HomeMy WebLinkAboutA0_Tenakee_scheduleIDTask NameDurationStartFinish1Task 1 Project Scoping & Contractor Solicitation300 daysTue 7/6/10Mon 8/29/112Task 2 Resource Indification & Analysis315 days?Mon 7/19/10Fri 9/30/113Fieldwork - geology, geochemistry, & geophysics90 days?Mon 7/19/10Fri 11/19/104Drilling 2 wells85 days?Mon 6/6/11Fri 9/30/115Task 3 Land Use, Permitting, & Environmental Analysis328 days?Wed 7/7/10Fri 10/7/116Task 4 Preliminary Design Analysis & Cost215 days?Mon 1/3/11Fri 10/28/117Task 5 Cost of Energy & Market Analysis35 days?Mon 9/12/11Fri 10/28/118Task 6 Simple Economic Analysis35 days?Mon 10/3/11Fri 11/18/119Task 7 Final Report & Recommendations55 days?Mon 10/3/11Fri 12/16/11Qtr 2Qtr 3Qtr 4Qtr 1Qtr 2Qtr 3Qtr 4Qtr 120112012TaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePage 1RECONNAISSANCE STUDYTENAKEE INLETGEOTHERMAL RESOURCE