HomeMy WebLinkAboutltr 071708 polar to dnr#1.-polarconsult alaska, inc...... ".__
~ ENGINEERS· SURVEYORS' ENVIRONMENTAL CONSULTANTS
July 17,2008
JILLRn:SE INVEST:\IENTS & BROKERAGE
1150 S COLONY WAY #3
PMB 183
PALMER, AK 99645
Subject: Delia Creek Project Description
Dear Jill Reese,
I have prepared the following description for the Delia Crcek Hydroelectric Project. As
you know we are in the pennitting phase of the project and have yet 10 perform a
eomplete design so some minor changes should be expected.
Project Description
Hatcher Pass Motherlode Lodge, LLC (HPML) plans to construet a 50 kW run of river
hydroelectric project on Delia Creek, IDeated in Hatcher Pass, Alaska. The Delia Creek
Hydroelectric Project (Projeet) will provide electrieity to the Motherlode lodge which is
owned by HPML. This energy will displace diesel fueled electrical generation.
There are four basic components that make up the run of river hydroelectric facility.
They are:
• Intake -Also referred to as the diversion structure, the intake consists of a small
dam (weir) that impounds the water in the creek so that it can be diverted into the
pipeline. This weir will be smaller than a typical beaver dam. Because of debris that
is carried along in the stream, a desander and screening box is used between the
intake and pipeline to ensure only clean water enters the pipeline. With the exception
of an equipment storage shed, the screening box is almost entirely buried.
• Penstock (pipeline) -Thc penstock conveys water from the intake down to the
powerhouse. The penstock is designed to minimize energy loss as it transports thc
water down to the powerhouse. Normally, the energy of the water falling dovmhill is
expended by friction. turbulence, and noise in the creek bed. The penstock minimizes
the energy losses on the way to the powerhousc so that there is a substantial amount
of energy in the fonn of water pressure available to produce power. The penstock
will be entirely buried.
• Powerhouse -The primary purpose of the pov..TThouse is to house and anchor the
turbomachinery. This consists of the water turbine, ,...·hich is coupled to thc electrical
generator. the generator is wired to the power line via switchgear. The powerhouse
will also contain miscellaneous mechanical equipment such as turbine controls and
project maintenance equipment.
• Power line -The power line conveys the electrical energy produced by the
generator to the utility's power distribution system. Because the powerhouse is
located very closc to the existing diesel generators there won't be a need for a typical
transmission line.
This project is a run of river project. Therefore. it does not store water and can only use
the water currently available in the creek to generate electricity. Run-ofriver projects are
1503 WEST 33RD AVENUE' SUITE 310 ·ANCHORAGE. ALASKA 99503
PHONE (907) 258-2420' FAX (907) 258-2419' HOMEPAGE wwwpolarconsult.net
POL\RCONSULT ALASKA, INC. 7/17/2008
advantageous because they are less costly to build and they do not change the amount of
water flowing below the project which helps protect fish and wildlife habitat. The
disadvantage of run-of-river projects is that they cannot utilize all of the water in the
creek during high flows, and thus cannot generate as much power as a storage project (a
project with a large dam).
Thc actual volume of water used and power generated by this project will vary
seasonally, with full output generally occurring from May through October and then
declining during the winter to a minimum powcr output occurring sometime in April.
The total water used and power generated will also vary slightly from year to year
depending on the amount of precipitation and weather.
The peak capacity of the Delia Project is approximately 50 kW with an annual energy
production of about 260,000 kWh.
Location
The project will be located directly across the Little Susitna River from the Motherlode
lodge. The powerhouse is located next to the Little Susitna River on HPML property.
The intake and penstock are located in and along the Delia Creek drainage valley.
Below is a detailed description of each project component. Concept illustrations and
preliminary engineering plans are available separately.
Intake
The project intake will consist of a short weir (diversion structure) of concrete, timber,
stone, or metal across Delia Creek. The weir will span the entire creek up to the flood
stage (a distance of about 20'). A spillway will be built into the weir so water in excess of
project flows will flow over the weir within the banks of the creek. The weir will be built
to the lowest height needed to allow water to flow slowly and smootWy through the
intake grates of the screening box. These grates will prevent large debris and animals
from entering the screening box. Preliminary design height for the weir is 4'.
Water enters the screening box at a low enough velocity that material such as sand and
gravel will be filtered out. Lcaves and floatable debris will be trapped by a 1/4" screen
that the water passes through. When either the screen or the box accumulates too much
debris to pass the water needed for the project a flush will occur. This involves opening a
submerged gatc(s) on the screening box that will allow water to briefly flow out of the
box very quickly taking the accumulated debris with it and discharging just below the
weir into the creek.
The screening box will be designed to handle approximately 2.0 cfs of water, and will be
mostly below grade. Atop of the screening box will be a shed to house the level
measuring and gate flushing equipment. The shed will be a very small structure. An air
vent will also protrude above ground just downstream from the screening box. The vent
will have an inverted U at the top and is screened to prevent debris from entering the
penstock.
Access to the project intake will be along the pipeline route. Construction equipment will
cross the Little Susitna at the nearest ford from the powerhouse. Maintenance access will
bc on foot or four wheeler utilizing the bridge to cross the Little Susitna. The bridge will
bc gated to allow only foot traffic by the public.
PAGE20F3
Project Penstock
Upon exiting the screening box the project water is conveyed to the powerhouse through
a pipeline called a penstock. The penstock will be an 8 or 10 inch diameter high density
polyethylene (HDPE) plastic pipe with some steel pipe possibly located near the
powerhouse. The pipe parallels the north side of the creek downstream from the intake
descending to the powerhouse. The total penstock length is about 2,600 feet.
The penstock may be exposed or partially buried in the upper section. The lower sections
will be entirely buried except where it crosses the Little Susitna River. Conduit will be
buried with the penstock to provide power and communications to the intake.
The bridge that will carry the pipeline aeross the Little Susitna River will be very similar
to the old bridge. Our drawing that we provided you showed some piling but upon
further review we will eliminate those piles and simply span the entire river. The existing
footings that are in plaee from the old bridge can be utilized for the new bridge.
Project Powerhouse and Tailrace
The powerhouse will be located near the banks of the Little Susitna River on HPML
property. The powerhouse will be accessible by the existing driveway that descends a
short distance from Hatcher Pass Road.
The powerhouse will be constructed on gravel and concrete fill. Native material
excavated from the powerhouse site will be deposited in a disposal area on HPML
property. The powerhouse will house the turbine, generator, switchgear, and controls.
The physical size of the building is dictated by the size of the equipment housed which is
not yet known. However, previous turbine designs similar to this project suggest that the
building will be no larger than 15 by 15 feet and less than 10 feet tall. The construction
materials willlikc1y consist of concrete block walls and a wooden roof.
The generation equipment will consist of a single turbine and generator with a rated
capacity of about 50 kW each. The turbine is called an impulse turbines (also referred to
as a Pelton wheel). The turbine has nozzles that discharge the high pressure water from
the pipeline onto buckets arranged around a shaft. The shaft of the turbine is then directly
connected to the generator which converts the rotational mechanical euergy to electrical
energy.
After exiting the turbine, project waters will flow through a grate structure designed to
keep animals and flsh from entering the turbine. Water will then flow through the
tailrace, which will be a rock-lined ditch, to the Little Susitna River.
If you have any questions regarding this Project please feel free to contact me.
Sincerely,
Daniel Hertrich, PE
PAGEJOFJ