HomeMy WebLinkAboutNAHP_Stakeholder Info
INFORMATION DOCUMENT
Nushagak Area Hydroelectric Project
Lake Elva and Grant Lake Projects
near:
Dillingham, Alaska
Prepared By:
Nushagak Electric and Telephone Cooperative
557 Kenny Wren Rd
PO Box 350
Dillingham, Alaska 99575
907-842-5251 tel.
907-842-2780 fax
www.nushtel.com
April, 2009
2
INTRODUCTION AND BACKGROUND
Nushagak Electric & Telephone Cooperative, Inc., (“NETC”), is evaluating a multiple-
development hydroelectric Project, the Nushagak Area Hydroelectric Project (“NAHP”,
“Project”), as described in this document. (Note that the Project was called the “Dillingham Area
Hydroelectric Project”, or DAHP, in earlier documents).
The NAHP would consist of the Grant Lake and Lake Elva hydroelectric projects (“Projects”,
“Grant Lake Project”, “Lake Elva Project”). Both Projects and portions of their transmission
systems would be located in Wood-Tikchick State Park administered by the State of Alaska
Department of Natural Resources (ADNR).
The proposed 1.5 megawatt (MW) installed capacity Lake Elva Project would be located 36
miles north by northwest of Dillingham, Alaska. The proposed 2.7 MW Grant Lake Project
would be located 43 miles north of Dillingham.
The purpose of the Projects would be to displace costs of diesel fuel electrical generation which
is currently NETC’s only generation alternative. The Grant Lake Project electrical generation
would meet NETC’s current base load and would equal the average generation of NETC’s diesel
power plant. Lake Elva Project generation would meet existing NETC’s peak loads.
BACKGROUND and NEED for PROJECT
NETC’s electrical generation is entirely petroleum-based, consisting of 7 diesel generators with
an installed capacity of 6.84 MW. Costs for diesel fuel, at 2008 levels, corresponded to NETC
electrical rates of about $0.46 per kilowatt hour, among the highest in Alaska. Continued
dependence on diesel as the sole electrical generating source has exposed the area’s commercial
and residential users to high costs and unstable pricing. In 2008, NETC revived feasibility
studies done in 1980 and 1981 (see page 12) of the NAHP with the intention of developing
renewable energy resources to address these issues.
In this document, NETC describes the 1) the proposed NAHP Projects, and 2) the proposed
process and schedule for completing feasibility studies and applying for necessary permits for
Project construction and long-term operation.
CONTACT WITH NETC
Interested parties are encouraged to contact NETC for information on this development. The
name, business address, phone number and email of the person authorized to act as agent for
NETC is:
Frank Corbin, CEO / General Manager
Nushagak Electric & Telephone Cooperative, Inc., dba Nushagak Cooperative
557 Kenny Wren Road
Post Office Box 350
Dillingham, AK, 99576
3
907-842-6315, Phone
907-842-2780 Fax
fcorbin@nushagak.coop
PRELIMINARY FEASIBILITY STUDY and REPORT
In 2008, NETC contracted EES Consultants of Kirkland, WA, to conduct a preliminary
feasibility study for the overall NAHP proposal as conceived at the time. The pre-feasibility
study was intended to update earlier evaluations of the project, in terms of today’s fuel, materials
and construction costs. The final report “Review of Dillingham Area Hydro Project” was
submitted in February, 2009, and is referenced in this document as the “EES Report”.
DESCRIPTIONS of the PROJECTS
In the following sections, English measurement units are used in all descriptions. Elevations are
in feet above mean low sea level and are denoted “El”.
The EES Report examined both storage and run of river configurations for each Project. The
four configurations described were:
• Lake Elva, Run of River;
• Lake Elva, Storage;
• Grant Lake, Run of River; and
• Grant Lake, Storage.
PROJECT LOCATIONS
The proposed location of the Projects would be:
The Lake Elva Project intake would be located in Sections 1, 2, 7, 11, 12, of Township 6-7S,
Range 58W of the Seward Meridian.
The approximate Lake Elva Project powerhouse location would be: WGS 1984 - longitude 159
degrees 03’ 52” west; latitude, 059 degrees 35’ 07” north.
The Grant Lake Project intake would be located in Sections 28, 29, 32, 33, of Township 4S,
Range 54-55W of the Seward Meridian.
The approximate Grant Lake Project powerhouse location would be: WGS 1984 - longitude 158
degrees 35’ 60” west; latitude, 059 degrees 47’ 12.5” north.
LAKE ELVA PROJECT
The Lake Elva Project would be located approximately 36 linear miles north of Dillingham,
Alaska, on Lake Elva and Elva Creek (Figure 2). Elva Creek drains into Lake Nerka, which is in
Wood-Tikchick State Park, a component of the State of Alaska state park system.
4
Two primary alternatives exist for Lake Elva Project configuration: the Storage Alternative and
the Run of River Alternative, as described below (Figure 1):
Lake Elva Project Run of River Alternative
In this project configuration, a 10-foot high diversion dam would be constructed at the outlet of
Lake Elva to allow the withdrawal of water through an intake structure (Figure 1). Water would
be conveyed through a 10,800 foot long penstock to the powerhouse housing a single 1500 kW
installed capacity turbine (Table 1). The powerhouse would be located approximately 2,600 feet
upstream from Elva Creek’s confluence with Lake Nerka. A temporary construction staging area
is proposed near the powerhouse.
Operated in run of the river mode, this alternative would offer only a small amount of storage
(about 2500 acre-feet) for short-term flow regulation. Flows below the powerhouse would be
only slightly modified from the natural hydrology.
Table 1. Lake Elva Run of River Project Features and Dimensions.
Spillway Elevation El 313
Minimum Reservoir Elevation El 305
Usable Storage 2500
Powerhouse Floor Elevation El 79
Penstock Length (ft) 10,800
Penstock Diameter (in) 48
Installed Capacity (kW) 1500
Lake Elva Storage Project Alternative
Under this alternative, an approximately 100-ft high earth fill dam would be constructed about
1.0 mi downstream of Lake Elva (See Figure 1). From the dam, a 6700-ft penstock would
convey water to a powerhouse housing a 1000 kW generator (Table 2). The powerhouse
location would be the same as for the Run of River alternative. Under this configuration, flows
below the powerhouse would be those necessary to optimize generation, but could be to some
extent regulated for instream purposes.
5
Figure 1. Lake Elva Project, Storage and Run of River Alternatives.
6
Table 2. Lake Elva Storage Project Features and Dimensions.
Spillway Elevation El 370
Minimum Reservoir Elevation El 320
Usable Storage (af) 26,800
Powerhouse Floor Elevation El 79
Penstock Length (ft) 6700
Penstock Diameter (in) 42
Installed Capacity (kW) 1000
Lake Elva Project Access
Construction access to the staging area during summer would be via barge across Lake
Aleknagik and Lake Nerka. Once at the Lake Elva construction site, access would be via a short
access road to the staging area and an approximately 1.7 mi-long road along the penstock route
to the damsite. In winter, equipment, materials, and supplies would be moved to the construction
sites for either alternative over the ice of Lake Aleknagik and Lake Nerka.
Access for maintenance during summer would be by float plane or small boat. During winter,
the project could be accessed via ski plane, snow machine or other over-ice vehicles.
GRANT LAKE PROJECT
As with the Lake Elva Project, two primary alternatives are being examined for the Grant Lake
Project: the Storage Alternative and the Run of River Alternative, as described below (Figure 2):
Both Grant Lake Project alternatives would be located approximately 43 linear miles north of
Dillingham, Alaska, on Grant Lake and Grant River (Figure 2). Grant River drains into Lake
Kulik, which is in Wood-Tikchick State Park, a component of the State of Alaska State Park
system.
Grant Lake Run of River Project Alternative
In this project configuration, an approximately 5-ft high diversion dam would be constructed at
the outlet of the Grant Lake. (Figure 2). An approximately one-mile long diversion canal would
be excavated approximately one mile north of the dam with an invert at El 468 (Table 3). The
canal would extend to a rock fill dike and intake 0.8 miles north-northwest of the dam . Water
would be withdrawn through the dike into a 5-foot diameter, 6,600-foot long pipe transitioning
through a surge tank to a 48-inch diameter, 3,100-foot long steel penstock to the powerhouse at
El 240. The powerhouse, located approximately 5.3 mi upstream from Grant Creek’s confluence
with Lake Kulik, would house a 3000 kW generator. A small amount of storage would be
available for regulation (10,000 acre-feet) of flows by manipulating the height of the lake. With
this project configuration, flows downstream of the powerhouse would be only slightly modified
from the natural hydrology.
7
Table 3. Grant Lake Run of River Project Features and Dimensions.
Spillway Elevation El 481
Minimum Reservoir Elevation El 476
Usable Storage (af) 10,000
Powerhouse Floor Elevation El 240
Penstock Length (ft) 8400
Penstock Diameter (in) 66
Installed Capacity (kW) 3000
Grant Lake Storage Project Alternative
Under this alternative, a 20 ft. high dam would be constructed at the outlet of Grant Lake (See
Figure 2). A canal would be constructed in the same location as for the Run of River
Alternative, and an intake installed in the diversion dam at that location. Water would be
conveyed through an 8,400 ft long penstock from the intake to the powerhouse with one Turgo
type turbine of about 1.7 MW installed capacity. Powerhouse locations for the Run of River and
Storage alternatives would be the same.
Under this alternative, flows below the powerhouse would be regulated to provide nearly
constant flow. The turbine would only operated at best efficiency in order to maximize
generation.
Table 4. Grant Lake Storage Project Features and Dimensions.
Spillway Elevation El 500
Minimum Reservoir Elevation El 478
Usable Storage (af) 52,500
Powerhouse Floor Elevation (af) 240
Penstock Length (af) 8400
Penstock Diameter (in) 60
Installed Capacity (kW) 1700
8
Figure 2. Grant Lake Project, Storage and Run of River Alternatives.
9
Grant Lake Project Access
Construction access for either Grant Lake Project alternative would be via barge or small boat
across Lake Aleknagik and Lake Kulik. Access could also be via a road paralleling the proposed
primary transmission route (see below). During winter, access would be over the ice of Lake
Aleknagik and Lake Kulik. Summer access for routine maintenance would be by float plane or
small boat. Winter access would be via ski plane or various ice vehicles.
LAKE ELVA, GRANT LAKE PROJECT OPERATIONS
In the EES Report, operations of the run of river and storage alternatives for both Projects were
simplified to provide a basis for comparison. Under the run of river alternatives, flows in stream
reaches between the Project intake and powerhouse (the “bypassed reaches”) were assumed to be
1 cubic foot per second (cfs). Below the powerhouses, flows were assumed to be essentially the
natural flow of the stream in question, composed of either powerhouse discharge or powerhouse
discharge plus spill.
For the storage alternatives, bypassed reach discharge were assumed to be 1 cfs, and discharges
downstream of the powerhouse were assumed to be the result of flow regulation to optimize
output, resulting in reduced flow variation relative to natural conditions.
Streamflow regimes in both bypassed reaches and those below the respective powerhouses will
be the subject of extensive consultation during further Project development.
TRANSMISSION FACILITIES
The primary transmission alternatives utilize either overhead, underground or submarine
transmission facilities to minimize aesthetic effects of structures within Wood-Tikchick State
Park (Figure 3). Under all routing alternatives for both Projects, the existing 7.2 kilovolt (kV)
distribution line between Dillingham and Aleknagik would be upgraded to 34.5 kV and a new
substation would be constructed about 5 mi north of Aleknagik.
In this document, the terminology for the various transmission routes has been simplified from
that used in the EES Report and referenced to known features or locations. We expect to use this
terminology instead of the EES Report terminology in the future.
Transmission routes from the two Projects are described below (Figure 3), as described below:
Lake Elva Project Transmission Routes
Two primary transmission routes are being evaluated for the Lake Elva Project, the Lower and
Upper Lake Nerka Transmission routes (See Figure 3).
10
Figure 3. Grant Lake and Lake Elva Projects Transmission Line Alternatives.
11
Lower Lake Nerka Transmission Route
In the Lower Lake Nerka Route, the first leg of the transmission line would be routed
approximately 24 mi to the south southwest from the Lake Elva Project powerhouse, to a point at
the northwest limit of the mountain range directly west of Snake Lake adjacent to Mable
Mountain. At this point, two routing alternatives are being considered: 1) The Snake Lake
Transmission Route, (named because of the popular local name for Lake Nunavaugaluk), on
whose east shore this route would travel; and 2) the Lake Aleknagik South Shore Transmission
Route, which would follow the south shore of Lake Aleknagik approximately 12 miles to the
town of Aleknagik.
Under the Snake Lake routing, the line would pass in a southeast direction along Snake Lake’s
eastern shore then turn east and join the upgraded line between Dillingham and Aleknagik. The
Lake Aleknagik South Shore Transmission Route would continue on the west shore of Lake
Aleknagik and join the upgraded Dillingham-Aleknagik line at the existing substation in
Aleknagik. Under both of these routings, the line would be either underground or overhead,
depending on terrain and visual factors.
Also under consideration is a submarine routing beneath Lake Aleknagik (the Lake Aleknagik
Transmission Route), in which the line would be routed underwater from the northwest corner of
Lake Aleknagik to the existing substation in Aleknagik (See Figure 3).
Upper Lake Nerka Transmission Route
Under this routing alternative, the transmission line would be routed underwater beneath Upper
Lake Nerka to the eastern end of Upper Lake Nerka (See Figure 3). At the end of the lake, the
line would emerge from the water and be routed either underground or overhead (depending
again on terrain and/or visual factors) to join with the Grant Lake Transmission Route (described
below).
Grant Lake Project Transmission Route
The proposed Grant Lake Project Transmission Route would be southeast from the Grant Lake
Project powerhouse through about 8 miles of new underground transmission to the border of
Wood-Tikchick State Park. From that point, the line would proceed in underground and/or
overhead segments outside the Park border to the south and then southwest for about 35 miles to
Aleknagik (See Figure 3).
PERMITTING and CERTIFICATION PROCESSES
In 2008, NETC requested that the Federal Energy Regulatory Commission (FERC) in
Washington D.C. determine whether the Projects would be jurisdictional under FERC
Regulations. Jurisdictional hydropower projects in the U.S. must receive a license from FERC
authorizing construction and operation under a set of FERC and state and federal resource
agency conditions.
12
To be deemed non-jurisdictional, projects must not:
• Be located on a navigable water of the United States;
• Occupy lands of the United States;
• Utilize surplus water or waterpower from a government dam; and
• Be located on a body of water over which Congress has Commerce Clause jurisdiction.
NETC applied for jurisdictional determination for the two Projects in 2008. In response, FERC
sent a determination that both projects were non-jurisdictional under FERC regulations.
Under this determination, NETC must still meet requirements of all applicable state and federal
statutes and regulations, including issuance of permits authorizing construction and operation
and demonstration that the project would be consistent with existing plans and other standards.
Each of the permits and certifications is expected to contain conditions under which construction
and operation may proceed.
NETC will conduct a meeting with appropriate permitting and certification agencies in the spring
of 2009 to develop a process for moving forward in the absence of FERC licensing requirements.
DESCRIPTION OF STUDIES TO DETERMINE THE FEASIBILITY OF THE
PROJECT
Nushagak Cooperative proposes to conduct several studies to determine overall NAHP Project
feasibility as well as feasibility of the individual Projects. The exact extent and nature of these
studies cannot be known until completion of early stage consultation with Alaska state and
Federal resource agencies, and results of more detailed engineering calculations.
Reconnaissance level studies of the Grant Lake and Lake Elva Projects are included in the
Reconnaissance Study of the Lake Elva and other Hydroelectric Power Potentials in the
Dillingham Area prepared for the Alaska Power Authority by Robert W. Retherford Associates
in February, 1980, and in the Lake Elva Project Detailed Feasibility Analysis completed in 1981
by R. W. Beck and Associates, Inc.
It was the purpose of the EES preliminary feasibility study to expand upon information in these
older studies and to preliminarily propose steps toward more detailed analysis and selection of
preferred alternatives. NETC proposes to continue with studies in all areas in association with
consultation with Alaska state and federal resource agencies to determine more exact design and
operation specifications to carry through the permitting and certification processes.
ECONOMIC and ENGINEERING FEASIBILITY EVALUATION
Hydrology. Hydrology data will be retrieved or generated to obtain applicable data on Elva
Creek and Grant River streamflows, if available, and lake levels in Lake Elva and Grant Lake.
Generation and Transmission. A detailed generation study will be performed to determine the
exact size and type of turbine/generator and switchgear. Once transmission alternatives have
13
been evaluated and initial route selections made, NETC will further evaluate
buried/overhead/submarine routings, associated equipment and materials, and costs.
Engineering Feasibility. Engineering feasibility studies will be performed in association with
field surveys and more detailed topographic mapping (to include LIDAR mapping) to determine
the constructability of the various project features in relation to subsurface conditions, vegetation
and topography.
Economic Feasibility. After preliminary selection of generation alternatives, detailed
generation studies will help determine energy generation potential under a range of
meteorological conditions. Energy study results will be used in association with power sales,
construction, maintenance and operations costs to determine the economic feasibility of the
selected alternatives.
ENVIRONMENTAL STUDIES
The exact nature and scale of environmental studies will be determined during agency
consultation and study planning. Generally, however, environmental field and/or office studies
are required to meet information needs in the following areas:
• Aquatic Resources
• Terrestrial Resources
• Water Use and Quality
• Geology and Soils
• Socioeconomics
• Cultural Resources
• Land Use and Recreation
• Aesthetics
NETC proposes to conduct a formal study planning process among appropriate Alaska state and
federal resource agencies in the Spring of 2009. NETC will conduct a technical meeting to
present the current project proposal and obtain input on studies which would begin in 2009. The
study planning process would result in timeframes for the various resource-related studies, to
support a schedule for the permitting/certification phase of the Project development.
DISTURBANCES from CONDUCTING STUDIES
Disturbances from conducting studies would be minimal. The only expected disturbance could
arise if extensive additional geotechnical work were required, but previous studies in this area
should preclude such a need. All onsite work will be coordinated with the appropriate Tribes
and state and federal resource agencies. Also, permanent or semi-permanent stream gaging
stations would require installation of structures which, depending on approved design, might be
visible from lakes and streams.
14
SCHEDULE for STUDY COMPLETION, PERMITTING AND CERTIFICATION
NETC proposes to conduct engineering feasibility studies, at a higher level of detail than in the
EES Report, during the second half of 2009, with the objective of developing a preliminary
design in late 2009 or early 2010. Also included in this design effort would be results from
resource agency consultation which might bear on project generating and transmission facility
features, locations and visual attributes.
By spring, 2010, NETC would have developed a design suitable for inclusion in a Coastal
Project Questionnaire (CPQ) submitted to ADNR. The CPQ would trigger involvement of all
other permitting and certification agencies. The permitting and certification process would likely
result in further design, construction and operation refinements which would serve as the basis
for conditions in the final permits and certifications.