HomeMy WebLinkAboutNWABSchool_Milestone Table(1)Milestone table for the NWAB School Alternate Energy Solar Awareness Project
The NWAB is proposing to complete installation of Tracking Solar arrays at each of 11 High-schools in
the Region. School maintenance personal and students will be utilized for the installation in
collaboration with local utility personal. AEA must receive and approve evidence that each milestone
has been reached prior to approving reimbursement or releasing funding for the corresponding tasks.
The milestones and corresponding tasks are outlined in the table below. Project timeline based on the
acceptance of an official grant agreement between NWAB and the State of Alaska.
Required Milestone Reimbursable Tasks Timeline
1. Reconnaissance Done Sep-Oct 2009
2. Feasibility Study Done September
October 2009
3. Conceptual Design
Done
October 2009
4. Ordering of Equipment
and materials
4.1 Put out bid on Equipment
4.2 Select vendor
4.3 Order Equipment
4.4 Distribute Equipment to Schools
July 2010
5. Construction
5.1 Mobilization
5.2 Site access and foundation installation
5.3 Creation of pedestals foundation
5.4 Assembly of arrays
July 2010
6. Integration of arrays
onto the grid
6.1 Connection by utility personal July 2010
7. Commissioning
7.1 Commissioning Aug 2010
8. Operations Report 8.1 Operation Report 30 Aug 2010-30
Aug 2011