Project Schedule — 2009 / 2010
April — August 2009: (Meteorological data collection)
• Finalize new met tower locations and configuration
• Upgrade and recalibrate existing Eva Creek met towers
• Install new met towers per meteorologist recommendation
$940,000.00
April — June 2009: (Transportation Limitations and Logistics)
• Determine land requirements for access and adequacy of existing
railroad sidings
• Design larger off-loading facilities at siding
$100,000.00
April — December 2009 (Electrical Interconnect and Integration)
• Economic Integration
• System relaying
• Communication system design $200,000.00
April 2009 — June 2010: (Initiate Infrastructure Permitting)
• Avian Issues, Studies and Impact Assessments
• Cultural resource assessment
• Biological resource assessment $760,000.00