HomeMy WebLinkAboutH - HBC AEA R3 Project ScheduleHumpback Creek Construction Schedule Summary Mowat August 2009 Schedule Job Complete 10/09/2010 TASK START DATE END DATE Mobilization 8/3/2009 12/19/2009 Site Access 9/12/2009 9/26/2009 Environmental 9/29/2009 10/2/2009 Outlet Portal Face 9/29/2009 10/23/2009 Outlet Portal  10/24/2009 11/2/2009 Tunnel Constuction 11/3/2009 1/18/2010 Penstock 1/19/2010 3/18/2010 Left Abutment Slope Scale 12/31/2009 2/2/2010 Intake Structure Excavation 2/3/2010 3/31/2010 Intake Portal 4/1/2010 4/3/2010 Intake Diversion Flume 3/23/2010 3/30/2010 Intake Diversion Foundation 3/31/2010 5/6/2010 Intake Structure  5/7/2010 5/28/2010 Intake Roof, Walls, and Mechanical 5/29/2010 6/15/2010 Intake Diversion Structure 6/17/2010 8/31/2010 Electrical & Commission 8/9/2010 9/17/2010 Demobilization 9/13/2010 10/9/2010