HomeMy WebLinkAboutWrangell Spur Road Project Application
Renewable Energy Fund Round 3
Grant Application
AEA 10-015 Application Page 1 of 11 10/7/2009
Application Forms and Instructions
The following forms and instructions are provided to assist you in preparing your application for
a Renewable Energy Fund Grant. An electronic version of the Request for Applications (RFA)
and the forms are available online at: http://www.akenergyauthority.org/RE_Fund-III.html
Grant Application
Form
GrantApp3.doc Application form in MS Word that includes an outline of
information required to submit a complete application.
Applicants should use the form to assure all information is
provided and attach additional information as required.
Application Cost
Worksheet
Costworksheet3
.doc
Summary of Cost information that should be addressed by
applicants in preparing their application.
Grant Budget
Form
GrantBudget3.d
oc
A detailed grant budget that includes a breakdown of costs by
milestone and a summary of funds available and requested to
complete the work for which funds are being requested.
Grant Budget
Form Instructions
GrantBudgetInst
ructions3.pdf
Instructions for completing the above grant budget form.
• If you are applying for grants for more than one project, provide separate application
forms for each project.
• Multiple phases for the same project may be submitted as one application.
• If you are applying for grant funding for more than one phase of a project, provide
milestones and grant budget for completion of each phase.
• If some work has already been completed on your project and you are requesting
funding for an advanced phase, submit information sufficient to demonstrate that the
preceding phases are satisfied and funding for an advanced phase is warranted.
• If you have additional information or reports you would like the Authority to consider in
reviewing your application, either provide an electronic version of the document with
your submission or reference a web link where it can be downloaded or reviewed.
REMINDER:
• Alaska Energy Authority is subject to the Public Records Act AS 40.25, and materials
submitted to the Authority may be subject to disclosure requirements under the act if no
statutory exemptions apply.
• All applications received will be posted on the Authority web site after final
recommendations are made to the legislature.
• In accordance with 3 AAC 107.630 (b) Applicants may request trade secrets or
proprietary company data be kept confidential subject to review and approval by the
Authority. If you want information is to be kept confidential the applicant must:
o Request the information be kept confidential.
o Clearly identify the information that is the trade secret or proprietary in their
application.
o Receive concurrence from the Authority that the information will be kept
confidential. If the Authority determines it is not confidential it will be treated as a
public record in accordance with AS 40.25 or returned to the applicant upon
request.
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 2 of 11 10/7/2009
SECTION 1 – APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
City and Borough of Wrangell
Type of Entity:
Local Municipal Government
Mailing Address
City & Borough of Wrangell
P.O. Box 531
Wrangell, Alaska 99929
Physical Address
City and Borough of Wrangell
205 Brueger Street
Wrangell, Alaska 99929
Telephone
(907) 874-2381
Fax
(907) 874-8952
Email
tdrooney@wrangell.com
1.1 APPLICANT POINT OF CONTACT
Name
Steven Henson
Title
Electrical Superintendent
Mailing Address
Wrangell Municipal Light & Power
P.O. Box 531
Wrangell, Alaska 99929
Telephone
(907) 874-3602
Fax
(907) 874-3614
Email
linedept@gci.net
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
An independent power producer in accordance with 3 AAC 107.695 (a) (1), or
X A local government, or
A governmental entity (which includes tribal councils and housing authorities);
Yes 1.2.2. Attached to this application is formal approval and endorsement for its project by
its board of directors, executive management, or other governing authority. If the
applicant is a collaborative grouping, a formal approval from each participant’s
governing authority is necessary. (Indicate Yes or No in the box )
Yes
1.2.3. As an applicant, we have administrative and financial management systems and
follow procurement standards that comply with the standards set forth in the grant
agreement.
Yes
1.2.4. If awarded the grant, we can comply with all terms and conditions of the attached
grant form. (Any exceptions should be clearly noted and submitted with the
application.)
Yes
1.2.5 We intend to own and operate any project that may be constructed with grant
funds for the benefit of the general public.
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 3 of 11 10/7/2009
SECTION 2 – PROJECT SUMMARY
This is intended to be no more than a 1-2 page overview of your project.
2.1 Project Title – (Provide a 4 to 5 word title for your project)
Spur Road Distribution Line Extension
2.2 Project Location –
Include the physical location of your project and name(s) of the community or communities that will
benefit from your project.
Spur Road (aka Ishiyama Drive) in the Wrangell community
2.3 PROJECT TYPE
Put X in boxes as appropriate
2.3.1 Renewable Resource Type
Wind Biomass or Biofuels
X Hydro, including run of river Transmission of Renewable Energy
Geothermal, including Heat Pumps Small Natural Gas
Heat Recovery from existing sources Hydrokinetic
Solar Storage of Renewable
Other (Describe)
2.3.2 Proposed Grant Funded Phase(s) for this Request (Check all that apply)
Reconnaissance X Design and Permitting
Feasibility X Construction and Commissioning
X Conceptual Design
2.4 PROJECT DESCRIPTION
Provide a brief one paragraph description of your proposed project.
Engineering design, survey services, permit acquisitions, material purchase and constructions for
the extending the existing distribution line on Spur Road with an additional 17 pole spans.
2.5 PROJECT BENEFIT
Briefly discuss the financial and public benefits that will result from this project, (such as reduced fuel
costs, lower energy costs, etc.)
Extending the distribution line increases potential consumers and allows for new development
and economic growth.
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 4 of 11 10/7/2009
2.6 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source
of other contributions to the project.
Engineering design services are estimated to cost $44,000.00. Survey and permitting costs are
estimated at $55,000.00. Material/Construction/Instillation costs are estimated at $62,386.00.
Total cost for the project will be $161,386.00
Grant funding requested $119,263.00 for engineering, surveying, permitting and materials
Wrangell In-Kind of $42,123.00 for construction and instillation
2.7 COST AND BENEFIT SUMARY
Include a summary of grant request and your project’s total costs and benefits below.
Grant Costs
(Summary of funds requested)
2.7.1 Grant Funds Requested in this application. $119,263.00
2.7.2 Other Funds to be provided (Project match) $42,123.00
2.7.3 Total Grant Costs (sum of 2.7.1 and 2.7.2) $161,386.00
Project Costs & Benefits
(Summary of total project costs including work to date and future cost estimates to get to a fully
operational project)
2.7.4 Total Project Cost (Summary from Cost Worksheet
including estimates through construction)
$161,386.00
2.7.5 Estimated Direct Financial Benefit (Savings) $
2.7.6 Other Public Benefit (If you can calculate the benefit in
terms of dollars please provide that number here and
explain how you calculated that number in your application
(Section 5.)
$
SECTION 3 – PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include a resume and references
for the manager(s). If the applicant does not have a project manager indicate how you intend to
solicit project management support. If the applicant expects project management assistance
from AEA or another government entity, state that in this section.
Steven Henson, Electrical Superintendent
Wrangell Municipal Light & Power
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 5 of 11 10/7/2009
3.2 Project Schedule
Include a schedule for the proposed work that will be funded by this grant. (You may include a
chart or table attachment with a summary of dates below.)
The proposed schedule for this phase is as follows
Description Schedule
Phase 1- RFP for Engineering 1 month after grant award
Phase 2 – Design/Permit 4 months after RFP award
Phase 3- Construction 2 months after permits received
3.3 Project Milestones
Define key tasks and decision points in your project and a schedule for achieving them. The
Milestones must also be included on your budget worksheet to demonstrate how you propose to
manage the project cash flow. (See Section 2 of the RFA or the Budget Form.)
Key project milestones for this project include the following:
Time frame Project Milestone
1 Month RFP for Engineering planning and design
4 Months* Engineering Planning, Design, Survey and Permitting
2 Months Wrangell Municipal Light & Power Construction of Power Line
The project will start when the grant is awarded and be completed approximately 7 months after
that date.
*This could be longer if there are any permitting delays
3.4 Project Resources
Describe the personnel, contractors, equipment, and services you will use to accomplish the
project. Include any partnerships or commitments with other entities you have or anticipate will
be needed to complete your project. Describe any existing contracts and the selection process
you may use for major equipment purchases or contracts. Include brief resumes and references
for known, key personnel, contractors, and suppliers as an attachment to your application.
City and Borough of Wrangell charter dictates that all large purchases must go through a formal
request for proposal or bid process for award. For this project we anticipate issuing an RFP for
the Engineering Design/Surveying/Permitting.
The anticipated consultant to perform this project is unknown at this time.
Wrangell Municipal Light & Power would acquire the needed materials and install the new
power line extension.
3.5 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 6 of 11 10/7/2009
Throughout the life of the project, the Project Manager will provide written and monthly updates
to AEA which will include at a minimum:
- Expenditures to date;
- Percent complete; and
- Narrative on progress including any scheduled changes.
In addition to the monthly progress reports, communications on project status will also be
provided verbally with the AEA Project Manager on an informal basis through emails and phone
conversations.
3.6 Project Risk
Discuss potential problems and how you would address them.
Only foreseeable problem is a possible delay in obtaining the DOT Right of Way permit. This
would delay the completion date.
SECTION 4 – PROJECT DESCRIPTION AND TASKS
• Tell us what the project is and how you will meet the requirements outlined in Section 2 of
the RFA.
• The level of information will vary according to phase(s) of the project you propose to
undertake with grant funds.
• If you are applying for grant funding for more than one phase of a project provide a
plan and grant budget form for completion of each phase.
• If some work has already been completed on your project and you are requesting funding for
an advanced phase, submit information sufficient to demonstrate that the preceding phases
are satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project.
There is currently a commercial customer interested in installing a three phase service for their
business. Along the proposed line extension there is land owned the City and Borough of
Wrangell and the State of Alaska Mental Health that are being considered for subdivision if
power becomes accessible.
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about
the number, size, age, efficiency, and type of generation.
The current distribution line on the Spur Road ends just past the Muskeg Meadows Golf Course,
approximately 8/10 mile Ishiyama Drive.
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 7 of 11 10/7/2009
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of
any impact the project may have on existing energy infrastructure and resources.
Currently Wrangell uses hydropower supplied from the Tyee Lake Hydroelectric Facility. No
foreseeable impact on the existing infrastructure or resources other than increased load as area
develops.
4.2.3 Existing Energy Market
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
The Spur Road distribution line supplies power exclusively to Muskeg Meadows Golf Course.
Due to the small amount of energy consumed by the golf course the impact of extending the
distribution line would have no effect.
4.3 Proposed System
Include information necessary to describe the system you are intending to develop and address
potential system design, land ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
• A description of renewable energy technology specific to project location
• Optimum installed capacity
• Anticipated capacity factor
• Anticipated annual generation
• Anticipated barriers
• Basic integration concept
• Delivery methods
Not Applicable
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the
project or how you intend to approach land ownership and access issues.
Land used for this project consists of Alaska Department of Transportation Right of Way.
Permits are required and will be obtained before install the new power poles.
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
• List of applicable permits
• Anticipated permitting timeline
• Identify and discussion of potential barriers
Alaska Department of Transportation Right of Way Permit will be required before this project.
Permit approval for a project this size can take up to 3 months. We do not anticipate any major
barriers as the existing right of way has already been cleared.
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 8 of 11 10/7/2009
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will
be addressed:
• Threatened or Endangered species
• Habitat issues
• Wetlands and other protected areas
• Archaeological and historical resources
• Land development constraints
• Telecommunications interference
• Aviation considerations
• Visual, aesthetics impacts
• Identify and discuss other potential barriers
Not Applicable
4.4 Proposed New System Costs and Projected Revenues
(Total Estimated Costs and Projected Revenues)
The level of cost information provided will vary according to the phase of funding requested and
any previous work the applicant may have done on the project. Applicants must reference the
source of their cost data. For example: Applicants Records or Analysis, Industry Standards,
Consultant or Manufacturer’s estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of
the project. Cost information should include the following:
• Total anticipated project cost, and cost for this phase
• Requested grant funding
• Applicant matching funds – loans, capital contributions, in-kind
• Identification of other funding sources
• Projected capital cost of proposed renewable energy system
• Projected development cost of proposed renewable energy system
Total cost is estimated at $161,386.00 for design/survey/permitting/material/and construction for
this project with a grant request of $119,263.00. Wrangell Municipal Light & Power will
construct and install the new power line with an in-kind contribution of $42,123.00
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by
the applicant.
(Note: Operational costs are not eligible for grant funds however grantees are required to meet
ongoing reporting requirements for the purpose of reporting impacts of projects on the
communities they serve.)
Not applicable
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
• Identification of potential power buyer(s)/customer(s)
• Potential power purchase/sales price - at a minimum indicate a price range
• Proposed rate of return from grant-funded project
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 9 of 11 10/7/2009
Currently Ketchikan Read Mix has property along the proposed line extension and have
expressed an interest in obtaining three phase power for their operation.
State of Alaska Mental Health owns land along the proposed extension that could be subdivided
and sold in an upcoming land sale.
City and Borough of Wrangell also owns land in the area and would like to develop the property
if power became available.
4.4.4 Project Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered
in evaluating the project.
See Attachment B
SECTION 5– PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings,
and how the people of Alaska will benefit from the project.
The benefits information should include the following:
• Potential annual fuel displacement (gal and $) over the lifetime of the evaluated
renewable energy project
• Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or cost based rate)
• Potential additional annual incentives (i.e. tax credits)
• Potential additional annual revenue streams (i.e. green tag sales or other renewable
energy subsidies or programs that might be available)
• Discuss the non-economic public benefits to Alaskans over the lifetime of the project
Line extension would supply power to an existing concrete and gravel business that is currently
running a diesel generator. There are public and privet lands along the distribution route that
could be developed with access to power
SECTION 6– SUSTAINABILITY
Discuss your plan for operating the completed project so that it will be sustainable.
Include at a minimum:
• Proposed business structure(s) and concepts that may be considered.
• How you propose to finance the maintenance and operations for the life of the project
• Identification of operational issues that could arise.
• A description of operational costs including on-going support for any back-up or existing
systems that may be require to continue operation
• Commitment to reporting the savings and benefits
Maintenance of the line would be included in Wrangell Municipal & Power’s normal O&M
for the distribution system
Renewable Energy Fund
Grant Application Round 3
AEA10-015 Grant Application Page 10 of 11 10/7/2009
SECTION 7 – READINESS & COMPLIANCE WITH OTHER GRANTS
Discuss what you have done to prepare for this award and how quickly you intend to proceed
with work once your grant is approved.
Tell us what you may have already accomplished on the project to date and identify other grants
that may have been previously awarded for this project and the degree you have been able to
meet the requirements of previous grants.
Wrangell Municipal Light & Power has obtained cost estimates regarding the project.
Attachment D
Steve Henson has discussed the possibility of development along the proposed extension with
both State and Local officials with positive reaction to the possibility of further development in
the area.
If this grant is approved the City of Wrangell would issue the RFP for Engineering/Surveying
immediately after the award. Wrangell Municipal Light & Power would start acquiring the
materials required when funding is released.
SECTION 8– LOCAL SUPORT
Discuss what local support or possible opposition there may be regarding your project. Include
letters of support from the community that would benefit from this project.
See Attachment A
SECTION 9 – GRANT BUDGET
Tell us how much you want in grant funds Include any investments to date and funding sources,
how much is being requested in grant funds, and additional investments you will make as an
applicant.
Include an estimate of budget costs by milestones using the form – GrantBudget3.doc
See Attachment C – Grant Budget Worksheet
I Renewable Energy Fund ,ALASKA
ENERGY AUTHORITY Grant Application Round 3
SECTION 9 -ADDITIONAL DOCUMENTATION AND CERTIFICATION
SUBMIT THE FOLLOWING DOCUMENTS WITH YOUR APPLICATION:
A. Resumes of Applicant's Project Manager, key staff, partners, consultants, and
suppliers per application form Section 3.1 and 3.4 ..
B. Cost Worksheet per application form Section 4.4.4.
C. Grant Budget Form per application form Section 9.
D. Letters demonstrating local support per application form Section 8.
E. An electronic version of the entire application on CD per RFA Section 1.6.
F. Governing Body Resolution or other formal action taken by the applicant's
governing body or management per RFA Section 1.4 that:
Commits the organization to provide the matching resources for project at the
match amounts indicated in the application.
Authorizes the individual who signs the application has the authority to
commit the organization to the obligations under the grant.
/Provides as point of contact to represent the applicant for purposes of this
application.
Certifies the applicant is in compliance with applicable federal, state, and local,
laws including existing credit and federal tax obligations.
F. CERTIFICATION
The undersigned certifies that this application for a renewable energy grant is truthful
and correct, and that the applicant is in compliance with, and will continue to comply
with, all federal and state laws including existing credit and federal tax obligations.
Print Name Jeff Jabusch
Signature(/' LA~ LLJ~
"7 n // ~ .......
Title
V
Acting Borough Manager
Date / / -5~.o9
AEA 10-015 Grant Application Page 11 of 11 10/7/2009
Attachment B
Renewable Energy Fund Round 3
Project Cost/Benefit Worksheet
RFA AEA10-015 Application Cost Worksheet Page 1 10-7-09
Please note that some fields might not be applicable for all technologies or all project
phases. The level of information detail varies according to phase requirements.
1. Renewable Energy Source
The Applicant should demonstrate that the renewable energy resource is available on a
sustainable basis.
Annual average resource availability.
Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel)
2. Existing Energy Generation and Usage
a) Basic configuration (if system is part of the Railbelt 1 grid, leave this section blank)
i. Number of generators/boilers/other
ii. Rated capacity of generators/boilers/other
iii. Generator/boilers/other type
iv. Age of generators/boilers/other
v. Efficiency of generators/boilers/other
b) Annual O&M cost (if system is part of the Railbelt grid, leave this section blank)
i. Annual O&M cost for labor
ii. Annual O&M cost for non-labor
c) Annual electricity production and fuel usage (fill in as applicable) (if system is part of the
Railbelt grid, leave this section blank)
i. Electricity [kWh]
ii. Fuel usage
Diesel [gal]
Other
iii. Peak Load
iv. Average Load
v. Minimum Load
vi. Efficiency
vii. Future trends
d) Annual heating fuel usage (fill in as applicable)
i. Diesel [gal or MMBtu]
ii. Electricity [kWh]
iii. Propane [gal or MMBtu]
iv. Coal [tons or MMBtu]
v. Wood [cords, green tons, dry tons]
vi. Other
1 The Railbelt grid connects all customers of Chugach Electric Association, Homer Electric Association, Golden Valley Electric
Association, the City of Seward Electric Department, Matanuska Electric Association and Anchorage Municipal Light and Power.
Attachment B
Renewable Energy Fund Round 3
Project Cost/Benefit Worksheet
RFA AEA10-015 Application Cost Worksheet Page 2 10-7-09
3. Proposed System Design Capacity and Fuel Usage
(Include any projections for continued use of non-renewable fuels)
a) Proposed renewable capacity
(Wind, Hydro, Biomass, other)
[kWh or MMBtu/hr]
b) Proposed Annual electricity or heat production (fill in as applicable)
i. Electricity [kWh]
ii. Heat [MMBtu]
c) Proposed Annual fuel Usage (fill in as applicable)
i. Propane [gal or MMBtu]
ii. Coal [tons or MMBtu]
iii. Wood [cords, green tons, dry tons]
iv. Other
4. Project Cost
a) Total capital cost of new system $161,386.00
b) Development cost
c) Annual O&M cost of new system
d) Annual fuel cost
5. Project Benefits
a) Amount of fuel displaced for
i. Electricity
ii. Heat
iii. Transportation
b) Price of displaced fuel
c) Other economic benefits
d) Amount of Alaska public benefits
6. Power Purchase/Sales Price
a) Price for power purchase/sale
7. Project Analysis
a) Basic Economic Analysis
Project benefit/cost ratio
Payback
Renewable Energy Fund Grant Round III Grant Budget Form 10-7-09 Milestone or Task Anticipated Completion Date RE- Fund Grant Funds Grantee Matching Funds Source of Matching Funds: Cash/In-kind/Federal Grants/Other State Grants/Other TOTALS 1. Project scoping and contractor solicitation for planning and design-Surveying 1 month after grant award $50,350.00 $ $50,350 2. Permit applications AK/DOT 4 months after RFP award $4,650.00 $ $4,650.00 3. Final environmental assessment and mitigation plans (as needed) $ $ $ 4. Resolution of land use, right of way issues $ $ $ 5. Permit approvals $ $ $ 7. Engineers cost estimate $44,000.00 $ $44,000.00 8. Updated economic and financial analysis $ $ $ 9. Negotiated power sales agreements with approved rates $ $ $ 10. Final business and operational plan $ $ $ TOTALS $99,000.00 $99,000.00 Budget Categories: Direct Labor & Benefits $ $ $ Travel & Per Diem $ $ $ Equipment $ $ $ Materials & Supplies $ $ $ Contractual Services $99,000.00 $ $99,000.00 Construction Services $ $ $ Other $ $ $ TOTALS $ $ $ Applications should include a separate worksheet for each project phase (Reconnaissance, Feasibility, Design and Permitting, and Construction)- Add additional pages as needed
Renewable Energy Fund Grant Round III Grant Budget Form 10-7-09 Milestone or Task Anticipated Completion Date RE- Fund Grant Funds Grantee Matching Funds Source of Matching Funds: Cash/In-kind/Federal Grants/Other State Grants/Other TOTALS 1. Confirmation that all design and feasibility requirements are complete. $ $ $ 2. Completion of bid documents N/A $ $ $ 3. Contractor/vendor selection and award 1 month after grant award $20,263.00 $ $20,263 4. Construction Phases – 5 months after grant award $ $42,123.00 In-Kind $42,123 5. Integration and testing $ $ $ 6. Decommissioning old systems $ $ $ 7. Final Acceptance, Commissioning and Start-up $ $ $ 8. Operations Reporting $ $ $ $ $ TOTALS $20,263.00 $42,123.00 $62,386.00 Budget Categories: Direct Labor & Benefits $ $19,683.00 In-Kind $19,683.00 Travel & Per Diem $ $ $ Equipment $ $22,440.00 In-Kind $22,440.00 Materials & Supplies $20,263.00 $ $22,263.00 Contractual Services $ $ $ Construction Services $ $ $ Other (Design/Permitting Phase Totals) $99,000.00 $ $99,000.00 TOTALS $119,263.00 $42,123.00 $161,386.00 Applications should include a separate worksheet for each project phase (Reconnaissance, Feasibility, Design and Permitting, and Construction)- Add additional pages as needed
Attachment D Wrangell Municipal Light Power
Cost Analysis for Spur Road Extension
$22 440 0010%men 2010
Quantity Discription Cost Total
17 45' Utility Pole 385 $6,545.00
14 10' Crossarms 59 $826.00
102 4x1/2 Lag Bolts 0.55 $56.10
102 20" Bolts 3.5 $357.00
68 Oval Eye Nuts 3.2 $217.60
68 14" Machine Bolts 2 $136.00
238 Curved Washers 0.85 $202.30
68 Carriage Bolts 1.5 $102.00
17000 Feet 2/0 ACSR 0.4 $6,800.00
3400 Feet Guy Wire 0.5 $1,700.00
102 Guy Preforms 2.5 $255.00
51 Guy Strain Insulators 24 $1,224.00
Current Price Total $18,421.00
10% Cost adjustment for 2010 $20,263.10
136 Hours for Lineman 55.148 $7,500.13
136 Hours for Lineman 55.148 $7,500.13
136 Hours for Ground Man 21.272 $2,892.99
Current Price Total $17,893.25
10% Cost adjustment for 2010 $19,682.57
136 Hours for Digger 65 $8,840.00
136 Hours for Bucket Truck 85 $11,560.00
Current Price Total $20,400.00
10%Cost adjustment for 2010 Cost adjust t for $22 440 00, .