ProjectSchedule
IDTask NameDurationStartFinish1Issue Notice to Proceed1 day?Thu 7/1/10Thu 7/1/102FERC Permit30 daysFri 7/2/10Thu 8/12/103Environmental Studies246 days?Fri 8/13/10Fri 7/22/114Winter Flow Study (2) sites143 daysMon 9/6/10Wed 3/23/115Summer Flow Study (4) sites90 daysThu 3/24/11Wed 7/27/11678Turbine Design42 daysFri 7/2/10Mon 8/30/109Order Turbine Components47 daysTue 8/31/10Wed 11/3/1010Turbine testing30 daysThu 11/4/10Wed 12/15/1011Order Gear Box Components45 daysTue 8/31/10Mon 11/1/1012Gear Box testing30 daysTue 11/2/10Mon 12/13/10131450 kW ESP Generator Prototype Start1 dayThu 12/16/10Thu 12/16/101550 KW Equipment Order79 days?Fri 12/17/10Wed 4/6/1116Barge Test 50 kW Prototype32 daysThu 4/7/11Fri 5/20/111718Tanana River Testing93 daysMon 5/23/11Wed 9/28/111920500 kW ESP Generator Equipment Order60 days?Thu 12/16/10Wed 3/9/1121500 KW Prototype Test, Barge/Verdigris?10 daysThu 4/7/11Wed 4/20/112223King Platform Permit25 daysThu 7/28/11Wed 8/31/1124Install 500 KW on King Platform11 daysThu 9/1/11Thu 9/15/112526Canned ESP Booster Order79 daysFri 12/17/10Wed 4/6/1127Canned ESP Booster Install5 daysThu 5/19/11Wed 5/25/112829500 KW ESP Generator Prototype Test200 daysFri 9/16/11Thu 6/21/127/1ChevronDTATerrasondTerrasondCentrilift,UAFCentriliftCentrilift,UAFCentriliftCentrilift12/16CentriliftUAFCentrilift,UAFCentriliftCentriliftChevronCentriliftChevronCentrilift51627718299201122331425617288193010214152661728920311122314255162771829102111223415266172881921324415267182992011223314255162781930102121324415266172810211122341526617289Jul 12Aug 9Sep 6Oct 4,Nov 1Nov 2Dec 2Jan 2Feb 2Mar 2Apr 1May 1Jun 1Jul 11Aug 8Sep 5Oct 3,Oct 3Nov 2Dec 2Jan 2Feb 2Mar 2Apr 1May 1Jun 1Jul 10Aug 7Sep 4Oct 2,Oct 3Nov 2Dec 2Jan 2Feb 1Mar 1Apr 1May 1Jun 1JTaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePage 1Project: ESP Generator Project1Date: Tue 11/10/09