HomeMy WebLinkAboutNugagak NETC AEA - Community Wind Power Project - Grant Application Section
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 1 of 23 Nushagak Community Wind Power Project
Application Forms and Instructions
The following forms and instructions are provided to assist you in preparing your application for a
Renewable Energy Fund Grant. An electronic version of the Request for Applications (RFA) and the
forms are available online at: http://www.akenergyauthority.org/RE_Fund-IV.html
Grant Application
Form
GrantApp4.doc Application form in MS Word that includes an outline
of information required to submit a complete
application. Applicants should use the form to assure
all information is provided and attach additional
information as required.
Application Cost
Worksheet
Costworksheet4.doc Summary of Cost information that should be
addressed by applicants in preparing their application.
Grant Budget Form GrantBudget4.doc A detailed grant budget that includes a breakdown of
costs by milestone and a summary of funds available
and requested to complete the work for which funds
are being requested.
Grant Budget Form
Instructions
GrantBudgetInstructions4.pdf Instructions for completing the above grant budget
form.
• If you are applying for grants for more than one project, provide separate application forms for
each project.
• Multiple phases for the same project may be submitted as one application.
• If you are applying for grant funding for more than one phase of a project, provide milestones and
grant budget for completion of each phase.
• If some work has already been completed on your project and you are requesting funding for an
advanced phase, submit information sufficient to demonstrate that the preceding phases are
satisfied and funding for an advanced phase is warranted.
• If you have additional information or reports you would like the Authority to consider in reviewing
your application, either provide an electronic version of the document with your submission or
reference a web link where it can be downloaded or reviewed.
REMINDER:
• Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials submitted
to the Authority may be subject to disclosure requirements under the act if no statutory
exemptions apply.
• All applications received will be posted on the Authority web site after final recommendations are
made to the legislature.
• In accordance with 3 AAC 107.630 (b) Applicants may request trade secrets or proprietary
company data be kept confidential subject to review and approval by the Authority. If you want
information is to be kept confidential the applicant must:
o Request the information be kept confidential.
o Clearly identify the information that is the trade secret or proprietary in their application.
o Receive concurrence from the Authority that the information will be kept confidential. If the
Authority determines it is not confidential it will be treated as a public record in accordance
with AS 40.25 or returned to the applicant upon request.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 2 of 23 Nushagak Community Wind Power Project
SECTION 1 – APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
Nushagak Electric and Telephone Cooperative (NETC)
Type of Entity:
“not-for-profit” cooperative utility
Mailing Address
PO Box 350 Dillingham, AK 99576
Physical Address
557 Kenny Wren Rd, Dillingham, AK
Telephone
907-842-5251
Fax
907-842-2780
Email
nushtel@nushtel.com
1.1 APPLICANT POINT OF CONTACT / GRANTS MANAGER
Name
Frank Corbin
Title
Chief Executive Officer / General Manager
Mailing Address
PO Box 350
Dillingham, AK 99576
Telephone
907-842-5251
Fax
907-842-2780
Email
fcorbin@nushagak.coop
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
X An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
An independent power producer in accordance with 3 AAC 107.695 (a) (1), or
A local government, or
A governmental entity (which includes tribal councils and housing authorities);
Yes
1.2.2. Attached to this application is formal approval and endorsement for its project by
its board of directors, executive management, or other governing authority. If the
applicant is a collaborative grouping, a formal approval from each participant’s
governing authority is necessary. (Indicate Yes or No in the box )
Yes
1.2.3. As an applicant, we have administrative and financial management systems and
follow procurement standards that comply with the standards set forth in the grant
agreement.
Yes
1.2.4. If awarded the grant, we can comply with all terms and conditions of the attached
grant form. (Any exceptions should be clearly noted and submitted with the
application.)
Yes
1.2.5 We intend to own and operate any project that may be constructed with grant
funds for the benefit of the general public.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 3 of 23 Nushagak Community Wind Power Project
SECTION 2 – PROJECT SUMMARY
This is intended to be no more than a 1-2 page overview of your project.
2.1 Project Title – (Provide a 4 to 5 word title for your project)
Nushagak Community Wind Power Project.
2.2 Project Location –
Include the physical location of your project and name(s) of the community or communities that will
benefit from your project.
The project will be located near the Kanakanak hospital and will be tied into the grid serving
Dillingham and Aleknagik, AK. The figure below shows the proposed location.
Figure 1. Kanakanak near Dillingham, AK and location of met tower 2259 (yellow) and proposed wind turbines (red
triangles).
Dillingham is located at the northern end of Nushagak Bay in northern Bristol Bay, at the
confluence of the Wood and Nushagak Rivers. It lies 327 miles southwest of Anchorage, and is
a 6 hour flight from Seattle. Dillingham can be reached only by air and sea.
The current population is 2,347 (2008 DCCED Certified Population)
Average summer temperatures range from 37 to 66; average winter temperatures range from 4
to 30. Annual precipitation is 26 inches, with 65 inches of snow. Heavy fog is common in July
and August. Winds of up to 60-70 MPH may occur between December and March.
Aleknagik is located at the head of Wood River on the southeast end of Lake Aleknagik, 16
miles northwest of Dillingham. Aleknagik is located in the Bristol Bay Recording District. The
area encompasses 11.6 sq. miles of land and 7.2 sq. miles of water. Average summer
temperatures range from 30 to 66 °F. Average winter temperatures range from 4 to 30 °F.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 4 of 23 Nushagak Community Wind Power Project
Average annual precipitation is 20 to 35 inches, and average annual snowfall is 93 inches.The
current population is 229 (2009 DCCED Certified Population). Nushagak Electric Cooperative in
Dillingham provides electricity to Aleknagik.
General Kanakanak site characteristics:
1. Close proximity to class 3 winds that blow off Nushagak Bay (approximately one mile to the
East (1.6 km)).
2. Owned by Choggiung Ltd., a community partner in the project
3. Lies within ½ mile (0.8 km) of a three phase utility grid
4. Surrounded by low vegetation consisting of tundra vegetation and willow less than 8’ in
height.
5. Large areas for potential expansion of wind farm
6. There are existing communication towers and buildings (Bristol Bay Area Health Corporation
Behavioral Health and FAA housing) near proposed turbine site.
2.3 PROJECT TYPE Put X in boxes as appropriate
2.3.1 Renewable Resource Type
X Wind Biomass or Biofuels
Hydro, including run of river Transmission of Renewable Energy
Geothermal, including Heat Pumps Small Natural Gas
Heat Recovery from existing sources Hydrokinetic
Solar Storage of Renewable
Other (Describe)
2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply)
Reconnaissance X Design and Permitting
Feasibility X Construction and Commissioning
X Conceptual Design
2.4 PROJECT DESCRIPTION
Provide a brief one paragraph description of your proposed project.
The Nushagak Community Wind Power Project proposes to erect two wind turbines (approximately
200-300 kW . e.g. Aeronautica 29-225kW ) and connect them into the adjacent electric grid operated
by Nushagak Electric and Telephone Cooperative (NETC) serving Dillingham and Aleknagik, Alaska.
This installation will deliver annually up to 900 mega watt hours of electric power and replace more
than 64 thousand gallons of diesel fuel.
The proposed Kanakanak site has enough wind to be considered a commercially viable site for a
small commercial sized mid-scale turbine. Such a device would produce in excess of $155,000/yr.
Further, such wind turbines will serve as an important educational tool for NETC to gain the
important skills and expertise to operate and maintain state of the art renewable technology. Such
knowledge is a central component to NETC developing a sustainable energy system that will
integrate renewable power sources with existing diesel technology.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 5 of 23 Nushagak Community Wind Power Project
2.5 PROJECT BENEFIT
Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel costs,
lower energy costs, etc.)
This project is designed explicitly to reduce diesel fuel consumption in the remote area served by
NETC and to help build the capacity to integrate renewable energy into the existing NETC grid.
These actions will stabilize NETC electricity production costs by promoting community and business
growth. Although such small scale turbines will have minimal effects on the overall electrical cost to
ratepayers, it will significantly increase NETC capacity to expand further into renewable energy in the
near future. The project will also help to reduce regional energy dependence by introducing
technology with a stable price production, as the price of diesel has been very volatile over the last
10 years. (Figure 1)
Figure 1. Extracted from Ameresco, Inc.’s Price Proposal- see attachment
Further, the project will serve as an important educational tool for both NETC and the surrounding
community for future expansion of renewable energy systems. The institutional and technical
knowledge learned will substantially decrease time, effort, and money hurdles for future expansion
into other renewable energy projects. Although the dollar value for the educational benefits is difficult
to measure, it is significant in terms of human and social capital.
2.6 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source of
other contributions to the project.
Ninety percent of the projected costs are anticipated to be grant funds with a ten percent NETC
match. The operational and maintenance cost for wind turbines acquired will be paid through
conventional means by the operating utility.
2.7 COST AND BENEFIT SUMARY
Include a summary of grant request and your project’s total costs and benefits below.
Grant Costs
(Summary of funds requested)
2.7.1 Grant Funds Requested in this application. $ 3,199400.10
2.7.2 Other Funds to be provided (Project match) $ 355,488.90
2.7.3 Total Grant Costs (sum of 2.7.1 and 2.7.2) $ 3,554,889
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 6 of 23 Nushagak Community Wind Power Project
Project Costs & Benefits
(Summary of total project costs including work to date and future cost estimates to get to a fully
operational project)
2.7.4 Total Project Cost (Summary from Cost Worksheet
including estimates through construction)
$ 3,554,889
2.7.5 Estimated Direct Financial Benefit (Savings) $ 155,000.00/yr
2.7.6 Other Public Benefit (If you can calculate the benefit in
terms of dollars please provide that number here and
explain how you calculated that number in your application
(Section 5.)
$ 20,000
SECTION 3 – PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include contact information, a
resume and references for the manager(s). If the applicant does not have a project manager
indicate how you intend to solicit project management support. If the applicant expects project
management assistance from AEA or another government entity, state that in this section.
Mr. Michael Favors, Project Manager and Engineer for Nushagak Cooperative will be the on-site
project manager for the wind power project. Mr. Michael Bartlett, Alaska Business Development
Manager for Ameresco, Inc. will serve as the off-site project manager, working in collaboration
with Mr. Favors Project Manager.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 7 of 23 Nushagak Community Wind Power Project
3.2 Project Schedule
Include a schedule for the proposed work that will be funded by this grant. (You may include a
chart or table attachment with a summary of dates below.)
3.3 Project Milestones
Define key tasks and decision points in your project and a schedule for achieving them. The
Milestones must also be included on your budget worksheet to demonstrate how you propose to
manage the project cash flow. (See Section 2 of the RFA or the Budget Form.)
Conceptual Design, Design and Permitting Milestones
Project scoping and contractor solicitation for planning and design Oct 2010
Permit applications (as needed) Oct 2010
Final environmental assessment and mitigation plans (as needed) Nov 2010
Resolution of land use, right of way issues Nov 2010
Final System Design Dec 2010
Engineers cost estimate Dec 2010
Permit approvals Jan 2011
Updated economic and financial analysis May 2011
Negotiated power sales agreements with approved rates May 2011
Final business and operational plan May 2011
Construction and Commissioning Milestones
Confirmation that all design and feasibility requirements are
complete.
Jan 2012
Completion of bid documents March 2012
Contractor/vendor selection and award April 2012
Construction Phases March 2012 -Sept 2012
Final Acceptance, Commissioning and Start-up Oct 2012
Training Oct 2012
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 8 of 23 Nushagak Community Wind Power Project
3.4 Project Resources
Describe the personnel, contractors, equipment, and services you will use to accomplish the
project. Include any partnerships or commitments with other entities you have or anticipate will
be needed to complete your project. Describe any existing contracts and the selection process
you may use for major equipment purchases or contracts. Include brief resumes and references
for known, key personnel, contractors, and suppliers as an attachment to your application.
NETC will ultimately be responsible for the successful completion of the project, working in
collaboration with partners that have managed similar projects and installed similar systems.
NETC’s Mr. Michael Favors has over 35 years in the communications industry serving remote
and rural areas of Alaska. He has successfully engineered and managed installation and
commissioning of numerous microwave systems in the 2, 6 and 23 Ghz frequency ranges. Mr.
Favors is experienced in remote mountaintop site repair, maintenance and design experience at
large USAF facilities and smaller private communications from small solar only sites to diesel
powered 20 Kw sites. His skill and experience in managing multiple projects from design
through completion and ability to problem solve and propose solutions to prevent future
occurrences, will be an asset to the Nushagak Community Wind Power Project and
compliments the services provided by the contractors.
NETC will be contracting with AMERESCO Inc., located in Anchorage, Alaska.
AMERESCO Inc.
6643 Brayton Dr.
Anchorage, AK 99507
907-277-1049
Every member of Ameresco's staff is a resource of dedicated knowledge. They are experienced
in demand-side management, energy savings performance contracts, cogeneration facilities,
renewable energy sources, energy procurement, risk management, billing services and power
plant development, financing, construction and operations. This experience enables Ameresco
to bridge the knowledge gap between customers' objectives and state-of-the-art solutions to
energy challenges.
The Ameresco Inc. team has overseen and participated in the design, development,
implementation and management of over $5 billion in successful energy projects.
Ameresco, Inc.’s, Michael Bartlett has 17 years of facility management, energy engineering,
project development, and project management experience. He has project development
leadership experience on over $200 million worth of energy savings and generation projects in
16 states and overseas. His project leadership and experience includes 35 performance based
projects over the past 10 years in the roles of engineering development, project and
construction management, operation and maintenance, and measurement and verification.
Michael holds certifications as a Project Management Professional, Certified Energy Manager,
Certified Business Energy Professional, and LEED AP. Michael also has a Bachelor of
Science Degree in Industrial Engineering from the University of Minnesota. His background,
education, and certifications make him an ideal project manager for this wind project.
Ameresco, Inc.’s Mr. Gary E. Gagnon brings a wide range of expertise in the areas of senior
management, engineering development, business and sales development, and project
management. For the past 16 years, Mr. Gagnon has worked in every aspect of providing
energy solutions to customers. Projects have ranged from the de-centralization of high
pressure steam plants to electric hot water heating systems for schools. Projects have all been
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 9 of 23 Nushagak Community Wind Power Project
“Turn Key” with one point of project responsibility for the customer to include design,
procurement, construction, commissioning and if required continuing service and maintenance.
Potential Wind Turbine System:
Aeronautica 29-225 wind turbines have been proposed for this project. Aeronautica Windpower
is a manufacturing and marketing company that builds and markets mid-scale commercial and
industrial (225 to 750 Kw) wind turbines. (Please see attached spec sheet.)
Additional important partners to this project include:
• Choggiung Ltd is the landowner of the proposed site. NETC and Choggiung, Ltd.
currently have an informal agreement on the site. If funded they intend to enter into a
formal agreement.
• UAF Bristol Bay Campus will utilize the turbines as educational tools for degree
programs and for workforce development on sustainable energy.
• The City of Dillingham offers their strong support of this project for the benefit of the
community.
3.5 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
The Nushagak Community Wind Project will be jointly managed by Michael Favors (NETC
Project Manager/Engineer 907.842.5251) and Michael W. Bartlett (AMERECO Account
Executive 508.598.4683) The project managers will be responsible in keeping the Nushagak
Board of Directors up to date on progress and will monitor milestones. The project managers
will also be responsible for compiling periodic progress reports for use by the Board of Directors,
community partners, and the Alaska Energy Authority.
3.6 Project Risk
Discuss potential problems and how you would address them.
The construction of wind turbines in rural Alaska carry with them both standard and site specific
risks that needs to be managed. Standard risks include design flaws, manufacturing defects or
increasing cost escalation, which can occur throughout all phases of any wind farm project
development, affecting the project’s profitability. Site specific risks relate to the isolated nature of
the construction site and include securing and delivering of equipment
Risk management will provide a science‐based approach to assess the potential impacts that a
wind energy project may have. It will be based on industry standards for risk analyses and risk
management frameworks - risk frameworks will reflect accepted scientific judgments and
learning through precautionary or adaptive approaches - designed by qualified experts.
In order to reduce the risks and secure the investment in turbines training packages risk
management will be applied during the development stages.
Risk management will provide help the project to:
• Assign objectives in terms of cost, scheduling and performance
• Improve cost estimates by managing realistic and relevant contingencies
• Maintain schedule milestones and performance indicators
• Enforce occupational, health, safety and environmental targets
• Assure greater certainty about financial and project execution outcomes
• Select proven technologies and suppliers that have delivered in rural Alaska
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 10 of 23 Nushagak Community Wind Power Project
SECTION 4 – PROJECT DESCRIPTION AND TASKS
• Tell us what the project is and how you will meet the requirements outlined in Section 2 of
the RFA.
• The level of information will vary according to phase(s) of the project you propose to
undertake with grant funds.
• If you are applying for grant funding for more than one phase of a project provide a
plan and grant budget form for completion of each phase.
• If some work has already been completed on your project and you are requesting funding for
an advanced phase, submit information sufficient to demonstrate that the preceding phases
are satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project.
Wind turbines offer a much needed source of renewable electrical energy to many remote
communities where fossil fuels are difficult and expensive to deliver. Now that wind turbines are
designed to withstand the harsh conditions of arctic environments, they can be a cost-effective
choice for isolated Alaskan communities.
Modern turbines such as the Aeronautica 29-225 provide a reliable and cost effective electric
power . Aeronautica 29-225 is being considered as it is simple and inexpensive to transport and
install. There are about 365 turbines of this sort installed in Denmark, the U.S., Germany, and
Sweden.
Wind analysis of the Dillingham Kanakanak areas have shown potential for wind energy
development. The Kanakanak site was determined to be the most viable site exhibiting class 3
winds at 30m.At 30m wind shear and turbulence was also measured and determined to be
present sue to trees the east and south and other building further to the west. Sustained wind
speeds should increase with height making the site more desirable. Thus the Kanakanak site is
considered to be in an area with a commercial wind resource.
Although higher wind locations may be in the region their increased distances from the grid make
them less cost effective (i.e. Cinnabar Mountain on Lake Aleknagik [estimated Class 6-7 and
Snake Lake Mountain [estimated Class 6-7]).
The Kanakanak site was chosen based on three important criteria: 1) proven wind resources
using met tower measurements, 2) close proximity of power grid, and 3) land use agreement in
place with land owner. The wind was appraisal using published wind maps (AEA) that used
computer modeling. Further, met towers collected wind data from 2005-2006 at the Kanakanak
site (Table 1).
Table 1. Wind data from Kanakanak site collected from 2005 to 2006
Hub Height Wind Speed Min. wind Max Wind Mean energy
(kW/hr/m2/yr
20 5.00 0.40 22.4 1,293
30 5.62 0.40 23.4 1,846
Current wind installations:
There are two operating residential wind turbines in Dillingham area, one near Kanakanak and
the other on Wood River Road. The Kanakanak installation consists of two Skystream 3.7
turbines that are providing 22% efficiency and the second installation consists of one Skystream
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 11 of 23 Nushagak Community Wind Power Project
3.7 turbine. Energy production data is being logged at both locations and each show that there is
enough wind at these residential sites to meet most electrical loads.
Other energy resources that have been investigated in the Dillingham region include
hydroelectric in the Wood Tikchik State Park, peat, biomass (municipal waste and wood), and
tidal. Of all these alternatives wind has the highest return on investment. (see supporting
documents)
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about
the number, size, age, efficiency, and type of generation.
The current generation system consists of seven diesel generators of various sizes which are
operated in optimal load matching configurations in order to supply the variances in the load
demand.
NETC DIESEL GENERATORS
Generator
Number Year Mfg. Kilowatt Capacity
1 1988 1135
2 2001 1050
3 2006 1050
4 2006 1050
5 2008 1050
6 2008 1050
7 2009 455
Total kW Capacity: 6,840
Average kW Load: 2,000
Average kWh per Year: 17,520,000
Since 2007 NETC has operated a solar array for telecommunications at Clarks Point.
NETC also has distributed generation guidelines for households including private wind turbines
and commercial connections to the NETC grid. NETC has helped the University of Alaska
Fairbanks Bristol Bay Campus to connect a 4 kwt solar array as well as two member owners to
connect residence scale wind power.
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of
any impact the project may have on existing energy infrastructure and resources.
The existing energy resource is 100% diesel generation with waste heat recovered and used as
space heating and adjacent buildings. This wind project proposal is considered a low-penetration
wind-diesel system and it will not have any significant negative impacts on the existing energy
resources.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 12 of 23 Nushagak Community Wind Power Project
4.2.3 Existing Energy Market
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
NETC currently serves about 1200 residential meters in the Dillingham/Aleknagik area. NETC’s
local electric demand runs approximately two thirds residential service (half of which qualifies for
PCE) and one third commercial load.
This project is a result of community request to develop renewable energies in the region.
4.3 Proposed System
Include information necessary to describe the system you are intending to develop and address
potential system design, land ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
• A description of renewable energy technology specific to project location
• Optimum installed capacity
• Anticipated capacity factor
• Anticipated annual generation
• Anticipated barriers
• Basic integration concept
• Delivery methods
• A description of renewable energy technology specific to project location
The energy production from any wind turbine is a function of the swept area of the turbine’s
blades, the size and efficiency of the mechanical system, and the aerodynamic efficiency of the
blades. These factors combine to determine values for an individual machine’s ‘capacity factor’
(the percent of time the turbine is estimated to be operating at the rated output over the course of
the year). When multiplied by the number of hours in a year, this allows the calculation of an
energy curve for individual turbines. While various wind turbines will operate at slightly better or
worse capacity factors, in general they will fall within a range of values which can be used to
illustrate the amount of power from various standard size turbines. The renewable energy system
proposed has two Aeronautica 29-225 wind turbines installed at 50m hub height at the
Kanakanak site. Table 2 shows the estimated energy output in KwHrs/yr using reference date
from the Kanakanak met tower (no. 2259)
Table 2. Estimated Aeronautics29 turbine output at 95% availability at the Kanakanak site
Turbine
Aeronautics29
Wind
speed
(m/s)
Time at
zero
output (%)
Time at
rated
output
Mean net
power
output
Mean net
energy
output
Capacity
factor
At 40 meters 6.09 15.2 1.5 50.2 439,650 22.3
At 50 meters 6.28 14.1 1.8 54.0 473,631 24.0
Data from AMERESCO 2010
• Optimum installed capacity
Maximum rated capacity of two Aeronautica 29-225 is 450 kw.
• Anticipated capacity factor
Anticipated capacity is 23%.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 13 of 23 Nushagak Community Wind Power Project
• Anticipated annual generation
Expected annual generation is 906 mW/year.
• Anticipated barriers
Anticipated barriers are limited as proven technology is used and delivery method is through
existing grid.
• Basic integration concept
Integration will be low penetration into the existing grid. Therefore, minimal impact to the current
electrical system.
• Delivery methods
An addition of 1 mile of transmission lines to the existing NETC Grid.
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the project
or how you intend to approach land ownership and access issues.
Choggiung LTD owns the real estate that the proposed wind turbine is to be located. Consultation
with Choggiung LTD and their board, has indicated that there should be no issues drawing up a
cost effective lease agreement for the land-use. (see attached letter of support under required
attachments)
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
• List of applicable permits
• Anticipated permitting timeline
• Identify and discussion of potential barriers
Permits needed:
• Alaska Coastal Management Program – This program (ACMP) evaluates projects within
the Coastal Zone (up to 200 miles inland) for consistency with statewide standards and
local enforceable policies, also as review involving all federal and state permitting
authorities and the Coastal District where the project is located.
• Land-use Permit - City of Dillingham
• Aviation Safety FAA application - Permit needed for towers taller than 200 feet or within a
few miles of an airport. The exact distance depends on the type of airport - use form 7460
• Fish impacts – ADF&G – Fishery Act and Anadromous Fish Act – streams General Permit
as streams are not impacted.
• Wetland Regional General Permits (GP) US Army Corps Engineers, Alaska Regulatory
District
• Habitat Conservation & Incidental Take Permit – when a potential exists for harm to
federally listed endangered or threatened species. Bird Collisions - USFWS – (Threatened
and Endangered Species, Migratory Bird Treaty Act and Bald and Golden Eagle
Protection Act) pre and post monitoring for bird mortality.
• History and Archaeology and State Historic Preservation – study and review of project by
Office of History and Archaeology (OHA) and State Historic Preservation Office(SHPO)
required by Section 106 of the National Historic Preservation Act.
• Land Lease– land ownership use permission (Choggiung LTD)
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 14 of 23 Nushagak Community Wind Power Project
Permitting timeline
• Jan 2011 identify all permits necessary and contact relevant agencies our intent to apply
and request information on application procedures.
• Apr 2011 Have application written and ready for review
• April 2011 begin submitting permits
• June 2011 Permits approved
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will
be addressed:
• Threatened or Endangered species
• Habitat issues
• Wetlands and other protected areas
• Archaeological and historical resources
• Land development constraints
• Telecommunications interference
• Aviation considerations
• Visual, aesthetics impacts
• Identify and discuss other potential barriers
Environmental issues:
• Threatened or Endangered species
There are no known threatened or endangered species in the project site. This issue will
also be addressed by pre and post monitoring for bird mortality at the site
• Habitat issues
There are minor habitat issues as approximately 2 acres of tundra habitat will be
influenced by the wind turbine construction and operation. Issues will be studied and
described in habitat report.
• Wetlands and other protected areas
The project will not impact wetlands
• Archaeological and historical resources
No known archaeological and historical sites at the project site, but archeologist should
survey site before construction
• Land development constraints
Wind turbines will be constructed on private land so there are no land development
constraints
• Telecommunications interference
Wind turbines will not interfere with telecommunications
• Aviation considerations
The Dillingham airport is approximately 2.7 miles (4.1 km)from the proposed wind
turbines. Thus filing a FAA 7460-1 is required .Since no military airports are in the vicinity,
the DOD is not likely to have any concerns about the site. The use of lighting on mid-scale
machines may probably be required, but it is suggested that a confirmation of this fact be
obtained from the FAA or Dillingham airport as part of the permitting process. Thus,
necessary permits from FAA must be obtained before construction
• Visual, aesthetics impacts
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 15 of 23 Nushagak Community Wind Power Project
Wind turbines are located in an area where there are existing communication towers the
have visual impacts. Turbines may be visible from Kanakanak area so community
meetings and scoping on issues will be conducted
• Identify and discuss other potential barriers
General Noise Issues - Noise considerations generally take two forms, state regulatory
compliance and nuisance levels at nearby residences:
Modern turbines are quiet enough to meet these considerations as they are masked by
the sound of the rushing wind.
No other major barriers are currently foreseen but community meetings and scoping will
occur to identify potential regional issues
4.4 Proposed New System Costs and Projected Revenues
(Total Estimated Costs and Projected Revenues)
The level of cost information provided will vary according to the phase of funding requested and
any previous work the applicant may have done on the project. Applicants must reference the
source of their cost data. For example: Applicants Records or Analysis, Industry Standards,
Consultant or Manufacturer’s estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of
the project. Cost information should include the following:
• Total anticipated project cost, and cost for this phase
• Requested grant funding
• Applicant matching funds – loans, capital contributions, in-kind
• Identification of other funding sources
• Projected capital cost of proposed renewable energy system
• Projected development cost of proposed renewable energy system
Total anticipated project cost is
Total Phase III & IV: $356,160
Total Phase V: $3,198,729
Total Project Costs: $3,554,889
Total requested grant funding: $3,199,400.10
Total applicant matching funds: $355,488.90
o Total Funding: $3,554,889
Identification of other funding sources; N/A.
Projected capital cost of proposed renewable energy system: $3,350,000
Projected development cost of proposed renewable energy system: $200,000
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by
the applicant.
(Note: Operational costs are not eligible for grant funds however grantees are required to meet
ongoing reporting requirements for the purpose of reporting impacts of projects on the
communities they serve.)
Operational and maintenance costs for two turbines are estimated to be $4,000.00/yr. Funds for
this cost will be incorporated into NETC standard O&M protocols for the entire electrical system.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 16 of 23 Nushagak Community Wind Power Project
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
• Identification of potential power buyer(s)/customer(s)
• Potential power purchase/sales price - at a minimum indicate a price range
• Proposed rate of return from grant-funded project
• Identification of potential power buyer(s)/customer(s)
Customers will include NETC rate payers, both commercial and residential
• Potential power purchase/sales price - at a minimum indicate a price range
$0.1781 kwh avoided fuel cost value
• Proposed rate of return from grant-funded project is 6:1 for matching cash contribution
and 0.6:1 for total project expenditures.
4.4.4 Project Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered in
evaluating the project.
The Project Cost Worksheet is attached.
The “Price Proposal for the Design and Installation Wind Power Project” prepared by Ameresco,
Inc., for NETC provided the main source of data included in the Project Cost Worksheet.
(attached)
Diesel Generators
Generator Power Production Capacity (kW) 6,840
Estimated Average Load (kW) 2,000
Net Power Production KWH/Year 17,520,000
Annual Fuel Consumption (From NETC) 1,250,000
Fuel Consumption Rate (kWh/gal) 14.016
Price per gal Diesel (2010) $2.53
Net Fuel Cost Power Production $3,162,500.00
Fuel Cost Per kWh ($/kWh) $0.1805
Annual O&M Costs (non-fuel) (as per NETC) $10,000.00
Wind Turbines (2x225 kW)
Power Production Capacity (kW) 450
Gross/Max Power Production (kWh/Year) 3,942,000
Capacity Factor (as per Ameresco report, pg. 8) 0.228
Anticipated Net Power Production (kWh/Year) 898,776
Wind-Diesel Integration Analysis
Fuel Consumption Rate (kWh/gal) 14.016
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 17 of 23 Nushagak Community Wind Power Project
Wind Supplement kWh/Year 898,776
Fuel Displaced gal/Year 64,125
Price per gal Diesel (2010) 2.53
Total Fuel Displacement Savings $162,236.25
Fuel Cost Displaced per kWh ($/kWh) $0.1805
Percent Total Fuel Cost Displaced 5.13%
Percent Non-Fuel O&M Cost Displaced (based on a percentage) $513,000.00
SECTION 5– PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings, and
how the people of Alaska will benefit from the project.
The benefits information should include the following:
• Potential annual fuel displacement (gal and $) over the lifetime of the evaluated renewable
energy project
• Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or cost based rate)
• Potential additional annual incentives (i.e. tax credits)
• Potential additional annual revenue streams (i.e. green tag sales or other renewable
energy subsidies or programs that might be available)
• Discuss the non-economic public benefits to Alaskans over the lifetime of the project
Potential benefits include:
• Potential annual fuel displacement (gal and $) over the lifetime of the evaluated renewable
energy project: 160,000 gallons/yr at $2.53/gallon (2010) for 15 years = 2.4 million
gallons.
• Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or avoided cost of fuel based rate): $0.1781 kwh at 897mwh/yr = $159,756 –
O&M of $4,000 = $155,756 over 15 years = $2,336,340
• Potential additional annual incentives (i.e. tax credits):
There is a potential for future tax credits and selling of green tags
• Discuss the non-economic public benefits to Alaskans over the lifetime of the project
- Educate NETC and the public about the importance of developing renewable energy
from local sources.
- In cooperation with the UAF Bristol Bay Campus and BBNA the turbines will serve as
educational tools for university degrees and workforce development on sustainability
energy. The project will generate about $20,000 in educational funds to the community
through the offering of courses at the UAF Bristol Bay Campus (one class generated
about $100/student per college credit for food lodging and fees – ten students in 20
classes for life of turbine = approximately $20,000)
- Develop a pathway for energy security by developing the human capital and capacity
for local expansion of renewable energy systems.
Social and human capital benefits include:
• Increased capacity for NETC to build and sustain advanced and integrated energy
systems. The training and hands on experience gained will be valuable as NETC expands
beyond diesel power generation systems.
• These small scale wind turbines will allow NETC to gain experience in integrating energy
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 18 of 23 Nushagak Community Wind Power Project
systems that will help the region develop economically and socially.
SECTION 6– SUSTAINABILITY
Discuss your plan for operating the completed project so that it will be sustainable.
Include at a minimum:
• Proposed business structure(s) and concepts that may be considered.
• How you propose to finance the maintenance and operations for the life of the project
• Identification of operational issues that could arise.
• A description of operational costs including on-going support for any back-up or existing
systems that may be require to continue operation
• Commitment to reporting the savings and benefits
• Proposed business structure(s) and concepts that may be considered.
The costs of the matching funds and annual O&M will be included into cooperative
overheads on a pro-rated annual basis.
• How you propose to finance the maintenance and operations for the life of the project
Grant funded at the onset and O&M from rate payers and general operation of coop.
through the electric rate base.
• Identification of operational issues that could arise.
Issues that might arise include variability in bird collisions, accessibility of spare parts and
maintenance equipment
• A description of operational costs including on-going support for any back-up or existing
systems that may be require to continue operation.
Total project cost includes specific technical training.
• Commitment to reporting the savings and benefits:
NETC will assign a project manager to report savings and benefits to rate payers. Reports
will be delivered at monthly at NETC Board meetings and annually to members at the
Annual General Meeting
SECTION 7 – READINESS & COMPLIANCE WITH OTHER GRANTS
Discuss what you have done to prepare for this award and how quickly you intend to proceed
with work once your grant is approved.
Tell us what you may have already accomplished on the project to date and identify other grants
that may have been previously awarded for this project and the degree you have been able to
meet the requirements of previous grants.
1) Reconnaissance:
a. Project scoping and contractor solicitation: NETC is a small utility that provides
electric power via an electric grid for the Dillingham/Aleknagik area. The average
load is about 2.1 MW, with the maximum of about 3.4 MW and minimum of about
1.4 MW. Except for a couple of existing non-utility renewable energy systems,
(less than 20 kW) all electric power is currently produced via diesel generators.
Because of the high cost of diesel and concerns about energy security, NETC
chose to explore renewable energy power generation and conduct a baseline
data study. Tom Marsik from the UAF Bristol Bay Environmental Science Lab was
contracted.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 19 of 23 Nushagak Community Wind Power Project
b. Resource identification and analysis: The purpose of the completed baseline
study was to compile information to determine what further studies needed to be
done to then determine the best alternative to diesel. (see attached study by
Marsik)
Alternatives considered in the baseline study were wind, conventional hydro,
solar, biomass, hydrokinetic/tidal, and geothermal. Working with AEA, NETC has
identified the wind resources for the project. For the Dillingham/Aleknagik region,
analysis of current wind data and AEA’s wind resource maps suggest there are
areas worth consideration to install wind turbines. These include:
i. Kanakanak, an area on the south side of Dillingham – Met tower data and
AEA’s wind resource map shows a Class 3 wind resource. An important
consideration of this site is the close proximity of existing three phase
power lines, thus a low cost for grid tie-in.
ii. Wind hot spots – Many wind hot spots likely exist in the region but
distance to grid tie-ins may add significant cost. These sites are worth
considering because of the potentially valuable of the wind resource.
Examples of potential hot spots include China Cap (predicted Class 4 to
Class 5), Cinnabar Mountain (predicted Class 7), Snake Lake Mountain
(predicted Class 7).
iii. NETC has a letter of intent with Ameresco, Inc. develop an advanced
feasibility study to construct wind turbines with diesel integration.
c. Land use, permitting, and environmental analysis: NETC has cultivated an
understanding from land owners and other stakeholders about the needs for this
wind project. Such stakeholders include Choggiung Ltd (land holder), BBAHC,
and the City of Dillingham.
d. Preliminary design analysis and cost: (see attached “Basic Study of Renewable
Energy Alternatives for Electricity Generation in Dillingham/Aleknagik Region”
prepared by Tom Marisk UAF Bristol Bay Environmental Lab)
e. Cost of energy and market analysis: (see attached “Basic Study of Renewable
Energy Alternatives for Electricity Generation in Dillingham/Aleknagik Region”)
f. Simple economic analysis: Preliminary economic analysis and energy cost/benefit
analysis is complete and demonstrates that two 225 kw turbines have the best
payback period of all scenarios analyzed. (Ameresco)
g. Final report and recommendations: Contractor supplied NETC with final report
with projected costs and recommendations to proceed with wind project.
(Ameresco and Marsik reports
2) Feasibility and Conceptual Design:
a. Project scoping and contractor solicitation. Based on an AEA wind data study
conducted from 2005 – 2006 it was concluded that wind offered a viable
renewable energy source. Next, Ameresco, Inc. submitted a price proposal for
the design and installation of the wind turbines in response a request from
NETC’s Board of Directors.
b. Detailed energy resource analysis:
Energy production has been measured at the Kanakanak site and shows there is
enough wind for commercial turbines. (Table 1). Further the wind was appraisal
using published wind maps (AEA) that used computer modeling.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 20 of 23 Nushagak Community Wind Power Project
Table 1. Wind data from Kanakanak site collected from 2006 to 2007
Hub Height Wind Speed Min. wind Max Wind Mean energy
(kW/hr/m2/yr
20 5.00 0.40 22.4 1,293
30 5.62 0.40 23.4 1,846
Table 2 shows the estimated energy output in KwHrs/yr using reference date from the
Kanakanak met tower (no. 2259)
Table 2. Estimated Aeronautics29 turbine output at 95% availability at the Kanakanak site
Turbine
Aeronautics29
Wind
speed
(m/s)
Time at
zero
output (%)
Time at
rated
output
Mean net
power
output
Mean net
energy
output
Capacity
factor
At 40 meters 6.09 15.2 1.5 50.2 439,650 22.3
At 50 meters 6.28 14.1 1.8 54.0 473,631 24.0
Data from AMERSCO 2010
c. Identification of land and regulatory issues: Choggiung LTD presently owns the
real estate that the proposed wind turbine is to be located. A consultation with
Choggiung LTD, and their board, has indicated that there should be no issues
drawing up a cost effective lease agreement for the land-use for wind turbines
d. Permitting and environmental analysis: All required permits have been identified;
from a preliminary review/assessment there should not be any environmental or
land use issues to hinder the proposed project (see sections 4.3.3 and 4.3.4)
e. Detailed analysis of existing and future energy costs and markets: The current
costs of diesel electrical power production are compared to the capital for
infrastructure, operations, and maintenance costs of wind technology, thus at this
point it has been concluded that a Kanakanak wind power project has a 10 to 20
year payback period, thus is a viable, cost-effective option (Ameresco Report
2010)
f. Assessment of alternatives: Other energy resources have been investigated in the
Dillingham region including hydroelectric in the Wood Tikchik State Park, peat,
biomass (municipal waste and wood), and tidal. (see Marsik’s 2009 report)
g. Conceptual design analysis and cost estimate: The renewable energy system
proposes two 225 kw Aeronautica 29 wind turbines or equivalent (450 kW gross
output) to be installed at 50m hub height at the Kanakanak site.
A wind turbine output comparison was conducted on:
WT50S, 30 hub height
WT50S, 40 hub height
NW100/21, 37 m hub height
Aeronautica 29-255, 40 m hub height
Aeronautica 29-255, 50 m hub height
The results are included in the attached “Price Proposal” prepared by Ameresco,
Inc.
h. Detailed economic and financial analysis:
The installation of two turbines will deliver annually up to 900 mega watt hours of
electric power and replace more than 64 thousand gallons of diesel fuel.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 21 of 23 Nushagak Community Wind Power Project
Anticipated annual revenue (based on i.e. a Proposed Power Purchase
Agreement price, RCA tariff, or avoided cost of fuel based rate): $0.1781 kwh at
897mwh/yr = $159,756 – O&M of $4,000 = $155,756 over 15 years = $2,336,340
Replace more than 64,000 gallons of diesel fuel annually with diesel cost at
$2.50/gal = $160,000 ($3,320,000 over 20 years)
diesel cost at $3.50/gal = $224,000 ($4,480,000 over 20 years
diesel cost at $4.00/gal = $256,000 ($5,120,000 over 20 years)
Potential annual fuel displacement (gal and $) over the lifetime of the evaluated
renewable energy project: 160,000 gallons/yr at $2.53/gallon (2010) for 15 years
= 2.4 million gallons.
i. Conceptual business and operations plans: These will be completed as part of the
design process. Final plans should be ready by May 2011
j. Final report and recommendations: The proposed Nushagak Community W ind
Power Project was presented to the community on Sept. 2, 2010 in the Dillingham
City Council chambers.
SECTION 8– LOCAL SUPORT
Discuss what local support or possible opposition there may be regarding your project. Include
letters of support from the community that would benefit from this project.
Local agencies in support of the Nushagak Community Wind Project include Bristol Bay Area
Health Corp., Bristol Bay Economic Development Corp., Chogguing Ltd, City of Dillingham,
Curyung Tribal Council, and UAF BBC. All NETC members would benefit from the added energy
security, cleaner air, and diesel savings this wind project will provide. One local company,
Chogguing Ltd., has already invested in a 15 kW wind turbine in downtown Dillingham which as
a projected payback period of 6 years. The UAF Bristol Bay Campus has invested heavily in
renewable energy education and started a “Sustainable Energy Initiative” in 2009. On 2-Sept-
2010 the Nushagak Community Wind Power Project was presented to the Dillingham City
Council where it was enthusiastically supported.
The consumption of fossil fuels for electricity, heating, and transportation has increased
significantly in rural Alaska over the last 5 years. This volatile pricing has limited economic
investment in the community. Further the increased use of fossil fuels results many undesirable
environmental influences including global warming, ocean acidity, acid rain, and water pollution.
Because of these negative environmental effects NETC realizes the need to reduce fossil fuel
use and is initiating a number of policies and programs including this wind project. NETC see this
project as a major step towards reducing its fossil fuel dependency and to promote investments
for a sustainable energy future.
In addition to the electrical energy produced and the deferred diesel cost, the project will serve
as an important education tool for sustainable development. The heavy use of fossil fuels in rural
Alaska is an issue of major concern as most communities are 100% dependent on diesel. The
ever increasing cost of diesel significantly increases the cost of living as well as creating a
difficult climate for economic growth and community development.
In 2008, AEA awarded Bristol Bay Area Health Corp (BBAHC) $100,000 in grant funds to
investigate the potential of wind as an energy source in the larger Dillingham regional area. This
larger wind study is still ongoing.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 22 of 23 Nushagak Community Wind Power Project
SECTION 9 – GRANT BUDGET
Tell us how much you want in grant funds Include any investments to date and funding sources,
how much is being requested in grant funds, and additional investments you will make as an
applicant.
Include an estimate of budget costs by milestones using the form – GrantBudget3.doc
Provide a narrative summary regarding funding sources and your financial commitment to the
project.
NETC will provide ten percent matching funds for this project. Funding for this match will come
from general NETC funds provided by ratepayers. O&M cost will be paid through general
Nushagak funds.
Renewable Energy Fund
Grant Application Round IV
AEA11-005 Grant Application Page 23 of 23 Nushagak Community Wind Power Project
SECTION 9 – ADDITIONAL DOCUMENTATION AND CERTIFICATION
SUBMIT THE FOLLOWING DOCUMENTS WITH YOUR APPLICATION:
A. Contact information, resumes of Applicant’s Project Manager, key staff, partners,
consultants, and suppliers per application form Section 3.1 and 3.4.
B. Cost Worksheet per application form Section 4.4.4.
C. Grant Budget Form per application form Section 9.
D. Letters demonstrating local support per application form Section 8.
E. An electronic version of the entire application on CD per RFA Section 1.6.
F. Authorized Signers Form.
G. Governing Body Resolution or other formal action taken by the applicant’s governing body
or management per RFA Section 1.4 that:
- Commits the organization to provide the matching resources for project at the match
amounts indicated in the application.
- Authorizes the individual who signs the application has the authority to commit the
organization to the obligations under the grant.
- Provides as point of contact to represent the applicant for purposes of this application.
- Certifies the applicant is in compliance with applicable federal, state, and local, laws
including existing credit and federal tax obligations.
H. CERTIFICATION
The undersigned certifies that this application for a renewable energy grant is truthful
and correct, and that the applicant is in compliance with, and will continue to comply
with, all federal and state laws including existing credit and federal tax obligations.
Print Name Frank Corbin
Signature
Title
Date