HomeMy WebLinkAbout10kW_PlanIDTask NameDurationStartFinish1Phase 3 (Design & Permits)70 days9/6/201012/10/20102Phase scope & Plan20 days9/6/201010/1/20103Regulatory20 days10/4/201010/29/20104Environmental Impact5 days10/4/201010/8/20105Land Use Resolution10 days10/4/201010/15/20106Permit Application20 days10/4/201010/29/20107System Design40 days10/4/201011/26/20108Phase 3 Review10 days11/29/201012/10/20109Phase 4 (Fabrication & Construction)181 days12/13/20108/22/201110Procurement & Fabrication100 days12/13/20104/29/201111Contractor Selection25 days12/13/20101/14/201112RFQ20 days12/13/20101/7/201113Review & Award5 days1/10/20111/14/201114Site Prep20 days1/17/20112/11/201115Installation20 days5/2/20115/27/201116Commissioning & Startup20 days5/30/20116/24/201117Operations Reporting1 day6/27/20116/27/201118Phase 4 Review40 days6/28/20118/22/2011AugSepOctNovDecJanFebMarAprMayJunJulAugSep0Q4 '10Q1 '11Q2 '11Q3 '11TaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePage 1Project: 10kW_PlanDate: 11/7/2009