Loading...
The URL can be used to link to this page
Your browser does not support the video tag.
Home
My WebLink
About
FH_Plan-1
IDTask NameDurationStartFinish1Phase 3 (Design & Permits)90 days9/6/20101/7/20112Phase scope & Plan20 days9/6/201010/1/20103Regulatory20 days10/4/201010/29/20104Environmental Impact20 days10/4/201010/29/20105Land Use Resolution20 days10/4/201010/29/20106Permit Application20 days10/4/201010/29/20107System Design60 days10/4/201012/24/20108Phase 3 Review10 days12/27/20101/7/20119Phase 4 (Fabrication & Construction)341 days1/10/20114/30/201210Procurement & Fabrication200 days1/10/201110/14/201111Contractor Selection80 days2/7/20115/27/201112RFQ40 days2/7/20114/1/201113Review & Award20 days5/2/20115/27/201114Site Prep80 days7/25/201111/11/201115Installation80 days11/14/20113/2/201216Commissioning & Startup30 days3/5/20124/13/201217Operations Reporting1 day4/16/20124/16/201218Phase 4 Review10 days4/17/20124/30/2012ueOctoeJaneMarApraJunJulueOctoeJaneMarApra'10Q4 '10Q1 '11Q2 '11Q3 '11Q4 '11Q1 '12Q2 '12TaskSplitProgressMilestoneSummaryProject SummaryExternal TasksExternal MilestoneDeadlinePage 1Project: FH_PlanDate: 11/7/2009