Loading...
HomeMy WebLinkAboutKiseralik Chikuminuk Hydro App part 4I a fl 4.2.3 4.2.4 1916/485(15) at the villages. (Taken from Retherford Associates, Single Wire Ground Return Report, 1982) Regional intertie cost of construction - $16,946,384. 0&M - $201,590 annual. Lake Chikuminuk Hydroelectric Projects 9.5 MW Project: Construction Cost - $152,549,913 (per Harza Engineering) 0&M - $469,980 24 MW Project: Construction Cost - $209,764,264 (per Harza Engineering) 0&M - $766,515 Note: Costs for construction and 0&M included here cover only generation and transmission of the power to Bethel and do not include the costs of distribution to the Region. Therefore the costs of the Regional intertie must be included to provide a complete picture of project costs. Coal -Fired Steam Turbine Plant 0&M - Fixed component $62.70/Kw/Yr - Variable component $4.32/Mwh Price of coal utilized is $140.00 per ton delivered to Bethel (Cape Beaufort coal per the consultant). Nominal BTU values are 13,000 per pound. The coal price is escalated at an average annual rate of 1.5%. The coal efficiency rate used was 7618 KWH/ton. This figure is subject to further losses due to plant efficiency rates. 4 MW Project: Construction Cost - $17,648,868 (per Harza) 0&M - $447,944 10 MW Project: Construction Cost - $38,503,671 (per Harza) 0&M - $995,432 9 I u ed 0 11 I I Note: Above construction costs only include those relative to power at Bethel. Full cost profiles for the region must include the distribution intertie. 4.3 Present Worth Analysis The following table is an illustration of the present worth of the base case costs in relation to selected proposed alternatives and the associated present worth ratios. Benefits of waste heat are not included in the present worth values. The diesel base case, the diesel intertie and coal scenarios would benefit as a result of waste heat capture. The hydroelectric cases would not as there is no heat production with hydro power generation without implementation of a sophisticated load management program. Construction Cost Present Worth* Present Worth Ratio TABLE 4 COST OF ELECTRICAL ENERGY SUPPLY $1985 (1986-2041) Base Case 157,585,808 Regional Intertie 18,975,878 192,336,286 .82 Sub -Regional interties Akiachak Athmautlauk Oscarville Oscarville Napaskiak Akiak Kwethluk Nunapitchuk Kasigluk Akiachak Akiak 499,421 159,085,388 846,013 159,690,713 3,250,002 161,108,189 3,252,307 161,725,159 2,358,420 164,036,808 .99 .99 .98 .97 .96 Construction Cost Present Worth* Present Worth Ratio Construction Cost Present Worth* Present Worth Ratio * A11 Project Costs 1916/485(16) Coal Fired Steam Plant 4MW IOMW 36,624,746 57,479,549 195,167,043 247,460,175 .81 .64 Lake Chikuminuk Hydroelectric Project 9.5MW 24MW 171,525,791 228,739,142 410,952,298 512,643,449 .38 .31 I Note: Above construction costs only include those relative to power at Bethel. Full cost profiles for the region must include the distribution intertie. 4.3 Present Worth Analysis The following table is an illustration of the present worth of the base case costs in relation to selected proposed alternatives and the associated present worth ratios. Benefits of waste heat are not included in the present worth values. The diesel base case, the diesel intertie and coal scenarios would benefit as a result of waste heat capture; the hydroelectric cases would not. 11 7 7 1 1916/485(16) I The alternatives are ranked in order of their present worth ratio (present worth cost of the base case divided by present worth cost of the alternative). All the coal-fired steam turbine cases and the Lake Chikuminuk cases are more capital intensive and have present worths much greater than the Base Case; therefore, their ratios fall below 1.0 by substantial margins. The intertie options, except for the Regional intertie, all cluster at 1.0. the project alternative break-even value. The price of fuel has the greatest effect on the outcome of the present worth analysis. A sensitivity analysis was performed increasing the escalation rate of the price of fuel to 0% for the first 3 years, then 3.5% for the next 17 years. It would be expected that the diesel alternative cases would be more attractive. Although the present worth of the base case increased 17%, the present worth ratios of the alternatives were affected minimally, and the order of the above rankings was retained. 5.0 CONCLUSION An economic energy source for the Bethel Region appears to lie neither in the coal-fired steam plant nor the Lake Chikuminuk hydroelectric options. Further, APA analysis of Harza's Lake Chikuminuk project designs revealed that the 9.5 MW project had insufficient capacity to meet the load requirements of the Bethel Region due to significant line losses. The 24 MW project, at an approximate cost of $33,000 per capita in the Region, may also suffer from design problems in power transmission. These conditions result from characteristics inherent in a transmission and distribution system which is too long for the load amount of being served. - Line losses on the order of thirty percent were calculated due to excessive charging current relative to the light loads. Balancing the load and maintaining proper voltages would require sophisticated and costly monitoring and control equipment to ensure safe and reliable operation of the transmission and distribution network. No redundancies or loops were incorporated in the consultant's design and no roadways for operation and maintenance would exist. A more direct solution to a dependable, less costly source of electrical generation appears to be in an alternative under the expanded base case options. In the short term, the intertie(s) would allow for greater economies of scale, less duplication of generation in the village --separate generation for school and village --and more dependable electricity. 1916/485(17) Because cost estimates and routing distances utilized for the Power Authority analysis were extremely conservative, it is felt that sufficient justification exists to perform more detailed site reconnaissance to refine the cost data and to develop a conceptual design specific to the needs and conditions of the Bethel region. Although the coal-fired steam plant has a high present worth cost in relation to the base case, the use of coal in the Region should not be dismissed summarily. The extensive coal resources in Alaska are the subject of increasing interest and study. At present, Arctic Slope Engineering, under contract to the Alaska Federation of Natives, is engaged in a development study of the Deadtall Syncline near Cape Beaufort for use in Western Alaska, including the Bethel Region. If the demand for coal were greatly increased, as it would be if all space heating in the villages were converted to direct coal combustion and a coal-fired steam plant were built, then the price of coal would most likely drop markedly. For instance, Arctic Slope Engineering's current analysis indicates that an FOB Bethel coal cost might be $127 per ton at 13,000 BTU per pound. There is a lack of definitive information and commitment at this time to the use of coal. A long term goal for the Bethel Region might be to determine the cost and availability of coal and the viability of such a plan. Since there is no established infrastructure for the delivery of coal to the Bethel Region, its viability as an economic option for energy generation is highly speculative. Harza's analysis of present worth for space heating supply showed a 30 percent reduction from the base case through the immediate conversion to direct coal combustion. This assumed a residential furnace replacement cost of $1200 per household, several hundred dollars per year for O&M and a delivered cost of $140/ton at 10,000 BTU per pound nominal values. Financing options were not addressed in the report. If an intertie system were in place, the utilization of coal for electrical generation would promote greater advantage of economies of scale than the diesel/intertie alternative with only coal-fired space heating. 1916/485(18) Kisarall*k Hydroelectric Potential Analysis Bethel — Section III Bethel - Section in APAIVE 111. ELECTRIC ENERGY RESO:U:RCEI I TI-Os section presents an analy'sis of exis;t;ing energy resources in the Bethel area,, J>a5et on available information, Published reports, U565 maps:, ffeld investigations and other available Ifteratur-e as listeP d in the hibliagra hies, uith oac, part, as :well as; communication with people in the area, have been utilized to complete knawledge on resourcts that can t>e deVeloped with known technology within the next twenty years. RtAOUtces have been analyzed in regard to economic and environ-mental feasibility, Except tor the potential oil and gas discoveries, 'which would require a very large scale develaMent and are not addressed in; this report, the development of the Golden Gate hYdY'Oelec:t,ric Site aRpears to be the best prospect to pr&vide tbt- required electrical energy in the future, Small communities without access to hydroelectric or geothermal energy Vill have to rely on. diesel , coal/Wood gigneration, transmissiom interties or implement wind and solat Power on a small scale. Unfortunately neither coal/ wood generation or win:d And solar power appear,tIq be economically advantageous at this time. , StOre restralAts ;on devel6paent of most potential resour"ce s are created by the present land statu$ uncertainties, Fievelopeable potential resourCes are however, ment4janed and economically evaluated on a�n approxim'a'te basis in tbis study regardless of the Potential land usage conflicts. The following potential energy resources will be discussed: I. *4r1electric Potential Z, Coal/Wood Entergy Con'versllon 3. Geothermal: Potential A-, Wind Power Potential 5Transmission Intertiec- 6, Conservation The available energy resources will be 4valuated in regaM tt, their potential to replata� or sopplement the pr:es:en:t ;jse of petr*114;eum f Uels. Bethel - SectionIII AP1/ The present state of the art in vi'nd and solar energy conversions idered to: be uneconomical on a "'utility" scale due to either high cost or questionable both these energyconversion technologiesbe pursued on a demonstration - or private individual level -in the near; future. Overall energy needs, however, most be filled by means of proven technology and economically feasible developments. Emphasis has been placed on reftewable, resources. This does riot imply that other resources have been overlooked but rather attempts to put then in perspective in regard to possi.ble development and costs. 1.!:!&2)pctric Potential !! i The Golden Hydro, on the Kisaralik River has the potentialEsupplythe,entire future needsof the Bethel projectarea through the year 2000, ,The energy from;,;the Golden Gate hy4ro can! ! - ! by c t numerous small village!s surro'unding Bethel to d centralized power distribution point located in Bethel, whic:h is in turn suppliedvia a>.milelongtransission line from the Golden Gate Wdro project. This concept: is showin in Figure 111-1. It is estimated that 1986 would prove to bethe earliestpossibledatefor e project permitsassuming all necessary ' z acquired. This completion ! date is, however,ouestiooable present1future landstatus+uncertain. projectThe _ i...E.iE....#"YukonDelta" National Wildlife Refuge created by the Federal Land Policy Management Act ;of November 16, 1978, Emergency Order 204E. The following pages address the preliminary geologic investigation, construction, construction cost, envirort- mental impact and energy potential of the Golden Gate Project. KiSaraliK River originates in the ilbuck Mountains and flows west-northwest approximately 110 miles where it empties into the K;skokwim River near the village of Akia . The proposed dam site is located in a narrow meandering gorge at approximate river mile 67 and $3.5 airline miles east-southeast of the City of Bethel, This site is in section 17, T , 2Wr Seward Meridian and identified as ""Lower Falls"" on the U.S. .S. Bethel - ) quadrangle although theta are no falls at the location. Where are no .significant falls anywhere along this section of river where a substantial head could be utilized, ""Ee=mow t s 4. . awl xw .� � ��. kx �'�� °�,. &aG� .B• g_ 'a�`,.�e. S`"�rakir .Ji& < �. +fir �- s_ '�., � h x ...8 w «;ramkj, ,. � t �'` � "'° ,,: ��a. <':i '� ,..,,,✓y, «.�'�z :� 4 •� -;�' Y w,. � �.`� s &', � � tea'' ., ^ .1 ^ _x Iwo'- -Me21 ism. Zxi IK vr in IK ..`6i y i lwwiyy : t; +4�M 'R 'B n . �1 3 Ap $ ■ s� JJJ�JJLA dX�/ <:K � �°•�' ... s' � 8��p� laaw � � c x tr �x 40 - jF ,ram � � •8iB (!!R +rEaliC +� _ «x ' F a _" z? a. K Drainage Area Normal Maximum ater Surface (msl EI, Minimum Water Surface, El. Tailwater El. Surface Area - Normal Max. W.S. Live Storage (70 ft. drawdown) Regulation Type Height Crest Elevation (nsl) Volume SPILLWAY Type Crest Elevation Width Design Discharge POWER TUNNEL Length: Finished Dia-meter POWER PLANT' Type Capacity MAxinum Gross Head Type of Turbines TRAtiWSSION LINE Vo I tage Length Conduc toTze ,r $* 544 sq, mi. (1409 L110 ft. (338 1060 ft. (323 805 ft. (245 m): 6700 Ac. (2680 a) 32-0,750 acft. (395.7 MCM) to cfs (22. 7 cms) Rockf i 11 ft. (96 M) ft. (343 a) 2,500,000 CY. (1,911,500 Asphaltic Concreto Ungated Side Channel 375 ft. (114 m) 87,000,cfs (2,464 cms) 925 ft' (282 m) 16 ft.6.9 m) modified horseshaeconcrete lined Undergtound 3000WW (2 units) Ve,rti"cal Fr�kis ,138 V -69 mi. (111 W 796.5 KCM� AC-$R Bethel Section IJI 4PA15/E The selected site offers several advantages, over other possible dam sites on the Kisaralik River. These are: (1) The topograpby is such that the volume of material t�, construct a. dam of sufficient height to providei" suitable storage and head for low winter flows is less than at the other sites. (2) The U-shaped bend in the river provides for a"very short over tunnel; a feature not evident at:the .`,.- other sites. (3) More favorable geologic conditions. (4) A natural bench at an appropriate height for the excavation of a side channel spillway. Several 'dam heights were investigated with respect to available prime power and :the of of dam vs. cost of power. Preliminary studiu. indicate a Jreservoir with normal maximum water surface at tl;evation 1110 will Orovid# the greatest ben4flt to cost ratio when using a regulated flow of., 800 cfs. All head and sUrage is developed with a rockfill dam 325 feet high with a crest at elevation U25 and a 90on 1110., This will create a reservoir having a capacity of 716,000 acre-feet of A usable storage of 320,750: acre feet is provided with a drawdovn of 70 feet. F i gure 111-2shows the'extent of the reservoir. Jhis chapteY�.9`ives a description of the Noject, tho Preliminary design of the major project elemeots,.;the schedule for the construction of the project and the est imate&osts. C ProJect Armaement, The Kisaralik River Project would consist of the fol:lowing principal elements., (1) A rockfill dam across the river, founded on rock, with a side channel spillway lhav:ing a crest at elev,ation 1110 on the north abutment..,,_,The up , k, slope of the dam would be 1.7 horizontal' to"I veritic`a The 'downstream slopoul,d ble�1.5 horizontal vertical." Ove-r"s,(ze rock would be placed against the downstream face for eart�hquake stability. T he d am would have a crest of 550 feet in length and 20 feet Bethel Section III. in width, An impervious membrane of asphaltic concrete on the upstreamface and a concrete grout Cap 8 longthe upstream toe would be Provided.. concrete intake structure with Invert at elevation 820 is provided with a trashrack bars the right abutment of the river. reinforced concrete lined tunnel feet in length with a finished diameter of 16 feet. underground powerhouse containing the turbines, venerators and electrical switchgear. 5 surface switchyard adjacent to the powerhouse adit containing the transformers, switches., etc. and transmission take -off structures.. Other facilities, including a 50 mile winter construction access road from near Wa , and transmission line. The powerplant would contain two generators rated at kv kW each, powered by vertical Francis turbines of 23,000 Hp each. The - protect would produce 1,31,400 ld per year. The not operating head would be in the order of 265 feet average flow is $00 cfs. The generating waits would have a overload rating of above their na pl Este rating. The head at which the outs would be required to operate, 30feet, is in the range normally covered by reaction (Francis) turbines. Vertical units were selected to minimize the horizontal dimensions of an underground powerhouse, minimum of two units should be installed so that the project, t which would be the major source of energy to the system, ould operate with one unit out of service., The installation of more than to units would require a larger powerhouse excavation and three 10 MW units with appurtenances would cost considerably more than t nits. if two 10 w units were installed initially with Rothe) - Sortion T') APAIS/E provisions for a future unit, all of the necessary excava- tion for the unit, in the powerhouse, tailrace and supply line would have to be done initially. The cost of installing three 10 MW units would be considerably higher than two 15 MW units in a one stage development and the cost of installing two 10 MW units with provisions for a .uture unit would cost approximately the same as installing two 15 MW units, The cost of mobilizing and providing camp facilities in this remote location is extremely high; therefore, stage development is not recommended. The installation of three or more units has the advantages of being able to operate the machines at a higher rate of efficiency and providing a greater peaking capacity with one unit down. During the early years of surplus energy, operation at a higher efficiency would result in spilling more water over the spillway. As, energy requirements approach the prime capacity of the plaint, the units would operate within a reasonable range of efficiency. With the long transmission line being the most vulnerable portion of the Project and hydruelectric units being very reliable, two 15 MW units have been selected for the purpose of this report. e. GeologyFoundation and ConstrAtionMaterials: The geo' ' ogy of the Bethel quandrangle was published in 1959 by Hoare and Coonrad (Map 1-285); there has been little `addition to this work since then. According to their classification., the bed"ck in the Lower Falls area is pert of the undifferentiated Gemuk group (KCg), of probable late Paleozoic and ftsozoic age. The unit is comprised of chiefly massive arcs thin -bedded, fine-grained siliceous rocks, some volcanic rocks, calcareous silt tone, and I imestone. At the damsite, the rocks are siliceous metasiltstones or argillites a ' nd'zcherts. The rocks are generally massive, displaying little evidence of former bedding planes. However, parting and outcrop patterns indicate a N20W strike for the original structure. Overprinting this texture are several zones of cherty, more resistant rock that trend roughly northwest and east -west, and at least two main joint sets (40EMON and NMMIE). While the structure of the unit is somewhat complex on a local scale, It appears to present-=, special probless for construction of a am. Bedrock ou'.crop on the hillsides above tine river is generally frost -riven and fractured, but fresher exposures adjacent to the scouring action of the river are more uniformly coMetent. A zone of especially Iresistant, cherty material cuts across the river in an east -west direction near the Lower Falls area. The zone is subParalltlproposed axis Of d.emajor portionr ckfM structure ;From numerous; outtrops or. both sides midstream,channel and feet of alluvium would r to be removed bottom x'a_♦ €r r r r ae • r of r were observed,: and there 's no indn of such from the regional ZOPPIng of 'Hoare and Coonrad. Tho mountainsides of the gorge area appear to have been Stable_ of majora 'Construction s be r from crosscuttingeither abutment. The a equidimentionaldebris one foot in rr. ta from the gorge one-half miles downstream Contain well -graded sandy Geologically, constroctioA Joiner sets. the dmsite is favorable, The most importa wouldProblem be adequate grojtinaOf I The watershed above' the proposed damsite was detervin to be r r, r � r r � r r r Bethel - Section III APA15/E The 544 square miles or 348,160 acres with 20 inches of runoff (1-67 feet) calcUlattg to 680,270 acte-fott of rwnoff per year. The total runoff of 580,270 acre-feet per year equates to an average annual flow of 800 cfs, It is believed that $00 cfs average would flow during the driest year and the power available used in this study would be firm with annual regulation. With a net head of 265 feet, the project would develop 15,000 continuous or 131,400 Wh of f I re energy per year. (See Appendix A -A), It is strongly recommended that a stream gage be installed near the proposed dansita at the earliest possible date. If the average annual flow is much greater than used iii this study, the dam shoU14 be designed for futvre raising, the power tunnel diameter increased, and the powerhouse' designed fot future expansion, if feasibility - level studies so indicate, 9, Description of Project Facilities: Dam: The da-m would be a non -overflow tockfill type Mounded on bedrock. The rockfill would have a maximum, height of 308 feet from elevation 810 to 1118. The crest would be 550 feet in length and 20 feet in width with a 7-foot high concrete coping wall on the upstream edge to elevation 1125 The rockfill iR the dam. with 'upstream slope of L7h-V and downstream slope of 1.5h;IV, will be zoned and compacted in the lifts with vibratory compactors. A concrete grout ca ' p will be placed along the, upstream toe to grout the rock joint sets. The dam would be sealed between the grout cap and the coping wall with asphaltic concrete pavement on the upstream face with an average thickness of 12 inches. A 20-foot high cofferdam placed upstream from the grout cap would divert the power water through the power tunnel during dam construction. The cofferdam would not 6e removed. A typical dam -section Is shown on Figure 111-7. An area -capacity curve for the reservoir is included in Figure I 11- 3, (2) SP-111WOY: The probable maximum flood for the Kisaralik ViverYas not been determined for this study. For estimating purposes, a spi,11way at elevatJon 1110 with a channel width of 375 feet and a slope of 5% Bethel, - Section 111 APAIVE Bethel - Section III APA15/E Each leg :of the trifurcation would contain a sph rical valve for positive closure of each waterway, The turbines and generators wll be connected by a vertical drive shaft. Each generator would have a continuous overload rating of 15 per ceht, Tunnel & Powerhouse are shown on Figure 111-6. (5) Transmission Lines: A substation at the powerhouse would trans -form the generated voltage of IM kV to the transmission voltage of 138 kV. Utilization of 138 kV nominal voltage anda 795 KCM conductor wo6ld as:sure ade:quate voltage levels in Bethel, Energy losses would be low due to the relatively large conductor chosen. An ;overhead line would strike northwest for approximately 56 miles turning sharply northward near Xwethluk and cross the Kuskokwim River. The I ine would -then turn southeast and terminate in a substation near Bethel. The total length of the transmission line woUld be approxi- mately 69 miles. (6) Access Roads-, There, are no access roads to; the si. �t the ''0 nt time. A winter access road approxi mately �50 miles in length from ;the village of -Aki to the project site would provide :the means of construction mobzation and demobzation. I A permanent road approximately 2 miles in length would be constructed downstream from the powerhouse to the concrete aggregate borrow area. A gravel strip would be constructed, at the end :of the pemanent road for project access with fixed wing aircraft. h - , Environmental and Other Concerns. Preliminary investigations indicate that caribou, moose, wolf, wolverine, grizzly bear, and b1ack bear habitats, and numerous raptor nesting sites along the Kisaralik River would probably be lost. There are no known archaeological sites in the area that would be inundated. However, to be certain that no sites ,,Are disturbed an archaeological survey should -be conducted prior to constrtictfbh. Bethel - Sect i on 1 l ApAIS/ The Kisara ik river impoundment would require further study to accurately assess the fishery in the river. Chums, king and silver salmon are known to spawn in the K saral'ik River an4-its tributaries .above the Golden Gate Falls (See Appendix Q-1). The transmission corridors would crass several small streams.. As there is a possibility that the transmission line construction could introduce sediment into these streams, A -study should be conducted daring the detailed environmental assessment, to determine the optimum methods of insuring that anadromeus fish streams are protected. Use of single wire ground return transmission system. wherever possible, would minimize visual impact. i.. Land Status - The powder-davelbp emt site is presently, located within the proposed Yukon Delta Wildlife 'Refuge (Federal Land Policy 14anaget t Act of Rovenber 16, 1978, Emergency Order 204E). The: 2114E withdrawal is valid for 3 gears. The Kisaralik River is also considered under Emergency Order 104t, which has not been invoked yet. This order would withdraw the river and ;a 2-4 mile corridor along each bank for a pare of Zg years and be more restrictive than the 204E order. If bills HR39 or S9 pass, the Kisaralik might also be included in the "Vild & Scenic i ver" system. j- Projett Construction; The project construction would be carried out by separate supp1 and. civil worts construction contracts. single general contractor would build the project. The contractor would be required to provide access to the site by constructing necessary barge facilities on the Kuskokwim River for unloading tonstnttion equipment, materials, supplies, etc.'as necessary to construct the project. The contractor wood construct the winter access road, air trip, permanent road, construction camp, - etc. as well as the other pmJect features and equipment installation. Overburd6 containing organic natter and decomposed rock removed from requiredexcavations would be used as fill material in the operator housing area on the left abutment of the river downstream of the powerhouse tailrace. ,