HomeMy WebLinkAboutDevil Canyon - 10-15-86WHITE PAPER
ON
THE DEVIL CANYON HYDROPOWER PROJECT
PREPARED BY
THE ANCHORAGE CHAMBER OF COMMERCE
ENERGY COMMITTEE
OCTOBER 15, 1986
the Anchorage Chamber of Commerce Energy Committee has been
addressing railbelt electrical energy issues for several years.
Its group is composed of Anchorage business leaders who meet on
a twice monthly basis with the objective of formulating energy
policy on behalf of its full Chamber membership. It has been
very active in working to insure that its adopted policies are
implemented at the Local and State levels. Over the years, it
has been instrumental in helping to secure funding for the
Anchorage/Fairbanks transmission intertie, the Bradley Lake
hydropower project, and exploration funds for the Susitna
hydropower project. It has helped forge and supported critical
State legislation designed not only to benefit railbelt
consumers, but consumers throughout rural Alaska and in
particular those that are benefiting from the "four dam pool."
Members of the Energy Committee have committed not only their
time to this effort, but considerable dollars as well. In
addition to their own out-of-pocket expenses associated with
travel and time lost for attendance at key Legislative and
utility meetings, they have been successful in raising private
financing to assist in meeting Chamber objectives. One such
example was the raising of some $200,000 from private sources
for an independent assessment of the financing for the Susitna
hydropower project. Another was the funding and production of
an objective 30 minute documentry film on energy alternatives
for the railbelt.
Continual assessment of the viability of the Susitna
hydropower project has been a major objective of the Energy
Committee. Susitna holds the promise of long term energy
independence for railbelt consumers, and a near term source of
construction jobs for at least sixteen years. While the project
appears to make long term economic sense for the railbelt, it is
beyond the ability of the State and local utilities to finance
at this time. Thus, the Energy Committee has undertaken a
review of the much smaller Devil Canyon hydropower project as a
possible near term alternative to the full Susitna development.
This "white paper" is an attempt to encapsulate the
technical, economic, and financial issues associated with the
Devil Canyon project. The information present in this paper is
a product of existing documents and reports in the public domain
and of personal interviews with key political and utility
officials. Considerable information is available for review.
Millions of dollars have been spent or exploring the technical
and environmental aspects of Devil Canyon, but only scant
attention has been given to studying Devil Canyon as a stand
alone element of the total electric utility system. Much of the
Devil Canyon site specific information was obtained from
investigations conducted over the years by the U. S. Army Corps
of Engineers, the U. S. Bureau of Reclamation, and more recently
Preface
Continued
by the State of Alaska particularly through the efforts of the
Alaska Power Authority.
In evaluating Devil Canyon, it has been necessary to compare
it to energy alternatives which would be developed in lieu of
Devil Canyon. Coal or natural gas fired thermal generation
appear to be the most probable alternatives; and hence, these
alternatives have been used as the economic yardsticks by which
to evaluate Devil Canyon in this paper. This report, however,
does not attempt to review these options to the same depth as
Devil Canyon. Rather, these alternatives have been reviewed
from the standpoint of resource availability and long term cost,
but no effort was made to assess the technical, financial and
environmental aspects of these alternatives.
The main objective of this report is to review the relative
strengths and weaknesses of a Devil Canyon project so that
Energy Committee members may determine if the project warrants
more in-depth consideration by State leaders. In the backwash
of the demise of Susitra, much effort is being exhibited by the
coal industry to induce the railbelt utilities to start planning
for conversion to coal fired generation. At the same time,
natural gas generation is being recognized for its economic
attractivness in the wake of the collapse of worldwide energy
prices, and in recognition of the availability of Cook Inlet
natural gas since the demise of the Pacific Alaska LIG project.
Perhaps from the chagrin of the Susitna exercise, no one appears
willing to conduct an assessment of the Devil Canyon project at
this time . The absence of this analysis has been a motivating
force for the Anchorage Chamber of Commerce Energy Committee to
produce this "white paper.'
DEVIL CANYON
SUMMARY CONCLUSIONS
1. Devil Canyon is technically feasible and there is a high
probability that the project can be built for a cost of $1.32
billion (1985$) not including finance charges. The project
would take six years to design and construct and it could be
completed as early as 1997.
2. The environmental impact associated with the development
of Devil Canyon appears to be minimal in comparison to full
basin development. The largest impact could be from human
encroachment into what is now a wilderness setting.
3 Devil Canyon and its surrounding environment could offer
a significant new recreational site for tourists who would
normally travel to Denali Park from Anchorage by way of
automobile or train. The project could complement State plans
to develop the recreational potential of Curry Ridge.
4. Devil Canyon could produce approximately 2.2 billion
kilowatt hours per year of electricity to meet a portion of the
railbelt energy needs. The railbelt presently consumes roughly
3.5 billion kilowatt hours annually. The annual distribution of
energy from the project does not match the seasonal energy
demands of the railbelt; however, development of upstream
storage or retiming the output from Eklutna, Bradley Lake, and
Cooper Lake hydropower projects would change the situation.
Retiming of the small hydro projects or development of upstream
storage would increase the cost of the revil Canyon option, but
additional energy benefits would accrue as well.
5. All of the existing thermal generation in the railbelt
will need to be replaced by the year 2012. A large portion will.
need to be replaced before the year 2000. Devil Canyon
generation could meet a portion of this replacement capacity.
The existing hydrogeneration at Eklutna, Bradley Lake, and
Cooper Lake would not need to be replaced.
6. In the absence of Devil Canyon, continued generation
using natural gas appears the most probable near term source of
electricity to meet Southcentral energy demands. There appears
to be a high probability of at least a 30 year supply of gas in
Cook Inlet to meet the domestic and export commitments at our
present use rate. However, given an annual growth in demand of
Only 1.3 percent over the present domestic and export
commitments, there is only a 23 year supply of this same gas.
7. One year of Devil Canyon generation will conserve the
equivalent of 10 months supply of natural gas annually for home
heating purposes in the Anchorage area.
CO azXu
PREFACE
2Lf&
iv
SUMMARY CONCLUSIONS
TECHNICAL INFORMATION
1
9ACKGROU ND
1
PRESENT STATUS
2
TECHNICAL ASPECTS OF DEVIL CANYON
2
ENVIRONMENTAL IMPACT
3
LAND STATUS
3
ENERGY OUTPUT
4
LICENSING REQUIREMENTS
5
ENERGY P-ND GENERATION REQUIREMENTS
7
NEED FOR NEW GENERATION
7
FUTURE ENERGY DEMAND
8
REVIEW OF OTHER ENERGY ALTERNATIVES
10
NATURAL GAS
10
COOK INLET NATURAL GAS AVAILABILITY
11
NATURAL GAS CONSUMPTION FORECASTS
12
NATURAL GAS PRICING
13
COAL FIRED GENERATION
15
COAL PLANT COSTS
16
COAL PRICING
17
FINANCIAL ANALYSIS
18
TECHNICAL INFORMATION
BACKGROUND
The Devil Canyon project has been studied on numerous
occasions in previous years but never as a stand-alone project.
Instead, it was always studied as an element of a combination of
dams to be built on the Susitna River. Interestingly, while
various proposals for full basin development have been proposed
over the decades, Devil Canyon has always remained an element of
those proposals. In fact, the proposed project features for
Devil Canyon have changed very little over the initial proposal
for developing the dam site in the early 1950's
Initial investigations were performed by the U. S. Army
Corps of Engineers and the Bureau of Reclamation in the 1940's.
In the 19�0's the Bureau focused its efforts on the Devil Canyon
site and conducted an extensive core drilling effort there.
They built a runway at the damsite and a 15 mile road to the
damsite from the railhead at Gold Creek. They submitted a
report to congress in 1962 that recommended developing Devil
Canyon as the first dam in what would eventually be a 4-dam
development of the Susitna River to include Watana, Vee, and
Denali dams located up -stream from Devil Canyon. The proposal
languished pending resolution of the Corps of Engineers thrust
to build the Rampart hydropower project on the Yukon River.
In 1972, Congress requested that the Corps of Engineers
review the 4-dam Bureau of Reclamation proposal and report its
findings to Congress. The Corps initiated its investigations in
the fall of 1974 and completed its assignment in December of
1975 with a recommendation that the project appeared to be
economically feasible and that the environmental impacts
associated with the projects development appeared acceptable.
The Corps scheme for developing the basin differed slightly from
that of the original Bureau proposal. Instead of four dams, the
Corps recommended the construction of only two dams: Devil
Canyon and a high Watana. The Corps proposal would include
Devil Canyon as originally proposed by the Bureau of
Reclamation, but Watana would be increased in height over the
Bureau design. By increasing Watana's height, the Vee damsite
would be eliminated by the Watana reservoir, and the Denali
damsite would become superfluous. The 2-dam scheme could
produce 95 percent of the energy of the 4-dam scheme, but it
would directly inundate only 60 percent as much area as the
4-dam proposal. Furthermore, the cost of the 2-dam proposal was
less than that of the 4-dam scheme.
The State of Alaska through the Alaska Power Authority took
over sponsorship of the Susitna project in January of 1980. The
Power Authority hired Acres American Inc., to conduct a detailed
investigation of the upper Susitna River and to
Devi). Canyon
Anchorage Chamber of Commerce
Ener.gy Committee
October 15, 1986
Page 2
establish base -line environmental data to support a license
application to the Federal Energy Regulatory Commission (FERC).
The investigations included additional core -drilling at Devil
Canyon as well as at Watana, and other basin locations. After
two and a half years of study and the expenditure of $35
million, the Power Authority confirmed that the Devil Canyon and
Watana projects did indeed represent the optimum way to meet the
railbelt future energy needs and applied for a license to
construct the project. The plan was to have Watana power on
line by 1993 and Devil Canyon power on line as future demand
dictated. As State revenues fell, it became apparent that it
would be difficult to finance the $3.5 billion Watana first
stage development without substantial assistance from the
earn`ngs from the perminent fund. Consequently the entire
project N _ put on hold despite the fact that a $1.3 billion
Devil Canyon project appeared to be economically feasible on its
own merit.
Although both projects are presently stalled, Devil Canyon
has never been seriously considered as a stand-alone project to
meet the energy needs of the railbelt. Preliminary analysis
indicates that it warrants this consideration. Furthermore, the
cost associated with making this evaluation is quite minimal.
The majority of the field investigations needed to address the
Devil Canyon project have already beer. performed. No other
energy project in the railbelt can be studied with the same
level of confidence as Devil Canyon without significant field
explorations. In addition to the work performed �)y the Corps of
Engineers and the Bureau of Reclamation, the Power Authority
spent roughly $150 million on its investigations. The Power
Authority estimates that roughly 85 percent of the Susitna
investigations can be directly usable for the Devil Canyon
project. It is estimated that a prefeasibility investigation of
the Devil Canyon project can be conducted for approximately
$300,000, and that a FERC license application could be prepared
for another $1.5 million. Additional geotechnical work would
also need to be performed during the licensing phase.
The most recent studies by Harza-Ebasco, the firm selected
by the Power Authority to license and design the Susitna
project, indicates that Devil Canyon as a stand-alone project
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 3
would cost approximately $1.323 billion in 1985 dollars not
including capitalized interest. Licensing could take two to
three years to complete and construction is estimated to require
six years. Access to the damsite would require the construction
of a new road from the parks highway through Chulitna pass or by
way of upgrading the existing road from Gold Creek. The dam
would consist of a concrete thin -arch structure in the main
canyon and an earth -fill cut-off dam on the .left abutment. The
thin -arch structure would have a maxim,.,:,' structural height of
roughly 645 feet and it would be 90 fe-, wide at its base and 20
feet wide at its top. The earth -fill structure would be roughly
245 feet high. The combined crest length of the two structures
would be approximately 2100 feet long.
The environmental impact associated with the project has
been studied extensively. While the lower Susitna River
supports an extensive anadromous fishery, few salmon have been
found to migrate above the Devil Canyon damsite. While the
variability of flow could be detrimental from a power
consumption standpoint, it will have positive environmental
consequences. Because the project will be operated in a
run -of -river mode, the downstream habitat will not be seriously
altered. Thus the impact on downstream fisheries should be
minimal. Upstream impact should also be minimal. The Devil
Canyon reservoir will be roughly 26 miles long and no more than
one half mile wide at its widest point. The reservoir will be
confined to a steep -walled canyon and the area flooded will
amount to only 7800 acres at maximum pool elevation. Some big
game habitat will be lost. Perhaps the biggest environmental
impact will be from the human pressure that would result to what
is presently a wilderness area.
The land in the project area and south of the river is
generally in the ownership of Native corporations, while the
Bureau of Land Management owns much of the land to the North of
the river. The Devil Canyon cost estimate includes $23 million
for lands and right of way purchases. The Natives have
generally been supportive of the project as they see it as a
means for opening up the economic potential of their lands.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 4
The present design calls for an above ground powerhouse with
an installed capacity of 460 W. Future investigations could
result in the powerhouse being located underground. The project
would be capable of producing roughly 2.2 billion kwh of
electricity annually. This amounts to roughly half of the
present energy consumption in the railbelt today. The
distribution of the energy from Devil Canyon would vary
considerably throughout the year. The Devil Canyon reservoir is
very small in comparison to the average annual streamflow of the
river. Consequently, there is little opportunity to store the
heavy summer flows for later release during the winter months.
Devil Canyon as a stand-alone project would essentially be
operated as a run -of -river project. Listed below is the
estimated year 2000 annual railbelt energy demand and the
corresponding energy capability of Devil Canyon stand-alone.
RAILBELT YEAR 2000 ENERGY DEMAND
AND DEVIL CANYON CAPABILITIES
(GIGAWATT HOURS)
MONTHLY
OTHER
RESIDUAL
DEVIL
MONTH
DEAD
1LUROPOWER
DEMAND
-CANYON
JAN
485
59
426
125
FEB
404
54
350
55
MAR
408
46
362
51
APR
360
39
321
47
MAY
331
35
296
271
JU N
304
28
276
300
JUL
312
34
278
309
AUG
322
45277
309
SEP
344
55
289
302
OCT
399
52
347
176
NOV
422
57
365
123
DEC
468
__44
409
_Ila
TOTAL
4559
563
3996
2191
(Other Hydropower includes Eklutna, Bradley, and Cooper)
It is obvious that most of Devil Canyon could be absorbed ty
the year 2000, and the remainder would be used as energy demand
grows. The major question that arises from the above table
involves the impact of Susitna on existing natural gas fired
Devil Canyon
Anchor age Chamber of Commerce
tic't�bei i�, i3c6
Page 5
ytrlerortivvl-, A +�oy-9 5, inN(cs49e"ta4 oT �-4,2 Ir+,p�[«i.r(AN5 vT
'.YC^�Y'-r��l-�.� .^ate.. i_ '�l.;L:1- .y . i • i, - �, _ �Ii. �i
.S'13'`►�`o; tM`� delav�ra.� _eN�f,;r 5qs hte
perfor�ea.
There are obvious ways to enhance the operation of Devil
Canyon. One method would be to construct additional storage
upstream of the Devil Canyon reservoir. This could result in a
significent additional expense, but it would also result in
additional energy output at Devil Canyon. The most apparent
method would be to change the operation of the existing
hydropower in the system to augment the low periods of Devil
Canyon output. This would require that both the Eklutna and
Bradley Lake reservoir capacities be slightly enlarged to be
able to store almost the equivalent of their respective basin's
natural runoff. The Cooper Lake reservoir is already large
enough to accommodate its basin's full annual runoff. The full
reservoir capacity of the three projects would allow them to be
operated at full continuous capacity during the winter when
Devil Canyon power is at its lowest, and they could then be shut
down for the balance of the year. Operation in this manor would
not diminish the energy output of the three projects it would
just alter the time of year that they are producing power. By
operating in this manner, gas generation could continue at a
more uniform rate throughout the year.
:4*6119 9:..�
The Federal government maintains jurisdiction over virtually
all hydropower 3evelopment in the United States. Those projects
that are not directly developed by one of the major Federal dam
building agencies such as the Corps of Engineers, Bureau of
Reclamation, or the Tennessee Valley Authority, must, with rare
exception, require a license from the Federal Energy Regulatory
Commission (FERC).
FERC is the agency established to carry out the intent of
the Federal Power Act (FPA) of 1920. FERC is a Congressional
Commission administered under the Department of Energy. The
criteria established by FERC to define its jurisdictional
authority over hydropower is very broad and appears designed to
give FERC total regulatory authority over its development. The
FERC jurisdiction appears premised on the view that hydro sites
are public resources and contain significant attributes to
classify them as being for the public good. Thus it is viewed
that the allocation of this resource should be made by the
government rather than by market considerations. Because
hydropower is viewed as a public resource, it is viewed that the
public has the right to decide how the resource will be
allocated and therefor the state property law system becomes
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1956
Page 6
superseded by the Federal Governments right of eminent domain as
articulated by FPA and administered by the FERC.
In order to assert its authority, FERC has established four
criteria under which it views all hydropower projects: (A) is
federal land involved in the project, (B) is the river
considered navigable, (C) is interstate transfer of power
involved, and (D) is the project resource of national interest?
While there would be no interstate transfer of power from the
project and there may be no federal land involved, and there may
even be a strong argument against the river being navigable, it
would appear difficult to argue against the national
significance of the water resource. In fact there is still a
federal power -site withdrawal for the entire Devil Canyon
reservoir as a result of the earlier intentions of the Bureau of
Reclamation. Consequently, it is extremely doubtful that the
state would be given an administrative exemption from the FERC
process. This would imply two courses of action: either seek a
Congressionel exemption from the FERC process, or submit a FERC
license application as before.
It is estimated that it would take only six months and
approximately $1.3 million to submit a FERC license application
for Devil Canyon. Furthermore, because project financing and
the need for power will not be as difficult to prove to FERC as
was the case with full Susitna, and since the environmental
impact of Devil Canyon is significantly less than for the full
Susitna development, the prospects for receiving a timely FERC
licensF are greatly enhanced. It could very well be that with
all of the previous studies conducted on Susitna that a FERC
license could be secured in a two year time frame once submitted
if the new governor an6 *he administration get behind the
project.
The alternative would be to convince Congress and FERC that
there is no overriding public interest in the project and that
it should be exempt from the FERC process. The argument would
be that Devil Canyon would be built almost entirely on state and
private land, that there will be no interstate transfer of power
from the project, that the Devil Canyon stretch of river is
surely not navigable (a doubtful legal argument), that the
federal government will be under no financial obligation for the
project, and that since the project will have a single purpose
(power) there is no overriding national interest in the
project. It would also be pointed out that the project
would
it
help conserve valuable depletable energy
hat
would lessen United States dependance on foreign oil and help
reduce the national trade defecit. Finally, it would be argued
that the project is needed to help stimulate a sagging Alaskan
economy.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 7
ENERGY AND GENERATION REQUIREMENTS
The need for the Devil Canyon project or any major energy
project is driven by the desire to provide service at the lowest
possible cost and the need to meet future energy requirements.
Future energy requirements are driven by increased demand as the
economy expands and by the need to replace obsolete plants. New
generation needed to replace retired facilities is relatively
easy to project. The design life of various types of generation
is well documented. The design life of the type of generation
facilities in the railbelt is as follows:
DESIGN LIFE OF POWER GENERATION
FACILITIES
DESIGN LIFE
(YEARS)
COAL FIRED STEAM TURBINE 35
GAS FIRED COMBUSTION TURBINE 25
GAS FIRED COMBINED CYCLE Ski
OIL FIRED INTERNAL COMBUSTION 20
HYDROPOWER
100±
Power generation in the railbelt is of various age and
type. With the above retirement schedule it is possble to
predict with reasonable accuracy the need to replace existing
units to meet present energy demands. Hydropower is generally
viewed as having a very long life because the major sunk costs
are in the long lived items such. as the dams, tunnels, and
spillways. The equipment in the powerhouse is replaced as
needed, but this represents a relatively small cost in
comparison to the total value of the facility.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 8
Based on the railbelt utilities retirement schedule, the
Power Authority has estimated that by the year
00, the
railbelt utilities will retire and need to replace at least
2025
t
mw of existing power generation. Furthermore, by Year
all of the existing thermal generation will have reached its
useful life and will need to be replaced. This represents a
combined total of 1097 MW of generation requirements. hat will V e to be
The only
replaced to accommodate existing p
generation that will not be replaced will be the three
hydropower projects: Eklutna, Cooper Lake, and Bradley Lake.
Devil Canyon would have an installed capacity of 460 tM-
However, because of the limited winter storage capacity o- its
reservoir, it would generally be credited with
only 230 W for
firm capacity purposes. It is appa ve
as energy demand does
retirement schedule, however, that so long
not diminish, new generation of Devil Canyon's magnitude will be
needed in the time -fame that it could be brought on line.
��1 RF ENER�_Y__DEMAI�I�
The need for generation to meet an increasing energy demand
is difficult to predict. The prior practice was to estimate the
future needs based on historical trends. This proved When a
acceptable and accurate technique up until the 1970
shift in national output and an energy conservation awareness
altered demand patterns. In the absence of historical trend
analysis, it has become necessary to disagregate the end uses
for energy in an attempt to develop future composite estimates.
This has generally been accomplished by developing econometric
computer models which attempt to simulate the demographic
setting and use characteristics of the marketplace.
In short, future plant additions for the railbelt were
projected by econometric modeling and by estimatingthe
useful
life of existing generation facilities. Load projections
generally remained the responsibility of railtheibelutilities,
but
the underlying assumptions which g projections
usually a product of economic modeling. The Institute of Social
and Economic Research has been recognized as having the best
the railbelt and the state
overall grasp of the demographics for
in general. The ISER work has remained the underlying
demographic input to the Devil Canyon analysis.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 9
The Power Authority utilized the ISER demographic data in
making its energy demand projections as presented in the
following table:
FORECAST OF RAILBELT
POPULATION AND ENERGY DEMAND
(Compound Annual Increase)
APA
$ISTORIC FQ.�CAST
STATE POPULATION GROWTH 3.5 1.0
RAILBELT POPULATION GROWTH 4.1 1.1
RAILBELT ENERGY DEMAND 9.6 1.6
RAILBELT PEAK DEMAND 9.6 1.6
It is obvious from the above forecasts that the Power
Authority estimates a maturing of the Alaska economy. This is
an opinion which up until the most recent oil price decline was
not shared by the railbelt utilities. The combined Utility
forecast for both energy and peak demand is 3.8% in comparison
to the Power Authority's 1.6% annual growth forecast. However,
informal discussions with area utilities have indicated that the
present economy has resulted in an adjustment downward in their
estimates of future energy demand increases.
Present railbelt annual energy and peak demand are 3,300 GWH
and 700 MW respectively. These are projected to reach 4,300 GWH
and 850 MW by the year 2000, and to 6,200 GWH and 1,200 MW by
the year 2020. It is clear that the market area will be of
sufficient size to absorb the majority of the 2,200 GWH which
Devil Canyon could provide annually.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 10
REVIEW OF OTHER ENERGY ALTERNATIVES
The economics of the Devil Canyon project are established by
comparing its life -cycle present worth costs to those of the
next lowest cost energy alternative. It has generally been
recognized that natural gas and coal generation options are the
two most probable alternatives that will be developed to meet
our electricity needs if Devil Canyon does not proceed. A third
option would be to develop a number of smaller hydropower
projects to meet the railbelt needs. This option has has been
rejected because of the high cost of such a plan and the
attendent environmental impact associated with new transmission
lines and access roads to the numerous small dam sites. Other
energy options considered and rejected include: tidal, oil,
nuclear, biomass, geothermal, wind, solar, and others. -
Most study efforts indicate that natural gas is the most
probable intermediate rangy option to meet railbelt needs and
that coal would meet our longer range needs in the absence of
Devil Canyon. Thus the economics of Devil Canyon is very
dependent on the projected future cost of these fuels and in
particular natural gas.
The two primary sources of natural gas for power generation
are from the North Slope fields and from the Cook Inlet area.
Most studies of North Slope gas generally indicate that the
price of the fuel for electric power generation makes it
noncompetitive when compared to a hydro or coal generation
resource. Furthermore, while it is the general opinion that
some sort of pipeline system will be developed to bring this gas
to market, no infrastructure presently exists nor are their
sufficient plans for its development to warrent the
consideration of North Slope gas for prudent power planning.
Finally, when world wide gas economics are such that a gas
pipeline is feasible, it is doubtful that United States energy
policy would allow the use of natural gas as a feedstock for
base load power generation. It is probable that fuel use
restrictions similar to those imposed under the Fuel Use Act of
1978 would be enforced.
Cook Inlet natural gas, however, is both price competitive
and readily available for power generation and other purposes.
The reserves are somewhat limited, but by imposing restrictions
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 11
on the future use of this resource, there could be cuff icient
supplies for long term local consumption. Thus while there is
an estimated 36,129 billion cubic feet of proven natural gas
reserves on the North Slope, the focus of this discussion will
be on the availability and price of Cook Inlet natural gas
supplies.
COOK INLET N T(7 RAL GAS AVAILABILITY
There are 4,664 billion cubic feet of proven reserves of
natural gas in Cook inlet. This gas is contained in some 15
different deposits throughout the area, and most of the gas was
found incidental to the exploration for oil. In addition to
these proven reserves, it is estimated that there is a 75%
probability of another 1,980 BCF of undiscovered but
commercially available reserves of natural gas in Cook Inlet.
With a present local use rate of roughly 65 BCF per year for
power generation and space heating, the proven and recoverable
Cook Inlet gas reserves represents a 100 year supply for future
domestic energy needs. However, there are substantial other
obligations for the use of this natural gas which significantly
precludes its availability for long term domestic energy needs.
Only 30% of the natural gas that is being produced in the Cook
Inlet area is being utilized for domestic purposes such as home
heating and k,cwer generation. The majority of the remainder is
being exported in the form of Liquefied Natural Gas (LNG) or as
ammonia and uria to Pacific Rim markets. In fact, 4,742 BCF of
Cook Inlet natural gas has already been produced and consumed
for all purposes in the 20 year period that the fields have been
in operation.
The 1985 Cook Inlet natural gas use rate was roughly 215
BCF. A summary of the 1985 natural gas consumption by use
category is provided in the table below according to figures
presented in a 1986 report by the State Department of Natural
Resources. Assuming this level of use for the duration of the
gas fields, the existing known reserves will be fully utilized
by the year 2008. The undiscovered reserves would extend the
life of the Cook Inlet field to the year 2017. Or in other
words, at our present use rate and assuming that no additional
demands would be placed upon the fields, there is a high
probability that there is at least a 30 year supply of natural
gas to meet the needs of Southcentral Alaska.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 19R6
Page 12
1985 COOK INLET NATURAL GAS CONSUMPTION
(Billion Cubic Feet/Year)
PURPOSE —BCF
Field Operations 17.780
Power Generation 40.096
Gas Utilities 24.470
LNG 65.381
Amonia - Uria 53.977
Producers 21.341
Unaccounted for (8,275)
TOTAL 214.770
II4rmal Demand Increases. Based on demographic data provided
by the Institute of Social and Economic Research (ISER), the
Department of Natural Resources estimates that the demand for
natural gas will increase by 1.3 percent annually. Thus, they
estimate that the 215 BCF 1985 demand will increase to 262 BC,
by the year 2000. This will have the effect of slightly
shortening the life -span of the existing Cook Inlet gas fields
and any future reserves. Assuming that this use rate were to
prevail beyond the year 2000, the present known reserves of gas
would be depleted by the year 2003 and the probable reserves
would be exhausted by the year 2010; thus indicating that
Southcentral has a 23 year gas supply rather than 30 years at
our present use rate.
Undiscovered Reserves. A Division of Geological a,id
Geophysical Survey, Department of Natural Resources 1983
inventory of oil and gas in Alaska summarised the petroleum
resources estimated throughout the State. The report estimated
probable Undiscovered Natural Gas in Cook Inlet as follows:
DNR ESTIMATES OF UNDISCOVERED NATURAL GAS
IN COOK INLET
Probability That Quantity Is Billions Of
At Least The Given Value Cubic Feet
7 5% 1,980
50% 3, 07 0
25% 4,380
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 13
No indication of the threshold at which the above natural
gas is economically feasible to develop was given. Since most
of the gas would have to be explored for exclusive of the
prospects for contiguous oil discovery, it is assumed that the
cost of the natural gas would be considerably higher than that
presently available to Cook Inlet consumers.
tnral Gas to FaiYhazlia. Present studies are being
conducted to assess the viability of constructing a natural gas
pipeline from Wasilla to Fairbanks. Department of Natural
Resources estimates that natural gas space heating could
eventually capture 75% of the market presently being supplied by
fuel oil and coal. Thus DNR assumes that gas for Fairbanks
space heating could require 25 BCF by the year 1997. This is a
relatively small amount in comparison to the total gas demand at
that time.
Under active consideration is a plan to build a 20" gas
pipeline from Wasilla to Fairbanks at a cost of'roughly $150
million. The gas would be used to displace existing oil and
coal fired generation. The local Fairbanks utilities would be
responsible for their own retrof iting and approximatly 40 BCF of
gas may be needed initially. Once in place for local power
generation, local feeder lines for space heating could be
developed.
revel q��nt S) D_y_iJ Can: ��n Hydropower. it is estimated by
the Alaska Power Authority that Devil Canyon could produce
roughly 2.2 billion RWH of electricity annually. If this amount
of electricity were to displace an equivalent amount of gas
fired generation, 20 BCF per annum of gas would be freed up for
other uses in Southcentral Alaska. This would have the effect
of slightly increasing the Cook Inlet gas supplies, but it is
less than the 24.5 BCF of natural gas used for space heating in
1985. If Cook Inlet gas were to become totally obligated to
other uses through supply contracts, and if natural gas reserved
today for future power veneration could be resold for home
heating purposes, Devil Canyon could significantly increase the
availability of natural gas for local consumption. The
alternative would be to negotiate obligations of natural gas
from the local producers to meet long term domestic needs.
One of the major issues involved in the Devil Canyon project
has been the estimate of the price of natural gas against which
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 14
to compare the hydropower option. This has been particularly
difficult during this period of energy price volatility and
natural gas availability.
It is generally conceded that the power generation industry
will not be able to receive new gas from the producers at the
favorable rates that Chugach Electric Association presently
enjoys under its existing gas contracts ($0.21/MCF). Instead it
is assumed that new Chugach contracts will be closer in terms to
those negotiated by Enstar two years ago. Under the: Enstar
contract, new gas would cost $2.32/MCF and it would increase or
decrease in cost in accordance with the cost of Cook Inlet
oil. There would also be a peak demand charge and an additional
charge to cover the cost of capital development associated with
the pipeline feeder system. It is generally assumed that future
Cook Inlet contracts wi.11 have some sort of indexing value that
reflects either the cost of future oil or perhaps some sort of
local consumer price index.
The Alaska Power Authority in its analysis developed two
scenarios for future gas prices. one is based on what the Power
Authority assumes is the netback price of natural gas. That is,
the price that gas would raise to if the gas were sold on the
international market, less the transportation costs from the
well head. The second set of values is based on the Wharton
estimates in the light of the most recent Enstar contracts. A
third estimate which the Power Authority generally has rejected
f rom consideration are those the State of Alaska Department of
Revenue uses to estimate future State revenue. A forth estimate
which has recently been introduced are those which are
reflective of the negotiations which CEA is presently conducting
with the producers of Cook Inlet natural gas. The CEA figures
were obtained from their analysis of the Devil Canyon project
and do not reflect the ultimate prices which may be agreed upon
as a result of negotiations. The CEA numbers imply that an
escalator of at least the rate of inflation is being considered
in the negotiations. It is premature to determine what
escalation factor will ultimatly be agreed on by both partiEs.
It is assumed however, that the CEA values are within the
ballpark of what may ultimately be negotiated.
A summary of the various gas price estimates in 1985
dollars is presented below. The CEA values reflect the numbers
presented in the CEA report adjusted to 1985 at their assumed
annual inflation rate of 5.5%. In the year 2010 and beyond,
Chugach assumes an annual escalation rate of 0.5% over
inflation.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 15
ESTIMATED
COOK INLET
NATURAL GAS
PRICES
(1985$)
Composite
Wharton
ADOR
Year
Netback
En 1.ar__
EnLIL.Z_
CEA
1985
$2.00
$2.00
$2: 00
$1.70
1990
2.37
2.35
1.98
1.64
2000
3.53
2.83
2.00
1.72
2010
5.37
3.53
2.09
1.80
2020
7.85
4.57
2.18
1.88
2030
8.70
5.96
2.29
1.97
Application of the four sets of natural gas assumptions
indicates that the Devil Canyon project is economically feasible
under the Netback and Wharton projections and economically
unattractive when compared to the DOR and CEA values.
The figures do not reflect the impact of mid -east
manipulations on oil prices or on the artificial impact which
may result from federal government restrictions on the use of
natural gas. It is quite possible that the ultimate indexing
factor would result in new CEA gas prices similar to that of the
recent Enstar contracts. The ultimate price will be strongly
reflective of the value that the producers believe other gas
users would be willing to pay. Therefore, LNG exports may
actually result in netback pricing. If this occurs, Devil
Canyon energy could become an attractive alternative to natural
gas fired generation. At any rate, Devil Canyon becomes more
attractive when deferred to a power on line date commensurate
with the depletion of Cook Inlet natural gas supplies around the
turn of the century.
There are significant deposits of price competitive coal
available for power generation in the railbelt. Before the
discovery of Cook Inlet natural gas, coal was the predominant
source of power generation for all railbelt utilities. With the
discovery of natural gas, however, the utilities that had access
to natural gas quickly converted their plants to provide for the
new feed -stock. Now, with the dwindling supplies of Cook Inlet
natural gas, the utilities have renewed their interest in
returning to coal fired generation.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 16
Conventional coal fired generation is characterized as
having moderately high capital and operating costs, and fuel
costs that are less than natural gas depending on transportation
requirements. Present day environmental impacts from coal
generation are significantly less than its past reputation. In
addition, there have been significant break-throughs in the
generation technology which may make coal generation even more
environmentally acceptable and cost competitive in the future.
These include coal gasification, fluidized bed, and insitu
generation technclogies. These technologies are in the
developing and early commercial stages and may be premature for
application in the Alaskan environment at this time. Diamond
Alaska has made public its study on conventional coal plant
generation for the railbelt, and it is presently reviewing the
other coal generation technologies. The results of these latter
studies are not presently available.
In their analysis of Susitna, the Alaska Power Authority
assumed that the most logical coal addition would be a
conventional 200 MR mine mouth plant located at Beluga. The
following table summarizes the Power Authority estimate for coal
fired generation in comparison to the estimates provided by
Diamond Alaska and the Matanuska Power Project:
COAL PLANT COST ESTIMATES
(1985 dollars)
APA MATANU SKA DIAMOND
BELUGA POWER PROJECT ALA.G. KA
CAPACITY OF PLANT (MW ) 200 153 141
CAPITAL COST ($/KW) $2593 $2451 $2261
0 & M COST (CENTS/KWH) 1.3 0.7 1.8
The above cost estimates for the Matanuska Power project and
the Diamond Alaska project do not include tra<ismission line
costs. All three estimates assume an 80% capacity.factor for
operational costs, and no finance charges are included in the
capital costs. As mentioned above, the newer technologies may
result in capital costs even lower than those shown above. At a
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 17
recent Railbelt Energy Committee meeting, one representative of
the coal industry indicated that it may be possible to develop
an 80 hW fluidized bed coal fired plant for as little as
$10001KW. However, while the technology has been successfully
demonstrated, it has received little commercial operational
experience.
CRAL PR I C I NG
Like natural gas pricing, the cost of coal has generally
been tied to some form of price escalator. Because of this
Golden valley Electric Association has reported a 2.2% real rate
(over and above the rate of inflation) of increase for coal
during the cast twenty years. Fairbanks Municipal Utilities has
reported a �.0$ rate of .increase during the past 10 years. For
its economic assessment of the Susitna Project, the Power
Authority assumed a coal price escalation rate of 1.5%. The
coal industry has generally objected to this rate and feels that
it is too high.
They point out that historical coal price increases between
1860 and 1970 have generally tracked the rate of inflation for
this period. They acknowledge that Alaska coal rate increases
paralleled the U. S. market in general between 1970 and 1985,
but that this is reflective of the oil crises of the 1970's.
While the coal prices have not dropped with the recent decline
in oil prices, and while future price upsets are certainly
possible, because of the large Alaska coal supply, the existance
of several coal competitors, and because of a large world
overage in supply, they believe that future price escalation
will be closer to the historic rate.
The actual 1985 cost of coal reported by Fairbanks power
consumers has been $1.30/14MBTU for Golden Valley Electric
Association mine -mouth generation at Healy, and $2.40/MMBTU for
the U. S. Military in Fairbanks. The differerr�e in t:ie price of
the coal for the two consumers has generally been for
transportation costs from the mine to the power plant.
By combining the fuel prices and construction costs
presented above, both the Power Authority and Chugach Electric
Association concluded that Devil Canyon is economically superior
to conventional coal fired generation. No attempt has been made
to review the economics of Devil Canyon against one of the
emerging coal technologies.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 18
FINANCIAL ANALYSIS
The ability to finance a Devil Canyon stand alone hydro
project has many of the same problems that plagued the larger
Susitna Project. Initially, the $5 billion necessary for the
construction of Susitna was to be obtained from grants from the
State. As revenues declined and alternative uses from funds
were identified it became apparent that the state would not be
able to honor its commitment to fund the project entirely with
State grants, and a fall back plan requiring a $2 billion
contribution from the State, plus any interest accrued thereon,
was proposed by the Power Authority. The Power Authority
suggested that the balance of any necessary project funds would
be raised by the sale of bonds, but they recognized that for the
State to successfully sell such a large bond issue, the moral
obligation of the State would be required.
By early 1985, it was apparent that State contributions of
this magnitude were not likely, and the Power Authority
developed still another concept to finance the project. The new
concept incorporated : mechanism whereby the State contribution
was viewed as a debt service subsidy in the early years of the
project rather than a construction grant. This concept resulted
in a significant reduction in the amount of money necessary from
the State and provided the additional benefit of delaying the
timing of such a contribution. Unfortunately under such a
concept the "mo_al obligation" of the State was no longer
considered adequate for the magnitude of the bond issue and
additional security was deemed necessary. Analyses of the
ability of the railbelt utilities to pay for the retirement of
the bonds indicated that revenue fonds were not likely to
provide more than a limited amount of the funding required. As
a result, the Power Authority concluded that it was necessary
for the State to dedicate other resources as additional security
for the bonds. The most likely resource for this purpose was
determined to be the permanent fund, which while technically
possible is politically impossible. Accordingly the Susitna
Project died because of the failure of the State to honor its
commitments for grant funds and the inability of the railbel t
utilities to finance a project of this magnitude.
Devil Canyon
Anchorage Chamber of Commerce
Energy Committee
October 15, 1986
Page 19
The demise of the Susitna project did not change the fact
that the residents of the railbelt would need new generating
capacity, it merely shifted the problem from the Power Authority
to the railbelt utilities. Consequently, large projects the
size of Susitna necessarily must yield to smaller projects that
can be added incrementally as needed. The State has indicated
that the monies previously allocated for Susitna could be used
by the railbelt utilities for projects which would benefit
railbelt consumers. Studies are presently underway to determine
the best use of the funds deposited in the Railbelt Energy Fund.
With the demise of the Susitna Project, and the
establishment of the Railbelt Energy Fund, the possibility of
building a stand alone hydro project at Devil Canyon which would
be financed entirely by the utilities was proposed. A
preliminary analysis of the project by E. F. Hutton indicated
that the project could be financed though significant issues
still need to be addressed:
1. The utilities would need a significant investment in the
project which would be obtained from the monies in the Railbelt
Energy Fund.
2. The "dry -hole" or noncompletion risk would have to be
minimized, and if possible, eliminated.
3. The State would have to assume some liability in the
project, either in addressing the "dry -hole" risk or in
guaranteeing the bonds issued by the utilities.
4. Ownership of the project would have to be clearly
determined, and power sales agreements signed by all utilities.
None of these items are insurmountable, but all are
important. The good news is that the project most likely could
be financed, but unless the utilities develop strategies to
minimize the risks assumed by the bond holders, the cost of
financing the project could easily tip the scale from an
acceptable project to an unacceptable project.