HomeMy WebLinkAboutCEA Transmission Line Signed AEA Grant Application - 11-10-09ALASKA Renewable Energy Fund Round 3
/ c, ENERGY AUTHORITY Grant Application
Application Forms and Instructions
The following forms and instructions are provided to assist you in preparing your application for
a Renewable Energy Fund Grant. An electronic version of the Request for Applications (RFA)
and the forms are available online at: http://www.akenergyauthority.org/RE Fund-Ill.html
Grant Application
GrantApp3.doc
Application form in MS Word that includes an outline of
Form
information required to submit a complete application.
Applicants should use the form to assure all information is
provided and attach additional information as required.
Application Cost
Costworksheet3
Summary of Cost information that should be addressed by
Worksheet
doc
applicants in preparing their application.
Grant Budget
GrantBudget3.d
A detailed grant budget that includes a breakdown of costs by
Form
oc
milestone and a summary of funds available and requested to
complete the work for which funds are being requested.
Grant Budget
GrantBudgetlnst
Instructions for completing the above grant budget form.
Form Instructions
ructions3. df
• If you are applying for grants for more than one project, provide separate application
forms for each project.
• Multiple phases for the same project may be submitted as one application.
• If you are applying for grant funding for more than one phase of a project, provide
milestones and grant budget for completion of each phase.
• If some work has already been completed on your project and you are requesting
funding for an advanced phase, submit information sufficient to demonstrate that the
preceding phases are satisfied and funding for an advanced phase is warranted.
• If you have additional information or reports you would like the Authority to consider in
reviewing your application, either provide an electronic version of the document with
your submission or reference a web link where it can be downloaded or reviewed.
REMINDER:
• Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials
submitted to the Authority may be subject to disclosure requirements under the act if no
statutory exemptions apply.
• All applications received will be posted on the Authority web site after final
recommendations are made to the legislature.
• In accordance with 3 AAC 107.630 (b) Applicants may request trade secrets or
proprietary company data be kept confidential subject to review and approval by the
Authority. If you want information is to be kept confidential the applicant must:
o Request the information be kept confidential.
o Clearly identify the information that is the trade secret or proprietary in their
application.
o Receive concurrence from the Authority that the information will be kept
confidential. If the Authority determines it is not confidential it will be treated as a
public record in accordance with AS 40.25 or returned to the applicant upon
request.
AEA 10-015 Application Page 1 of 15 10/7/2009
ALASKA
Renewable Energy Fund
Grant Application Round 3
SECTION 1 —APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
Chugach Electric Association, Inc.
Type of Entity:
Electric Utility (Cooperative)
Mailing Address
Physical Address
P.O. Box 196300
5601 Electron Drive
Anchorage, Ak 99519-6300
Anchorage, Ak 99519
Telephone
Fax
Email
(907) 762-4759
907 762.4688
ron vecem@chugachelectric.com
1.1 APPLICANT POINT OF CONTACT
Name
Title
Ronald K. Vecera
Director of Project Development
Mailing Address
P.O. Box 196300
Anchorage, Ak 99519-6300
Telephone i
Fax
Email
(907) 762-4759
(907) 762-4688
ron_vecera@chugachelectric.com
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
X
An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
An independent power producer in accordance with 3 AAC 107.695 (a) (1), or
A local government, or
A governmental entity (which includes tribal councils and housing authorities);
1.2.2. Attached to this application is formal approval and endorsement for its project by
its board of directors, executive management, or other governing authority. If the
Yes
applicant is a collaborative grouping, a formal approval from each participant's
governing authority is necessary. (Indicate Yes or No in the box )
1.2.3. As an applicant, we have administrative and financial management systems and
Yes
follow procurement standards that comply with the standards set forth in the grant
agreement.
Yes
1.2.4. If awarded the grant, we can comply with all terms and conditions of the attached
grant form. (Any exceptions should be clearly noted and submitted with the
application.)
Yes
1.2.5 We intend to own and operate any project that may be constructed with grant
funds for the benefit of the general public.
AEA10-015 Grant Application Page 2 of 15 10/7/2009
ALASKA 41c) Renewable Energy Fund
amp
/CIIED ENERGY AUTHORITY Grant Application Round 3
SECTION 2 — PROJECT SUMMARY
This is intended to be no more than a 1-2 page overview of your project.
2.1 Project Title — (Provide a 4 to 5 word title for your project)
Transmission Line to Renewable Energy Resources
2.2 Project Location —
Include the physical location of your project and name(s) of the community or communities that will
benefit from your project.
This project will determine the routing and design for a transmission line to connect a potential
geothermal energy resource (Mt. Spurr) and a potential hydro resource (Lake Chakachamna) to
the existing Railbelt system. Both of these potential resources are on the west side of Cook Inlet
and the closest interconnection point is at Chugach's Beluga power plant. The nearest
community to the project is the Native Village of Tyonek. The communities that could benefit
from the project include all of the communities served by the Railbelt utilities.
2.3 PROJECT TYPE
Put in boxes as appropriate
2.3.1 Renewable Resource Type
Wind
Biomass or Biofuels
Hydro, including run of river
X
Transmission of Renewable Energy
Geothermal, including Heat Pumps
Small Natural Gas
Heat Recovery from existing sources
Hydrokinetic
Solar
Storage of Renewable
Other (Describe)
2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply)
Reconnaissance
X
Design and Permitting
X
Feasibility
Construction and Commissioning
Conceptual Design
2.4 PROJECT DESCRIPTION
Provide a brief one paragraph description of your proposed project.
Chugach is proposing to begin the process of route selection and permitting for a new
transmission line linking the potential geothennal renewable energy resource at Mt. Spurr to the
existing Chugach system. The project would include one or more high voltage transmission lines
which will connect to the existing substation and transmission lines at Beluga. The line would
be built for a maximum operating voltage of 230kV but could be initially operated at a lower
voltage to match first stage development of 50 MW of the geothermal project. The line would
cover a distance of at least 40 miles, depending on the routing. The initial phase would
investigate feasible routes and select a preferred route, including permitting and right of way
AEA10-015 Grant Application Page 3 of 15 10/7/2009
ALASM
INED
Renewable Energy Fund
Grant Application Round 3
acquisition. While Chugach would own and operate the line, all purchasers (presumably all
Railbelt utilities) would be able to access the renewable energy. The line would be designed to
also accommodate the development of a hydro resource at Lake Chakachamna.
2.5 PROJECT BENEFIT
Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel
costs, lower energy costs, etc.)
Assessment of the geothermal resource potential at Mt. Spurr is taking place by Ormat
Technologies. Geothermal is a renewable resource that would offset fossil fuel generated
electricity for the entire Railbelt. This would lower fael costs, lower carbon emissions and
enhance rate stability. It would also help diversify the mix of generation resources for the
Railbelt and ameliorate the impact of declining Cook Inlet natural gas supply and deliverability.
It its 2008 AEA renewable energy grant application, Ormat quantified the benefit of geothermal
energy production. Ormat asserted savings, assuming a 50 MW plant, of 900,000 barrels of oil
and reduced carbon emissions of 250,000 tons over the 30 year project life. The project is
believed to have a resource potential of 50 to 150 MW.
Geothermal energy from Mt. Spurr (and any future hydro from Lake Chakachamna) will only be
accessible to Railbelt utilities if there is a transmission link from the new generation to
Chugach's existing system. The proposed link will provide for the reliable transport of new
renewable, base load energy to the interconnected systems of Alaska's Railbelt and allow all
participating utilities to realize the benefits listed above.
2.6 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source
of other contributions to the project.
Phase 1 of the project would consist of:
- Route selection and preliminary design estimated to cost approximately $550,000, and
- Assessment of permit requirements estimated to cost approximately $50,000.
- Chugach will provide an estimated $20,000 of project supervision and other labor to
manage these tasks and secure agreement from participants on the route.
AEA10-015 Grant Application Page 4 of 15 10/7/2009
/c ALASKA Renewable Energy Fund
GMED ENERGY AUTHORrrY Grant Application Round 3
Phase 2 of the project would consist of:
Acquisition of permits and rights -of -way estimated to cost approximately $300,000, and
Geotechnical/survey work and final design, estimated to cost approximately $800,000.
Chugach will provide an estimated $60,000 of project supervision and other labor to
manage these tasks and secure agreement from participants on an initial and final
configuration.
Funding for Phase 1 and Phase 2 in the amount of $1.7 million is the subject of this grant
request. If one or both of the renewable energy projects prove viable, and construction proceeds,
the funding for this major infrastructure addition would be pursued and is expected to be a
combination of financing by participants and available grant opportunities. The construction
cost of a 45 mile transmission line is expected to be about $60 million.
2.7 COST AND BENEFIT SUMARY
Include a summary of grant request and your project's total costs and benefits below.
Grant Costs
(Summary of funds requested)
2.7.1 Grant Funds Requested in this application.
$1,700,000
2.7.2 Other Funds to be provided (Project match)
$ 80,000
2.7.3 Total Grant Costs (sum of 2.7.1 and 2.7.2)
$1,780,000
Project Costs & Benefits
(Summary of total project costs including work to date and future cost estimates to get to a fully
operational project)
2.7.4 Total Project Cost (Summary from Cost Worksheet
$61,780,000
including estimates through construction)
2.7.5 Estimated Direct Financial Benefit (Savings)
$
2.7.6 Other Public Benefit (If you can calculate the benefit in
$
terms of dollars please provide that number here and
explain how you calculated that number in your application
(Section 5.)
As mentioned above, if either of these renewable energy resources proves to be viable, the public
benefit of this project is that it allows access by all Railbelt utilities to the renewable energy. All
utilities will realize the benefits of reduced fuel costs, lower carbon emissions, conservation of
fossil fuel resources, diversification of generation resources and the economies of scale of larger
projects. While it is difficult to quantify this as a benefit of the transmission line, the line is
essential to the delivery of newly developed renewable energy.
AEA10-015 Grant Application Page 5 of 15 10/7/2009
/�ALASHKA
Renewable Energy Fund
Grant Application Round 3
SECTION 3 — PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include a resume and references
for the manager(s). If the applicant does not have a project manager indicate how you intend to
solicit project management support. If the applicant expects project management assistance
from AEA or another government entitv. state that in this section.
The Project Manager is Dora Gropp, P.E. She is a long-term Chugach Employee and a well
known expert in Transmission & Distribution construction and operations. Her professional bio
is attached. She will be supported by Chugach's extensive in-house engineering staff and the use
of qualified consulting engineers and contractors.
3.2 Project Schedule
Include a schedule for the proposed work that will be funded by this grant. (You may include a
chart or table attachment with a summary of dates below.)
Phase 1 (Feasibility): 7/1/10 to 6/30/11
Phase 2 (Design & Permitting): 7/1/11 to 6/30/13
3.3 Project Milestones
Define key tasks and decision points in your project and a schedule for achieving them. The
Milestones must also be included on your budget worksheet to demonstrate how you propose to
manage the project cash flow. (See Section 2 of the RFA or the Budget Form.)
Comprising the project phases identified previously, the following decision points have been
identified and are included on the project worksheets:
- Route selection reporUAgreement on preferred route by all participants
- Assessment of permit requirements
- Agreement on initial and final configuration of the line by all participants
- All permits and rights -of -way acquired
- Geotechnical, Survey and Final design
3.4 Project Resources
Describe the personnel, contractors, equipment, and services you will use to accomplish the
project. Include any partnerships or commitments with other entities you have or anticipate will
be needed to complete your project. Describe any existing contracts and the selection process
you may use for major equipment purchases or contracts. Include brief resumes and references
for known, key personnel, contractors, and suppliers as an attachment to your application.
AEA10-015 Grant Application Page 6 of 15 10/7/2009
/ALASKA Renewable Energy Fund
GEE) ENERGY AUTHORITY Grant Application Round 3
Chugach has in-house expertise in its Transmission Services department and its project manager
is knowledgeable in transmission line projects and very capable of managing the processes
described in this application. Engineering Services for route selection, permitting and design
will be performed by consultants, who will be selected through a qualification/RFP process. All
materials and construction will be purchased through competitive bidding.
3.5 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
Chugach will prepare monthly status reports as well as budget reports to accompany requests for
grant funds.
3.6 Project Risk
Discuss potential problems and how you would address them.
The project features and schedule will be driven by the renewable energy projects it will serve.
Basic feasibility and route selection can be determined independently from these projects. Line
configuration and installation schedules will depend heavily on the timing of the renewable
energy projects. Final design, material procurement and construction will be closely coordinated
with the other parties. We will adopt a design which will allow scaling the project to the size of
the generation project it serves to the start of construction.
Cost overruns can occur due to delays, late design changes and unanticipated field conditions.
Extensive field work will be directed to capture field conditions. Close coordination with
participants will avoid late design changes as well as delays.
Natural events such as floods, volcanic activity or earthquakes can also lead to delays. Worker
safety during such events will be addressed at every stage of the project.
Participant change is a risk that can be an opportunity or a threat. Loss of a participant shifts
funding burdens to the remaining ones. The vicinity of coal resources may also allow other
participants to join and supplement funding.
AEA10-015 Grant Application Page 7 of 15 10/7/2009
/c ALASKA Renewable Energy Fund
� ENERGY AUTHORITY Grant Application Round 3
SECTION 4 — PROJECT DESCRIPTION AND TASKS
• Tell us what the project is and how you will meet the requirements outlined in Section 2 of
the RFA.
• The level of information will vary according to phase(s) of the project you propose to
undertake with grant funds.
• If you are applying for grant funding for more than one phase of a project provide a
plan and grant budget form for completion of each phase.
• If some work has already been completed on your project and you are requesting funding for
an advanced phase, submit information sufficient to demonstrate that the preceding phases
are satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project.
A grant application submitted to AEA in November 2008 by Ormat Technologies (leaseholder for
the potential geothermal resource at Mt. Spurr) indicated a proposed development of a 50 to 150
MW project. TDX Power, Inc. is working to develop Lake Chakachamna. Chugach's proposed
project would connect these new energy resources to the existing Chugach system.
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about
the number, size, age, efficiency, and type of generation.
There is currently no existing energy system at Mt. SptuT or Lake Chakachamna.
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of
any impact the project may have on existing energy infrastructure and resources.
No existing energy resources are currently being used at Mt. Spurr or Lake Chakachamna.
Chugach's proposed project will extend the transmission system to these projects so that
renewable energy resources that are developed can be delivered to Railbelt utilities.
4.2.3 Existing Energy Market
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
The existing energy market consists of the Railbelt utilities and the communities they serve. The
AEA10-015 Grant Application Page 8 of 15 10/7/2009
lORITY
� AENELASHKA
Renewable Energy Fund
Grant Application Round 3
existing load is primarily residential and commercial. Electrical energy needs are met with
generation that is primarily natural gas, supplemented by hydro, and also by coal and diesel in the
Fairbanks area. Successful development of renewable energy resources will allow diversification
of the generation mix for existing customers and provide a source of renewable and stable priced
energy for years to come. It would also reduce the need for scarcer natural gas supplies to be
used for power generation.
4.3 Proposed System
Include information necessary to describe the system you are intending to develop and address
potential system design, land ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
• A description of renewable energy technology specific to project location
• Optimum installed capacity
• Anticipated capacity factor
• Anticipated annual generation
• Anticipated barriers
• Basic integration concept
• Delivery methods
The system design is for the transmission link to newly developed renewable energy sources. The
number of circuits, voltage level and conductor size will be dictated by development of the
renewable energy projects. The geothermal project can be served by a single 138kV transmission
line in its initial configuration of 50 MW. Larger development of this resource and/or the
Chakachamna hydro plant would require a double circuit at 230kV to provide adequate capacity
and reliability.
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the
project or how you intend to approach land ownership and access issues.
To be determined during Phase 1 of the project.
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
• List of applicable permits
• Anticipated permitting timeline
• Identify and discussion of potential barriers
AEA10-015 Grant Application Page 9 of 15 10/7/2009
ALASKA
Renewable Energy Fund
Grant Application Round 3
To be determined during Phase 1 of the project.
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will
be addressed:
• Threatened or Endangered species
• Habitat issues
• Wetlands and other protected areas
Archaeological and historical resources
• Land development constraints
• Telecommunications interference
• Aviation considerations
• Visual, aesthetics impacts
• Identify and discuss other potential barriers
To be determined during Phase 1 of the project.
4.4 Proposed New System Costs and Projected Revenues
(Total Estimated Costs and Projected Revenues)
The level of cost information provided will vary according to the phase of funding requested and
any previous work the applicant may have done on the project. Applicants must reference the
source of their cost data. For example: Applicants Records or Analysis, Industry Standards,
Consultant or Manufacturer's estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of
the project. Cost information should include the following:
• Total anticipated project cost, and cost for this phase
• Requested grant funding
• Applicant matching funds — loans, capital contributions, in -kind
• Identification of other funding sources
• Projected capital cost of proposed renewable energy system
See section 2 and grant/budget forms. Chugach has constructed several transmission lines and
has the experience and knowledge to rough estimate transmission line costs based on the terrain
and their length.
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by
the applicant.
(Note: Operational costs are not eligible for grant funds however grantees are required to meet
ongoing reporting requirements for the purpose of reporting impacts of projects on the
communities they serve.)
AEA10-015 Grant Application Page 10 of 15 10/7/2009
ALASKA
Renewable Energy Fund
ENERGY AUTHORITY Grant Application Round 3
Maintenance of the transmission line is estimated at $250,000 per year. This expense would be
funded through the rate structure applicable to project participants.
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
• Identification of potential power buyer(s)/customer(s)
• Potential power purchase/sales price - at a minimum indicate a price range
Not applicable.
4.4.4 Project Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered
in evaluating the project.
Download the form, complete it, and submit it as an attachment. Document any conditions or
sources your numbers are based on here.
The Project Cost/Benefit worksheet is not applicable. Costs and benefits are in the context of a
transmission line to deliver the renewable energy projects (Mt. Spurr geothermal, Chakachamna
hydro) that are currently in progress on the west side of Cook Inlet. The renewable energy
projects allow stable priced renewable energy to be used to displace fossil fueled energy. This
conserves the fuel resources, reduces carbon emissions, diversifies the generation mix, etc. These
benefits are substantial. While they result from the development of the geothermal or hydro
renewable energy systems, the proposed transmission line is essential to realize these benefits.
SECTION 5— PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings,
and how the people of Alaska will benefit from the project.
The benefits information should include the following:
• Potential annual fuel displacement (gal and $) over the lifetime of the evaluated
renewable energy project
• Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or cost based rate)
• Potential additional annual incentives (i.e. tax credits)
• Potential additional annual revenue streams (i.e. green tag sales or other renewable
energy subsidies or programs that might be available)
• Discuss the non -economic public benefits to Alaskans over the lifetime of the project
The primary benefit will be the delivery of renewable energy. The value of geothermal energy,
as estimated by Orniat, was previously cited. For this project (and Chakachamna) to be
developed there must be a path to get the energy to the market. The proposed project is the
essential link to do so. In addition to allowing the delivery of clean, stably priced renewable
AEA10-015 Grant Application Page 11 of 15 10f7/2009
/ ALAS KA
Renewable Energy Fund
mil ENERGY AUTHORITY Grant Application Round 3
energy, this project will also benefit Alaskans by helping to conserve available supplies of natural
gas.
SECTION 6— SUSTAINABILITY
Discuss your plan for operating the completed project so that it will be sustainable.
Include at a minimum:
• Proposed business structure(s) and concepts that may be considered.
• How you propose to finance the maintenance and operations for the life of the project
• Identification of operational issues that could arise.
• A description of operational costs including on -going support for any back-up or existing
systems that may be require to continue operation
• Commitment to reporting the savings and benefits
Transmission lines have a design life of 40 to 50 years. The proposed line would become part of
Chugach's transmission system and be operated and maintained while renewable energy projects
require the service. Operating and maintenance costs consist primarily of line losses, inspections
and replacement of damaged or wom parts. Cost recovery will occur via the rate structure
necessary to recover the net capital investment (after any grants received) and O&M expenses
associated with the transmission line.
SECTION 7 — READINESS & COMPLIANCE WITH OTHER GRANTS
Discuss what you have done to prepare for this award and how quickly you intend to proceed
with work once your grant is approved.
Tell us what you may have already accomplished on the project to date and identify other grants
that may have been previously awarded for this project and the degree you have been able to
meet the requirements of previous grants.
AEA10-015 Grant Application Page 12 of 15 10/7/2009
/ALASKA
Renewable Energy Fund
e ENERGY AUTHORITY Grant Application Round 3
Work on Phase 1 will commence as soon as grant funds are available and the results of Ormat's
2010 assessment activities indicate a continued likelihood of project development. A Request for
Proposals for Engineering Services for the route selection study can be released within 6 weeks of
funding availability.
No previous grants have been solicited or received for this project.
SECTION 8— LOCAL SUPORT
Discuss what local support or possible opposition there may be regarding your project. Include
letters of support from the community that would benefit from this project.
A letter of support was received from Homer Electric and is included in the grant application
package.
SECTION 9 — GRANT BUDGET
Tell us how much you want in grant funds Include any investments to date and funding sources,
how much is being requested in grant funds, and additional investments you will make as an
applicant.
Include an estimate of budget costs by milestones using the form — GrantBudget3. doc
Provide a narrative sunzmmy regarding funding sources and your financial commitment to the
project.
AEA10-015 Grant Application Page 13 of 15 10/7/2009
/� ALASM
Renewable Energy Fund
Grant Application Round 3
Chugach is requesting grant funding in the amount of $1.7 million. Chugach will provide in-
house labor in the estimated amount of $80,000 to manage the project and provide other support
as needed. Estimates of the costs for the initial phases of this project (feasibility, design and
permitting) are shown in the attached Grant/Budget documents.
If the geothermal resource proves viable and the transmission project proceeds to construction, a
financing plan including funding sources and financing on behalf of all participants will be
developed. Adjustments will be made based on developments at Lake Chakachamna.
AEA10-015 Grant Application Page 14 of 15 10/7/2009
ALAS KA
Renewable Energy Fund
Grant Application Round 3
SECTION 9 — ADDITIONAL DOCUMENTATION AND CERTIFICATION
SUBMIT THE FOLLOWING DOCUMENTS WITH YOUR APPLICATION:
A. Resumes of Applicant's Project Manager, key staff, partners, consultants, and
suppliers per application form Section 3.1 and 3.4.
B. Cost Worksheet per application form Section 4.4.4.
C. Grant Budget Form per application form Section 9.
D. Letters demonstrating local support per application form Section 8.
E. An electronic version of the entire application on CD per RFA Section 1.6.
F. Governing Body Resolution or other formal action taken by the applicant's
governing body or management per RFA Section 1.4 that:
- Commits the organization to provide the matching resources for project at the
match amounts indicated in the application.
- Authorizes the individual who signs the application has the authority to
commit the organization to the obligations under the grant.
- Provides as point of contact to represent the applicant for purposes of this
application.
- Certifies the applicant is in compliance with applicable federal, state, and local,
laws including existing credit and federal tax obligations.
F. CERTIFICATION
The undersigned certifies that this application for a renewable energy grant is truthful
and correct, and that the applicant is in compliance with, and will continue to comply
with, all federal and state laws including existing credit and federal tax obligations.
Print Name
Bradley W. Evans
7
Signature
Title
Chief Execu O ' er
Date
November 10, 2009
AEA10-015 Grant Application Page 15 of 15 10/7/2009