Loading...
HomeMy WebLinkAboutORPC_COOK INLET_ScheduleSheet1ORPC-Alaska Cook Inlet Tidal Project ScheduleStart Task Finish TaskPhase 1 – ReconnaissanceDesign physical site characterization study (current velocity profiling/ bathymetry) 07/2008 11/2008Design biological site characterization study for beluga whales 09/2008 05/2009Design biological site characterization study for salmon 09/2008 05/2009Biological site characterization(Beluga Salmon Study) design 09/2008 11/2008Initiate interconnect study 09/2008 09/2009Initiate logistics research 07/2008 12/2009Identify permitting issues 07/2007 10/2009Phase 2 - Feasibility/Conceptual DesignPerform physical site characterization and analyze data 05/2009 12/2009Perform biological site characterization and analyze data 05/2009 12/2009Begin Negotiations for power purchase agreements 08/2009 12/2010Develop preliminary design OCGen™ Module for Cook Inlet application 10/2009 05/2010Develop preliminary design of power transmission system 10/2009 05/2010Develop preliminary design of mooring system 10/2009 05/2010Develop preliminary design of deployment plan 10/2009 05/2010Develop plan to address permitting issues 10/2008 12/2009Phase 3 - Final Design/PermittingFinalize power purchase agreements 01/2011 04/2011Complete design of OCGen™ module 05/2010 10/2010Complete design of power transmission system 05/2010 10/2010Complete design of mooring system 02/2010 10/2010Complete design of deployment approach 05/2010 10/2010Secure necessary permits 01/2010 04/2011Phase 4 – ConstructionOrder and secure project components 10/2010 01/2011Page 1 Sheet1Secure contracts for deployment of OCGen™ Module 10/2010 03/2011Ship system components to Port McKenzie 03/2011 04/2011Assemble OCGen™ Module at Port McKenzie 04/2011 05/2011Deploy OCGen™ Module in Cook Inlet 06/2011 07/2011Establish monitoring systems (biological, physical) 06/2011 09/2011Collect data from initial testing and analyze 09/2011 12/2011Page 2