HomeMy WebLinkAboutAEA10-015 Budget - Project CostsProject Cost Investment ($000) Turbines 1,577.10$ Combustion Equipment 1,485.00$ Fuel Handling Equipment 175.00$ Buildings and Foundations $ 774.50 Misc. Control Room and Equipment $ 39.10 Site Prep $ 100.00 Balance of Plant and Installation $ 872.00 Freight 351.59$ Owners CM / Insurance $ 50.23 Working Capital $ 502.27 Enginneer and Architect $ 427.72 Start-up and Commissioning $ 50.00 Financing Fees / Construction Interest $ 185.84 Miscellaneous / Contingency $ 502.27 Total Investment $ 7,092.62 Subsidies/Grants $ 3,351,120.00 Project Development Costs ($000) Permits and Legal $ 100.00 Enginneer and Architect $ 175.00 Total Project Development Costs $ 275.00 p Costs $ 7,367.62