HomeMy WebLinkAbout07 Attachment H Prelim Constr ScheduleIDTask NameDurationStartFinish1Phase III - Finalize Design99 daysMon 11/9/09Thu 4/1/102Develop design to 95% level30 daysMon 11/9/09Mon 12/21/093Submit to AEA for review/approval7 daysTue 12/22/09Tue 1/5/104Submit to CRSD for review/approval7 daysWed 1/6/10Thu 1/14/10595% Design Complete0 daysThu 1/14/10Thu 1/14/106Submit to Fire Marshall for review and finalize 100%Issued For Construction plan set45 daysFri 1/15/10Thu 3/18/107Finalize 100% issued for construction plan set10 daysFri 3/19/10Thu 4/1/108Approval to Construct Issued0 daysThu 4/1/10Thu 4/1/109Round 3 Appropriation and Notice to Proceed withpreliminary procurement0 daysThu 7/1/10Thu 7/1/1010Phase IV - Construction165 daysFri 7/2/10Mon 1/24/1111Begin Procurement (issue solitations for boilers andcontractors30 daysFri 7/2/10Fri 8/6/1012Contractor/vendor selection and award14 daysMon 8/9/10Tue 8/24/1013Materials arrive on site30 daysWed 8/25/10Wed 9/29/1014Project kickoff meeting0 daysMon 9/13/10Mon 9/13/1015Site work begins0 daysMon 9/13/10Mon 9/13/1016Building & silo shells completed30 daysMon 9/13/10Sat 10/16/1017Trenching and piping6 daysMon 10/18/10Sat 10/23/1018Begin inside mechanical work20 daysMon 10/25/10Tue 11/16/1019Site electrical20 daysMon 11/8/10Fri 12/3/1020Integration & testing4 daysSat 12/4/10Wed 12/8/1021Final inspection, acceptance, commissioning, andstartup3 daysThu 12/9/10Sat 12/11/1022Operations reporting5 daysThu 12/9/10Tue 12/14/1023Project closeout30 daysMon 12/13/10Mon 1/24/111/144/17/19/139/1311/11/11/11/12/12/12/12/1/31/11/11/21/32/72/12/22/23/73/13/23/24/44/14/14/25/25/95/15/25/36/66/16/26/27/47/17/17/28/18/88/18/28/29/59/19/19/210/10/10/10/10/11/11/11/11/12/12/12/12/1/21/91/11/21/3 '09Dec '09Jan '10Feb '10Mar '10Apr '10May '10Jun '10Jul '10Aug '10Sep '10Oct '10Nov '10Dec '10Jan '11F20102011TaskMilestoneSummaryCopper River School DistrictKenny Lake School Wood Pellet Heating SystemPreliminary Construction ScheduleAttachment HPage 1Project: Kenny Lake Wood Pellet District Heating SystemDate: Mon 11/9/09091110 Kenny Lake School Wood Pellet Prelim Constr Schedule.mpp