turbine45 daysWed 9/21/11Tue 11/22/1121Motor: HMI U 800/2080/233X, 16R (SE27672MA)45 days?Wed 9/21/11Tue 11/22/112223Prototype Permit60 days?Wed 11/23/11Tue 2/14/1224Prototype Test, Verdigris River30 daysWed 2/15/12Tue 3/27/122526Prototype Permit60 days?Mon 10/15/12Fri 1/4/1327Prototype Test, Nenana Test Site30 daysWed 5/9/12Tue 6/19/122829Canned ESP Booster Order60 daysMon 10/15/12Fri 1/4/133031Prototype Install15 daysMon 11/26/12Fri 12/14/1232Canned ESP Booster3 daysMon 2/18/13Wed 2/20/134/4ChevronDTATerrasondTerrasondCentrilift,UAFCentriliftCentrilift,UAFCentriliftCentriliftQuality MarineChevron9/20Tulsa UnivCentriliftUAFCentriliftCentriliftMarchAprilMayJuneJulyAugustSepteOctobeNovemDecemJanuarFebruaMarchAprilMayJuneJulyAugustSepteOctobeNovemDecemJanuarFebruTaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePage 1Project: ESP Generator ProjectDate: Wed 9/15/10