Subject: Submittal of Application - Renewable Energy Fund Grant Program
Dear Mr. White:
The Four Dam Pool Power Agency (FDPPA) is pleased to submit the enclosed application for
Renewable Energy Grant funding. The proposed use of grant funds is to conduct an Integrated
Resource Plan for a soon-to-be interconnected region of Southeast Alaska. The Swan-Tyee
Intertie is under construction and completion is scheduled by the end of 2009. With the
completion of this Intertie, the communities of Ketchikan, Wrangell and Petersburg will all be
interconnected for the first time. In addition, an Intertie connecting the City of Kake to the
FDPPA system is in the planning process as well as a potential short interconnection to
Metlakatla.
The FDPPA is also undergoing a restructuring whereby two of the Agency’s four projects are
being transferred or sold back to the member utilities. The FDPPA is a Joint Action Agency
organized under State Statute and will remain the same although the name will be changed to
the Southeast Alaska Power Agency (SEAPA). This planned restructuring is scheduled to close
in January, 2009. SEAPA will remain the owner of the Swan Lake and Tyee Lake hydroelectric
facilities as well as associated transmission lines providing Agency power to Ketchikan,
Wrangell and Petersburg including the Swan-Tyee Intertie.
The FDPPA is currently developing an Operating Plan for the interconnected Tyee Lake and
Swan Lake projects. The purpose of this plan is to maximize the use of existing hydroelectric
power from these projects through efficient operation and water management. The goal is to
eliminate or reduce diesel generation in the interconnected communities to the maximum extent
possible. With loads increasing in the communities due to ‘fuel switching’ and other normal
growth, more hydroelectric power will have to be developed in the future along with a
combination of increased efficiencies and demand side management. This next step, fully
described in the grant application, is Integrated Resource Planning.
Butch White
Grant Manager
Alaska Energy Authority
Subject: Submittal of Application - Renewable Energy Fund Grant Program
Page 2
The FDPPA is requesting $252,000 in Renewable Energy Grant funds, which the FDPPA will
match with a $60,000 contribution. The hard-dollar match is in addition to FDPPA staff which
will contribute an estimated 500 hours to manage this IRP effort.
The FDPPA acknowledges and agrees that this Integrated Resource Planning project and
project results are for the benefit of the general public and the FDPPA will not deny any person
use or benefit of the project or project results due to race, religion, color, national origin, age,
physical handicap, sex, marital status, changes in marital status, pregnancy or parenthood.
I serve as the Grantee Project Manager. If you have any questions regarding this submittal,
please do not hesitate to call me at (907) 258-2281. Thank you for your consideration of this
grant application.
Sincerely,
Eric Wolfe, PE
Director of Special Projects
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 1 of 17 9/2/2008
http://akenergyauthority.org/RE_Fund.htmlApplication Forms and Instructions
The following forms and instructions are provided for preparing your application for a
Renewable Energy Fund Grant. An electronic version of the Request for Applications (RFA)
and the forms are available online at http://www.akenergyauthority.org/RE_Fund.html
The following application forms are required to be submitted for a grant recommendation:
Grant Application
Form
GrantApp.doc Application form in MS Word that includes an outline of
information required to submit a complete application.
Applicants should use the form to assure all information is
provided and attach additional information as required.
Application Cost
Worksheet
Costworksheet.doc Summary of Cost information that should be addressed
by applicants in preparing their application.
Grant Budget
Form
GrantBudget.xls A detailed grant budget that includes a breakdown of
costs by task and a summary of funds available and
requested to complete the work for which funds are being
requested.
Grant Budget
Form Instructions
GrantBudgetInstr.pdf Instructions for completing the above grant budget form.
• If you are applying for grants for more than one project, provide separate application
forms for each project.
• Multiple phases for the same project may be submitted as one application.
• If you are applying for grant funding for more than one phase of a project, provide a plan
and grant budget for completion of each phase.
• If some work has already been completed on your project and you are requesting
funding for an advanced phase, submit information sufficient to demonstrate that the
preceding phases are satisfied and funding for an advanced phase is warranted.
• If you have additional information or reports you would like the Authority to consider in
reviewing your application, either provide an electronic version of the document with
your submission or reference a web link where it can be downloaded or reviewed.
REMINDER:
• Alaska Energy Authority is subject to the Public Records Act, AS 40.25 and materials
submitted to the Authority may be subject to disclosure requirements under the act if no
statutory exemptions apply.
• All applications received will be posted on the Authority web site after final
recommendations are made to the legislature.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 2 of 17 9/3/2008
SECTION 1 – APPLICANT INFORMATION
Name (Name of utility, IPP, or government entity submitting proposal)
The Four Dam Pool Power Agency
Type of Entity:
Joint Action Agency
Mailing Address
P.O. Box 110987
Physical Address
1301 Huffman Rd, Ste 201
Telephone
(907) 258-2481
Fax
(907) 258-2287
Email
www.fdpa.org
1.1 APPLICANT POINT OF CONTACT
Name
Dave Carlson
Title
Chief Executive Officer
Mailing Address
P.O. Box 110987
Anchorage, AK 99511-0987
Telephone
(907) 258-2281
Fax
(907) 258-2287
Email
dcarlson@fdppa.org
1.2 APPLICANT MINIMUM REQUIREMENTS
Please check as appropriate. If you do not to meet the minimum applicant requirements, your
application will be rejected.
1.2.1 As an Applicant, we are: (put an X in the appropriate box)
An electric utility holding a certificate of public convenience and necessity under AS
42.05, or
An independent power producer, or
A local government, or
x A governmental entity (which includes tribal councils and housing authorities);
Yes
1.2.2. Attached to this application is formal approval and endorsement for its project by
its board of directors, executive management, or other governing authority. If a
collaborative grouping, a formal approval from each participant’s governing
authority is necessary. (Indicate Yes or No in the box )
Yes
1.2.3. As an applicant, we have administrative and financial management systems and
follow procurement standards that comply with the standards set forth in the grant
agreement.
Yes
1.2.4. If awarded the grant, we can comply with all terms and conditions of the attached
grant form. (Any exceptions should be clearly noted and submitted with the
application.)
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 3 of 17 9/3/2008
SECTION 2 – PROJECT SUMMARY
Provide a brief 1-2 page overview of your project.
2.1 PROJECT TYPE
Describe the type of project you are proposing, (Reconnaissance; Resource Assessment/ Feasibility
Analysis/Conceptual Design; Final Design and Permitting; and/or Construction) as well as the kind of
renewable energy you intend to use. Refer to Section 1.5 of RFA.
This project is a combination of reconnaissance, resource assessment, and feasibility analysis. The
deliverable resulting from the expenditure of grant and matching funds is the first Integrated Resource
Plan (IRP) for the future interconnected cities of Ketchikan, Wrangell, and Petersburg (the cities).
These cities will be connected via the Swan-Tyee Intertie transmission line which is currently under
construction and scheduled for completion by the end of 2009. The IRP will also include the nearby
communities of Kake and Metlakatla as transmission links to these communities are currently in the
planning process.
2.2 PROJECT DESCRIPTION
Provide a one paragraph description of your project. At a minimum include the project location,
communities to be served, and who will be involved in the grant project.
An integrated resource plan (IRP) identifies the future resource portfolio that achieves a set of
objectives that have been established by stakeholders of the IRP process. The resource portfolio is a set
of supply-side and/or demand-side improvements that eliminate any identified energy or capacity
deficits. Supply side improvements would be new generation construction, or modifications to existing
generation assets such that energy production or available capacity is increased. Demand side
improvements are system efficiency improvements or peak load modification measures. Stakeholders
include concerned citizen groups, commercial and industrial customers, utility or city government
officials, and representatives of state agencies. The stakeholders and the IRP issuing body (The Four
Dam Pool Power Agency, FDPPA) establish the objectives that govern how the resource portfolio is
established. Most IRP objectives are governed by the 3 major categories of cost, risk, and
environmental impact. The IRP process includes stakeholder input with final content decisions made by
the issuing body (FDPPA).
A note on restructuring:
The FDPPA is also undergoing a restructuring whereby two of the Agency’s four projects are being
transferred or sold back to the member utilities. The FDPPA is a Joint Action Agency organized under
State Statute and will remain the same although the name will be changed to the Southeast Alaska
Power Agency (SEAPA). This planned restructuring is scheduled to close in January, 2009. SEAPA
will remain the owner of the Swan Lake and Tyee Lake hydroelectric facilities as well as associated
transmission lines providing Agency power to Ketchikan, Wrangell and Petersburg including the Swan-
Tyee Intertie.
Developing an IRP requires an analysis of the regions generation and transmission system, and an
estimation of the regions load growth. Generation and load forecasts are modeled to determine when
and to what extent future energy and/or capacity deficits occur. Energy and capacity deficits are
resolved by a combination of constructing new generation facilities, and through load growth rate or
peak hour value reduction via demand side management. The IRP then documents a short term and
long term plan to address the energy and capacity deficits.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 4 of 17 9/3/2008
2.3 PROJECT BUDGET OVERVIEW
Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source
of other contributions to the project. Include a project cost summary that includes an estimated total
cost through construction.
The total budget for the IRP project is $312,000 with $60,000 contributed by the FDPPA, and an
assumed AEA grant amount of $252,000. FDPPA’s contribution is entirely direct funds with no in-
kind funds proposed. Of the total, $40,000 is for load research equipment and inflow metering,
$268,000 for contractual services (consultants), and the remaining $4000 budgeted for managerial
travel expenses associated with project management services.
IRP Budget ($1000's) FDPPA FDPPA FDPPA AEA Total
Task dir. exp Contractor Total Grant
Creation of Advisory Panel 0
Creation of Plan Criteria 0
Creation of Resource Portfolio Objectives 0
Analysis of Existing System 2 18 20 2 22
Analysis of future systems 3 8 11 23 34
Forecast Load Growth 0 8 8 48 56
Forecast Inflow Levels 0 8 8 42 50
Determine Reserve Criteria 0 1 1 0 1
Determine Energy and Capacity deficits 2 2 10 12
Conduct Resource Portfolio Feasibility
Studies 3 3 80 83
Perform Economic Analysis 1 1 2 32 34
Summarize Findings, write Report 5 5 15 20
Totals 6 54 60 252 312
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 5 of 17 9/3/2008
2.4 PROJECT BENEFIT
Briefly discuss the financial benefits that will result from this project, including an estimate of
economic benefits (such as reduced fuel costs) and a description of other benefits to the Alaskan public.
The primary benefit of an Integrated Resource Plan (IRP) is involvement of the public
stakeholders in the vitally important electrical system planning process. Integration is done on
two planes:
1. Integrating public policy with utility technical expertise
2. Integrating generation, transmission, and distribution planning
This integration ensures the regional system is planned to meet stakeholder objectives. Using a
regional IRP process prevents expensive, stranded asset formation and ensures the opportunity
for continued growth for all communities in the region. Planning is performed on two levels, a
short term (next 5 years) plan, and a long term plan that identifies longer lead time issues such as
new hydro asset construction. Additionally, if a system wide efficiency gain of just .5% is
achieved; diesel fuel consumption will be reduced by 75,000 gallons (based on generation of
225,000 MWh annually and a heat rate of 15 gal/kWh). The other over-riding goal is to reduce
regional diesel generation to a reserve role, and move all primary generation to renewable
resources.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 6 of 17 9/3/2008
2.5 PROJECT COST AND BENEFIT SUMARY
Include a summary of your project’s total costs and benefits below.
2.5.1 Total Project Cost
(Including estimates through construction.)
$ 312,000
2.5.2 Grant Funds Requested in this application. $ 252,000
2.5.3 Other Funds to be provided (Project match) $ 60,000
2.5.4 Total Grant Costs (sum of 2.5.2 and 2.5.3) $ 312,000
2.5.5 Estimated Benefit (Savings) $ 150,000 annually
2.5.6 Public Benefit (If you can calculate the benefit in terms of
dollars please provide that number here and explain how
you calculated that number in your application.)
$ the IRP will identify
public benefit
SECTION 3 – PROJECT MANAGEMENT PLAN
Describe who will be responsible for managing the project and provide a plan for successfully
completing the project within the scope, schedule and budget proposed in the application.
3.1 Project Manager
Tell us who will be managing the project for the Grantee and include a resume and references for
the manager(s). If the applicant does not have a project manager indicate how you intend to
solicit project management Support. If the applicant expects project management assistance
from AEA or another government entity, state that in this section.
Over-all IRP project management and coordination of IRP tasks will be supplied by the FDPPA.
The bulk of the analysis effort and some of the IRP project management, at the task level, will be
provided by contractors (consultants).
Eric Wolfe, a FDPPA employee and current Director of Special Projects, will be the IRP Project
Manager. Mr. Wolfe has 20 years of utility engineering and management experience. Mr.
Wolfe has advised utilities on; hydro turbine and hydroelectric plant sizing, lost revenue effects
resulting from relicensing mitigation, forward production and cost estimates, and system
operations. As part of Idaho Power Company’s Planning Group, Mr. Wolfe contributed to the
IRP effort, managed the implementation of decision support software, and supplied the Planning
Group’s marketing arm with term and day-ahead buy/sell volumes.
Mr. Kevin Cooney of Summit Blue Consulting will manage portions of the project concerning
load forecasting, demand side management, and portions of the portfolio feasibility studies. Mr.
Cooney has 20 years of experience in the electric utility sector, primarily as a consultant. His
areas of expertise include but are not limited to renewable energy evaluation, energy efficiency
program evaluation, and IRP process management.
Economic analysis tasks and economic analysis sub-tasks will be managed by Mr. John
Heberling of D. Hittle Associates. Mr. Heberling has over 25 years of experience consulting to
electric utilities in the fields of electric utility finance, rate structure, and cost evaluation.
References for the project management team can be obtained by review of the enclosed resumes
of Attachment A.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 7 of 17 9/3/2008
3.2 Project Schedule
Include a schedule for the proposed work that will be funded by this grant. (You may include a
chart or table attachment with a summary of dates below.)
The initial phase planning tasks, such as the formation of the advisory panels, creation of the
plan criteria, and the creation of the resource portfolio objectives will not require AEA funds,
thus these tasks can start before FY 2010. The bulk of the project takes place during the 3rd and
4th quarter of 2009. The target date for issue of the draft IRP is June 2010. A Microsoft Project
schedule with task ID, durations, predecessor criteria, and end dates is enclosed in the
Attachments.
3.3 Project Milestones
Define key tasks and decision points in your project and a schedule for achieving them.
The key tasks for the IRP process are listed below and a Gantt chart of the project is listed in the
Attachments.
3.4 Project Resources
Describe the personnel, contractors, equipment, and services you will use to accomplish the
project. Include any partnerships or commitments with other entities you have or anticipate will
be needed to complete your project. Describe any existing contracts and the selection process
you may use for major equipment purchases or contracts. Include brief resumes and references
for known, key personnel, contractors, and suppliers as an attachment to your application.
The primary personnel of this project will be consultants with previous IRP experience. Within
task levels engineering consultants will be utilized. Potential engineering consultants will be
evaluated on the basis of their previous knowledge and work history regarding the task at hand.
Any consultants with both the appropriate experience and previous work history in Southeast
Alaska hydropower will be given preference.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 8 of 17 9/3/2008
Equipment, Load Forecast:
The on-going exchange from oil fired boilers to electric element water heating will cause both a
step change in the load curve as well as a shape change. The step portion occurs during the first
couple of years during the exchanges. The shape change means more electrical demand for the
same weather condition will occur in the future even though the number of households or
businesses could have remained constant. Small inexpensive digital devices mounted on electric
meters can quantify the difference between similar households with and without oil fired boilers
use. At this time we do not know the appropriate number of devices, or if devices are absolutely
necessary, but the budgetary provision for physical measurement should be made.
Equipment, Inflow Forecast:
It is quite possible streamflow measurement or weather stations may have to be added at
strategic locations in the region. Additionally, existing sites may need communication or
upgrade improvements.
Other Resources:
Numerous feasibility studies for individual projects have been previously completed and
submitted to the Alaska Energy Authority. These studies will be carefully reviewed to eliminate
any duplication of efforts.
3.5 Project Communications
Discuss how you plan to monitor the project and keep the Authority informed of the status.
Advisory Council meetings will be web based to keep travel time and travel costs to a minimum.
The project manager(s) will submit quarterly progress reports to AEA, and to the advisory
council, and the general public will have access to documentation either from an established ftp
site or from a new web page. The AEA should have representation on the Advisory Council and
casual periodic communication between AEA and the FDPPA is expected.
3.6 Project Risk
Discuss potential problems and how you would address them.
There is very limited to no physical or financial risk with producing an IRP.
SECTION 4 – PROJECT DESCRIPTION AND TASKS
• Tell us what the project is and how you will meet the requirements outlined in Section 2 of the
RFA. The level of information will vary according to phase of the project you propose to
undertake with grant funds.
• If you are applying for grant funding for more than one phase of a project provide a plan and
grant budget for completion of each phase.
• If some work has already been completed on your project and you are requesting funding for
an advanced phase, submit information sufficient to demonstrate that the preceding phases
are satisfied and funding for an advanced phase is warranted.
4.1 Proposed Energy Resource
Describe the potential extent/amount of the energy resource that is available.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 9 of 17 9/3/2008
Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be
available for the market to be served by your project.
The IRP at this time is thought to have the following main tasks:
• Creation of Advisory Council
• Creation of Planning Criteria
Planning criteria examples include; what percentile inflow and what percentile load
forecast should be used for energy and capacity analysis, what planning horizon should be
used such as 10 or 20 years, and how often the IRP should be updated such as every 2
years or sometimes up to 5 years.
• Creation of resource portfolio objectives
Resource portfolio objectives are typically a combination of reliability, cost, risk, and
environmental constraints. Cost concerns are expressed or measured through wholesale
tariff or consumer rate increase limits, risk is expressed ultimately by rate or bond costs,
or through stand-by or second tier generation costs, and environmental concerns are
expressed by state or federal pollution limits, the desire for green tag income, or through a
community willingness to implement a more environmentally oriented energy policy.
Resource objective implementation examples:
- the stipulation that new resources must be renewable or a stated percentage
renewable
- the inclusion of demand side management
- the inclusion of transmission upgrade/efficiency improvements
- resource portfolio over-all cost expressed in consumer rate increase
• Forecast load growth
• Forecast inflow levels and durations
Generation systems comprised predominantly of hydroelectric assets require inflow
forecasts to predict future generation capability.
• Determine future reserve criteria
• Analysis of existing system
Compile historic generation records, reliability estimates, and infrastructure reports
previously documented such that future generation estimates can be made. Build a
generation and transmission model such that existing and proposed facilities can be
analyzed.
• Determine energy and capacity deficits
• Conduct resource portfolio feasibility studies
• Analysis of Future System
• Perform economic analyses
This analysis condenses the portfolio options into a single cost criteria such as $/kWh or
in terms of general rates. The single cost value is then incorporated into an over-all cost
benefit analysis that includes reliability of service, environmental benefit, and community
enhancement
• Summarize findings into short term and long term plans, compile and distribute IRP
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 10 of 17 9/3/2008
4.2 Existing Energy System
4.2.1 Basic configuration of Existing Energy System
Briefly discuss the basic configuration of the existing energy system. Include information about
the number, size, age, efficiency, and type of generation.
The existing energy system.
Source: AK-BC Intertie Feasibility Study
Hatch Acres, 2007
Existing
Generation Diesel Hydro
Average
Hydro
capacity Capacity Energy
Site MW MW MWh
Metlakatla 3.3 4.9 16,100
Ketchikan 15 12.3 69,600
Swan Lake - 22.5 78,275
Tyee Lake - 22.5 116,800
Wrangell 8.1 - -
Petersburg 10.1 2.0 10,400
Kake - - -
4.2.2 Existing Energy Resources Used
Briefly discuss your understanding of the existing energy resources. Include a brief discussion of
any impact the project may have on existing energy infrastructure and resources.
During the winter of 2007 and 2008 Ketchikan Public Utilities (KPU) generated significant
energy using diesel engines to meet demand. Low inflows into their hydro projects and into
FDPPA’s Swan Lake reduced hydro output thus forcing a long period of diesel generation. In the
next few years this condition will be avoided as additional hydro generation, not previously
available, will be available to KPU from Tyee over the newly completed Intertie. As Wrangell
and Petersburg loads grow, less and less Tyee generation will be available to KPU (explained in
Section 4.2.3). Future load - generation balance levels are difficult to estimate as load growth is
uncertain and thorough hydrologic records are not available. This leads into the purpose of an
IRP. The fundamental purpose of the IRP is to project future energy and capacity shortfalls, and
after identifying the shortfalls suggest the most cost effective alternatives that also meet the
criteria established by the Advisory Council.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 11 of 17 9/3/2008
4.2.3 Existing Energy Market
Discuss existing energy use and its market. Discuss impacts your project may have on energy
customers.
Rates and Agreements
The Four Dam Pool Power Agency (FDPPA) is undergoing restructuring as a result of the sales
of Terror Lake and Solomon Gulch hydroelectric projects. The restructured agency, The
Southeast Alaska Power Authority (SEAPA) will own Tyee and Swan Lake generation projects,
as well as transmission lines connecting the cities of Petersburg, Wrangell, and Ketchikan.
Energy sales from SEAPA to Southeast municipalities will be in accordance with a new Power
Sales Agreement (PSA) which at this time is under negotiation. Terms of this agreement identify
generation from Tyee Lake (Tyee) and Swan Lake (Swan) as dedicated, additional dedicated, and
excess or surplus. Tyee dedicated generation means the output is first dedicated to the cities of
Petersburg and Wrangell, the next portion of energy available, additional dedicated, can be
imported by Ketchikan via the new Swan-Tyee Intertie. Any available energy in excess of the
dedicated and additional dedicated amounts can be sold as non-firm excess at an interruptible
rate. Output from Swan has the same classifications except the dedicated portion is held by
Ketchikan, and additional dedicated amounts are held by Petersburg and Wrangell. The dedicated
and additional dedicated rate is $69/MWh. Non-firm sales rates are negotiable. There is no
charge for voltage support or capacity under the existing PSA.
Municipal Loads
Load Peak
MWh MW
Ketchikan 152,160 28.9
Petersburg 38,949 8.81
Wrangell 20,571 -
Kake 2,974 -
Metlakatla 14,500 -
2006 Municipal Loads
Source: AK-BC Intertie Feasibility Study
Hatch-Acres
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 12 of 17 9/3/2008
4.3 Proposed System
Include information necessary to describe the system you are intending to develop and address
potential system design, land ownership, permits, and environmental issues.
4.3.1 System Design
Provide the following information for the proposed renewable energy system:
• A description of renewable energy technology specific to project location
• Optimum installed capacity
• Anticipated capacity factor
• Anticipated annual generation
• Anticipated barriers
• Basic integration concept
• Delivery methods
Future systems will continue to be a mix of Hydroelectric (primary) and diesel electric (reserves)
generation facilities. The potential for new transmission lines to capture new resources as well as
connect stranded communities exists. Renewable sources such as wind and tidal generation will
be evaluated, and demand side measures that help reduce peak hour load or reduce consumption
will be evaluated. The term demand side measure may be new for some readers so a partial list of
demand side measures is shown below.
• Remote control feeder operation for interruptible loads
• Retail and Commercial Housing improvements such as insulation credits, building code
modifications, CFD lighting benefit, and automated heating controls for peak hour
demand reduction.
• Transmission line or distribution efficiency improvements
4.3.2 Land Ownership
Identify potential land ownership issues, including whether site owners have agreed to the project
or how you intend to approach land ownership and access issues.
No land ownership issues with this project.
4.3.3 Permits
Provide the following information as it may relate to permitting and how you intend to address
outstanding permit issues.
• List of applicable permits
• Anticipated permitting timeline
• Identify and discussion of potential barriers
No permits with this project.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 13 of 17 9/3/2008
4.3.4 Environmental
Address whether the following environmental and land use issues apply, and if so how they will
be addressed:
• Threatened or Endangered species
• Habitat issues
• Wetlands and other protected areas
• Archaeological and historical resources
• Land development constraints
• Telecommunications interference
• Aviation considerations
• Visual, aesthetics impacts
• Identify and discuss other potential barriers
No environmental issues with this project.
4.4 Proposed New System Costs (Total Estimated Costs and proposed Revenues)
The level of cost information provided will vary according to the phase of funding requested and
any previous work the applicant may have done on the project. Applicants must reference the
source of their cost data. For example: Applicants Records or Analysis, Industry Standards,
Consultant or Manufacturer’s estimates.
4.4.1 Project Development Cost
Provide detailed project cost information based on your current knowledge and understanding of
the project. Cost information should include the following:
• Total anticipated project cost, and cost for this phase
• Requested grant funding
• Applicant matching funds – loans, capital contributions, in-kind
• Identification of other funding sources
• Projected capital cost of proposed renewable energy system
• Projected development cost of proposed renewable energy system
All estimated costs for preparing and issuing the IRP were listed in Section 2.3 Project Budget
Overview.
4.4.2 Project Operating and Maintenance Costs
Include anticipated O&M costs for new facilities constructed and how these would be funded by
the applicant.
• Total anticipated project cost for this phase
• Requested grant funding
All estimated costs for preparing and issuing the IRP were listed in Section 2.3 Project Budget
Overview.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 14 of 17 9/3/2008
4.4.3 Power Purchase/Sale
The power purchase/sale information should include the following:
• Identification of potential power buyer(s)/customer(s)
• Potential power purchase/sales price - at a minimum indicate a price range
• Proposed rate of return from grant-funded project
Not applicable to the IRP project.
4.4.4 Cost Worksheet
Complete the cost worksheet form which provides summary information that will be considered
in evaluating the project.
Download the form, complete it, and submit it as an attachment. Document any conditions or
sources your numbers are based on here.
A cost worksheet form has been completed to the extent applicable for a grant to issue an IRP.
Many of the items in the form, regional generation, load, sales, and the appropriate development
of renewable generation will be addressed by the IRP, and cannot be stated at this time.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 15 of 17 9/3/2008
4.4.5 Business Plan
Discuss your plan for operating the completed project so that it will be sustainable. Include at a
minimum proposed business structure(s) and concepts that may be considered.
Not Applicable to IRP process.
4.4.6 Analysis and Recommendations
Provide information about the economic analysis and the proposed project. Discuss your
recommendation for additional project development work.
During the IRP process, economic analyses by utilities in the region will be reviewed. These
reviews are intended to make the economic evaluation within the IRP consistent with previous
works. If no consistency can be achieved, the reasons for the inconsistencies will be documented.
SECTION 5– PROJECT BENEFIT
Explain the economic and public benefits of your project. Include direct cost savings, and how
the people of Alaska will benefit from the project.
The benefits information should include the following:
• Potential annual fuel displacement (gal and $) over the lifetime of the evaluated renewable
energy project
• Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price,
RCA tariff, or avoided cost of ownership)
• Potential additional annual incentives (i.e. tax credits)
• Potential additional annual revenue streams (i.e. green tag sales or other renewable energy
subsidies or programs that might be available)
• Discuss the non-economic public benefits to Alaskans over the lifetime of the project
An integrated resource plan (IRP) identifies the future resource portfolio that achieves a set of
objectives that have been established by stakeholders of the IRP process. The resource portfolio
is a set of supply-side and/or demand-side improvements that have been approved by the public
and thus a general understanding of loads, resources, and the resulting rates is gained.
Stakeholders include concerned citizen groups, commercial and industrial customers, utility or
city government officials, and representatives of state agencies. Including non-economic
measures such as environmental concerns and social benefit assures the general public will
benefit though a well researched and documented process. The IRP reduces the chance of
stranded asset construction and provides the list of alternatives based on cost, risk, and
environmental impact.
Renewable Energy Fund
Grant Application
AEA 09-004 Grant Application Page 16 of 17 9/3/2008
SECTION 6 – GRANT BUDGET
Tell us how much your total project costs. Include any investments to date and funding sources,
how much is requested in grant funds, and additional investments you will make as an applicant.
Include an estimate of budget costs by tasks using the form - GrantBudget.xls
Provide a narrative summary regarding funding sources and your financial commitment to the
project.
Estimated consultant fees were based on a rough estimate for project scope. The IRP effort was
estimated to be significantly less than the effort expended by Northwest Utilities. The
assumption of reduced effort was based on the reduced complexity of load and generation
resources, the lack of a connected market or markets, and the lack of complex transmission
evaluations. Planning managers at Avista, Idaho Power, and Seattle City Light were consulted
for broad scope discussions and feedback concerning the IRP effort. Examples of these
Northwest Utility IRP reports are stored on the FDPPA’s ftp site and can also be downloaded
from the utility web sites.
The Four Dam Pool Power Agency will commit $60,000 to the IRP effort. The project total cost
is estimated at $312,000. In addition to the cash commitment, FDPPA is volunteering staff time
to over-see and manage this project.
Renewable Energy Fund ALASKA
ENERGY AUTliORITY Grant Application
SECTION 7 -ADDITIONAL DOCUMENTATION AND CERTIFICATION
SUBMIT THE FOLLOWING DOCUMENTS WITH YOUR APPLICATION:
A. Resumes of Applicant's Project Manager, key staff, partners, consultants, and
suppliers per application form Section 3.1 and 3.4
B. Cost Worksheet per application form Section 4.4.4
C. Grant Budget Form per application form Section 6.
D. An electronic version of the entire application per RFA Section 1.6
E. Governing Body Resolution per RFA Section 1.4
Enclose a copy of the resolution or other formal action taken by the applicant's
governing body or management that:
authorizes this application for project funding at the match amounts indicated in
the application
authorizes the individual named as point of contact to represent the applicant for
purposes of this application
states the applicant is in compliance with all federal state, and local, laws
including existing credit and federal tax obligations.
F. CERTIFICATION
The undersigned certifies that this application for a renewable energy grant is truthful
and correct, and that the applicant is in compliance with, and will continue to comply
with, all federal and state laws including existing credit and federal tax obligations.
Print Name DAu~P -e.. .C-.A ~ LS.~~
Signature ~j
Title C)\=~~c...~G~\&i= ~~~
Date \\ ~\~ I~'S
AEA 09-004 Grant Application Page 16 of 16 9/3/2008