HomeMy WebLinkAboutATTACHMENT F 1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
ATTACHMENT F
FISHHOOK HYDROELECTRIC PROJECT FEASIBILITY STUDY
Primary factors affecting the technical and financial viability are as follows:
· Permitting - obtaining the legal authority and public acceptance to
construct the project.
· Resource availability - the quantity of the water available and the ability to
divert the required quantity to the project.
· Soils - Unexpected or adverse soil conditions can significantly affect
viability primarily in the area of construction cost.
· Engineering - Any unusual technical or engineering challenges for
construction can affect viability.
· Construction - Project management, unexpected costs or delays during
construction, or unaccounted expenses can affect the viability.
· Operation - reliability and unexpected operating conditions can affect
project viability.
· Contracts and Energy Market - Contracts and energy price fluctuations
can significantly impact the financial feasibility and project viability.
Mitigating and/or limiting risk with all foreseeable and reasonable possibilities for the
above issues will maximize project viability.
Permitting
Risk to the lender is completely mitigated because FRE is not asking for any loan money
until the project is fully permitted and authorized to construct. FRE will only utilize
bo rrowed money for the actual construction phase of the Project.
As of this date all remaining permits should be relatively straightforward. The only
foreseeable exception at this stage is obtaining a conditional use permit from the
Matanuska-Susitna Borough. The following describes the permits needed for the Project
and their current status:
FERC exemption - Applied for this permit on February 23rd, 2007. The Project is not on
federal land, does not affect navigable waters, and does not affect interstate commerce.
An exemption was granted on April 30th, 2007.
RCA utility application - The Regulatory Commission of Alaska (RCA) requires FRE to
demonstrate a fitness, willingness, and ability to complete the Project and provide power
before issuing a certific ate. They have 2 weeks upon receipt of the application to rule on
its completeness and, if complete, 6 months thereafter to make a decision on the
application. FRE has drafted an application for a certificate. The principle outstanding
item needed before submitting the application to the RCA is a financial commitment for
the Project from a lending institution. This has been held up pending receipt of an offer
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
from a utility to purchase power that has just recently been received. Power purchase
contract details still need to be finalized.
Based upon recent reversal of DNR's position requiring a charitable land lease for the
project, FRE has elected to request an exemption from RCA regulation.
DNR easement/lease application - The Department of Natural Resources land lease
process is the primary state permitting process that will drive the review of the project
and solicit public comments. DNR recently notified FRE that it can use the competitive
lease process for this project, which is not dependent on utility certification. Based on
this new information, FRE has requested that DNR proceed with the leasing process for
this project. The public process (which takes 60 days) for the competitive lease will
commence later in 2008.
DNR water rights - FRE applied for water rights in April of 2006. Water rights will be
issued after DNR Habitat Division makes a determination on the Project and the land
leasing is initiated.
Habitat Permit - Discussions with State fish and game review staff has resulted in a
preliminary agreement regarding the Project. The tentative investigation by Habitat
revealed Dolly Varden habitat in the lower 200 yards of the current Fishhook Creek
mouth. The old channel, where the Project tailrace will discharge, is considered superior
habitat and capable of supporting salmon spawning if the culvert is adequate. During the
summer of 2007 FRE Members found juvenile salmon in the old channel reach (none
were found in the current mouth reach).
Habitat has tentatively stated that if the fo llowing conditions are met then a permit will be
issued:
· Move the powerhouse up 200 yards from the culvert, effectively creating 200
yards of new habitat to make up for the possible loss at the current mouth.
Current design drawings reflect this change.
· Upgrade the culvert to the standards necessary for passage of adult salmon. FRE
has agreed to this and included such costs in the cost estimate for the Project.
· Provide a bypass to allow for continuous flows to the tailrace during turbine
maintenance. FRE has agreed to this and included such costs in the cost estimate
for the Project.
Matanuska-Susitna Borough - An easement application has been submitted to the Mat-Su
Borough. Thus far, they have indicated that the easement will be granted after the DNR
approves the project.
The Mat-Su Borough has indefinitely suspended development and adoption of the
Hatcher Pass Special Use District regulations. Until these are reactivated, no further
permits are required.
Under the SPUD, the Mat-Su Borough would likely require a conditional use permit for
the project. As the name implies, such a permit is conditional and what conditions, if
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
any, may be imposed are not known. It is possible that conditions could be required that
could significantly impact the project feasibility.
Public Involvement - FRE has presented the Project to the Fishhook Community Council
and received numerous comments, most of which were incorporated into the Project
design. Overall, the comments tended towards a neutral stance. Similar reactions were
obtained from the few who commented on the Project when it was displayed at the 2007
MEA annual meeting. Finally, letters describing the Project have been distributed to all
Mat-Su area State Senators and Representatives and the Governor, no ne of whom have
responded with comments.
Resource availability
The amount of power produced each year is a direct function of the available water.
Accurately accounting for the quantity and fluctuations in the water supply (hydrology)
are crucial in determining the overall project economics. A secondary effort in hydrology
is to determine maximum flood levels which can impact the engineering of the Project.
The primary basis for determining Project hydrology is analyzing and comparing
measurements taken at the intake with the USGS flow measurements on the Little Susitna
River which encompasses the Fishhook Creek drainage basin.
The United States Geological Survey (USGS) has maintained a gauging station on the
Little Susitna River at the Wasilla -Fishhook Road bridge since July 1946 (USGS Gauge
#15290000). The historical record consists of daily average flow readings. These values
are used for statistically estimating year to year power production including the minimum
expected power output for any given year.
The USGS also publishes real-time data for the gauge which consists of provisional data
averaged every 15 minutes. The real time data is used to verify that instantaneous flow
measurements taken at the intake site match those at the USGS gauge site after scaling
for basin size. Any significant discrepancy would indicate that scaling by the basin size
is not appropriate. To account for seasonal variation numerous instantaneous flow
measurements at the intake were taken throughout the year and compared with the real
time data at the USGS gauge.
The USGS gauging station is located approximately 3 miles downstream from the mouth
of Fishhook Creek. The basin and gauging location is shown in Figure 1.
Daily flow data from USGS gauge #15290000 was scaled by relative basin size to
determine the expected flows for Fishhook Creek. Table 1 summarizes basin areas for
the USGS gauge and the Fishhook sub-basin (begins at Project intake).
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
Table 1: Attributes of Gauging Station and Project Creeks
Little Susitna River USGS
Gauge #15290000 Proposed Fishhook Creek Intake
Location 618 42.6’ N
1498 13.8’ W
618 46.0’ N
1498 16.3’ W
Drainage Area
(sq. mi.) 61.90 6.66
Percentage of
Gauged Basin 100% 10.76%
Gauge/Intake
Elevation (feet) 916.6 2,550
Basin
Description
Mountainous alpine areas with
some alpine valley bottomlands.
Generally southerly facing.
Mountainous alpine areas with
negligible alpine valley
bottomlands. Generally easterly
facing.
To validate the expected stream flows based upon the USGS gauge on the Little Susitna
River, actual stream flow measurements were taken using a Swoffer Current Velocity
Meter. The following table summarizes these measurements where a corresponding real
time flow for the Little Susitna River was published.
Table 2 - Flow Measurements at Intake Compared with USGS
Measurements
Date
Fishhook
Intake Flow,
cfs
Little Susitna
Flow, cfs Ratio, %
3/24/2006 14:15 2.2 24 9.4%
7/7/2006 13:45 33.2 401 8.3%
7/8/2006 15:00 33.2 321 10.3%
10/20/2006 17:30 23.8 201 11.9%
4/9/2007 18:00 2.8 23 12.0%
5/12/2007 15:30 5.7 65 8.7%
Average 10.1%
As can be seen by the table, the average flow at the intake of the Fishhook Project is
slightly less than the expected 10.76% based on scaling the basin area. This could be due
to several factors:
· Inaccuracies in the method of the measurements at the Fishhook intake
using the Swoffer flow meter.
· Differences in soil type of the sub-basin on average compared to the full
basin.
· Differenc es in flow releases and timing due to elevation and/or
precipitation/runoff relationships.
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
Most likely, the error is due to the flow meter and the associated difficulty in obtaining
accurate flow readings at low velocities and in rough stream beds. However, to remain
on the conservative side, the value of 10.1% of the USGS reported Little Susitna flow is
assumed for the statistical analysis to estimate yearly project economics.
The long term record of data on the Little Susitna is beneficial in that accurate estimates
of the yearly power of the proposed project can be derived. As detailed above, the flow
data will be scaled by a factor of 10.1%. Before doing so, a review of the data follows
along with the procedure to obtain an average year of power production used for the
economic analysis.
The following chart graphically depicts yearly summaries for the dataset. A somewhat
noticeable aspect of the Little Susitna record set is a trend towards decreased peak runoff
values and an increase in minimum runoff values. There is also an obvious upward trend
in median values.
Figure 1 - USGS Little Susitna Gaging Summary
This indicates that there is a trend towards higher low to moderate flows. These are the
flows that are most important to the Project. This is further evidenced by the following
graph depicting the average daily Project flows for the record set split into two time
periods using 1979 as dividing point. The average is calculated using maximum values
of 30 cfs since this is the maximum flow that can be utilized by the Project. This
USGS Little Susitna Gaging Summary
0.0
2.0
4.0
6.0
8.0
10.0
12.0
14.0
16.0
1949 1959 1969 1979 1989 1999
YearMedian & Min Flow, cfs1
10
100
1000
Max Flow, cfsMedian Flow
Min Flow
Max Flow
5 per. Mov. Avg. (Median Flow)
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
streamflow trend is confirmed by USGS publications in 2005 (USGS Fact Sheets 2005-
3017 and 2005-3018).
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
Figure 2 - Daily Average Project Flows
In order to remain slightly conservative, the entire record will be averaged on a daily
basis to estimate average yearly power production. Actual average yearly power
production, if the trend remains, should be approximately 5% higher. The following
table summarizes the statistical results of the hydrology analysis in terms of Project
power output (as opposed to stream flows).
In conclusion, the long period of record at the USGS gaging station provides a high
degree of confidence in seasonal and annual flow variations available to the project. The
streamflow analysis presented tends towards the conservative side and the expected
average power production should generally increase in the future based on current trends
although this is not included in the economic analysis.
Table 3 - Summary Statistics of Annual Power Output, kWh
Annual Power Output, kWh
Median 7,630,000
Average 7,440,000
Min 5,320,000
Max 9,300,000
Daily Average Project Flow
0.0
5.0
10.0
15.0
20.0
25.0
30.0
1/1 2/1 3/1 4/1 5/1 6/1 7/1 8/1 9/1 10/1 11/1 12/1
DateProject Flow, cfsPre 1979 Avg flow
Post 1979 Avg flow
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
Soils
The soils around the Project are generally known to consist of gravelly and/or sandy silt
with cobbles and boulders strewn about. Preliminary investigations have confirmed this.
The exception to this is along the creek bank at the upper section of the Project which
appears to be almost entirely cobbles and boulders. Some hauled in backfill may be
required for this section of pipe. However, the pipe in this area consists of HDPE which
can accommodate local site conditions with its flexibility and rugged nature. Bedding
requirements for the HDPE are not as stringent as for steel pipe so this will also reduce
the select backfill required.
The final design phase of the Project, which is scheduled for the summer of 2008,
includes a full geotechnical investigation.
Engineering
No significant technical challenges are foreseen at this time in terms of engineering the
Project. Proper feasibility, however, requires careful attention to the amount power
produced. Small errors in miscalculations can have significant impacts. The following
illustrates the methods employed to arrive at the quantity of energy produced by the
Project.
The procedure used for the energy analysis was to numerically simulate operation of the
Fishhook project using actual historical daily flow values. This included accounting for
head loss in the pipeline as a function of flows and calculating the turbine output based
on the actual head, flow, and turbine operating efficiency at the given flow rate.
The calculation of the head loss in the pipeline is based on the explicit solution of the
Darcy-Weisbach equation presented by Streeter and Wylie 1. Roughness values for the
high density polyethylene (HDPE) pipe and for the steel pipe are 0.000005' and 0.00015'
respectively. Water kinematic viscosity has been interpolated at a temperature of 36
degrees F. For a total length of pipeline equal to 7,700’, the maximum head loss at the
design flow rate of 30 cfs is 62 feet. The static head for the project is 1,048'.
The total water-to-wire efficiency, which includes losses from the
generator and the transformer, is multiplied with the turbine
efficiency curve. Based on information provided by turbine
suppliers, the turbine and generator combined efficiency is
expected to be about 83%. An additional 2% is expected in the
transformer. Net system efficiency should be approximately
81%. As a conservative estimate, a net turbine efficiency of 77%
has been selected for calculating project output. The table to the
left shows the water-to-wire efficiency used for various
percentages of total project flow rate.
To obtain good efficiency at low flows, the Project design
includes a 1500 kW turbine and a smaller 400 kW turbine. This also provides some
power production when a turbine is offline for maintenance.
1 Fluid Mechanics, 8th Edition, Streeter and Wylie, 1985, McGraw-Hill Publishing Company
Flow % Efficiency
0% 0%
5% 0%
10% 46%
20% 65%
40% 73%
60% 77%
80% 77%
100% 77%
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
With the flow data, the pipeline losses, the net water to wire efficiency, power from the
Project is calculated using the potential energy remaining. The calculation is basically a
units conversion having the following form: 11.3455*0.746*Flow*Head/100*Efficiency.
Construction
A detailed construction cost estimate was prepared in 2007. Generally, prices used were
based on small quantity estimates so some savings will occur for large material orders.
On the other hand, actual material prices will likely increase by the time FRE begins
ordering materials so a new estimate will be generated once permitting approval is
obtained and prior to accepting any loans. This will be part of the final design.
The cost estimate, while detailed, incorporates a 20% contingency factor. While the
construction of the Project is deemed to be relatively straightforward due to the mild
slopes, road access and proximity to urban centers, and the simple nature of the Project
(there are no unique challenges or aspects to this Project), a conservative approach is
required to mitigate risks on the part of FRE Members and its lenders.
Nearly all aspects of construction will be put out to bid to bonded contractors. Large
items such as purchase of the turbine and generator and possibly the pipe will be done
directly by FRE. Even so, the cost estimate includes a contractor profit of 10% on the
entire construction budget - another somewhat conservative approach.
The cost estimate also allows for a generous amount of labor. Total budgeted
construction man hours translate into a 5 man crew working 60 hours a week for 5.5
months.
The economic analysis contains a complete breakdown of the construction cost estimate.
FRE’s development plan. included at the end of this application, contains a more detailed
discussion on all aspects of the construction.
Operation
One of the most important aspects of a hydroelectric project is maintaining reliable
operation. Attention to detail and identifying potential problems and finding appropriate
solutions are critical. This is especially true in the first few years of operation.
Run-of-river projects are particularly prone to reliability problems due to the lack of a
large reservoir and the associated intake difficulties. FRE has paid particular attention to
this critical component of the Project.
Fortunately, the bed load and erosion potential at Fishhook Creek is significantly less
than many other creeks, including McRoberts Creek which has a very high bed load.
FRE Member 's experience with intake design and operation at the McRoberts Creek
hydro has aided substantially in developing effective systems to handle high bed loads
without project disruption. This technology will be applied to the Fishhook Creek as
well. The schemes employed at McRoberts Creek are also very effective at trapping and
flushing floating debris such as sticks and leaves. Such debris will likely be comparable
in quantity at Fishhook Creek.
Another potential problem at run of river intakes is the handling of flood flows. FRE
Members witnessed first hand the massive floods of August 2006 (designated 100-year
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
floods by the USGS) in Hatcher Pass. Surprisingly, no erosion or bank jumping occurred
at the intake site. FRE expects no major problems after witnessing this event given that
this was nearly an all time record flood (the August 2006 flood was the second highest
flow recorded in the Little Susitna River). FRE will design the intake to easily pass the
record flood without any difficulty.
Contracts and Energy Market
Power sales contracts and the regional energy market will directly control project revenue
and thus project viability. FRE is in advanced contract negotiations with MEA for the
project, and expects a contract to be completed by November 2008.
Power Sales Contracts
FRE will sell the power to Matanuska Electric Association, Inc. (MEA). Until the end of
2014, MEA is an all-requirements customer of Chugach Electric Association, Inc. (CEA).
FRE, MEA, and CEA have verbally agreed to allow FRE to sell power to MEA at the
avoided energy cost that MEA pays CEA for power. This approach is revenue-neutral to
MEA and CEA, and thus protects their ratepayers from incurring stranded costs. MEA
and CEA are currently working to amend their contract to allow the Fishhook project,
and a contract amendment is expected by spring 2008. This contract amendment will be
approved by FRE, MEA, CEA and the RCA before FRE finalizes any loan obligations.
After 2014, FRE will continue to sell power to MEA. The pricing terms are still being
negotiated, but for project viability, continued sales on an avoided-cost basis is assumed.
Energy Market
To assess project viability in terms of contracts, CEA and MEA's avoided cost of energy
must be projected. For both utilities, the avoided cost of energy for the life of the Project
will be natural gas. MEA's generation plans have included use of coal, however this
would be for their base generation. Their peaking generation, which is what would be
offset by the Project, would be fired by natural gas.
Cook Inlet's natural gas market is currently in a state of flux, as proven reserves are
nearing depletion, and numerous gas contracts, including CEA's gas supply contracts,
will be expiring in the first five years of the Project. Historical and near-term projected
gas prices for CEA delivery under their existing contracts are presented in Figure 3.
CEA is currently negotiating new gas supply contracts for sales starting in approximately
2010. The terms of these contracts are unknown, but similar recent supply contracts (for
Enstar, Inc., the regional gas utility) have trended towards pricing based upon the Henry
Hub price for natural gas. In recent years, the Henry Hub price has generally been
bounded between $6 – 8 per MCF, excepting major supply disruptions, such as Hurricane
Katrina in 2005, which resulted in a temporary spike to around $14 per MCF. This will
result in a considerable increase in CEA's future natural gas costs. Any future MEA
natural gas contract s are expected to follow a similar price structure.
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
Figure 3 – Historical and Projected Natural Gas Prices to CEA
Mitigating this projected increase in future gas costs will be the increased efficiency of
new generation units planned by both CEA and MEA. CEA's aggregate heat rate of their
current thermal generation is approximately 10,800 MCF/kWh. With their planned new
generation, CEA's aggregate heat rate is estimated to improve to as low as 8,000
MCF/kWh (if they cease providing energy to MEA and Homer Electric Association, Inc.
(HEA) after 2014). This increased efficiency would largely counter the expected
increase in natural gas costs, resulting in a future avoided energy cost similar to the
current energy cost.
A 'bullet line' has been proposed to deliver natural gas from Fairbanks to Anchorage.
This line would tap the proposed North Slope Gas line. Given that the Cook Inlet natural
gas market is already migrating towards a national pricing structure, the availability of
gas from the bullet line is not viewed as a significant downside risk, unless this gas or the
1503 West 33rd Avenue, Anchorage, Alaska 99503
Phone: (907) 258-2420 Fax: (907) 258-2419
Fishhook Renewable Energy, LLC
pipeline is heavily subsidized by the State of Alaska. Also, it is considered unlikely that
this gas would be available to the Cook Inlet market until the twilight years of the
Project's financing, and thus will have minimal to no impact on project viability from a
revenue standpoint.
CEA and Municipal Light and Power (MLP) have proposed a merger. If these two
utilities completely merged, CEA could gain access to MLP's wholly-owned 1/3rd share
of the Beluga Gas Field. This gas is available to MLP (and presumably a successor
combined MLP-CEA) at cost, which is approximately $1 to 2 per MCF. If this gas were
made wholly available to a merged MLP-CEA, it would supply generation needs for
approximately 5 years. This is a worst case scenario, and is considered very unlikely, as
it would require nullification of several existing gas supply contracts and retention of the
all-requirements contract with MEA to impact FRE. In the event of this worst case
scenario, FRE would have to evaluate mitigating strategies such as refinancing the
project debt to remain solvent.
While there are many considerable unknowns that directly influence any forecast of the
avoided cost of energy over the life of the Project, FRE expects many of the most critical
unknowns to be resolved before project financing and construction commences. Best
available information regarding these unknowns at this time indicates that the project will
remain viable.
In consideration of these various factors in aggregate, FRE has assumed a power sales
rate of $0.05/kWh, over the life of the Project. Considering the totality of variables that
govern the future avoided cost of energy, FRE believes that this forecast is conservative.