HomeMy WebLinkAbout06 Attachment G Prelim ScheduleIDTask NameDurationStartFinish1Phase I - Reconnaissance Complete0 daysFri 10/31/08Fri 10/31/082Grant Award and NTP from AEA0 daysFri 9/10/10Fri 9/10/103Phase II - Feasibility Study / ConceptualDesign (35%)151 daysMon 9/13/10Fri 4/15/114Project scoping and consultant solicitation30 daysMon 9/13/10Fri 10/22/105Perform engineering analysisfeasibility study86 daysMon 10/25/10Fri 2/25/116Prepare detailed energy resourceanalysis30 daysMon 10/25/10Tue 12/7/107Identify land and regulatory issues30 daysMon 10/25/10Tue 12/7/108Preliminary permitting andenvironmental analysis30 daysMon 10/25/10Tue 12/7/109Detailed analysis of existing andfuture energy costs and markets30 daysMon 10/25/10Tue 12/7/1010Assessment of alternatives10 daysWed 12/8/10Tue 12/21/1011Prepare conceptual design analysisand cost estimate20 daysWed 12/22/10Thu 1/20/1112Detailed economic and financialanalysis10 daysFri 1/21/11Thu 2/3/1113Submit draft feasibility study to AEAfor review/comment5 daysFri 2/4/11Thu 2/10/1114Submit draft feasibility study to HCSfor review/comment7 daysFri 2/11/11Mon 2/21/1115Finalize report and recommendations4 daysTue 2/22/11Fri 2/25/1116Issue final Feasibility Study document0 daysFri 2/25/11Fri 2/25/1117Conceptual Design35 daysMon 2/28/11Fri 4/15/1118Develop design to 35% level20 daysMon 2/28/11Fri 3/25/1119Submit 35% design to AEA for review/ comment / approval5 daysMon 3/28/11Fri 4/1/1120Submit 35% design to HCS / PublicReview and Comment7 daysMon 4/4/11Tue 4/12/1121Issue 35% Concept Design plan set3 daysWed 4/13/11Fri 4/15/119/102/254/158/299/59/129/199/2610/30/10/10/20/311/71/11/21/212/52/12/12/21/21/91/161/231/302/62/132/202/273/63/133/203/274/34/104/174/24Sep '10Oct '10Nov '10Dec '10Jan '11Feb '11Mar '11Apr '112011TaskSplitProgressMilestoneSummaryHoonah City School District Hoonah City Schools Proposed Wood-fired Hydronic Heating SystemPreliminary Feasibility Study ScheduleAttachment GPage 1Project: Hoonah Wood-fired Hydronic Heating SystemDate: Tue 11/10/09