HomeMy WebLinkAbout(Attachment A) Project ScheduleAttachment "A"
Gulkana, Alaska
Jun '11 Jul '11 Aug '11 Sep '11 Oct '11 Nov '11 Dec '11 Jan '12 Feb '12 Mar '12
1 0 days 6/1/2011 6/1/2011
2 30 days 7/1/2011 7/31/2011
Phase II - Complete the ordering of
the equipment to finalize the project
4 120 days 8/1/2011 11/30/2012
5 30 days 8/1/2011 8/31/2011
6 110 days 9/1/2011 12/22/2011
7 10 days 9/1/2011 9/10/2011
8 10 days 9/11/2011 9/21/2011
9 30 days 9/22/2002 10/22/2011
10 60 days 10/22/2011 12/22/2011
11 90 days 1/1/2012 3/31/2012
Project: Gulkana Village Council Pellet Fuels Project Task
Date: September 15, 2010
Summary
2012
Page 1
Phase IV - Start complete production
3
Phase III - Installation
Conveyors
Belt air filters
Baggers
Dryers
Phase I - Reconnaissance Complete
Grant Award
The remainder of equipments
Pellet mill waiting time
Gulkana Village Council
ID Task Name Duration Start Finish
Milestones
Preliminary Schedule:
Proposed Pellet Fuels Project
120 days 8/1/2011 11/30/2012
2011