HomeMy WebLinkAboutADF&G_Heatd � � Sarah Palin
333 RASPBERRY ROAD
ANCHORAGE, ALASKA 99518-1599
DEPARTMENT OF FISH AND GAME PHONE: (907) 267-2452
FAX.- (907) 267-2419
DIVISION OF SPORT FISH
May 20th12008
Too. Randy Hobby
Ti*qun Energy, Inc
Randy,
The Alaska Department of Fish and Game i's in the final stages of planning for construction of
a new hatchery near the existing Elmendorf Sport Fish Hatchery and is seeking opportunities to
reduce long-term op;,.., ational costs., Tiqun Energy has illustrated the potential to support our needs
through renewed operation of the KAPP cogeneration facility. ADF&G would be eager to enter
Rk
intoan agreement with Tiqun provided that ADF&D is not required to accept additional
operational or regulatory risk and that meaningful monitary savings can be realized. ADF&G iffis
currently enguaged in final facility planning and should begin detailed design work in May of
2008, During this design phase we will be finalizing the thermal demand and power use profiles
for the facility.
The following table presents the general estimated building and process water heating needs.
Heat need Amount Comment
Peak process water load, 11. 0 mmbtu /hr May be able to use condenser cooling water with
includes 100 gpm truck fill final heating using district heat
Peak building heat load 5.6 mmb tu hr Must use district heat
Lightest process water Load 3.6 mmbtu hr May be able to use condenser cooling water with
final heating using district heat
Average yearly process water 7.0 mmbtu/hr May be able to use condenser cooling water with
load final heating using district heat
Average yearly heating load, 9.0 mmbtu/hr Must use district heat for building HVAC
process plus building HVAC
Previous Maximum Heat Load 150 mmbtu/hr Up to 9,000 gpm of 75°F water
received from US Militry Power
Plant on Elmendorf AFB
Estimated Power Demand 500-600 kW/hr ■
5/000/000 kW yr
Note: It should be noted that this analysis does not consider the pumping energy needs to push the heatd
water through heat exchangers. The cost of pumping must be considered in evaluating the economics of
this heat source.
While ADF&(i currently plans to install on site natural gas fired boilers to provide this heat we
dare prepared LO accommodate the use oi other heat sources such as low temp (80° r ) condenser
cooling water and higher temperature district heat. Maximum well water flow to the facility may
be as high as 2,300 gpm but we do not anticipate heating more t
F),, Until
minimize
Ti'*qun to evaluate and execute a 1
resource and creates the greatest
Sincerely,
�9
Jeff Milton
ADF&G, Division of SportFish
Hatchery Program Supervisor
333 Raspberry Road
Anchorage, AK 99518
-
I- 907267-2523
han 1,600 gpm t"roin (40° F64'
further dtfesign work is complete ese are simply estimates and we will be working to
this demand ns much ns possible. However, ADF&G would like t
maximixes t
on -ierm supply contract that
operational savings for the Hatchery.
t
o work closely with
he benefical use of this
*.