Renewable Energy Fund Round 4
Project Cost/Benefit Worksheet
RFA AEA11-005 Application Cost Worksheet Page 1 7-21-10
Please note that some fields might not be applicable for all technologies or all project
phases. The level of information detail varies according to phase requirements.
1. Renewable Energy Source
The Applicant should demonstrate that the renewable energy resource is available on a
sustainable basis.
Annual average resource availability. 59,000 acres of timber land within 10 miles of site.
Dedication of 1,400 acres of the borough owned
timber land will result in an 80-100 year rotation.
Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel)
2. Existing Energy Generation and Usage
a) Basic configuration (if system is part of the Railbelt1 grid, leave this section blank)
i. Number of generators/boilers/other Fuel oil fired boiler
ii. Rated capacity of generators/boilers/other 2957 MBH output
iii. Generator/boilers/other type Burnham V-11 series Oil
iv. Age of generators/boilers/other One year old
v. Efficiency of generators/boilers/other 85%
b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank)
i. Annual O&M cost for labor
ii. Annual O&M cost for non-labor
c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the
Railbelt grid, leave this section blank)
i. Electricity [kWh]
ii. Fuel usage
Diesel [gal]
Other
iii. Peak Load
iv. Average Load
v. Minimum Load
vi. Efficiency
vii. Future trends
d) Annual heating fuel usage (fill in as applicable)
i. Diesel [gal or MMBtu] 25,964 gallons
ii. Electricity [kWh]
iii. Propane [gal or MMBtu]
iv. Coal [tons or MMBtu]
v. Wood [cords, green tons, dry tons]
1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric
Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power.
Renewable Energy Fund Round 4
Project Cost/Benefit Worksheet
RFA AEA11-005 Application Cost Worksheet Page 2 7-21-10
vi. Other
3. Proposed System Design Capacity and Fuel Usage
(Include any projections for continued use of non-renewable fuels)
a) Proposed renewable capacity
(Wind, Hydro, Biomass, other)
[kW or MMBtu/hr]
1,400 acres of dedicated timberland sustainably harvested
and replanted would heat the school in perpetuity.
b) Proposed annual electricity or heat production (fill in as applicable)
i. Electricity [kWh]
ii. Heat [MMBtu] 0.95
c) Proposed annual fuel usage (fill in as applicable)
i. Propane [gal or MMBtu]
ii. Coal [tons or MMBtu]
iii. Wood [cords, green tons, dry tons] 253 cords
iv. Other
4. Project Cost
a) Total capital cost of new system 750,000
b) Development cost
c) Annual O&M cost of new system 9,463
d) Annual fuel cost 50,600
5. Project Benefits
a) Amount of fuel displaced for
i. Electricity
ii. Heat 20,800
iii. Transportation
b) Current price of displaced fuel 58,448
c) Other economic benefits
d) Alaska public benefits Renewable energy education
6. Power Purchase/Sales Price
a) Price for power purchase/sale
7. Project Analysis
a) Basic Economic Analysis
Project benefit/cost ratio 0.79
Renewable Energy Fund Round 4
Project Cost/Benefit Worksheet
RFA AEA11-005 Application Cost Worksheet Page 3 7-21-10
Payback (years) 25