Loading...
HomeMy WebLinkAboutAttachment 3.2 Project Schedule Gannt ChartIDTask NameDurationStartFinish1Phase I - Reconnaissance Complete0 daysFri 12/12/08Fri 12/12/082Grant Award and Notice to Proceed (NTP)10 daysFri 12/19/08Mon 1/5/093Phase 2 - Resource Assessment / FeasibilityAnalysis / Conceptual Design (35%)73 daysMon 1/5/09Wed 4/15/094Gather existing Data15 daysMon 1/5/09Fri 1/23/095Gather geotechnical data for boiler and chipstorage building15 daysMon 1/26/09Fri 2/13/096Write Feasibility Report and develop plans to35%40 daysThu 2/5/09Wed 4/1/097Issue 35% Planset0 daysWed 4/1/09Wed 4/1/098AEA, agencies, contracted parties review andcomment on report and plans10 daysThu 4/2/09Wed 4/15/099Phase 3 - Final Design163 daysThu 4/16/09Fri 12/4/0910Develop planset to 65%65 daysThu 4/16/09Fri 7/17/0911AEA, agencies review and comment10 daysMon 7/20/09Fri 7/31/0912Develop planset to 95%21 daysMon 8/3/09Mon 8/31/0913AEA, agencies review and comment10 daysTue 9/1/09Tue 9/15/0914State Fire Marshall review and approvepermit22 daysWed 9/16/09Thu 10/15/0915Complete planset to 100%, write bidspecifications12 daysFri 10/16/09Mon 11/2/0916School Board review/approve final plansetand bid package22 daysTue 11/3/09Thu 12/3/0917Issue 100% For Construction Plans0 daysFri 12/4/09Fri 12/4/0918Phase 4 - Construction Phase234 daysMon 12/7/09Mon 11/1/1019Issue RFP22 daysMon 12/7/09Thu 1/7/1020Bid Award22 daysFri 1/8/10Mon 2/8/1021Construction88 daysTue 6/1/10Thu 9/30/1022Commissioning/Startup10 daysFri 9/17/10Thu 9/30/1023Final Inspection/Acceptance0 daysThu 9/30/10Thu 9/30/1024Closeout Activities22 daysFri 10/1/10Mon 11/1/1012/124/112/49/30Dec '08Jan '09Feb '09Mar '09Apr '09May '09Jun '09Jul '09Aug '09Sep '09Oct '09Nov '09Dec '09Jan '10Feb '10Mar '10Apr '10May '10Jun '10Jul '10Aug '10Sep '10Oct '10Nov '1020092010TaskSplitProgressMilestoneSummaryProject SummaryDeadlineDelta/Greely School DistrictDelta Junction, AKDelta High SchoolBulk Wood Heating SystemSection 3.2 Project ScheduleDelta High School - Home of the HuskiesPage 1Project: Preliminary Schedule Wood HeatingDate: Wed 10/1/08