Loading...
HomeMy WebLinkAboutMekoryuk AK Wind Turbines and Controls App Alaska Village Electric Cooperative Application for Renewable Energy Fund Grant Alaska Energy Authority Mekoryuk, Alaska Wind Turbines and Controls October 8, 2008 Table of Contents Grant Application 1 Resumes 2 Cost Worksheet 3 Grant Budget Form 4 Delegation of Authority 5 Supplemental Materials 6 Tab 1 Grant Application Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 1 of 12 9/2/2008 SECTION 1 – APPLICANT INFORMATION Name (Name of utility, IPP, or government entity submitting proposal) Alaska Village Electric Cooperative Type of Entity: Electric Utility Mailing Address 4831 Eagle Street Anchorage, AK 99503 Physical Address [same] Telephone (907)565-5531 Fax (907)562-4086 Email 1.1 APPLICANT POINT OF CONTACT Name Brent Petrie Title Manager, Community Development Mailing Address 4831 Eagle Street Anchorage, AK 99503 Telephone (907)565-5358 Fax (907)561-2388 Email bpetrie@avec.org 1.2 APPLICANT MINIMUM REQUIREMENTS Please check as appropriate. If you do not to meet the minimum applicant requirements, your application will be rejected. 1.2.1 As an Applicant, we are: (put an X in the appropriate box) X An electric utility holding a certificate of public convenience and necessity under AS 42.05, or An independent power producer, or A local government, or A governmental entity (which includes tribal councils and housing authorities); Yes 1.2.2. Attached to this application is formal approval and endorsement for its project by its board of directors, executive management, or other governing authority. If a collaborative grouping, a formal approval from each participant’s governing authority is necessary. (Indicate Yes or No in the box ) Yes 1.2.3. As an applicant, we have administrative and financial management systems and follow procurement standards that comply with the standards set forth in the grant agreement. Yes 1.2.4. If awarded the grant, we can comply with all terms and conditions of the attached grant form. (Any exceptions should be clearly noted and submitted with the application.) Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 2 of 12 9/3/2008 SECTION 2 – PROJECT SUMMARY Provide a brief 1-2 page overview of your project. 2.1 PROJECT TYPE Describe the type of project you are proposing, (Reconnaissance; Resource Assessment/ Feasibility Analysis/Conceptual Design; Final Design and Permitting; and/or Construction) as well as the kind of renewable energy you intend to use. Refer to Section 1.5 of RFA. We propose a project to complete the Final Design & Permitting and Construction of a system to add electrical generation from wind power to the existing electrical generation and distribution system. 2.2 PROJECT DESCRIPTION Provide a one paragraph description of your project. At a minimum include the project location, communities to be served, and who will be involved in the grant project. Our project involves the final design, permitting, construction, erection, startup, and commissioning of two wind turbines to supplement the existing power generation and distribution system for the community of Mekoryuk. Participants in the project include AVEC, STG, and Northern Power. AVEC will provide overall project management and electrical system engineering for the project. STG will be the general contractor, responsible for the design and installation of all civil works, erection of the wind turbines, and installation of all ancillary electrical systems. Northern Power will provide Northwind 100 wind turbines and startup & commissioning services. Site control has already been completed. The foundation design is completed. Permitting is underway, having already relocated the turbines in response to input from Fish & Wildlife. 2.3 PROJECT BUDGET OVERVIEW Briefly discuss the amount of funds needed, the anticipated sources of funds, and the nature and source of other contributions to the project. Include a project cost summary that includes an estimated total cost through construction. The project requires $3,506,406 to complete. Design & Permitting are already complete. Construction will require $3,486,130. Commissioning will require $20,276. AVEC will provide a cash contribution totaling $350,641. 2.4 PROJECT BENEFIT Briefly discuss the financial benefits that will result from this project, including an estimate of economic benefits(such as reduced fuel costs) and a description of other benefits to the Alaskan public. The primary financial benefit from this project will be reduced fuel costs to the people of Mekoryuk. Simulations of wind resource versus load demand result in an estimated gross fuel savings of over 38,000 gallons of diesel fuel per year at the Mekoryuk plant, from efficiency improvements due to new automated switchgear, from diesel-powered generation being displaced by wind, and by displacing diesel-fired hot water heating with excess electrical energy from the wind turbines. Global Energy Concepts conducted an independent study of wind turbine availability for AVEC. That study concluded that gross production estimates of energy production from wind turbines should be reduced by 18% to account for downtime. AVEC has anecdotal evidence to indicate Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 3 of 12 9/3/2008 that downtime is decreasing with experience and is currently somewhat less than that figure at existing Northwind 100 sites. Nevertheless, for the purposes of this grant application, we will reduce expected fuel savings for electricity production by 18%, that being the most recent independently estimated figure available. Reducing the gross estimate by 18%, we expect to save almost 33,000 gallons of diesel fuel per year at Mekoryuk. At AVEC’s 2008 actual average price of fuel at Mekoryuk of $4.47/gallon, savings will exceed $146,000 per year. If the price of fuel rises to $5.50/gallon, the savings will exceed $180,000 per year. If downtime can be cut in half, reduced to 9% from the 18% we are carrying for this application, then annual savings will approach $160,000 at current diesel prices and $197,000 at $5.50/gallon. In addition to the direct fuel reduction are the benefits of: - reduced long-term dependence on outside sources of energy; - reduced exposure to fuel price volatility; - reduced air pollution resulting from reducing fossil fuel combustion; - reduced possibility of spills from fuel transport & storage; and - reduced overall carbon footprint and its contribution to climate change. 2.5 PROJECT COST AND BENEFIT SUMARY Include a summary of your project’s total costs and benefits below. 2.5.1 Total Project Cost (Including estimates through construction.) $3,506,406 2.5.2 Grant Funds Requested in this application. $3,155,765 2.5.3 Other Funds to be provided (Project match) $350,641 2.5.4 Total Grant Costs (sum of 2.5.2 and 2.5.3) $3,506,406 2.5.5 Estimated Benefit (Savings) ($160,000) per year 2.5.6 Public Benefit (If you can calculate the benefit in terms of dollars please provide that number here and explain how you calculated that number in your application.) SECTION 3 – PROJECT MANAGEMENT PLAN Describe who will be responsible for managing the project and provide a plan for successfully completing the project within the scope, schedule and budget proposed in the application. 3.1 Project Manager Tell us who will be managing the project for the Grantee and include a resume and references for the manager(s). If the applicant does not have a project manager indicate how you intend to solicit project management Support. If the applicant expects project management assistance from AEA or another government entity, state that in this section. Alaska Village Electric Cooperative’s (AVEC) project management approach to this project, and to its overall energy upgrade program, is to utilize a team approach consisting of AVEC staff, external consultants and construction management contractors. AVEC provides a project team from its operating staff. The President and CEO acts as Program Executive and maintains ultimate authority programmatically and financially. The manager of the community development group acts as program manager. The group provides internal focus and coordination of special projects including project development, planning, construction coordination, and reporting. Resources include a project coordinator, contracts clerk, accountant, engineer, and community liaison. The vice president and manager of AVEC’s Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 4 of 12 9/3/2008 engineering group provide technical input on generation and distribution issues to the team. Additionally, the engineering group provides specifications, design and drawings for AVEC construction of diesel power plants and distribution systems. The manager of operation and construction provides construction management and commissioning input on behalf of new construction performed by AVEC staff. The manager of administrative services provides support in accounting, payables, financial reporting, and capitalization of assets in accordance with RUS guidelines. The project management team’s structure is designed to provide flexibility for the AVEC participants. They have operational responsibilities to the Cooperative as well as project development responsibilities. The functional-interface relationships allow engineering tasks, village government and public relations tasks, procurement functions, and internal construction operations to be dovetailed into the project development process. Cross utilization of talent and resources is an advantage to the project delivery process, providing economies of scale for utilization of project resources. For project delivery, an amalgamated team approach is utilized. To support the AVEC team, design consultants and construction managers (CM) are selected. Both disciplines are derived from a resource bank of professional firms with applicable histories of performance in rural Alaska. The construction manager works concurrently with the design consultant through design development to provide constructability insight and value engineering to maximize the overall effectiveness of the final construction documents. Concurrent with design development, material and equipment procurement packages are formulated by the CM in collaboration with AVEC’s purchasing manager. Each package is competitively procured or issued from cooperative materials. Purchase orders are formulated with delivery dates consistent with dates required for barge or air transport consolidation. Multiple materials and/or equipment are detailed for consolidated shipments to rural staging points, where secondary transport to the village destination is provided. The CM tracks the shipments and provides handling services to and around the destination project sites. The CM is responsible for the construction activities for all project components of the facility upgrade. Local labor forces are utilized to the maximum extent possible to construct the projects. Local job training is provided as a concurrent operation under the management and direction of the CM. All construction costs, direct and indirect are reimbursed on a cost only reimbursement to the CM or paid directly by AVEC. For the facilities applied for in this application, AVEC is responsible for managing the commissioning process in content with the CM, designers and vendors. That entails testing and training of operational personnel, as well as providing for all contract closeout documents. AVEC’s concern and objective is to have a managed project delivery approach from inception through operation. Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 5 of 12 9/3/2008 3.2 Project Schedule Include a schedule for the proposed work that will be funded by this grant. (You may include a chart or table attachment with a summary of dates below.) Grant Award Announcement: 12/15/08 Authorization to Proceed: 1/05/09 Permitting: 8/15/08-12/31/08 Order Wind Turbines & Towers: 1/12/09 Complete Electrical System Design: 4/17/09 Complete Civil Works Design: 4/17/09 Hire Installation Contractor: 5/18/09 Turbines Ready to Ship: 7/13/09 Complete Civil Works: 8/14/09 Turbines On Site: 8/17/09 Complete Turbine Erection & Electrical Works: 9/12/09 Complete Turbine Commissioning: 9/26/09 Complete Secondary Load Controller Commissioning: 10/23/09 3.3 Project Milestones Define key tasks and decision points in your project and a schedule for achieving them. Authorization to Proceed: required as early as possible to allow turbines to be ordered. Order Wind Turbines & Towers: 6 months required from order to ready-to-ship date. Permits Obtained: required by 4/1/09 to allow time to hire contractor to ready for start of construction season. Complete Civil Works: needs to be done by time turbines arrive on site. Complete Turbine Commissioning: needs to be done early enough in the season to allow time to commission and tune the secondary load controller. 3.4 Project Resources Describe the personnel, contractors, equipment, and services you will use to accomplish the project. Include any partnerships or commitments with other entities you have or anticipate will be needed to complete your project. Describe any existing contracts and the selection process you may use for major equipment purchases or contracts. Include brief resumes and references for known, key personnel, contractors, and suppliers as an attachment to your application. AVEC will ultimately be responsible for successful completion of the project, using partners that have successfully installed similar systems in the recent past. Electrical system engineering will be subcontracted, using current internal procurement practices and selection of engineering service providers from prequalified organizations. STG will provide the wind turbine foundations on a design/build basis, as they have done on previous similar projects. STG will also provide all ancillary electrical equipment and install the wind turbines and the electrical balance of plant. 100kW Northwind 100 wind turbines from Northern Power will be used. The permanent magnet, direct drive Northwind 100 is the latest wind turbine model from Northern Power, based on earlier NW100 wind turbine models that AVEC has installed and operated in wind/diesel applications for several years now. Developed in conjunction with NASA, NREL, and NSF specifically for remote use in extreme environments, the Northwind 100 embodies the most recent design practices in the industry. Northern Power’s experience with wind/diesel control systems complements AVEC’s. Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 6 of 12 9/3/2008 3.5 Project Communications Discuss how you plan to monitor the project and keep the Authority informed of the status. AVEC will assign a project manager to the project. One responsibility of the project manager will be to compile periodic progress reports for use by the Authority. Weekly and monthly project coordination meetings will be held with the project team to track progress and address issues as they arise. 3.6 Project Risk Discuss potential problems and how you would address them. In general, logistics, construction activities and weather all contain siginficant risks. AVEC routinely purchases Builder’s Risk insurance to mitigate its exposure to these risks. In addition to outside insurance, the experienced team of AVEC and STG with projects much like this one in similar circumstances reduces much of the risk. Logistics is a routine issue in rural Alaska. AVEC and STG both have extensive experience with the logisitcal conditions found in this Alaskan village. Advance planning and allowing time for contingencies is crucial to success in such environments. Construction can be challenging in rural Alaska. Both AVEC and STG routinely conduct construction operations in villages much like this one. Weather is another challenge when working in rural Alaska. AVEC and STG have worked in this area for years. As with logistics, allowing time for contingencies is important. SECTION 4 – PROJECT DESCRIPTION AND TASKS • Tell us what the project is and how you will meet the requirements outlined in Section 2 of the RFA. The level of information will vary according to phase of the project you propose to undertake with grant funds. • If you are applying for grant funding for more than one phase of a project provide a plan and grant budget for completion of each phase. • If some work has already been completed on your project and you are requesting funding for an advanced phase, submit information sufficient to demonstrate that the preceding phases are satisfied and funding for an advanced phase is warranted. 4.1 Proposed Energy Resource Describe the potential extent/amount of the energy resource that is available. Discuss the pros and cons of your proposed energy resource vs. other alternatives that may be available for the market to be served by your project. Mekoryuk is a high-value, class 7 wind regime for wind power generation. During 2007, 943,600 kWh of energy was generated at the Mekoryuk power plant using 67,500 gallons of diesel fuel. A two-machine array of Northwind 100 wind turbines generating almost 480,000 kWh per year could displace up to 50% of the energy normally generated by diesel, and provide excess energy to heat water for use at the school or water plant. Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 7 of 12 9/3/2008 The village of Mekoryuk is blessed with abundant winds but finds its fuel supply limited and costly. Solar power from photovoltaic solar arrays is a potential alternative, but suffers from higher capital cost and lower resource availability than wind at this site. Production of energy using tidal motion in the sea is a newly developing possibility. Technology to make use of tidal motion is as yet immature. Even after initial development activities have been completed, the sub-arctic maritime environment of much of Alaska will provide additional challenges to the use of this developing technology. 4.2 Existing Energy System 4.2.1 Basic configuration of Existing Energy System Briefly discuss the basic configuration of the existing energy system. Include information about the number, size, age, efficiency, and type of generation. The existing power plant at Mekoryuk consists of three separate diesel-powered engine generator sets, of 207 kW, 284 kW, and 250 kW capacity. These gensets were originally installed and started up in 1994, 1984, and 1988, and most recently rebuilt in 2006, 2003, and 2007. The overall plant generated 13.97 kWh for each gallon of fuel consumed in 2007. 4.2.2 Existing Energy Resources Used Briefly discuss your understanding of the existing energy resources. Include a brief discussion of any impact the project may have on existing energy infrastructure and resources. The existing power plant produces electrical energy by burning diesel fuel in engine-driven generators. By adding wind turbines to the existing system, we expect the project to provide the same amount of electrical energy using substantially less diesel fuel than is true today. In addition to offsetting much of the diesel-generated electricity, we also expect to use whatever wind-generated energy that exceeds electrical demand to heat water, also displacing diesel fuel that is presently burned in boilers. 4.2.3 Existing Energy Market Discuss existing energy use and its market. Discuss impacts your project may have on energy customers. Mekoryuk sits on the north shore of Nunivak Island in the Bering Sea. It is subject to subzero temperatures, extended periods of darkness and blowing snow. Reliable electric service is essential to maintaining home heating systems necessary to safeguard the health of the population, especially the elderly and infants. Mekoryuk is classified as an isolated village, relying on air transportation for delivery of medical goods and transport of sick or injured individuals or mothers nearing childbirth. Reliable electric service is essential to maintaining vital navigation aides for the safe operation of aircraft. Runway lights, automated weather observation stations, VASI lights, DME’s and VOR’s are all powered by electricity. Emergency medical service is provided in Mekoryuk by a health aide. Therefore medical problems and emergencies must be relayed by telephone or by some other communication means for outside assistance. Operation of the telephone system requires electricity. Reliable telephone service requires reliable electric service. Water in Mekoryuk comes from a well. Reliable electric service is required for the continuous Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 8 of 12 9/3/2008 operation of the water and wastewater systems and to prevent freezing of the systems which will cause extensive damage and interruptions in service. Mekoryuk is subject to long periods of darkness. Reliable electric service is essential for the operation of home lighting, streetlights and security lighting. Children walk to school and outside lighting helps them find their way and be on the look out for hazards such as deep snow or in the extreme case, polar bears. Residents of Mekoryuk rely on a subsistence lifestyle where food is gathered and harvested and then stored for when it is needed. Refrigeration is essential for the extended storage of perishable food stuffs. Reliable electric service is essential for proper freeze storage of food. We expect the addition of wind turbines to the electric generation system to reduce the amount of diesel fuel used on the island for power generation and for heating. 4.3 Proposed System Include information necessary to describe the system you are intending to develop and address potential system design, land ownership, permits, and environmental issues. 4.3.1 System Design Provide the following information for the proposed renewable energy system: • A description of renewable energy technology specific to project location • Optimum installed capacity • Anticipated capacity factor • Anticipated annual generation • Anticipated barriers • Basic integration concept • Delivery methods Renewable Energy Technology Description The system we plan includes two 100kW Northwind 100 wind turbines, along with electric boilers to make use of excess electrical energy produced when the wind-based generating capacity exceeds the electrical demand. The Northwind 100 represents a new generation of wind turbines. Its permanent-magnet, direct- drive architecture is the current state of the art for advanced wind turbine design. That architecture overcomes many of the challenges of connecting old-style induction generators to electrical distribution grids. The permanent-magnet generator is connected to a full power converter that converts its variable, low-frequency, alternating-current output to direct current, then back to tightly regulated alternating current for output to the grid. The permanent-magnet generator requires no reactive power to energize its magnetic field, removing that influence from the grid. The power converter allows a broad degree of control over the form and quality of the power output to the grid. The capacitance and active controls in the power converter allow reactive power to either be consumed or produced by the Northwind 100 regardless of its real power output, even in the complete absence of wind. The turbine controls allow power output to be controlled by dynamic grid conditions, including automatic output reduction or complete shutdown, regardless of wind conditions. The combination of advanced controls and integrated disk braking allows gradual ramping of turbine output up or down, minimizing flicker and maximizing usable power. Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 9 of 12 9/3/2008 We expect two Northwind 100 wind turbines to produce over 50% of the electricity consumed on the island today. The wind turbines should supply almost 480,000 kWh of electrical energy annually, including over 110,000 kWh for use to heat water. Anticipated Barriers Logistical and weather barriers are common in the area. AVEC has routinely overcome these barriers in similar projects in similar areas. Permitting can sometimes affect projects adversely. On Mekoryuk, AVEC has already determined an alternate site for the wind turbines in response to concerns expressed by Fish & Wildlife. Basic Integration Concept The wind turbines will interconnect with the existing diesel power plant. Secondary load control will dispatch boilers as required to use excess wind energy while allowing the diesel generators to continue running at efficient levels. Delivery Methods The wind-generated electrical energy will be delivered using the existing electrical distribution grid. 4.3.2 Land Ownership Identify potential land ownership issues, including whether site owners have agreed to the project or how you intend to approach land ownership and access issues. AVEC has control of the land required for the installation of the wind turbines and for their connection to the existing power plant. Reference: Lease Agreement 2004-000860-0. 4.3.3 Permits Provide the following informationas it may relate to permitting and how you intend to address outstanding permit issues. • List of applicable permits • Anticipated permitting timeline • Identify and discussion of potential barriers Permitting is underway. This project has been anticipated and planned for several years already. Final permits await only final design. The proposed location of the turbines has been revised once, based on input from Fish & Wildlife. 4.3.4 Environmental Address whether the following environmental and land use issues apply, and if so how they will be addressed: • Threatened or Endangered species • Habitat issues • Wetlands and other protected areas • Archaeological and historical resources • Land development constraints • Telecommunications interference • Aviation considerations Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 10 of 12 9/3/2008 • Visual, aesthetics impacts • Identify and discuss other potential barriers No environmental issues have come up. The proposed turbine location has been revised, based on input from Fish & Wildlife. 4.4 Proposed New System Costs (Total Estimated Costs and proposed Revenues) The level of cost information provided will vary according to the phase of funding requested and any previous work the applicant may have done on the project. Applicants must reference the source of their cost data. For example: Applicants Records or Analysis, Industry Standards, Consultant or Manufacturer’s estimates. 4.4.1 Project Development Cost Provide detailed project cost information based on your current knowledge and understanding of the project. Cost information should include the following: • Total anticipated project cost, and cost for this phase • Requested grant funding • Applicant matching funds – loans, capital contributions, in-kind • Identification of other funding sources • Projected capital cost of proposed renewable energy system • Projected development cost of proposed renewable energy system This application is for the last phase of the project. Preliminary work has already been done. We anticipate that the project will cost $3,506,406 to complete from this point. We are requesting $3,155,765 from AEA. AVEC will provide $350,641 as a cash contribution toward the project. Source of Cost Data Anticipated costs for wind equipment are per manufacturer’s estimates; all other cost estimates are derived from recent experience of Applicant and its consultants and construction managers, based on similar projects recently constructed or now under construction. 4.4.2 Project Operating and Maintenance Costs Include anticipated O&M costs for new facilities constructed and how these would be funded by the applicant. • Total anticipated project cost for this phase • Requested grant funding AVEC’s existing NW100 wind turbines require two maintenance visits a year. Those visits currently cost AVEC $3,500 per turbine per year. The new Northwind 100 model requires only one maintenance visit each year. So the two turbines at Mekoryuk will require a combined annual maintenance cost of $3,500. This cost will be funded by ongoing energy sales in the village. 4.4.3 Power Purchase/Sale The power purchase/sale information should include the following: • Identification of potential power buyer(s)/customer(s) • Potential power purchase/sales price - at a minimum indicate a price range • Proposed rate of return from grant-funded project Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 11 of 12 9/3/2008 The project breaks even at 17 years. 4.4.4 Cost Worksheet Complete the cost worksheet form which provides summary information that will be considered in evaluating the project. Download the form, complete it, and submit it as an attachment. Document any conditions or sources your numbers are based on here. See the attachment. 4.4.5 Business Plan Discuss your plan for operating the completed project so that it will be sustainable. Include at a minimum proposed business structure(s) and concepts that may be considered. The project will be incorporated into AVEC’s power plant operation. Maintenance will be managed in the same way as the maintenance of the diesel plant is managed. 4.4.6 Analysis and Recommendations Provide information about the economic analysis and the proposed project. Discuss your recommendation for additional project development work. The wind turbines and control systems provided as part of this project will be fully incorporated into AVEC’s power plant operations. From that perspective, the wind turbines will be treated as generating equipment, just like the generator sets. Maintenance schedules will be routinely developed and managed. The result will be improved reliability from the existence of additional generating sources and reduced fuel consumption from the use of wind. We do not anticipate any additional project development work at this site following this project. SECTION 5– PROJECT BENEFIT Explain the economic and public benefits of your project. Include direct cost savings, and how the people of Alaska will benefit from the project. The benefits information should include the following: • Potential annual fuel displacement (gal and $) over the lifetime of the evaluated renewable energy project • Anticipated annual revenue (based on i.e. a Proposed Power Purchase Agreement price, RCA tariff, or avoided cost of ownership) • Potential additional annual incentives (i.e. tax credits) • Potential additional annual revenue streams (i.e. green tag sales or other renewable energy subsidies or programs that might be available) • Discuss the non-economic public benefits to Alaskans over the lifetime of the project We expect two Northwind 100 wind turbines will displace 32,880 gallons of diesel fuel each year. So far in 2008, AVEC has spent an average of $4.4657 per gallon for the fuel it has used to generate electricity. If that continues to be the rate through the first year of operation of the wind turbines, then we will save $146,833 during that first year. Assuming a 4% rate of inflation for the next 20 years, we expect the project to save over $4.3 million over that period of time. At this rate, the project breaks even at just over 17 years. The non-economic benefits to the Alaskan population at large will be from the reduced carbon Renewable Energy Fund Grant Application AEA 09-004 Grant Application Page 12 of 12 9/3/2008 footprint of the power plant. By reducing the amount of fuel burned on the island by over 50%, we will prevent over 350 tons of carbon dioxide from entering the atmosphere each year. SECTION 6 – GRANT BUDGET Tell us how much your total project costs. Include any investments to date and funding sources, how much is requested in grant funds, and additional investments you will make as an applicant. Include an estimate of budget costs by tasks using the form - GrantBudget.xls. Provide a narrative summary regarding funding sources and your financial commitment to the project. AVEC is committed to providing $350,641 toward the completion of this project. Tab 2 Resumes Tab 3 Cost Worksheet  Renewable Energy Fund   Application Cost Worksheet Please note that some fields might not be applicable for all technologies or all project phases. Level of information detail varies according to phase requirements. 1. Renewable Energy Source The Applicant should demonstrate that the renewable energy resource is available on a sustainable basis. Annual average resource availability. 7.46 m/s, from V3 report of 12/4/07 Unit depends on project type (e.g. windspeed, hydropower output, biomasss fuel) 2. Existing Energy Generation a) Basic configuration (if system is part of the railbelt grid, leave this section blank) i. Number of generators/boilers/other 3 ii. Rated capacity of generators/boilers/other 207kW / 284kW / 250kW iii. Generator/boilers/other type diesel engine generators iv. Age of generators/boilers/other Dates of original startup: ’94 / ’84 / ‘88 Dates of last rebuild: ’06 / ’03 / ‘07 v. Efficiency of generators/boilers/other 13.97 kWh/gallon b) Annual O&M cost i. Annual O&M cost for labor ii. Annual O&M cost for non-labor c) Annual electricity production and fuel usage (fill in as applicable) i. Electricity [kWh] 943,618 kWh (2007) ii. Fuel usage (if system is part of the Railbelt grid, leave this section blank Diesel [gal] 67,552 gallon (2007) Other iii. Peak Load 240 kW (2007) iv. Average Load 108 kW (2007) v. Minimum Load 54 kW (estimated) vi. Efficiency vii. Future trends d) Annual heating fuel usage (fill in as applicable) i. Diesel [gal or MMBtu] 84,000 gallons (from CDR of 7/28/06) ii. Electricity [kWh] iii. Propane [gal or MMBtu] iv. Coal [tons or MMBtu] v. Wood [cords, green tons, dry tons] vi. Other RFA AEA 09-004 Application Cost Worksheet Page 1  Renewable Energy Fund     3. Proposed System Design a) Installed capacity 200 kW (wind turbine) b) Annual renewable electricity generation i. Diesel [gal or MMBtu] ii. Electricity [kWh] 478,000 kWh iii. Propane [gal or MMBtu] iv. Coal [tons or MMBtu] v. Wood [cords, green tons, dry tons] vi. Other 4. Project Cost a) Total capital cost of new system $3,506,405 b) Development cost c) Annual O&M cost of new system d) Annual fuel cost (savings) ($160,000) 5. Project Benefits a) Amount of fuel displaced for i. Electricity 26,000 gallons ii. Heat 3,000 gallons iii. Transportation b) Price of displaced fuel $4.4657 / gallon (2008 actual average) c) Other economic benefits d) Amount of Alaska public benefits 6. Power Purchase/Sales Price a) Price for power purchase/sale N/A 7. Project Analysis a) Basic Economic Analysis Project benefit/cost ratio Payback 17 years   RFA AEA 09-004 Application Cost Worksheet Page 2 Tab 4 Grant Budget Form Alaska Energy Authority ‐ Renewable Energy FundMekoyuk WindBUDGET INFORMATIONBUDGET SUMMARY:Milestone or TaskFederal Funds State FundsLocal Match Funds (Cash)Local Match Funds (In‐Kind)Other FundsTOTALS1. Design/Permitting $0.00 $0.00 $0.002. Construction $3,137,517.00 $348,613.00 $3,486,130.003. Commissioning $18,248.00 $2,028.00 $20,276.00$0.00$0.00$0.00$0.00TOTALS $3,155,765.00 $350,641.00 $0.00 $3,506,406.00BUDGET CATAGORIES:1234567TOTALSDirect Labor and Benefits$0.00Travel, Meals, or Per Diem$0.00Equipment$0.00Supplies$0.00Contractual Services $0.00 $3,486,130.00 $20,276.00 $3,506,406.00Construction Services$0.00Other Direct Costs$0.00TOTAL DIRECT CHARGES $0.00 $3,486,130.00 $20,276.00 $0.00 $0.00 $0.00 $0.00 $3,506,406.00Milestone # or Task #RFA AEA09-004 Budget Form 10/8/2008 1:17 PM2 Mekoryuk Wind STG 100208 for AEA grant applic CM Wind GenerationITEM QUAN UNUNIT MAT'L COSTTOTAL MAT'L COST HRS PER UNIT LABOR HOURSLABOR RATETOTAL LABOR COSTUNIT EQUIP COST TOTAL EQUIP COST UNIT SUB COSTTOTAL SUB COSTUNIT FRT COSTTOTAL FRT COST TOTAL COST UNIT WT. TOTAL WT. CM SUPPLIED COSTSWIND PADS AND ACCESS ROADSS.Flora Access Rd. Est. 11/30/06 $25,000.00 $50,000.00 $25,000.00 0 $125,000.00 $225,000.00#REF!Foundtations - STG supplied CostsKobelco Crane 1.5 Mo 0 170 0 90 0 24000 36000 0 0 0.15 31,500 $67,500 140000 210000Down the Hole Hammer 1 Mo 0 130 85 0 13000 13000 0 0 0.2 7,000 $20,000 35000 35000D25- 32 Pile hammer / leads 1.5 Mo 0 70 0 0 8500 12750 0 0 0.25 0 $12,750 0 0Loader/ support 980 1.5 Mo 0 130 85 0 10500 15750 0 0 0.2 18,000 $33,750 60000 9000024" Dia .75 wall x 55' Piles 8 EA 8849.5 70,796 17 136 90 12240 0 0 0.33 33,264 $116,300 12600 100800Thermal Syphons 12 EA 2600 31,200 9 108 0 0 0 0 0.33 3,960 $35,160 1000 12000Rock Anchor 12 EA 1400 16,800 19 228 95 21660 0 0 0.33 2,178 $40,638 550 6600Tower Base Steel 2 EA 65000 130,000 0 0 0 0 0 0 0 0 0.33 19,800 $149,800 30000 60000Circle Caps 12 EA 300 3600 0 0 0 0 0 0 0 0 0.33 1,267 $4,867 320 3840Crane Mats for access 0 Mo 0 130 0 0 7500 0 0 0 0.33 0 $0 60000 0Skid steer 2 Mo 0 130 85 0 4000 8000 0 0 0.2 3,200 $11,200 8000 16000rigging, welders, tools 2 Mo 0 130 0 0 5000 10000 0 0 0.25 6,250 $16,250 0 25,000Foundation Load Test 1 EA01500 10 15 110 1650 500 500 0 0 1.5 225 $3,875 150 150Crane Operator (foundations) 1 EA 0 10 40 90 3600 5000 5000 0 0 0.25 0 $8,600 0 0Welders 3 EA 0 50 150 85 12750 0 0 0 0 0.25 0 $12,750 0 0Foreman 1 EA 0 50 50 95 4750 0 0 0 0 0.25 0 $4,750 0 0Subtotal $253,896.00 727 $56,650.00 $101,000.00 0 $126,644.20 $538,190.20 559390Wind tower erectionWelders 2 EA 0 0 100 200 85 17000 0 0 0 0 0 0 $17,000 0 0Crane Operator 1 EA 0 0 144 144 85 12240 0 0 0 0 0 0 $12,240 0 0Foreman 1 EA 0 0 144 144 95 13680 0 0 0 0 0 0 $13,680 0 0Electrical 2 EA 1500 3,000 0 0 88.57 0 0 0 7000 14000 0 0 $17,000 0 0Tower Paint 0 EA 0 0 0 0 65 0 0 0 5000 0 0.25 0 $0 0 0Subtotal 3,000 488 42,920 0 14000 0 $59,920 63840TOTAL - Wind towers $281,896.00 1,215 $149,570.00 $126,000.00 14,000 $251,644.20 $823,110.20 623,230Transf SUB cost to Labor14,000.00$ (14,000.00)$ SUBTOTAL: 281,896.00$ 163,570.00$ 126,000.00$ 251,644.20$ 823,110.20$ FIELD SUPPORT:105,410.34$ CM COST:62,500.00$ TOTAL INCL. CM & FS991,020.54$ CONTIN @ 10%:28,189.60$ 16,357.00$ 12,600.00$ 25,164.42$ 99,102.05$ TOTAL CM COSTS: 310,085.60$ 179,927.00$ 138,600.00$ 276,808.62$ 1,090,122.59$ AVEC SUPPLIED COSTSNPS 100A Wind Turbines2 EA 400,000 800,000 0 0 0 0 0 19310 19,310 1 130,000 $949,310 130000Integration control module1 EA 1,130,000 70,00050,000 $1,250,000AVEC project mgmt, travel, etc.$50,000TOTAL - AVEC Spplied Costs $1,930,000.00 $70,000.00 $0.00 $19,310.00 $180,000.00 $2,249,310.00Work Order Total:$3,339,433AVEC 5% Admin:$166,973GRAND TOTAL:$3,506,406 Tab 5 Delegation of Authority Tab 6 Supplemental Materials • Mekoryuk Location Map • Wind Towers Site Plan • Efficiency Change Controls with Wind Added